Page 1: Fs2012 october

Financial StatementsFor the Period

September 1, 2012 ‐ October 31, 2012

For the Meeting of the Board of Trustees ‐ November 15, 2012

for

Houston Community College System&

Houston Community College Public Facility Corporation

Page 2: Fs2012 october

Memorandum Management Discussion & Analysis

Summary HCCS Unrestricted Revenue & Expenditures 1

Adjusted Budgets by Division 2

Actual YTD by College  2

Cash Flow Analysis 3

Contact Hours Reimbursement 8

Enrollment Data 9Charts Revenue & Expenditure YTD thru October 31, 2012 10

Revenue and Expenditures with Trendlines 11

Revenue Source Comparison By Year 12

Expenditure Source Comparison By Year 13

Fund Balances Balance Sheet By Fund   14

Designated Funds Budget Summary / Cash Position 15

Capital Projects & Unexpended Plant Fund Projects 16

    Unexpended 2004 CIP Projects 17

    Plant Fund Maintenance Tax Notes 2006 (Central Utility Plant Project) 25

Maintenance Tax Notes/Sr. Lien Bonds 2008 26

Maintenance Tax Notes 2010 28

Bonds/Notes Schedule of Bonds & Maintenance Tax Notes 29

Auxiliary Sources and Uses of Auxiliary Funds 30

Restricted Funds Grants, Contracts and Student Aid 32

Position Control 2013 Positions 38

Pos. Control Charts FTE (Full‐Time Equivalent) Monthly Comparison 41

Duplicated Headcount Monthly Comparison 50

Unduplicated Headcount Monthly Comparison 51

Statement of Net Assets PFC 1

Statement of Cash Flows  (Cash Basis‐ Interim Period) PFC 2

Public Safety Institute PFC 3

Westgate PFC 4

Hayes Road ‐ Alief Project PFC 5

Northline Mall Project PFC 6

Houston Community College ‐ Public Facility Corporation

Table of ContentsFor the Period September 1, 2012 ‐ October 31, 2012

For the Meeting of the Board of Trustees

Houston Community College System

Page 3: Fs2012 october

MEMORANDUM  

To:    Houston Community College System          Board of Trustees 

 

    Via:    Dr. Mary Spangler, Chancellor  

From:    Dr. Art Tyler, Deputy Chancellor     Chief Operating Officer  

Date:    November 8, 2012  

Re:  Financial Report for Month Ended October 31, 2012     

 

Enclosed please find the preliminary financial reports for the month ending October 31, 2012 for your review.  The financial report is an internal management report submitted to the Board of Trustees to compare actual financial activities to the approved budgets, strategic priorities, and financial policies for the reported fiscal year.   

 

Operating Fund net revenue through October 31, 2012 is $64,311,638 which is 4.9% below last year.  Expenditures year‐to‐date total $49,676,408 which is 13.5% less than the same time last year, for a net of $14,635,230. 

 

The reserves for the month of October 2012 are $62,779,856 or 21.2% of revenues (see page IV).  Thus, we continue to project a healthy fiscal strength for the college. 

Page 4: Fs2012 october

Managements Discussion and Analysis

Thru October 31, 2012

Revenues

Expenditures 

Tuition and Fees net revenue year to date totaled $43,969,299 which is 7.3% lower than the same time last year.  

Current enrollment numbers for Fall 2012 are trending downward at 5%.  We are projecting tuition and fees 

revenue to be $114,588,415.  

i

Insurance/Risk Management payments totaled $6,562,016 year‐to‐date, 5.7% above last year.  The increase is 

due to an increase in insurance premiums.  Total expenses for the year are expected to be within budget at 

$6,871,724.

Tuition & Fee‐Extended Learning receipts totaled $2,020,284 year to date, 6.3% above last year.  Total tuition 

and fees‐Extended Learning at fiscal year end are expected to be $6,188,581.

Marketing and Advertising expense totaled $299,509 year‐to‐date, a 29.9% increase compared to last year.  

Marketing expenses are projected to be $1,496,807 at fiscal year end.

Rental and Leases expenses totaled $396,792 year‐to‐date, which is 77.8% below the previous year.  Total 

expenses at  year end are projected to be $3,821,064.

Total revenue collections, net of exemptions and waivers, totaled $64,311,638 year‐to‐date.  This is a 4.9% decrease below last year. 

Total Salaries are $28,641,907 year‐to‐date, 0.4% below the previous year.  Total salaries at year end are 

expected to be $163,550,787.

Benefits costs totaled $3,080,654 year‐to‐date, 29.4% above last year.  Total benefits at fiscal year end are 

expected to be $18,209,301.

Contract Services expense totaled $1,832,381 year‐to‐date.  Fiscal year end expenses are projected to be 

$23,747,083.

Total revenues and expenditures by expense type for the Operating Fund for 2012‐2013 are reported on page one, 

behind the tab Detailed Financial Statements. Highlights of financial activities year‐to‐date are as follows:

State Appropriations received year to date totaled $17,867,571, 0.4% below last year. Total appropriations 

received are expected to be $70,014,007.  This amount was reduced by $218,031 due to a formula reallocation 

to align with the Legislative Budget Board data and methodology.

Ad Valorem Tax collections totaled $12,311 year‐to‐date.  The year‐to‐date total is 24.4% below last year.  We 

project total tax revenue for the fiscal year will be $102,195,871

Utilities costs totaled $1,085,312 year‐to‐date.   We will continue to monitor these costs.  Total utilities cost at 

fiscal year end is projected to $12,889,610.

Page 5: Fs2012 october

Managements Discussion and Analysis

Thru October 31, 2012

Budget Priorities funding allocated for the year are detailed below through October 31, 2012. 

Contingency/Budget Priorities

Capital Outlay & Equipment

Position Management

Other

Total Contingency/Budget Priorities

Grants

Unexpended Plant Fund  

Public Facility Corporation

Total grant awards (federal, state & private) year‐to‐date total, $43,830,979.

Cash Position ‐ The use of the Unexpended Plant Fund Excluding 2004 CIP for deferred maintenance projects was 

discontinued in FY 2009.  All deferred maintenance expense is captured in the operating account.  See page 15 

for prior year encumbrances. 

Unexpended Plant Fund Projects include current construction, deferred maintenance, and property acquisition 

projects for a budget of $46,124,917.  Funds for these projects are 100% committed.  See page 16 for more 

details.

The 2004 CIP budgets are $263,779,995 and are 99.98% committed. The spending categories in the schedule 

have now been revised for more ease of reference to the Board approved budget.  Please see page 17 for the 

summary and pages 19 through 23 for details.

The Maintenance Tax Note 2006 tracks the financial progress of the Central Utility Plant.  Commitments year‐to‐

date total $12.5 million, 99.87% of budget.  See page 25 for the details. 

The Public Facility Corporation tracks the progress of the PFC ‐ Public Safety Institute, Katy Campus (Westgate), 

Alief and Northline Mall deferred maintenance, new construction and renovation projects.  Expenditures year‐to‐

date total $100.8 million, 98.7% of budget. See pages PFC 1‐6 for details. 

ii

5,834,411$       

3,800,000           4,481,452           (681,452)            

Instructional and Other Materials expenses totaled $1,268,115 year‐to‐date, which is 22% below last year.  

Expenses in this area are projected to be $11,215,877.

Transfers/Debt activities totaled $5,005,690 year‐to‐date.  Items in this expense category include all student 

revenue bond payments, transfers for scholarship matching funds, and transfers to the Unexpended Plant Fund.  

Total expenses are expected to be $33,699,339.

Total operating fund expenditures year‐to‐date total $49,676,408, a 13.5% decrease below last year.  

Budget expenditures for grant‐funded projects so far this year total $2,136,514.

Budgeted

1,445,240           513,014              932,226             

11,372,376$      5,287,191$        6,085,185$       

Expensed Remaining

6,127,136$        292,725$           

The college has received $340,529 in new grant awards since the beginning of the current fiscal year. 

Page 6: Fs2012 october

Managements Discussion and Analysis

Thru October 31, 2012

Balance Sheet – Operating Fund   

Cash and Investments

Cash

Investments

    Total

Fund Balance

Unaudited Fund Balance, August 31, 2012

Projected Revenue @ 08/31/2013

Total Projected Revenue

Projected Expenses @ 08/31/2013

FY 2012 Purchase Order Roll 

Total Projected Expenses @ 08/31/2013

Ending Fund Balance (Beg. Fund Balance + Revenue ‐ Expenses)

Required Reserve for FY 2013 (11% Projected Revenues)

Added Reserves

Additional Expenditures Funded From Reserves:

FY2012‐2013 Salary Increases

Total Expenses Paid From Reserves

Added Reserves

Required Reserve for FY 2013 (11% Projected Revenues)

Current Reserves

% of Total Operating Revenue

The projected reserves at October 31, 2012 of $62,779,856 is an estimate at this time and represents 21.2% of 

expected general fund revenue for this fiscal year, which is within our financial stability policy requiring us to maintain 

a fund balance of 9% ‐11% of general fund revenues as of August 31.  

iii

(1,836,560)         ‐                           (1,836,560)                 

(1,836,560)$       ‐$                         (1,836,560)                 

30,226,539$              

32,553,317$              

62,779,856$              

21.2%

Budget

298,335,238$            

64,616,416$              

32,553,317$              

32,063,099$              

Expense to Date  Balance 

295,939,244              

362,951,654$            

295,939,244$            

2,395,994                   

10,984,386              ‐                                

78,338,534$           45,537,947$          

67,012,410$              

October 2012 October 2011

67,354,148$           45,537,947$          

Page 7: Fs2012 october

FY2011‐12 FY2012‐13

Tuition

Budget:AdjustedBudgetFY2012‐13 43,067,676$Exemptions&Waivers (2,899,110)AdjustedBudgetFY2012‐13,Net 40,168,566$

RevenuesReceived:Tuition 48,824,432 21,611,314 20,065,809

Waivers&Exemptions:DualCredit (5,170,736) (2,390,985) (2,133,727)Other (1,693,502) (709,011) (765,383)

TotalWaivers&Exemptions (6,864,238) (3,099,996) (2,899,110)TotalTuitionRevenue,Net 41,960,194$ 18,511,318$ 17,166,699$

Tuition‐ExtendedLearning

Budget:BudgetFY2012‐13 6,188,581$Exemptions&Waivers (448,758)BudgetFY2012‐13,Net 5,739,823$

RevenuesReceived:

Tuition 8,853,381 2,356,317 2,469,042Waivers&Exemptions:

Corrections (2,612,080) (455,319) (448,758)

TotalELTuitionRevenue,Net 6,241,301$ 1,900,998$ 2,020,284$

Exemptions&WaiversDeptofCorrections 2,612,080$ 455,319$ 448,758$DualCreditWaiver 5,170,736 2,390,985 2,133,727

Other:EmployeeFeeExemptions 84,810 34,701 29,491Firemen 42,521 23,691 12,155Hazelwood 906,036 360,138 451,740Deaf&Blind 309,603 129,168 123,026HighRankingHiSCHGrad 868 372 1,271ChildofDisabledVetETC 431 978 1,139NonresMilitaryPer&Dep 2,390 708 ‐NonresTeach/ResearchAsst 13,905 5,418 5,841NonresCompetitiveScholar ‐ ‐ 1,062SeniorCitizens 18,730 8,017 6,519ScholarshipDistribution 1,450 1,450 ‐ApprenticeshipWaivers (28) ‐ ‐SpecialFeesWaiverHFD 117 117 ‐AVISAWaiver(Non‐AlienWaiver) 1,110 1,110                    ‐RefugeeWaiver (1,554) (1,110) (162)FosterChildren‐Resident 294,543 135,096 127,937FireAcademyWaiver 157 ‐ ‐UndocumentedStudents 2,171 1,282 ‐TXTomorrowWaiver 2,874 2,875 ‐PeaceOfficerExemption 13,368 5,000 5,364

TotalOtherExemptions 1,693,502 709,011 765,383GrandTotalExemptions&Waivers 9,476,318$ 3,555,315$ 3,347,868$

Note:AsofDecember31,2008,thefinancialstatementsreflectallexpensesincurredforExemptionsandWaiversasnetoftuitionandfeerevenue.PriortothisdateExemptions&Waiverswereshownasanexpenditureandrevenuewasshownasgrossrevenue.

iv

Exemptions&WaiversThruOctober31,2012

Year‐to‐DateActivitythru10/31/2012

Year‐to‐DateActivitythru10/31/2011

EndofYearActivityAccount

Page 8: Fs2012 october

g

YTD Adjusted Budget

YTD Actuals Thru 

October 31, 2012

YTD Actuals Thru 

October 31, 2011

2012‐2013 Inc/(Dec) 

vs. 2011‐2012

Actuals % 

Inc/(Dec)YTD vs. 

