from pioneering to industrializing offshore wind: lessons learned from horns rev ii
DESCRIPTION
From pioneering to industrializing offshore wind: Lessons learned from Horns Rev II Stockholm, September 14th, 2009. Contents. Offshore wind challenges and DONG Energy introduction Key lessons learned from HRII and key steps in industrializing offshore. DONG Energy – an introduction. - PowerPoint PPT PresentationTRANSCRIPT
1
From pioneering to industrializing offshore wind: Lessons learned from Horns Rev II
Stockholm, September 14th, 2009
Contents
2
Offshore wind challenges and DONG Energy introduction
Key lessons learned from HRII and key steps in industrializing offshore
DONG Energy – an introduction
DONG Energy is one of the leading energy companies in Northern Europe
We are headquartered in Denmark. Our business is based on procuring, producing, distributing and trading in energy and related products in Northern Europe
DONG Energy has app. 6,000 employees and had a turnover of more than DKK 60 billion in 2008
3
0200 04 10090701 03 0805 06Total
Total
DONG Energy has pioneered offshore wind
DE share (2009)
90 45Barrow
40 20Middelgrunden
165 133Rødsand
160 64Horns Rev I
90 0Kentish Flats
173 173Gunfleet Sands I & II
90 90Burbo
209 209Horns Rev II
1018 734
4
MW
Constructed 551 MW of the current appr. 1 GW offshore capacity
Building the worlds largest offshore wind farm to date (HRII)
DONG Energy holds a substantial offshore wind pipeline – under construction and planning
* Figures represent DONG Energy's share of the projects
Offshore wind projects under construction (1063 MW)
Offshore wind projects under engineering/planning (more than 1,500 MW)
Borkum Riffgrund I(134 MW)*Borkum Riffgrund II(388 MW)*
Horns Rev II (209 MW)
Walney I+II (367 MW)
London Array I (315 MW)*
Walney III(180 MW)
London Array II (185 MW)*
West of Duddon Sands (165 MW)*
Westermost Rough (240 MW)
Wigtown Bay (280 MW)
Gunfleet Sands I+II (172 MW)
More than 1000 MW offshore wind under construction
Pipeline to ensure growth past 2013
Furthermore, offshore pipeline could be strengthened from DK offshore tender, UK round 3 and other licences
5
Offshore wind in the EU is expected to see high growth rates over the coming decades
6Source: "Pure Power", EWEA March 2008
Offshore wind is still more expensive than onshore – and the renewable technologies are more expensive than thermal
7
143
107100
Coal Gas Onshore
172*
Offshore
* Of which 5-10% covers export cable and substationSource: Poyry Energy Consultants, DONG Energy estimates on full load hours
Index: coal=100; 2010 forward fuel prices (May 2009)
Contents
8
Offshore wind challenges and DONG Energy introduction
Key lessons learned from HRII and key steps in industrializing offshore
The installation process can be divided in many intra-linked processes
9
Synergies between parks
Geotechnical exploration
Scale advantages on vessels
Installation of foundations
Improvement of design Optimisation of installation process
Installation of WTG Standardisation of installation concept Optimisation of installation process
Commisioning Repeated use of generator Optimization of transfer vessels
Cable installation Optimisation of installation concept Integration of cable and WTG installation
Substation installation
Standardisation of design Scale advantages in procurement
Onshore grid connection
Scale advantages in procurement
HR II: The project and key lessons learned
10
Project Details
Generating capacity 209 MW
91 Siemens 2.3 MW turbines
CAPEX milDKK 3,500
35 km2 wind farm area
Water depths between 9 and 18 meters
Tidal range up to 1.2 meters
Average wind speed 9.7 m/sec.
Synergies with earlier projects
2.3 MW WTG employed again
Same installation vessel used
Layout optimised
Applying the same turbine enhances the learning curve for installation
11
# of WTGs
Installation time
CONCEPTUAL
Future desired state
WTG INSTALLATION
0 7520
Time-saving potentialCurrent HRII
experience
Strict monitoring on progress can ensure correction of time-table delay
12
ILLUSTRATIVE EXAMPLE
WTG INSTALLATION
100%
0%
Actual % complete
Planned % complete
Weeks
Progress
Horns Rev 2 – Installation progress curve
Next step: Pipeline approach in order to capture synergies
13
Operational issues in installation
Sourcing component packages, incl. interfaces
WTG installation Foundation installation Array and export cable
installation Commissioning Test and hand-over
Scale advantage in sourcing Improved planning – interface management and installation flow Minimizing risk – leveraging technical learning curve
Smooth production cycle
MW
Years Years
CONCEPTUAL
Horns Rev 1 offshore wind farm, Denmark
Thank you for your attention