Rhode Island Convention Center • Providence, Rhode IslandRhode Island Convention Center • Providence, Rhode Island
Fort Buchanan’s Water Harvesting Initiatives
Session: Alternative Water Resources
Mr. Anibal NegronUSAG Fort Buchanan PR
August 10, 2016
Rhode Island Convention Center • Providence, Rhode Island
Fort Buchanan Net Zero Water Strategy
Issues / Actions
Photos 1. ESPC Project 1:1a. High Efficiency Fixtures (toilets, urinals, showerheads) : Completed
1b. DFMWR Well Water Fed Irrigation System : 100% completed
2. ESPC Project 2:2a. Leak Detection Survey: Performed , 8 leaks found & repaired
2b. Water Harvesting: Completed , Includes 9 Buildings (330KSF)
2c. Potable Water Well Construction: Completed & Operating.
3. Facility Reduction Program:3a. 118,454 SF (FY11), 62,931 SF (FY13), and 36,024 SF (FY14)
4. Advanced Metering System:4a. All Buildings above 20KSF. ECD by 1st QTR FY16 (95% completion rate)
5 . PNNL Water Balance Study and Net Zero Roadmap completed
Current Status
Roadmap Way-Ahead1. Issues:
1a. No treatment facilities on Post and aged Water Distribution System
2. Actions:2a. Hydraulic Modeling Study managed by USACE-Mobile District Office is ongoing to determine Water Distribution System condition and provide upgrade/repair recommendations. ECD: 1st QTR FY172b. PNNL completed (4th QTR FY15) a Feasibility Study (FS) for a Waste Water Treatment Plant (WWTP) & Reclaim Water Reuse Strategy. FS concluded that the project is feasible and complies with Savings to Investment Ratio (SIR) of 1 and 19 years of Simple Payback. USACE Mobile will conduct a planning Charrette for a WWTP design including a 2nd Well. Estimate Implementation cost is approx. $5M. EST: FY17 / ECD: FY19.
Lake for Golf CourseIrrigation System
Final Road Map
FY20
FY12
FY15
FY14
FY13
FY16
FY17
FY18FY19
Water Balance
ESPC Project 2
Facility Reduction Plan
ESPC Project 3 (TBD)
Meet NZW 60% reduction goal
EMAP No 4 (Water Conservation) approved by GC
ESPC Project 1
Advanced Metering System
Future New Construction and Demolitions (TBD)
Hydraulic Modeling study
Rhode Island Convention Center • Providence, Rhode Island
ID DESCRIPTION
ECM 2.1 Air Cooled Chillers Replacement
ECM 3.1 Energy Management Control Systems (EMCS)
ECM 4.1 HVAC System and Split AC Systems Retrofit
ECM 5.1 Lighting Upgrades and Occupancy Sensors
ECM 5.2 Street Lighting Upgrades to LED
ECM 10.1 Solar Photovoltaic Systems: Roof mounted at 606 and 689.
ECM 10.2 Solar Thermal Water Heating
ECM 10.3 Wind Power Generation: (3 turbines @ 275 kW each)
ECM 12.1
Water Conservation Initiatives:
1. DFMWR Irrigation System
2. Building Water fixtures
ECM 14.1 Retro Commissioning Services
ID DESCRIPTION
ECM 3.1 Energy Management Control Systems
ECM 4.1 HVAC System and Split AC Systems Retrofit
ECM 5.1 Lighting Upgrades and Occupancy Sensors
ECM 5.2 Street Lighting Upgrades
ECM 10.1Solar Photovoltaic Systems (Parking Canopy @ Buildings 689, 353, 161, and Old DPW Site)
ECM 12.1
Water Conservation Initiatives:
1. Leak Detection Analysis
2. Rain Water Harvesting (9 Buildings with a combined total area of 337,227sf)
ECM 12.2 Ground Water Well for Potable Usage
COMBINED TOTAL (ESPC Project 2 only)
Project 1 MOD: ECM 6.1
Building 689 reflective Roofing
Project 1 Mod: ECM 10.1
Ground Mounted PV System at Bldgs 21, 556, and 538
ESPC 1 ESPC 2
ECM: Energy Conservation Measure
Energy Saving Performance Contract (ESPC)
Rhode Island Convention Center • Providence, Rhode Island
Fort Buchanan’s Net Zero Water Road Map
Rhode Island Convention Center • Providence, Rhode Island
PXTra Water Harvesting4,400 GalPXTra Water Harvesting4,400 Gal
Middle School Water Harvesting4,400 GalMiddle School Water Harvesting4,400 Gal
Fort Buchanan’s Rainwater Harvesting Systems
Rhode Island Convention Center • Providence, Rhode Island
Fort Buchanan’s Rainwater Harvesting Sites (continued)
Bowling Center Water Harvesting 4,400 GalBowling Center Water Harvesting 4,400 Gal
High School Water Harvesting 9,000 GalHigh School Water Harvesting 9,000 Gal
Rhode Island Convention Center • Providence, Rhode Island
Fort Buchanan’s Rainwater Harvesting Savings (continued)
Annual SavingsImplementation Cost
Simple Payback of 5.78 Years
Rhode Island Convention Center • Providence, Rhode Island
Fort Buchanan’s Rainwater Harvesting Savings
Design Capacity
Annual Savings
Rhode Island Convention Center • Providence, Rhode IslandEnergy Exchange: Federal Sustainability for the Next Decade9
Rhode Island Convention Center • Providence, Rhode Island
Proposed Onsite Reclaimed Wastewater
Membrane Bioreactor (MBR):• MBR technology to treat wastewater to non‐
potable standards• Application for reclaimed water: golf course
irrigation• Offset the use of groundwater• Potential savings: 11 million gallons per year
Rhode Island Convention Center • Providence, Rhode Island
U.S
. Arm
y ph
oto
by S
GT
Jam
es S
eles
nick
Mr. Anibal Negron, Chief Environmental Division, 787‐707‐3575, [email protected]
Mr. Keith Grezlik, Environmental Protection Specialist, 787‐707‐3579, [email protected]
Ms. Wanda B. Robles, Environmental Compliance 787‐707‐3572, [email protected]
Mr. Derrick Stepanof, Installation Restoration 787‐707‐3573, [email protected]
Mr. Victor Rodriguez, Environmental Conservation787‐707‐3508, [email protected]
Mr. Francisco J. Méndez, SEMS Coordinator787‐707‐3522, [email protected]
Mr. Osvaldo Fantauzzi, New Pollution Prevention787‐707‐2553, [email protected]