PriorYTD

Projected Actuals 

2012‐2013

Projected 2012‐2013 

Inc/(Dec) vs. Adj 

Budget

Projected 2012‐

2013 Inc/(Dec) vs. 

Adj Budget %

REVENUES

State Appropriations 70,232,038$           17,867,571$      17,947,320$      (79,749)$            ‐0.44% 70,014,007$      (218,031)$           ‐0.31%Ad Valorem Taxes 102,195,871           12,311               16,286               (3,975)                ‐24.41% 102,195,871     ‐                       0.00%Tuition, Net 43,067,676             17,166,699        18,511,318       (1,344,619)        ‐7.26% 43,067,676       ‐                       0.00%Fees 71,520,739             26,802,600        28,898,132       (2,095,532)        ‐7.25% 71,520,739       ‐                       0.00%Other Local Income* 2,952,370                359,518             296,900             62,617               21.09% 2,952,370         ‐                       0.00%Tuition & Fee, Net

 ‐‐ Extended Learning6,188,581                2,020,284            1,900,998           119,286              6.27% 6,188,581           ‐                         0.00%

Grant Revenue ‐                                82,656                 39,998                 42,657                 106.65% ‐                        ‐                        

Total Revenues 296,157,275           64,311,638          67,610,952         (3,299,315)          ‐4.88% 295,939,244$     (218,031)$            ‐0.07%

EXPENSES

Faculty‐FT  53,221,588             10,765,367        10,479,826       285,541            2.72% 53,221,588       ‐                       0.00%

Faculty‐PT 30,518,118             5,200,028          5,297,312         (97,284)             ‐1.84% 30,518,118       ‐                       0.00%

Librarian/Counselor‐FT  4,896,219                911,991             1,223,935         (311,944)           ‐25.49% 4,896,219         ‐                       0.00%

Librarian/Counselor‐PT 829,099                  113,283             97,729               15,553               15.91% 829,099             ‐                       0.00%

Staff‐FT 64,192,361             10,437,687        10,315,289       122,398            1.19% 64,192,361       ‐                       0.00%Staff‐PT 9,893,402                1,213,552          1,327,230         (113,678)           ‐8.57% 9,893,402         ‐                         0.00%

     Sub‐total Salaries 163,550,787           28,641,907          28,741,321         (99,414)               ‐0.35% 163,550,787       ‐                             0.00%

Employee Benefits 18,209,301             3,080,654          2,380,567         700,087            29.41% 18,209,301       ‐                       0.00%

Supplies Gen Exp 5,627,847                888,373             774,519             113,854            14.70% 5,627,847         ‐                       0.00%

Travel 938,063                  129,398             90,430               38,968               43.09% 938,063             ‐                       0.00%

Marketing Costs 1,496,807                299,509             230,612             68,896               29.88% 1,496,807         ‐                       0.00%

Rental & Leases 3,821,064                396,792             1,783,642         (1,386,850)        ‐77.75% 3,821,064         ‐                       0.00%

Insurance/Risk Mgmt 6,871,724                6,562,016          6,205,960         356,056            5.74% 6,871,724         ‐                       0.00%

Contract Services 23,747,083             1,832,381          1,351,373         481,009            35.59% 23,747,083       ‐                       0.00%

Utilities 12,889,610             1,085,312          738,062             347,251            47.05% 12,889,610       ‐                       0.00%

Other Departmental Expenses 1,786,272                412,863             350,298             62,565               17.86% 1,568,241         (218,031)             ‐12.21%

Instructional & Other Materials 11,215,877             1,268,115          1,626,814         (358,699)           ‐22.05% 11,215,877       ‐                       0.00%

Maintenance & Repair 1,211,077                60,616               58,856               1,760                 2.99% 1,211,077         ‐                       0.00%

Transfers/Debt 33,699,339             5,005,690          13,072,784       (8,067,095)        ‐61.71% 33,699,339       ‐                       0.00%

Contingency 2,923,114                ‐                          ‐                          ‐                           0.00% 2,923,114         ‐                       0.00%Capital Outlay 8,169,310                12,781               40,275               (27,493)             ‐68.26% 8,169,310         ‐                         0.00%

     Total Expenses  296,157,275           49,676,408        57,445,514       (7,769,106)        ‐13.52% 295,939,244     (218,031)             ‐0.07%

REVENUES H/(L) Vs EXPENSES 0                              14,635,230        10,165,439       4,469,791         ‐                          ‐                          

* Includes interest & dividends income, fines & penalties and parking fines

1

HOUSTON COMMUNITY COLLEGE2012‐2013 Revenues & Expenditures  HCCS CURRENT UNRESTRICTED

Page 9: Fs2012 october

 CENTRAL 

 NORTH

WEST 

 NORTH

EAST 

 SOUTH

WEST   SOUTH EAST   COLEMAN 

 EXTENDED 

LEARNING 

 CHAN‐

CELLOR 

DEPUTY CHAN‐

CELLOR 

INSTITU‐

TIONAL 

EFFECTIVE‐

NESS 

 INSTRUC‐

TION 

 INFO

TECH 

 STUDENT 

SUCCESS   SYSTEM   HCCS 

 % of 

Adjusted 

Budget 

EXPENSES

Faculty‐FT  10,274,237      10,146,406      7,282,384         12,064,145     4,907,675       5,860,770       2,370,440       ‐                  ‐                    ‐                   180,406          135,125          ‐                  ‐                  53,221,588      17.97%

Faculty‐PT 4,753,315         6,327,932         4,066,211         5,833,205        3,779,081       1,790,194       3,637,035       ‐                  ‐                    ‐                   330,386          759                 ‐                  ‐                  30,518,118      10.30%

Librarian/Counselor‐FT  1,119,093         1,115,400         886,744            683,319           613,571          53,730            2,887              ‐                  ‐                    ‐                   340,010          ‐                  81,465            ‐                  4,896,219        1.65%

Librarian/Counselor‐PT 87,030              194,185            119,380            182,495           82,452            33,248            ‐                  ‐                  ‐                    ‐                   19,773            ‐                  110,536          ‐                  829,099           0.28%

Staff‐FT 5,366,410         4,311,675         4,720,002         5,617,026        3,658,512       2,365,929       3,722,075       3,683,972       15,437,806    102,108           3,394,112       7,518,710       4,294,024       ‐                  64,192,361      21.68%

Staff‐PT 1,985,499         1,643,253         741,149            1,481,270        1,226,383       441,322          619,862          263,028          573,372           ‐                   261,790          235,344          421,130          ‐                  9,893,402        3.34%

     Sub‐total Salaries 23,585,584      23,738,851      17,815,870      25,861,460     14,267,674    10,545,193    10,352,299    3,947,000       16,011,178    102,108           4,526,477       7,889,938       4,907,155       ‐                  163,550,787    55.22%

Employee Benefits ‐                     ‐                     ‐                     4                       ‐                  ‐                  ‐                  ‐                  ‐                    ‐                   ‐                  ‐                  ‐                  18,209,297    18,209,301      6.15%

Supplies Gen Exp 226,414            375,314            200,632            229,606           202,137          337,228          209,666          311,425          1,356,826        ‐                   151,064          219,779          7,756              1,800,000       5,627,847        1.90%

Travel 103,360            88,682              34,545              62,926             56,181            87,347            70,555            121,304          140,510           ‐                   56,671            83,281            32,701            ‐                  938,063           0.32%

Marketing Costs 49,979              46,349              109,159            36,266             89,207            38,323            191,180          81,220            853,124           ‐                   ‐                  2,000              ‐                  ‐                  1,496,807        0.51%

Rental & Leases 34,418              123,010            1,314,554         633,560           41,484            508,719          48,180            24,980            228,951           ‐                   ‐                  853,487          9,721              ‐                  3,821,064        1.29%

Insurance/Risk Mgmt 794                    15                       ‐                     154                  ‐                  ‐                  ‐                  ‐                  ‐                    ‐                   ‐                  676                 ‐                  6,870,085       6,871,724        2.32%

Contract Services 321,129            277,847            57,350              49,485             168,144          345,565          58,574            427,798          13,687,586    ‐                   111,335          2,252,284       31,883            5,958,103       23,747,083      8.02%

Utilities 5,025                ‐                     4,600                ‐                   ‐                  ‐                  ‐                  ‐                  1,575,778        ‐                   ‐                  1,400,000       ‐                  9,904,207       12,889,610      4.35%

Other Departmental Expenses 80,205              45,543              39,683              43,695             139,172          85,724            52,044            299,064          234,893           ‐                   136,159          213,624          138,493          277,973          1,786,272        0.60%

Instructional & Other Materials 449,461            306,438            137,914            265,802           68,115            364,475          1,350,175       36,261            131,277           ‐                   1,058,476       6,769,694       277,789          ‐                  11,215,877      3.79%

Maintenance & Repair 116,709            24,787              52,353              33,463             15,772            84,713            158,150          825                 704,028           ‐                   8,472              8,870              416                 2,519              1,211,077        0.41%

Transfers/Debt ‐                     845,619            5,636,142         1,155,001        ‐                  ‐                  ‐                  ‐                  3,264               ‐                   ‐                  ‐                  ‐                  26,059,313    33,699,339      11.38%

Contingency 50,000              29,647              60,250              49,044             40,000            50,000            ‐                  83,000            125,000           ‐                   50,000            50,000            50,000            2,286,173       2,923,114        0.99%

Capital Outlay 602,055            310,856            284,443            135,237           282,606          559,924          30,859            58,150            1,055,548        ‐                   1,089              719,534          1,873              4,127,136       8,169,310        2.76%

Total Budget 25,625,133      26,212,958      25,747,495      28,555,703     15,370,492    13,007,211    12,521,682    5,391,027       36,107,963    102,108           6,099,743       20,463,167    5,457,787       75,494,806    296,157,275    100.00%

 CENTRAL 

 NORTH

WEST 

 NORTH

EAST 

 SOUTH

WEST   SOUTH EAST   COLEMAN 

 EXTENDED 

LEARNING 

 CHAN‐

CELLOR 

DEPUTY CHAN‐

CELLOR 

INSTITU‐

TIONAL 

EFFECTIVE‐

NESS 

 INSTRUC‐

TION 

 INFO

TECH 

 STUDENT 

SUCCESS   SYSTEM   HCCS 

 % of 

Actuals 

EXPENSES

Faculty‐FT  2,126,793         2,052,681         1,469,276         2,457,524        1,003,606       1,165,509       468,512          ‐                  ‐                    ‐                   7,253              14,211            ‐                  ‐                  10,765,367      21.67%

