frst 557 forest operations module lecture 3c optimum...
TRANSCRIPT
FRST 557
Forest Operations Module
Lecture 3c
Optimum Road Standards
Special Case Study: No Timber Developed
1.0 Lesson Overview:
The preceding parts of this lecture assumed that the entire road is developing harvestable
timber adjacent to it. There are cases however where a section of road may not develop
timber. Often this occurs in situations where, due to physical differences in construction,
costs also vary significantly from those used for the rest of the road network.
Very difficult construction through a canyon where the numbers change significantly may
even have the indicated road class reduced for the section.
FRST 557 – Lecture 3c – Special Case Study: No Timber Developed
2
2.0 Lesson Preparation:
Review the last two lessons and be certain that you understand the concept of finding the
optimum road standard.
3.0 Lesson Objective:
On completion of this lesson, you will know how to adapt the approach to finding an
optimal solution to one example of a variation in physical conditions..
4.0 The Problem:
Optimum Road Standards (using the non-uniform road system method) have already been
developed for the following illustration with the exception of a short section between km
14.8 and km 16.0:
L = 66 km
v = 22,000 m3 / km
Summary:
Class 1 km 0 to km 45.1 (45.1 km)
Class 2 km 45.1 to km 59 (13.9 km)
Class 3 km 59 to km 66 (7.0 km)
V M = 220,000 m 3
Mainline
Sort Yard
Class 1? Class 2?
Class 3?
km 55
km 59
Branch B
Branch C
km 66
VC = 210,000 m3
VB = 250,000 m3
km 14.8 to km 16.0
Steep rock canyon requiring
drilling & blasting and end haul.
No timber developed (v = 0)
FRST 557 – Lecture 3c – Special Case Study: No Timber Developed
3
The following is a detail of the circled area of the previous diagram.
Between km 14.8 and km 16.0, the main road goes through a steep-sided canyon. This
section of road will require extensive rockwork and the excavation will have to be hauled
away. Although a road class for this section has already been determined using average
data, the cost structure in the canyon will be significantly different. The costs from km
14.8 to the sort and beyond km 16.0 are unchanged, but for JUST the canyon section (km
14.8 to 16.0), projected alternative costs are as follows:
Timber volume information is the same as in the original scenario EXCEPT that there is
NO timber development along the canyon section of road (i.e. v = zero)
How can the original plan accommodate this information if the objective is to minimize
costs?
5.0 The Solution
As with the previously examined examples, an iteration is required each time there is a
change to one or more variable. In this case the costs of each road class have changed.
The iteration always works from the “back end” toward the destination.
Since the timber developed along the road is zero (v = 0) the analysis changes to a uniform
road standard problem with a break-even point between each alternative road class. (It
would take an increasing volume over the length of road to justify an increase in
standard.) If the accumulated volume at km 16.0 is less than the critical volume at the
break even, the lower class road is built. If the accumulated volume is more, then the
higher class road can be justified.
Class R
$/km
h
$/m3/km
1a 1,290,000 0.21
2a 854,000 0.28
3a 750,000 0.37
km 14.8
km 16.0
FRST 557 – Lecture 3c – Special Case Study: No Timber Developed
4
CT(N) = CT(N+1)
where:
CT is the total cost of construction and ongoing costs
N is the class of road
or specifically, in this case, CT(1) = CT(2) and CT(2) = CT(3)
The following chart is a general illustration of the cumulative costs for increasing volumes
with each of three classes of road.
The actual total volume (V) is entering the section of road at km 16.0 so call it V16.
The total cost of either alternative is equal to the construction cost (the cost per km times
the length) plus the operating costs (volume times $/m3/km times length).
CT(N) = RNL + VhNL So if the breakeven is where:
CT(N) = CT(N+1) then:
RNL + VChNL = RN+1L + VChN+1L
Where the break even volume (or critical volume) is identified as VC
Tota
l Co
st p
er
km o
f R
oa
d
Cumulative Volume Hauled (m3)
Cumulative Cost per km vs Cumulative Volume Hauled
Class 1
Class 2
Class 3
Class 2 breakeven
Class 1 breakeven
FRST 557 – Lecture 3c – Special Case Study: No Timber Developed
5
Solving the equation for VC:
Using the data from Section 4.0, the actual volume at km 16.0 is:
V16 = VM + VC + VB+ v(66 – 16.0) = 1,780,000 m3
For the first iteration at km 16.0, look at the critical volume to justify Class 2a over
Class 3a (VC2a)
=
=
= 1,155,556 m
3
Since V16 > , at least Class 2a is justified.
But Class 1a should also be checked as a possibility, so what is the critical volume ( to justify Class 1a?
=
=
= 6,228,571 m
3
Since V16 < , there is not sufficient volume to justify a Class 1a road.
Conclusion: km 14.8 to km 16.0 will be constructed to a Class 2a standard.
Summary for the entire road:
Class 1 km 0 to km 14.8 (14.8 km)
Class 2a km 14.8 to km 16.0 (1.2 km)
Class 1 km 16.0 to km 45.1 (29.1 km)
Class 2 km 45.1 to km 59.0 (13.9 km)
Class 3 km 59.0 to km 66.0 (7.0 km)
The following chart illustrates the data for the actual example. Since the actual
cumulative volume at km 16.0 is 1,780,000 m3, the optimum choice is the Class 2a road.
FRST 557 – Lecture 3c – Special Case Study: No Timber Developed
6
6.0 Other Applications
This case study is but one of many unique situations that can occur. To find an optimal
solution for a range of choices, the objective must be identified along with the critical
variable, the input variables determined, and the appropriate approach – usually
comparing two alternatives at a time in an iterative process. Where the choice is between
two alternatives (i.e. all one or all the other) it will be a break even analysis. If the choice
is an appropriate combination of the alternatives, the optimal choice will be indicated as a
minimum total cost of all combinations of the alternatives.
$0
$500,000
$1,000,000
$1,500,000
$2,000,000
$2,500,000
$3,000,000
$3,500,000
$4,000,000
$4,500,000
$5,000,000
Tota
l Co
st p
er k
m o
f R
oa
d
Cumulative Volume Hauled (m3)
Cumulative Cost per km vs Cumulative Volume Hauled
Class 1a
Class 2a
Class 3a
Class 2a breakeven
1,155,556 m3
Class 1a breakeven
6,228,571 m3
Class 1a optimum
Class 2a optimum
Class 3a optimum