Faculty‐PT 863,641            1,121,076         691,602            1,031,769        642,549          244,146          556,861          ‐                  ‐                    ‐                   48,385            ‐                  ‐                  ‐                  5,200,028        10.47%

Librarian/Counselor‐FT  192,522            200,948            173,775            134,877           118,217          8,942              2,886              ‐                  ‐                    ‐                   64,097            ‐                  15,727            ‐                  911,991           1.84%

Librarian/Counselor‐PT 10,624              24,832              21,902              31,347             10,837            4,562              ‐                  ‐                  ‐                    ‐                   ‐                  ‐                  9,180              ‐                  113,283           0.23%

Staff‐FT 882,835            684,495            768,050            907,153           588,615          392,304          599,788          613,210          2,551,147        17,018             559,503          1,203,221       670,349          ‐                  10,437,687      21.01%

Staff‐PT 214,088            226,727            113,066            205,727           146,126          45,740            100,598          21,082            60,988             ‐                   17,301            18,552            43,559            ‐                  1,213,552        2.44%

     Sub‐total Salaries 4,290,501         4,310,759         3,237,672         4,768,396        2,509,949       1,861,204       1,728,645       634,291          2,612,135        17,018             696,539          1,235,984       738,815          ‐                  28,641,907      57.66%

Employee Benefits ‐                     ‐                     ‐                     3                       ‐                  ‐                  ‐                  ‐                  ‐                    ‐                   ‐                  ‐                  ‐                  3,080,650       3,080,654        6.20%

Supplies Gen Exp 21,095              26,341              29,106              43,209             34,133            30,580            44,638            43,712            182,774           ‐                   31,108            14,530            24,512            362,634          888,373           1.79%

Travel 3,328                13,959              3,476                5,913               2,782              14,675            20,293            22,204            13,951             ‐                   16,012            8,263              4,544              ‐                  129,398           0.26%

Marketing Costs 1,098                11,097              ‐                     12,228             8,996              1,346              34,694            5,984              224,066           ‐                   ‐                  ‐                  ‐                  ‐                  299,509           0.60%

Rental & Leases 30,000              13,825              200,832            36,275             5,000              72,051            2,418              1,720              33,012             ‐                   ‐                  854                 805                 ‐                  396,792           0.80%

Insurance/Risk Mgmt ‐                     ‐                     ‐                     ‐                   ‐                  ‐                  ‐                  ‐                  ‐                    ‐                   ‐                  ‐                  ‐                  6,562,016       6,562,016        13.21%

Contract Services 9,934                14,427              4,578                5,365               4,540              236,033          14,716            6,330              703,849           ‐                   3,789              27,580            19,076            782,166          1,832,381        3.69%

Utilities 1,168                ‐                     ‐                     ‐                   ‐                  ‐                  ‐                  ‐                  87,103             ‐                   ‐                  279,200          ‐                  717,841          1,085,312        2.18%

Other Departmental Expenses 4,695                2,300                2,517                5,144               1,138              16,192            17,290            30,393            15,477             ‐                   16,407            17,488            9,452              274,370          412,863           0.83%

Instructional & Other Materials 56,533              18,277              5,800                11,179             3,605              14,993            76,918            ‐                  1,436               ‐                   182,016          893,213          4,146              ‐                  1,268,115        2.55%

Maintenance & Repair 10,203              1,870                1,682                658                  1,681              1,089              14,353            ‐                  23,674             ‐                   4,853              552                 ‐                  ‐                  60,616             0.12%

Transfers/Debt ‐                     221,329            1,651,966         664,709           ‐                  ‐                  ‐                  ‐                  ‐                    ‐                   ‐                  ‐                  ‐                  2,467,686       5,005,690        10.08%

Contingency ‐                     ‐                     ‐                     ‐                   ‐                  ‐                  ‐                  ‐                  ‐                    ‐                   ‐                  ‐                  ‐                  ‐                  ‐                    0.00%

Capital Outlay 2,020                3,360                78                       4,030               1,739              ‐                  ‐                  ‐                  1,555               ‐                   ‐                  ‐                  ‐                  ‐                  12,781             0.03%

Total Expense 4,430,574         4,637,542         5,137,707         5,557,110        2,573,563       2,248,162       1,953,966       744,633          3,899,032        17,018             950,724          2,477,664       801,349          14,247,363    49,676,408      100.00%% of Adjusted 

Budget by Division 17.29% 17.69% 19.95% 19.46% 16.74% 17.28% 15.60% 13.81% 10.80% 16.67% 15.59% 12.11% 14.68% 18.87% 16.77% 100.00%

Remaining Balance 21,194,559      21,575,416      20,609,788      22,998,593     12,796,929    10,759,049    10,567,716    4,646,394       32,208,931    85,090             5,149,019       17,985,503    4,656,438       61,247,443    246,480,867   

HOUSTON COMMUNITY COLLEGE2012‐2013 Expenditures

YTD Adjusted Budget by Division

YTD Actuals by Division

2

Page 10: Fs2012 october

Sept. Oct. Nov. Dec. Jan. Feb. Mar. Apr. May June July  Aug.

Central                                 FY2013 8.77% 17.29%

                                              FY2012 8.89% 17.89% 27.03% 35.01% 41.49% 49.28% 58.01% 66.97% 74.34% 81.43% 88.98% 94.59%

Northwest                          FY2013 8.26% 17.69%

                                              FY2012 8.55% 18.72% 27.39% 33.69% 38.31% 46.70% 55.31% 66.77% 74.43% 81.57% 89.43% 95.09%

Northeast                           FY2013 6.80% 19.95%

                                              FY2012 6.70% 20.76% 27.75% 33.82% 40.16% 46.70% 53.35% 76.04% 82.19% 88.46% 94.27% 98.45%

Southwest                          FY2013 8.59% 19.46%

                                              FY2012 8.58% 19.19% 28.11% 36.68% 43.63% 50.96% 58.38% 71.97% 79.03% 85.23% 92.21% 96.87%

Southeast                            FY2013 7.94% 16.74%

                                              FY2012 8.68% 17.97% 27.56% 35.39% 41.33% 49.39% 57.90% 67.21% 74.92% 81.69% 89.81% 95.46%

Coleman                              FY2013 8.06% 17.28%

                                              FY2012 8.26% 17.29% 25.18% 32.46% 39.63% 47.52% 55.02% 63.80% 71.21% 79.83% 87.22% 93.29%

Extended Learning            FY2013 7.79% 15.60%

3                                               FY2012 7.97% 15.68% 23.55% 30.39% 37.09% 45.43% 53.07% 60.96% 69.35% 76.72% 84.68% 91.63%

Chancellor                           FY2013 7.14% 13.81%

                                              FY2012 8.66% 16.11% 23.27% 30.27% 39.34% 45.84% 53.37% 61.08% 68.18% 74.82% 81.30% 89.24%

Deputy Chancellor             FY2013 4.52% 10.80%

                                              FY2012 4.52% 10.28% 16.85% 22.58% 31.70% 38.52% 45.34% 51.71% 59.06% 69.23% 76.82% 80.46%

Institute Effectiveness      FY2013 8.33% 16.67%

                                              FY2012 5.76% 15.21% 22.37% 29.85% 38.13% 45.15% 52.82% 59.23% 67.73% 76.94% 85.77% 94.82%

Instruction                          FY2013 6.55% 15.59%

                                              FY2012 6.73% 16.23% 22.67% 28.96% 35.81% 42.78% 52.10% 59.22% 65.59% 72.63% 82.25% 89.27%

Info Tech                              FY2013 5.56% 12.11%

                                              FY2012 20.14% 33.96% 40.28% 45.47% 52.99% 59.23% 64.92% 71.03% 76.35% 82.70% 88.44% 99.49%

Student Success                 FY2013 7.33% 14.68%

                                              FY2012 8.33% 15.89% 23.44% 30.58% 40.76% 48.76% 56.63% 65.19% 72.58% 80.37% 90.28% 98.41%

System                                 FY2013 12.41% 18.87%

                                              FY2012 22.23% 25.94% 29.46% 32.09% 36.45% 39.69% 43.39% 63.98% 68.16% 71.84% 79.45% 88.27%

Total HCCS                           FY2013 8.55% 16.77%

                                              FY2012 12.05% 20.09% 26.81% 32.55% 38.82% 45.08% 51.63% 65.11% 71.48% 77.90% 85.35% 91.73%

Houston Community College

Cash Flow Analysis ‐ Monthly Percentage of Budget UsedFY2013 vs. FY2012

Page 11: Fs2012 october

Adjusted Budget 

FY2012

YTD Actuals Thru 

October 31, 2011 % of Budget Used

Adjusted Budget 

FY2013

YTD Actuals Thru 

October 31, 2012 % of Budget Used

EXPENSES

Faculty‐FT  11,323,534          2,288,526        20.21% 10,274,237        2,126,793          20.70%

Faculty‐PT 3,769,822             652,854           17.32% 4,753,315           863,641             18.17%

Librarian/Counselor‐FT  1,048,871             204,943           19.54% 1,119,093           192,522             17.20%

Librarian/Counselor‐PT 49,873                  10,145              20.34% 87,030                10,624                12.21%

Staff‐FT 5,296,359             885,076           16.71% 5,366,410           882,835             16.45%

Staff‐PT 1,809,062             259,108           14.32% 1,985,499           214,088             10.78%

     Sub‐total Salaries 23,297,521          4,300,653        18.46% 23,585,584        4,290,501          18.19%

Employee Benefits ‐                         ‐                    ‐                 ‐                        ‐                     ‐                 

Supplies Gen Exp 221,448                24,950              11.27% 226,414              21,095                9.32%

Travel 98,911                  2,486                2.51% 103,360              3,328                 3.22%

Marketing Costs 56,879                  9,911                17.43% 49,979                1,098                 2.20%

Rental & Leases 84,498                  19,500              23.08% 34,418                30,000                87.16%

Insurance/Risk Mgmt 794                        ‐                    0.00% 794                       ‐                     0.00%

Contract Services 330,483                20,049              6.07% 321,129              9,934                 3.09%

Utilities ‐                         ‐                    ‐                 5,025                  1,168                 0.00%

Other Departmental Expenses 62,728                  4,406                7.02% 80,205                4,695                 5.85%

Instructional & Other Materials 456,640                64,632              14.15% 449,461              56,533                12.58%

Maintenance & Repair 86,838                  8,885                10.23% 116,709              10,203                8.74%

Transfers/Debt ‐                         ‐                    ‐                 ‐                        ‐                     ‐                      

Contingency 44,919                  ‐                    0.00% 50,000                ‐                     ‐                      

Capital Outlay 170,356                2,521                1.48% 602,055              2,020                 0.34%

     Total Expenses  24,912,015          4,457,994        17.89% 25,625,133        4,430,574          17.29%

Adjusted Budget 

FY2012

YTD Actuals Thru 

October 31, 2011 % of Budget Used

Adjusted Budget 

FY2013

YTD Actuals Thru 

October 31, 2012 % of Budget Used

EXPENSES

Faculty‐FT  10,093,756          2,026,124        20.07% 10,146,406        2,052,681          20.23%

Faculty‐PT 4,196,906             783,430           18.67% 6,327,932           1,121,076          17.72%

Librarian/Counselor‐FT  842,964                177,207           21.02% 1,115,400           200,948             18.02%

Librarian/Counselor‐PT 133,561                20,999              15.72% 194,185              24,832                12.79%

Staff‐FT 3,488,099             581,738           16.68% 4,311,675           684,495             15.88%

Staff‐PT 1,168,139             188,254           16.12% 1,643,253           226,727             13.80%

     Sub‐total Salaries 19,923,425          3,777,751        18.96% 23,738,851        4,310,759          18.16%

Employee Benefits ‐                         ‐                    ‐                 ‐                        ‐                     ‐                 

Supplies Gen Exp 289,729                6,648                2.29% 375,314              26,341                7.02%

Travel 76,266                  7,807                10.24% 88,682                13,959                15.74%

Marketing Costs 41,176                  10,105              24.54% 46,349                11,097                23.94%

Rental & Leases 73,501                  10,716              14.58% 123,010              13,825                11.24%

Insurance/Risk Mgmt ‐                         ‐                    0.00% 15                         ‐                     0.00%

Contract Services 286,700                37,375              13.04% 277,847              14,427                5.19%

Utilities ‐                         ‐                    ‐                 ‐                        ‐                     0.00%

Other Departmental Expenses 34,464                  9,547                27.70% 45,543                2,300                 5.05%

Instructional & Other Materials 168,602                12,297              7.29% 306,438              18,277                5.96%

Maintenance & Repair 24,154                  668                   2.77% 24,787                1,870                 7.54%

Transfers/Debt 875,943                228,548           26.09% 845,619              221,329             ‐                      

Contingency 30,858                  ‐                    0.00% 29,647                ‐                     ‐                      

Capital Outlay 92,998                  2,066                2.22% 310,856              3,360                 1.08%

     Total Expenses  21,917,816          4,103,528        18.72% 26,212,958        4,637,542          17.69%

Central College

Detail Cash Flow Analysis ‐ Monthly Percentage of Budget Used

Northwest College

Detail Cash Flow Analysis ‐ Monthly Percentage of Budget Used

4

Page 12: Fs2012 october

Adjusted Budget 

FY2012

YTD Actuals Thru 

October 31, 2011 % of Budget Used

Adjusted Budget 

FY2013

YTD Actuals Thru 

October 31, 2012 % of Budget Used

EXPENSES

Faculty‐FT  8,043,440             1,564,811        19.45% 7,282,384           1,469,276          20.18%

Faculty‐PT 2,891,228             607,570           21.01% 4,066,211           691,602             17.01%

Librarian/Counselor‐FT  1,100,054             189,965           17.27% 886,744              173,775             19.60%

Librarian/Counselor‐PT 116,019                14,864              12.81% 119,380              21,902                18.35%

Staff‐FT 4,551,958             760,527           16.71% 4,720,002           768,050             16.27%

Staff‐PT 678,197                113,375           16.72% 741,149              113,066             15.26%

     Sub‐total Salaries 17,380,896          3,251,113        18.71% 17,815,870        3,237,672          18.17%

Employee Benefits ‐                         ‐                    ‐                 ‐                        ‐                     ‐                 

Supplies Gen Exp 329,948                21,392              6.48% 200,632              29,106                14.51%

Travel 31,865                  1,780                5.59% 34,545                3,476                 10.06%

Marketing Costs 46,417                  1,533                3.30% 109,159              ‐                     0.00%

Rental & Leases 1,263,216             212,784           16.84% 1,314,554           200,832             15.28%

Insurance/Risk Mgmt ‐                         ‐                    ‐                 ‐                        ‐                     ‐                 

Contract Services 56,049                  2,025                3.61% 57,350                4,578                 7.98%

Utilities 4,600                    ‐                    0.00% 4,600                  ‐                     0.00%

Other Departmental Expenses 46,640                  5,319                11.41% 39,683                2,517                 6.34%

Instructional & Other Materials 150,923                8,805                5.83% 137,914              5,800                 4.21%

Maintenance & Repair 27,811                  3,415                12.28% 52,353                1,682                 3.21%

Transfers/Debt 5,640,942             1,697,155        30.09% 5,636,142           1,651,966          ‐                      

Contingency 41,706                  ‐                    0.00% 60,250                ‐                     ‐                      

Capital Outlay 48,101                  106                   0.22% 284,443              78                      0.03%

     Total Expenses  25,069,114          5,205,427        20.76% 25,747,495        5,137,707          19.95%

Adjusted Budget 

FY2012

YTD Actuals Thru 

October 31, 2011 % of Budget Used

Adjusted Budget 

FY2013

YTD Actuals Thru 

October 31, 2012 % of Budget Used

EXPENSES

Faculty‐FT  13,860,660          2,768,588        19.97% 12,064,145        2,457,524          20.37%

Faculty‐PT 5,613,233             1,055,307        18.80% 5,833,205           1,031,769          17.69%

Librarian/Counselor‐FT  1,621,480             378,227           23.33% 683,319              134,877             19.74%

Librarian/Counselor‐PT 259,572                32,770              12.62% 182,495              31,347                17.18%

Staff‐FT 5,718,965             965,972           16.89% 5,617,026           907,153             16.15%

Staff‐PT 1,665,551             285,110           17.12% 1,481,270           205,727             13.89%

     Sub‐total Salaries 28,739,460          5,485,973        19.09% 25,861,460        4,768,396          18.44%

Employee Benefits ‐                         ‐                    ‐                 4                           3                         ‐                 

Supplies Gen Exp 254,387                23,399              9.20% 229,606              43,209                18.82%

Travel 65,224                  4,536                6.95% 62,926                5,913                 9.40%

Marketing Costs 37,367                  5,121                13.71% 36,266                12,228                33.72%

Rental & Leases 855,864                75,872              8.87% 633,560              36,275                5.73%

Insurance/Risk Mgmt 113                        ‐                    ‐                 154                       ‐                     0.00%

Contract Services 42,150                  5,951                14.12% 49,485                5,365                 10.84%

Utilities ‐                         ‐                    ‐                 ‐                        ‐                     ‐                 

Other Departmental Expenses 42,828                  13,019              30.40% 43,695                5,144                 11.77%

Instructional & Other Materials 239,436                22,736              9.50% 265,802              11,179                4.21%

Maintenance & Repair 19,554                  1,106                5.66% 33,463                658                    1.97%

Transfers/Debt 2,492,129             687,010           27.57% 1,155,001           664,709             57.55%

Contingency 44,734                  ‐                    0.00% 49,044                ‐                     0.00%

Capital Outlay 129,654                637                   0.49% 135,237              4,030                 2.98%

     Total Expenses  32,962,900          6,325,360        19.19% 28,555,703        5,557,110          19.46%

5

Northeast College

Detail Cash Flow Analysis ‐ Monthly Percentage of Budget Used

Southwest College

Detail Cash Flow Analysis ‐ Monthly Percentage of Budget Used

Page 13: Fs2012 october

Adjusted Budget 

FY2012

YTD Actuals Thru 

October 31, 2011 % of Budget Used

Adjusted Budget 

FY2013

YTD Actuals Thru 

October 31, 2012 % of Budget Used

EXPENSES

Faculty‐FT  5,652,540             1,085,038        19.20% 4,907,675           1,003,606          20.45%

Faculty‐PT 2,654,529             509,731           19.20% 3,779,081           642,549             17.00%

Librarian/Counselor‐FT  694,643                121,811           17.54% 613,571              118,217             19.27%

Librarian/Counselor‐PT 67,814                  7,582                11.18% 82,452                10,837                13.14%

Staff‐FT 3,354,662             561,745           16.75% 3,658,512           588,615             16.09%

Staff‐PT 993,213                162,621           16.37% 1,226,383           146,126             11.92%

     Sub‐total Salaries 13,417,402          2,448,528        18.25% 14,267,674        2,509,949          17.59%

Employee Benefits ‐                         ‐                    ‐                 ‐                        ‐                     ‐                 

Supplies Gen Exp 188,962                27,228              14.41% 202,137              34,133                16.89%

Travel 48,263                  4,892                10.14% 56,181                2,782                 4.95%

Marketing Costs 115,335                11,002              9.54% 89,207                8,996                 10.08%

Rental & Leases 177,160                46,311              26.14% 41,484                5,000                 12.05%

Insurance/Risk Mgmt ‐                         ‐                    ‐                 ‐                        ‐                     ‐                 

Contract Services 135,939                50,999              37.52% 168,144              4,540                 2.70%

Utilities ‐                         ‐                    ‐                 ‐                        ‐                     ‐                 

Other Departmental Expenses 182,266                3,250                1.78% 139,172              1,138                 0.82%

Instructional & Other Materials 60,917                  7,718                12.67% 68,115                3,605                 5.29%

Maintenance & Repair 15,172                  341                   2.25% 15,772                1,681                 10.66%

Transfers/Debt ‐                         ‐                    ‐                 ‐                        ‐                     ‐                      

Contingency 32,436                  ‐                    0.00% 40,000                ‐                     0.00%

Capital Outlay 93,901                  219                   0.23% 282,606              1,739                 0.62%

     Total Expenses  14,467,753          2,600,488        17.97% 15,370,492        2,573,563          16.74%

Adjusted Budget 

FY2012

YTD Actuals Thru 

October 31, 2011 % of Budget Used

Adjusted Budget 

FY2013

YTD Actuals Thru 

October 31, 2012 % of Budget Used

EXPENSES

Faculty‐FT  6,690,713             1,210,153        18.09% 5,860,770           1,165,509          19.89%

Faculty‐PT 1,191,206             192,664           16.17% 1,790,194           244,146             13.64%

Librarian/Counselor‐FT  186,866                31,188              16.69% 53,730                8,942                 16.64%

Librarian/Counselor‐PT 31,357                  5,230                16.68% 33,248                4,562                 13.72%

Staff‐FT 2,356,976             389,144           16.51% 2,365,929           392,304             16.58%

Staff‐PT 361,635                54,849              15.17% 441,322              45,740                10.36%

     Sub‐total Salaries 10,818,753          1,883,227        17.41% 10,545,193        1,861,204          17.65%

Employee Benefits ‐                         ‐                    ‐                 ‐                        ‐                     ‐                 

Supplies Gen Exp 318,629                23,680              7.43% 337,228              30,580                9.07%

Travel 78,252                  10,395              13.28% 87,347                14,675                16.80%

Marketing Costs 43,823                  ‐                    0.00% 38,323                1,346                 3.51%

Rental & Leases 489,486                74,720              15.27% 508,719              72,051                14.16%

Insurance/Risk Mgmt ‐                         ‐                    ‐                 ‐                        ‐                     ‐                 

Contract Services 322,241                146,093           45.34% 345,565              236,033             68.30%

Utilities ‐                         ‐                    ‐                 ‐                        ‐                     0.00%

Other Departmental Expenses 62,343                  10,575              16.96% 85,724                16,192                18.89%

Instructional & Other Materials 294,951                14,851              5.04% 364,475              14,993                4.11%

Maintenance & Repair 50,834                  2,488                4.89% 84,713                1,089                 1.29%

Transfers/Debt ‐                         ‐                    ‐                 ‐                        ‐                     ‐                      

Contingency 48,017                  ‐                    0.00% 50,000                ‐                     0.00%

Capital Outlay ‐                         ‐                    0.00% 559,924              ‐                     0.00%

     Total Expenses  12,527,329          2,166,029        17.29% 13,007,211        2,248,162          17.28%

Southeast College

Detail Cash Flow Analysis ‐ Monthly Percentage of Budget Used

Coleman College

Detail Cash Flow Analysis ‐ Monthly Percentage of Budget Used

6

Page 14: Fs2012 october

Adjusted Budget 

FY2012

YTD Actuals Thru 

October 31, 2011 % of Budget Used

Adjusted Budget 

FY2013

YTD Actuals Thru 

October 31, 2012 % of Budget Used

EXPENSES

Faculty‐FT  2,379,308             450,340           18.93% 2,370,440           468,512             19.76%

Faculty‐PT 3,205,781             520,649           16.24% 3,637,035           556,861             15.31%

Librarian/Counselor‐FT  67,910                  11,318              16.67% 2,887                  2,886                 99.97%

Librarian/Counselor‐PT ‐                         ‐                    0.00% ‐                        ‐                     0.00%

Staff‐FT 3,674,157             608,246           16.55% 3,722,075           599,788             16.11%

Staff‐PT 689,123                79,696              11.56% 619,862              100,598             16.23%

     Sub‐total Salaries 10,016,279          1,670,249        16.68% 10,352,299        1,728,645          16.70%

Employee Benefits ‐                         ‐                    ‐                 ‐                        ‐                     0.00%

Supplies Gen Exp 199,366                14,020              7.03% 209,666              44,638                21.29%

Travel 68,930                  8,194                11.89% 70,555                20,293                28.76%

Marketing Costs 206,496                68,960              33.40% 191,180              34,694                18.15%

Rental & Leases 47,975                  3,909                8.15% 48,180                2,418                 5.02%

Insurance/Risk Mgmt ‐                         ‐                    ‐                 ‐                        ‐                     0.00%

Contract Services 93,052                  2,309                2.48% 58,574                14,716                25.12%

Utilities ‐                         ‐                    ‐                 ‐                        ‐                     ‐                 

Other Departmental Expenses 54,193                  12,232              22.57% 52,044                17,290                33.22%

Instructional & Other Materials 1,178,083             79,596              6.76% 1,350,175           76,918                5.70%

Maintenance & Repair 102,500                16,932              16.52% 158,150              14,353                9.08%

Transfers/Debt ‐                         ‐                    ‐                 ‐                        ‐                     ‐                      

Contingency ‐                         ‐                    ‐                 ‐                        ‐                     ‐                      

Capital Outlay 7,942                    912                   0.00% 30,859                ‐                     0.00%

     Total Expenses  11,974,816          1,877,313        15.68% 12,521,682        1,953,966          15.60%

Detail Cash Flow Analysis ‐ Monthly Percentage of Budget Used

7

Division of Extended Learning

Page 15: Fs2012 october

2006-07 2007-08 2008-09 2009-10 2010-11 2011-12Academic 12,077,904 12,739,232 14,345,992 16,652,752 17,802,080 17,354,256

Technical 4,378,250 4,422,336 4,883,890 5,680,164 5,924,078 5,822,072

Continuing Education 2,091,365 1,847,195 1,810,761 1,880,857 1,914,445 1,798,940

Total Fundable Contact Hou 18,547,519 19,008,763 21,040,643 24,213,773 25,640,603 24,975,268

Source: Certified CBM004 & CBM00C.

8

HOUSTON COMMUNITY COLLEGEAnnual Fundable Contact Hours 

FY 2006-07 thru FY 2011-12

0

5000000

10000000

15000000

20000000

25000000

30000000

2006‐07 2007‐08 2008‐09 2009‐10 2010‐11 2011‐12

Continuing Education Technical Academic

+5.9%+15.1%

+10.7%+2.5%

‐2.6%

Page 16: Fs2012 october

HOUSTON COMMUNITY COLLEGEUnduplicated Headcount Comparison Semester‐To‐Semester (FY 2009‐10 thru FY 2012‐13)

Fall Semester (Unduplicated Enrollment ‐ All Students)*

Spring Semester (Unduplicated Enrollment ‐ All Students)

Summer Semester (Unduplicated Enrollment ‐ All Students)

* As of November 07, 2012.

9

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

-70

-60

-50

-40

-30

-20

-10 0 10 20 30 40 50 60 70 80 90

Spr 12

Spr 11

Spr 10

Census Day

First Class Day

Spr 12 Enrollment:‐5.9% (Spr12 to 11)‐1.4% (Spr12 to 10)

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000

45,000

50,000

-62

-52

-42

-32

-22

-12 -2 8 18 28 38 48 58 68

Sum 12

Sum 11

Sum 10

First Class Day

Census Day

Sum 12 Enrollment:‐0.0%  (Sum12 to 11)‐4.1% (Sum12 to 10)

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000-1

10

-100 -90

-80

-70

-60

-50

-40

-30

-20

-10 0 10 20 30 40 50 60 70

Fall 12

Fall 11

Fall 10Fall 12 Enrollment:

‐5.5%  (Fall12 to 11)‐1.9% (Fall12 to 10)

First Class Day

Census Day

Page 17: Fs2012 october

HOUSTON COMMUNITY COLLEGERevenues & Expenditures Comparison Year to Date Thru October 31, 2012

2009 Positions

Revenues Expenditures Rev H/(L) Exp

YTD Actuals Thru October 31, 2012 64,311,638           49,676,408          14,635,230       

YTD Actuals Thru October 31, 2011 67,610,952           57,445,514          10,165,439       

(3,299,315)            (7,769,106)          

10

 ‐

 10,000,000

 20,000,000

 30,000,000

 40,000,000

 50,000,000

 60,000,000

 70,000,000

Revenues Expenditures

Page 18: Fs2012 october

` HOUSTON COMMUNITY COLLEGEMonthly Revenues & Expenditures Comparison Year to Date By Month

Revenues SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 58,227,650  9,431,856 

2011‐2012 61,685,752  9,480,515  24,214,599  37,832,575 66,013,487 35,495,964 10,116,378 16,794,724  15,263,177 9,332,949 7,924,181 9,726,145

2009 Positions

Expenditures SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 28,324,834  24,699,442 

2011‐2012 37,698,782  23,302,047  20,581,833  17,164,427 19,407,583 18,185,253 18,965,252 39,130,360  18,696,899 18,586,628 21,489,075 18,505,226

11

 ‐ 5,000,000

 10,000,000 15,000,000 20,000,000 25,000,000 30,000,000 35,000,000 40,000,000 45,000,000 50,000,000 55,000,000 60,000,000 65,000,000 70,000,000

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐ 5,000,000

 10,000,000 15,000,000 20,000,000 25,000,000 30,000,000 35,000,000 40,000,000 45,000,000 50,000,000 55,000,000 60,000,000 65,000,000 70,000,000

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

Page 19: Fs2012 october

HOUSTON COMMUNITY COLLEGERevenues Comparison Year to Date Thru October 31, 2012 by Source

2009 Positions

State 

Appropriations Ad Valorem Taxes Tuition, Net Fees

Other Local 

Income* Extended Learning Grant Revenue Total Revenues

YTD Actuals Thru October 31, 2012 17,867,571  12,311 17,166,699 26,802,600 359,518 2,020,284 82,656 64,311,638

YTD Actuals Thru October 31, 2011 17,947,320  16,286 18,511,318 28,898,132 296,900 1,900,998 39,998 67,610,952

(79,749)  (3,975) (1,344,619) (2,095,532) 62,617 119,286 42,657 (3,299,315)

12

 ‐

 5,000,000

 10,000,000

 15,000,000

 20,000,000

 25,000,000

 30,000,000

StateAppropriations

Ad Valorem Taxes Tuition, Net Fees Other LocalIncome*

Extended Learning Grant Revenue

Page 20: Fs2012 october

HOUSTON COMMUNITY COLLEGEExpense Comparison Year to Date Thru October 31, 2012 by Source

2009 Positions

YTD Actuals Thru Faculty‐FT  Faculty‐PT

Librarian/

Counselor‐FT 

Librarian/

Counselor‐PT Staff‐FT Staff‐PT

Employee 

Benefits

Supplies Gen 

Exp Travel

Marketing 

Costs

Rental & 

Leases

Insurance/

Risk Mgmt

Contract 

Services Utilities

Other 

Departmental 

Expenses

Instructional & 

Other 

Materials

Maintenance & 

Repair

Transfers/

Debt Capital Outlay      Total Expenses 

 October 31, 2012  10,765,367  5,200,028  911,991  113,283  10,437,687  1,213,552  3,080,654  888,373  129,398  299,509  396,792  6,562,016  1,832,381  1,085,312  412,863  1,268,115  60,616  5,005,690  12,781  49,676,408 

 October 31, 2011  10,479,826  5,297,312  1,223,935  97,729  10,315,289  1,327,230  2,380,567  774,519  90,430  230,612  1,783,642  6,205,960  1,351,373  738,062  350,298  1,626,814  58,856  13,072,784  40,275  57,445,514 

285,541  (97,284)  (311,944)  15,553  122,398  (113,678)  700,087  113,854  38,968  68,896  (1,386,850)  356,056  481,009  347,251  62,565  (358,699)  1,760  (8,067,095)  (27,493)  (7,769,106) 

13

 ‐

 1,000,000

 2,000,000

 3,000,000

 4,000,000

 5,000,000

 6,000,000

 7,000,000

 8,000,000

 9,000,000

 10,000,000

 11,000,000

 12,000,000

 13,000,000

 14,000,000

 15,000,000

 16,000,000

 17,000,000

 18,000,000

 19,000,000

 20,000,000

 21,000,000

 22,000,000

 23,000,000

 24,000,000

 25,000,000

 26,000,000

 27,000,000

 28,000,000

 29,000,000

 30,000,000

Page 21: Fs2012 october

     Unrestricted  Auxiliary  Restricted  Total 

Unexpended 

Plant Renewal 

 Retirement of 

Debt 

Investment in 

Plant  Total 

Consolidation & 

Elimination  Total All Funds 

ASSETSCurrent Assets:

Cash &  cash equivalents 67,354,148$        9,371,308$        ‐$                         76,725,456$       1,421,844$         9,866,965            ‐$                          11,288,809$            ‐$                              88,014,265$           

Restricted cash & cash equivalents ‐                             ‐                           12,493,313       12,493,313        138,011,474      681,148               ‐                           138,692,622           ‐                                151,185,935          

Short term Investments ‐                             ‐                           ‐                          ‐                           ‐                           ‐                           ‐                           ‐                                ‐                                ‐                                

Accounts/Other receivable (net) 13,293,133          2,613,138           9,758,795          25,665,066        70,798                747,950               ‐                           818,748                   ‐                                26,483,814            

Deferred charges ‐                             669,701              ‐                          669,701              ‐                           ‐                           ‐                           ‐                                ‐                                669,701                  

Prepaids ‐                             76,674                ‐                          76,674                1,762,224           ‐                           ‐                           1,762,224                ‐                                1,838,898               

Total Current Assets 80,647,281          12,730,821        22,252,108       115,630,210      141,266,340      11,296,063         ‐                           152,562,403           ‐                                268,192,613          

Non‐current Assets:

Deferred charges, net ‐                             ‐                           ‐                          ‐                           3,548,100           ‐                           2,601,880           6,149,980                ‐                                6,149,980               

Restricted long‐term investments ‐                             ‐                           ‐                          ‐                           2,869,441           2,683,632            ‐                           5,553,073                ‐                                5,553,073               

Long‐term investments 10,984,386          ‐                           ‐                          10,984,386        ‐                           ‐                           ‐                           ‐                                ‐                                10,984,386            

Capital Assets, net ‐                             ‐                           ‐                          ‐                           71,886,315        ‐                           654,277,934      726,164,249           ‐                                726,164,249          

Total Non‐current Assets 10,984,386          ‐                           ‐                          10,984,386        78,303,856        2,683,632            656,879,814      737,867,302           ‐                                748,851,688          

Total Assets 91,631,667$        12,730,821$      22,252,108$      126,614,596$     219,570,196$     13,979,695$       656,879,814$     890,429,705$          ‐$                              1,017,044,301$      

LIABILITIESCurrent Liabilities:

Accounts payable 8,094,952             523,799              8,067,292          16,686,043        44,739                ‐                           ‐                           44,739                     ‐                                16,730,782            

Accrued liabilities 92,789                  2,871                   31,449                 127,109                1,442,493             558,933               ‐                             2,001,426                  ‐                                  2,128,535                 

Compensated absences 2,351,464             ‐                           ‐                          2,351,464           ‐                           ‐                           ‐                           ‐                                ‐                                2,351,464               

Funds held for others 17,527                  107,889              473,043             598,459              189,209              ‐                           ‐                           189,209                   ‐                                787,668                  

Deferred revenue ‐                             297,461              1,236,491          1,533,952           1,474,662           ‐                           (1,600,060)         (125,398)                  ‐                                1,408,554               

Notes payable‐current portion ‐                             ‐                           ‐                          ‐                           4,655,000           ‐                           2,595,000           7,250,000                ‐                                7,250,000               

Bonds payable‐current portion ‐                             ‐                           ‐                          ‐                           ‐                           ‐                           14,175,000        14,175,000             ‐                                14,175,000            

Capital lease obligations‐current ‐                             ‐                           ‐                          ‐                           ‐                           ‐                           ‐                           ‐                                ‐                                ‐                                

Total Current Liabilities 10,556,732          932,020$            9,808,275          21,297,027        7,806,103           558,933               15,169,940        23,534,976             ‐                                44,832,003            

Non‐current Liabilities:

Deposits ‐                             ‐                           ‐                          ‐                           ‐                           ‐                           ‐                           ‐                                ‐                                ‐                                

Notes payable ‐                             ‐                           ‐                          ‐                           146,206,719      ‐                           31,405,318        177,612,037           ‐                                177,612,037          

Bonds payable ‐                             ‐                           ‐                          ‐                           62,554,009        1,279,420            269,438,431      333,271,860           ‐                                333,271,860          

Capital lease obligations ‐                             ‐                           ‐                          ‐                           ‐                           ‐                           108,309,832      108,309,832           ‐                                108,309,832          

Total Non‐current Liabilities ‐                             ‐                           ‐                          ‐                           208,760,728      1,279,420            409,153,581      619,193,729           ‐                                619,193,729          

Total Liabilities 10,556,732$        932,020$            9,808,275$        21,297,027$       216,566,831$     1,838,353$         424,323,521$     642,728,705$          ‐$                              664,025,729$         

 Fund Balance‐ 

August 31, 2012 Unaudited  67,012,410          11,758,303         9,079,932            87,850,645          3,709,864             9,980,240            235,429,798        249,119,902             ‐                                  336,970,547            

Revenues Over Expenditures

     Unrestricted 14,062,525          40,498                14,103,023        14,103,023            

     Restricted 3,363,901          3,363,901           3,363,901               

     Net Investment in Plant     (706,497)             2,161,102            (2,873,504)         (1,418,899)              (1,418,899)             

Total Fund Balances 81,074,935$        11,798,801$      12,443,833$      105,317,569$     3,003,367$         12,141,342$       232,556,294$     247,701,003$          ‐$                              353,018,572$         

 Total Liabilities &  Fund Balances  91,631,667$        12,730,821$      22,252,108$      126,614,596$     219,570,197$     13,979,695$       656,879,815$     890,429,708$          ‐$                              1,017,044,301$      

    14 

PLANT & BOND FUNDS

Houston Community CollegeBalance Sheet By Fund

For Month Ended October 31, 2012

CURRENT & LOAN FUNDS

Page 22: Fs2012 october

TOTAL 

Unexpended Plant Funds

Total Unexpended Plant Fund Balances per Books (847,186)$           

  Spending/Encumbrances/Reserve for Future Use

‐ Encumbrances/PO Issued General Unexpended FY13 847,186               

Total  Plant Fund PO 847,186$             

     Anticipated Unexpended Plant Shortfall ‐$                         

HOUSTON COMMUNITY COLLEGEUnexpended Plant Fund Excluding 2004 CIP

Cash Position to October 31, 2012

15

Page 23: Fs2012 october

Description of Use

Total Budget to 

Date

Total 

Expenditures      

To Date

Encumbrances To 

Date Unexpended

DEFERRED MAINTENANCE FY05

System Administration 604,863$                604,863$                ‐$                              ‐$                             

Subtotal 604,863$               604,863$               ‐$                              ‐$                           

DEFERRED MAINTENANCE  FY06

System Administration 649,625$                649,624$                ‐$                              ‐$                             

Northwest College 412,743                412,743                ‐                               ‐                            

Coleman College 190,738                190,736                ‐                               ‐                            

Subtotal 1,253,106$            1,253,103$            ‐$                              ‐$                           

DEFERRED MAINTENANCE  FY07

System Administration 775,610$                775,610$                ‐$                              ‐$                             

Central College 373,917                373,917                ‐                               ‐                            

Northwest College 599,383                599,383                ‐                               ‐                            

Northeast College 1,059,733             1,059,733             ‐                               ‐                            

Southwest College 74,607                  74,607                  ‐                               ‐                            

Southeast College 38,742                  38,742                  ‐                               ‐                            

Coleman College 9,900                    9,900                    ‐                               ‐                            

Subtotal 2,931,893$            2,931,892$            ‐$                              ‐$                           

DEFERRED MAINTENANCE  FY08

System Administration 10,195$                  10,195$                  ‐$                              ‐$                             

Central College 478,637                478,637                ‐                               ‐                            

Northwest College 1,217,755             1,217,755             ‐                               ‐                            

Northeast College 494,886                494,886                ‐                               ‐                            

Southwest College 42,063                  42,063                  ‐                               ‐                            

Coleman College 73,813                  73,813                  ‐                               ‐                            

Subtotal 2,317,348$            2,317,349$            ‐$                              ‐$                           

OTHER GENERAL PROJECTS

Minor Construction 657,807$               657,807$               ‐$                              ‐$                           

System 11,555,483           10,990,789           564,694                 ‐                            

Central College 3,054,409             2,906,526             147,883                 ‐                            

Northwest College 4,060,039             4,044,540             15,499                   ‐                            

Northeast College 626,331                619,524                6,807                     ‐                            

Southwest College 1,103,100             1,000,997             102,103                 ‐                            

Southeast College 1,995,204             1,987,854             7,350 ‐                            

Coleman College 1,341,159             1,341,159             ‐                            

Subtotal 24,393,532$         23,549,196$         844,336$                ‐$                           

SURPLUS PROPERTY

Palmetto Property ‐ Purchase 495,154$               495,154$               ‐$                              ‐$                           

Dixie Property‐ Refund 20,000                  20,000                  ‐                            

 288 Property‐ Purchase 1,142,402             1,139,552             2,850                     ‐                            

Warehouse Property 12,966,619           12,966,619           ‐                               ‐                            

Subtotal 14,624,175$         14,621,325$         2,850$                    ‐$                           

Total Anticipated Uses 46,124,917$          45,277,728$          847,186$                ‐$                             

UNEXPENDED PLANT FUND PROJECTSas of October 31, 2012

16

HOUSTON COMMUNITY COLLEGE

Page 24: Fs2012 october

 

Total Budget 

to Date

Total 

Expenditures   

To Date

Encumbrances 

To Date

% of 

Expen‐ 

ditures Unexpended

% of 

Total 

BudgetSources:

Central College 2001A Bond 25,318,535$      

2003 Limited Tax Bond and Premium 150,748,497      

Actural Interest Earned 2003 Limited Tax Bonds 20,868,074         

2005 Limited Tax and Building Bond 1,875,000           

2003/2005 LTD Bond Issuance Cost (2,068,522)          

2006 Jr Lien Bond Std Revenue Bond 30,000,000         

Bond Issuance Cost (913,149)             

Actual Interest Earned 2006 Jr Lien Bonds 2,608,533           

Transferred to Fund 7305/Hayes Road (3,169,049)          

2008 Maintenance Tax Notes 56,912,320         

2008 MTN Bond Issuance Cost (1,056,912)          

Actual Interest Earned 2008 MTN 1,654,029           

2008 Sr. Lien Bond             1,714,953 

Transferred to Residual CIP Funds         (20,712,314)

Total Available with Reclassification 263,779,995$    

Uses:

Construction 119,626,029$     119,499,752$     126,277$              100% ‐$                          0%

CPMS PGAL  11,121,809          11,121,809          ‐                             100% ‐                             0%

Facility Planning 1,677,989            1,677,989            ‐                             100% ‐                             0%

Architect Fees and Engineering 7,604,912            7,505,762            99,149                  100% ‐                             0%

Other Costs including Bldg/Land Purchase 2,273,077            2,258,218            14,859                  100% ‐                             0%

Inspectors 890,000               890,000               ‐                             100% ‐                             0%

Design Standard 103,370               103,370               ‐                             100% ‐                             0%

Site Improvement and Infrastructure Development 52,562,059          51,540,329          1,021,730            100% ‐                             0%

IT Infrastructure Master Plan 29,728,464          29,038,477          689,987                100% ‐                             0%

Furniture and Fixtures 14,352,845          13,909,258          443,071                100% 516                       0%

Small Business 567,383               567,383               ‐                             100% ‐                             0%

Administrative Services 3,376,760            3,186,703            190,057                100% (0)                           0%

Material Testing 574,120               537,606               36,513                  100% ‐                             0%

Contingency for Construction 48,562                  0% 48,562                  100%

Surveying 471,813               460,552               11,260                  100% ‐                             0%

Design and Geotech 110,911               110,111               800                        100% ‐                             0%

Signage 70,000                  70,000                  100% ‐                             0%

Blue Light Security 126,000               115,200               10,800                  100% ‐                             0%

PGAL Website Development 181,208               181,208               ‐                             100% ‐                             0%

System Architect Furniture Consultant 11,367                  11,367                  100% ‐                             0%

Northline Demolition‐Pizza Hut 226,246               226,246               100% ‐                             0%

Police Cars 342,223               341,613               610                        100% ‐                             0%

Bering St. Property 50,687                  50,687                  100% ‐                             0%

General Repairs & Maintenance 2,079,239            2,079,239            100% ‐                             0%

Land Purchase 1,919,729            1,919,729            100% ‐                             0%

Amatuer Sports Complex ‐ Willie Gay Hall 2,235,067            2,213,648            18,119                  100% 3,300                    0%

Total Construction Cost 252,331,872$     249,616,259$     2,663,234$          100% 52,378$               0%

Note: Expenditures Not In Construction Schedule

Deferred Maintenance 5,000,000$          5,000,000$          ‐$                           100% ‐$                          0%

IT Development 6,448,123            6,448,122            ‐                             100% ‐                             0%

263,779,995$     261,064,381$     2,663,235$          100% 52,378$               0%

Anticipated Budget Shortfall/Surplus (0)                          

*Footnote on next page

HOUSTON COMMUNITY COLLEGE2004 CIP Projectsas of October 31, 2012

17

Page 25: Fs2012 october

2003/2005 Limited Tax Bonds 2003 2005 TotalBond counsel fees 150,000 57,000 207,000Underwriters' discount 814,813 57,000 871,813Insurance premium 558,764 558,764Financial advisory fee 205,391 68,081 273,472Rating agencies fees 114,350 16,000 130,350Printing costs 10,386 4,506 14,892CPA consent letter fee 1,500 1,500 3,000Verification fees 3,500 3,500Paying agent fee 300 5,432 5,732

1,855,504 213,018 2,068,522

2006 Jr Lien Revenue BondsBond counsel fees 79,500Underwriters' discount 509,509Insurance premium 117,904Financial advisory fee 137,910Rating agencies fees 54,850Printing costs 3,502CPA consent letter fee 1,500Verification fees 3,500Paying agent fee 4,974

913,149

2008 Maintenance Tax NotesBond counsel fees 63,500Underwriters' discount 342,526Insurance premium 498,600Financial advisory fee 95,105Rating agencies fees 47,100Printing costs 9,617Paying agent fee 463

1,056,912

18

HOUSTON COMMUNITY COLLEGE2004 CIP Projects Footnotes

as of October 31, 2012

Page 26: Fs2012 october

Total Budget to 

Date

Total 

Expenditures   

To Date

Encumbrances 

To Date Unexpended

Central ‐ San Jacinto:*

Construction Cost 1,241,868$         1,241,868$         ‐$                         

CPMS PGAL 111,440              111,440              ‐                         ‐                          

Facilities Space Programming 393,715              393,715              ‐                         ‐                          

Material Testing  ‐                           ‐                           ‐                         ‐                          

IT Infrastructure Capital Projects 10,000                5,687                  4,314                 ‐                          

Design Standards 3,904                  3,904                  ‐                          

  Total Central ‐ San Jacinto 1,785,007$          1,780,694$          4,314$               ‐$                          

Central ‐ Learning Hub/Science Bldg:*

Construction Cost 21,484,282$       21,455,534$       28,748$             -$ CPMS PGAL 1,967,801           1,967,801           ‐                          

Facilities Space Programming 148,096              148,096              ‐                         ‐                          

Architect and Engineering 1,242,506           1,242,506           ‐                          

Furniture, Fixtures & Equipment 2,049,869           2,019,706           30,163              ‐                          

Inspectors 187,000              187,000              ‐                          

Project Software 7,614                  7,614                  ‐                          

Design Standards 15,086                15,086                ‐                          

Site Infrastructure Improvements 5,693,396           4,979,400           713,994            ‐                          

IT Infrastructure Master Plan 2,751,121           2,726,528           24,593              ‐                          

Design Geotech 10,150                10,150                ‐                          

Material Testing  32,994                32,356                638                    ‐                          

Surveying  69,453                64,118                5,335                 ‐                          

Blue Light Security 18,000                16,200                1,800                 ‐                          

  Total Central ‐ Learning Hub/Science 

Bldg:*

35,677,368$        34,872,095$        805,271$           ‐$                          

NEC ‐ Learning Hub:*

Construction Cost 14,001,119$       14,001,119$       ‐                          

CPMS PGAL 1,187,440           1,187,440           ‐                          

Facilities Space Programming 145,889              145,889              ‐                          

Architect and Engineering 723,556              723,556              ‐                          

Furniture, Fixtures & Equipment 1,660,682           1,651,908           8,774                 ‐                          

Other Costs including Bldg/Land Purchase ‐                           ‐                          

Inspectors 205,000              205,000              ‐                         ‐                          

Project Software ‐                           ‐                          

Design Standards 9,015                  9,015                  ‐                          

Site Infrastructure Improvements 92,682                92,682                ‐                         ‐                          

IT Infrastructure Master Plan 1,250,254           1,249,836           418                    ‐                          

Design Geotech ‐                           ‐                          

Material Testing  131,870              123,607              8,263                 ‐                          

Surveying  71,081                71,081                ‐                          

  Total NEC ‐ Learning Hub 19,478,588$        19,461,133$        17,455$             ‐$                          

HOUSTON COMMUNITY COLLEGE2004 CIP Projects

as of October 31, 2012

19

 *Note 1  Budgets are adjusted as cost estimate changes; otherwise, budget is preliminary from inception. 

Page 27: Fs2012 october

Total Budget to 

Date

Total 

Expenditures   

To Date

Encumbrances 

To Date Unexpended

HOUSTON COMMUNITY COLLEGE2004 CIP Projects

as of October 31, 2012

NEC ‐ Science Engineering & Technology:*

Construction Cost 11,627,061$       11,626,428$       633$                   ‐$                         

CPMS PGAL 857,203              857,203              ‐                         ‐                          

Facilities Space Programming 52,058                52,058                ‐                          

Architect and Engineering 635,906              635,906              ‐                          

Furniture, Fixtures & Equipment 644,019              607,016              37,003              ‐                          

Other Costs including Bldg/Land Purchase 84,400                73,800                10,600              ‐                          

Inspectors ‐                           ‐                          

Project Software ‐                           ‐                          

Design Standards 6,818                  6,818                  ‐                          

Site Infrastructure Improvements 15,423,846        15,339,461        84,385              (0)                        

IT Infrastructure Master Plan 1,173,585           1,160,824           12,761              ‐                          

Design Geotech 28,500                28,500                ‐                          

Material Testing  95,465                95,465                ‐                         ‐                          

Surveying  15,960                10,035                5,925                 ‐                          

Blue Light Security 18,000                16,200                1,800                 ‐                          

  Total NEC ‐ Science Eng & Technology 30,662,821$        30,509,714$        153,107$           (0)$                       

NEC ‐ Pinemont:

CPMS PGAL 6,269$                 6,269$                 ‐$                        ‐$                         

Facilities Space Programming 71,292                71,292                ‐                         ‐                          

Other Costs including Bldg/Land Purchase

102,156              102,156             

‐                          ‐                            

Surveying  22,483                22,483                ‐                         ‐                          

  Total NEC ‐ Pinemont 202,200$              202,200$              ‐$                        ‐$                          

SEC - Felix Fraga (Drennan):*Construction Cost 12,419,860$       12,333,251$       86,609$             ‐$                         

CPMS PGAL 1,216,969           1,216,969           ‐                          

Facilities Space Programming 227,023              227,023              ‐                          

Architect and Engineering 850,383              835,511              14,872              ‐                          

Furniture, Fixtures & Equipment 1,007,615           977,469              30,146              ‐                          

Other Costs including Bldg/Land Purchase 62,466 62,466                ‐                          

Inspectors - ‐                          

Project Software - ‐                          

Design Standards 6,873                  6,873                  ‐                          

Site Infrastructure Improvements 5,981,474           5,959,525           21,949              ‐                          

IT Infrastructure Master Plan 1,279,923           1,268,405           11,518              ‐                          

Design Geotech 19,000                18,200                800                    ‐                          

Material Testing  150,272              137,662              12,610              ‐                          

Surveying  27,674                27,674                ‐                          

HUB/Small Business Program ‐                           ‐                           ‐                         ‐                          

HUB/Small Business Program ‐                           ‐                          

Bering St Property 50,687                50,687                ‐                          

Signage ‐                           ‐                          

Blue Light Security 18,000                16,200                1,800                 ‐                           Total SEC - Felix Fraga (Drennan):* 23,318,219$        23,137,915$        180,304$           ‐$                          

20

 *Note 1  Budgets are adjusted as cost estimate changes; otherwise, budget is preliminary from inception. 

Page 28: Fs2012 october

Total Budget to 

Date

Total 

Expenditures   

To Date

Encumbrances 

To Date Unexpended

HOUSTON COMMUNITY COLLEGE2004 CIP Projects

as of October 31, 2012

SEC ‐ Felix Morales:*

Construction Cost 3,653,331$         3,653,330$         ‐$                         

CPMS PGAL 667,905              667,905              ‐                          

Facilities Space Programming 62,181                62,181                ‐                          

Architect and Engineering 367,853              351,968              15,885              ‐                          

Furniture, Fixtures & Equipment 929,072              898,276              30,796              ‐                          

Inspectors ‐                           ‐                           ‐                         ‐                          

Project Software ‐                           ‐                           ‐                         ‐                          

Design Standards 3,117                  3,117                  ‐                         ‐                          

Site Infrastructure Improvements 98,015                96,070                1,945                 ‐                          

IT Infrastructure Master Plan 1,165,326           1,008,321           157,005            ‐                          

Design Geotech ‐                           ‐                           ‐                         ‐                          

Material Testing  10,009                5,808                  4,201                 ‐                          

Surveying  1,225                  1,225                  ‐                         ‐                          

  Total SEC ‐ Felix Morales 6,958,033$          6,748,200$          209,832$           ‐$                          

SEC ‐ Learning Hub:*

Construction Cost 16,555,351$       16,550,039$       5,312$               ‐$                         

CPMS PGAL 1,744,048           1,744,048           ‐                          

Facilities Space Programming 126,588              126,588              ‐                          

Architect and Engineering 875,415              875,415              ‐                          

Furniture, Fixtures & Equipment 2,006,664           1,839,187           167,476            ‐                          

 Other Costs including Bldg/Land Purchase  32,480                  28,221                  4,259                  ‐                            

Inspectors 258,000              258,000              ‐                         ‐                          

Project Software ‐                           ‐                          

Design Standards 9,367                  9,367                  ‐                          

Site Infrastructure Improvements 12,134,156        12,000,427        133,729            ‐                          

IT Infrastructure Master Plan 2,177,705           2,157,010           20,695              ‐                          

Administrative Services ‐                           ‐                          

Design Geotech 9,525                  9,525                  ‐                         ‐                          

Material Testing  122,370              115,883              6,487                 ‐                          

Surveying  144,094              144,094              ‐                          

Blue Light Security 18,000                18,000                - ‐                          

  Total SEC ‐ Learning Hub 36,213,761$        35,875,804$        337,958$           ‐$                          

21

 *Note 1  Budgets are adjusted as cost estimate changes; otherwise, budget is preliminary from inception. 

Page 29: Fs2012 october

Total Budget to 

Date

Total 

Expenditures   

To Date

Encumbrances 

To Date Unexpended

HOUSTON COMMUNITY COLLEGE2004 CIP Projects

as of October 31, 2012

SW ‐ Missouri City:*

Construction Cost 8,891,630$         8,891,630$         ‐$                         

CPMS PGAL 601,635              601,635              ‐                         ‐                          

Facilities Space Programming 194,111              194,111              ‐                          

Architect and Engineering 989,044              958,905              30,139              ‐                          

Furniture, Fixtures & Equipment 1,053,411           1,011,146           42,265              ‐                          

 Library & Bookstore  1,991,575           1,991,575           ‐                          

Inspectors ‐                           ‐                          

Project Software ‐                           ‐                          

Design Standards 4,999                  4,999                  ‐                          

Site Infrastructure Improvements 5,061,234           5,061,234           ‐                         ‐                          

IT Infrastructure Capital Projects 2,259,481           2,246,083           13,398              ‐                          

Design Geotech ‐                           ‐                          

Material Testing  ‐                           ‐                          

Surveying  48,311                48,311                ‐                          

Blue Light Security 18,000                16,200                1,800                 ‐                          

  Total SW ‐ Missouri City 21,113,430$        21,025,828$        87,602$             ‐$                          

SW ‐ West Loop Phase I:*

Construction Cost 9,033,809$         9,031,922$         1,887$               ‐$                         

CPMS PGAL 1,033,865           1,033,865           ‐                          

Facilities Space Programming 76,260                76,260                ‐                          

Architect and Engineering 718,694              718,694              ‐                          

Furniture, Fixtures & Equipment 2,166,396           2,154,214           12,182              ‐                          

Design Standards 8,170                  8,170                  ‐                          

IT Infrastructure Capital Projects 2,893,767           2,864,190           29,577              ‐                          

Design Geotech 22,116                22,116                ‐                          

Material Testing  21,141                21,140                1                        ‐                          

Surveying  14,995                14,995                ‐                         ‐                          

Exterior Signage 70,000                70,000                ‐                         ‐                          

Blue Light Security 18,000                16,200                1,800                 ‐                          

  Total SW ‐ West Loop Phase I 16,077,212$        16,031,765$        45,447$             ‐$                          

22

 *Note 1  Budgets are adjusted as cost estimate changes; otherwise, budget is preliminary from inception. 

Page 30: Fs2012 october

Total Budget to 

Date

Total 

Expenditures   

To Date

Encumbrances 

To Date Unexpended

HOUSTON COMMUNITY COLLEGE2004 CIP Projects

as of October 31, 2012

SW ‐ Learning Hub ‐ Stafford:*

Construction Cost 20,717,717$       20,714,629$       3,088$               ‐$                         

CPMS PGAL 1,727,234           1,727,234           ‐                          

Facilities Space Programming 180,778              180,778              ‐                          

Architect and Engineering 1,193,942           1,155,688           38,254              ‐                          

Furniture, Fixtures & Equipment 2,835,121           2,750,339           84,265              517                     

Inspectors 240,000              240,000              ‐                          

Project Software ‐                           ‐                          

Design Standards 15,845                15,845                ‐                          

Site Infrastructure Improvements 8,077,256           8,011,530           65,726              ‐                          

IT Infrastructure Capital Projects 2,611,069           2,535,820           75,249              ‐                          

Design Geotech 21,620                21,620                ‐                          

Material Testing  ‐                           ‐                          

Surveying  56,536                56,536                ‐                          

Blue Light Security 18,000                16,200                1,800                 ‐                          

  Total SW ‐ Learning Hub ‐ Stafford 37,695,119$        37,426,219$        268,382$           517$                    

System ‐ Network:

IT Infrastructure Capital Projects 12,162,330$       11,817,556$       344,774$           ‐                          

Administrative Services 3,376,760           3,186,703           190,057            ‐                          

PGAL Website Development 181,209              181,208              1                        ‐                          

HUB/Small Business Program 567,383              567,383              ‐                         ‐                          

 System Architect Furniture Consultant 

11,367                11,367               

‐                            

 Ft. Bend Library Inflation Cost Increase 

‐                          

‐                            

Northline Demolition‐Pizza Hut 226,246              226,246              ‐                          

Police Cars 342,223              341,613              610                    ‐                          

General Repairs & Maintenance 2,079,239           2,079,239           ‐                          

Land Purchase 1,919,729           1,919,729           ‐                          

Amatuer Sports Complex ‐ Willie Gay Hall 2,235,067           2,213,648           18,119              3,300                 

  Total ‐ System ‐ Network 23,101,553$        22,544,692$        553,559$           3,300$                 

Construction Contingency 48,562$               ‐$                           ‐$                        48,562                 

Subtotal Above 252,331,873$      249,616,258$      2,663,232$        52,378$               

100.00% 98.92% 1.06% 0.02%

EXPENDITURES NOT IN CONSTRUCTION SCHEDULE

Deferred Maintenance 5,000,000$         5,000,000$         ‐$                        ‐$                         

IT Development 6,448,123           6,448,122           ‐                         ‐                          

GRAND TOTAL 263,779,996$      261,064,380$      2,663,232$        52,378$               

100.00% 98.97% 1.01% 0.02%

23

 *Note 1  Budgets are adjusted as cost estimate changes; otherwise, budget is preliminary from inception. 

Page 31: Fs2012 october

 

Total Budget to 

Date

Total 

Expenditures to 

Date  Encumbrances  Unexpended

Sources:Transferred CIP Funds 20,712,314

Uses:

Central Learning Hub/Science Bldg:

Site Infrastructure Improvements 6,599,554$         76,954$                 168,284$              6,354,316$        

NEC ‐ Science Engineering & Technology:

Site Infrastructure Improvements 100,059 2,184 97,875                  ‐                         

SEC ‐ Learning Hub:

Site Infrastructure Improvements 1,992,932 ‐                             1,992,932             ‐                         

System ‐ Network:

IT Infrastructure Capital Projects 7,569,405 2,966,394            4,523,027             79,984              

Site Infrastructure Improvements 96,600 ‐                             96,600                  ‐                         

 

 Construction Contingency 1,163,695 ‐                             1,163,695         

Contingency 3,190,069           ‐                             3,190,069         

Total Construction Cost 20,712,314$       3,045,533$           6,878,718$           10,788,064$     

Anticipated Budget Shortfall/Surplus ‐                          

24

HOUSTON COMMUNITY COLLEGE SYSTEMResidual CIP Funds

as of  10/31/12

Page 32: Fs2012 october

Total Budget 

to Date

Total 

Revenues /  

Expenditures 

To Date

Encumbrances To 

Date Unexpended

Sources of funds:

Proceeds from 

2006 Tax Maintenance Notes 12,000,000$   

Discount (88,756)            

Bond Issuance Cost (256,244)          

Interest Income 835,338           

Funds Available 12,490,338$  

Uses of funds:

Site Infrastructure 341,092$          327,728$          13,364$                 ‐$                     

Project Management 450,479            450,479            ‐                              ‐                       

Construction 8,805,292         8,805,292         ‐                              ‐                       

Design Phase 1,117,820         1,117,820         ‐                              ‐                       

Architecture 17,822              17,822              ‐                       

Material Testing & Inspection 6,399                6,399                ‐                              ‐                       

Land/Demolition 420,541            420,541            ‐                              ‐                       

Survey 9,473                9,473                ‐                              ‐                       

Construction‐Maintenance 1,259,003         1,247,114         11,889                   ‐                       

Contingency 62,416              46,700              15,716            

Grand Total Uses 12,490,338$    12,449,368$    25,253$                 15,716$          

Net Available 0$                    

25

HOUSTON COMMUNITY COLLEGEMaintenance Tax Notes 2006 (Central Utility Plant Project)

as of October 31, 2012

 Note: Budgets are adjusted as contracts are awarded; otherwise, budget is preliminary from inception. 

Page 33: Fs2012 october

Total Budget to 

Date

Total Revenues 

/  Expenditures 

To Date

Encumbrances To 

Date Unexpended

Sources:

2008 Maintenance Tax Notes 39,780,489$     

2008 Maintenance Tax Notes‐Phase 1 Infrastructure 15,078,286      

Transferred to CIP Residual Fund (7170) (17,522,242)     

Interest Earned To date 1,677,987        

Funds Available for Projects 39,014,520$     

Uses:

Site Infrastructure Improvements 5,666,582$        5,162,973$       503,609$              0$                      

Architectural/Engineering Fees 165,537            151,654           13,883                  ‐                         

IT Infrastructure Master Plan 19,553,388       19,199,543      353,845                ‐                         

Furniture, Fixtures & Equipment 5,056,049         4,572,572        483,477                ‐                         

Material Testing 33,351               29,035              4,316                    ‐                         

Construction 5,437,915         5,381,526        56,389                  ‐                         

Construction Management  132,478            132,478           ‐                         

Campus Security 243,116            242,415           600                       101                   

Truck Driving School 99,200               99,200              ‐                         

Land 517,306            517,306           ‐                         

Energy  Services 8,860                 8,860                ‐                         

Design GEOTECH 5,189                 5,189                ‐                             ‐                         

Surveying 16,310               16,310              ‐                             ‐                         

Contracted Services 2,079,239         2,079,239        ‐                         

Residual Funds for Completion of CIP Projects ‐                          ‐                        ‐                             ‐                         

Total  39,014,520$      37,598,300$    1,416,119$           101$                  

Bond Issuance Cost:

Bond counsel fees 63,500$            

Underwriters' discount 342,526           

Insurance premium 498,600           

Financial advisory fee 95,105              

Rating agencies fees 47,100              

Printing costs 9,617                

CPA consent letter fee 463                   

Total 1,056,912$       

HOUSTON COMMUNITY COLLEGE SYSTEM 2008 Maintenance Tax Notes & Senior Lien Bonds

as of October 31, 2012

Fund 7203 

Fund 7203 ‐ Maintenance Tax Notes

26

Page 34: Fs2012 october

Total Budget to 

Date

Total Revenues 

/  Expenditures 

To Date

Encumbrances To 

Date Unexpended

Source:

2008 Senior Lien Bonds:

Southeast Workforce Project 14,300,000$     

  Emergency Preparedness 1,000,000        

Interest Earned To date 469,549           

Funds Available for Projects 15,769,549$     

Uses:

Operation and Maintenance 77,034               77,034              ‐                    

Major Repairs and Renovation 821,560            820,726           834                       ‐                    

South East Work Force Project 3,717,599         3,447,891        269,708                ‐                    

Land  Purchase (Rosalie Property) 2,314,967         2,314,967        ‐                    

Material Engineering and Testing 8,380                 3962 4,418                    ‐                    

Construction of Workforce Building 7,262,398         6,995,583        266,815                ‐                    

Residual Funds for All Projects 1,567,611         1,567,611        

15,769,549$      13,660,163$    541,775$              1,567,611$       

Bond Issuance Cost:

Bond counsel fees 123,267$          

Underwriters' discount 336,128           

Insurance premium 620,827           

Financial advisory fee 100,981           

Rating agencies fees 51,750              

Printing costs 5,880                

Paying agent fee 460                   

Verification fee 5,000                

Escrow agent fee 4,600                

1,248,893$       

27

Fund 7308 ‐ Senior Lien Bonds

HOUSTON COMMUNITY COLLEGE SYSTEM 2008 Maintenance Tax Notes & Senior Lien Bonds

Fund 7308as of October 31, 2012

Page 35: Fs2012 october

Total Budget to 

Date

Total Revenues 

/  Expenditures 

To Date

Encumbrances To 

Date Unexpended

Central 

San Jacinto Memorial 21,391,231$      7,703,630        3,247,345            10,440,257$     

J.B. Whitely Bldg.  4,540,000         669,110           1,134,290            2,736,600        

Theater One 1,699,500         159,101           48,311                  1,492,088        

Staff Instructional Services 1,100,000         153,621           35,334                  911,045           

Curriculum Innovation Center 190,000            ‐                        190,000           

Fine Arts Parking Structure 190,000            138,731           37,452                  13,818              

Crawford Annex 68,200               18,138              ‐                             50,062              

Learning Hub/Science Bldg. 27,500               15,953              ‐                             11,547              

Planned Parenthood Renovation 1,608,769         1,605,024        3,746                    ‐                         

  Total Central  30,815,200$      10,463,307$     4,506,477$           15,845,417$     

Northeast 

Automotive Tech. Training Ctr. 4,000,000$        630,213$          65,599$                 3,304,188$       

Pinemont  66,558               39,237              ‐                             27,321              

Codwell Hall  438,000            204,117           166,538                67,345              

Codwell Hall Shower (Temp) 150,000            ‐                        150,000           

Roland Smith Truck Driving Ctr.  140,000            54,406              ‐                             85,594              

Northline 120,000            11,636              2,789                    105,575           

Public Safety Institute 115,000            11,668              ‐                             103,332           

NE Science and Tech. Bldg 49,500               ‐                        49,500              

NE Learning Hub 47,500               6,309                ‐                             41,191              

  Total Northeast 5,126,558$        957,585$          234,925$              3,934,046$       

Southeast 

Angela Morales 599,000$           413,199$          ‐$                            185,801$          

Office City 38,500               ‐                        ‐                             38,500              

  Total Southeast 637,500$           413,199$          ‐$                            224,301$          

Southwest

Stafford Campus (7 Bldgs) 4,242,406$        3,927,204$       315,201$              ‐$                       

Scarcella Center 927,356            347,710           91,289                  488,357           

Alief 138,680            132,664           ‐                             6,016                

Academic Ctr Sienna Plantation 93,500               85,660              7,736                    104                   

Stafford Learning Hub 54,000               ‐                        54,000              

Applied Technology Center 50,000               1,715                ‐                             48,285              

Greenbriar Annex 30,000               22,033              414                       7,553                

  Total Southwest 5,535,942$        4,516,986$       414,641$              604,315$          

System

System Building  2,368,630$        1,599,627$       769,002$              ‐$                       

Teaching Enhancement Renovations 2,737,135         1,037,074        88,462                  1,611,599        

Surface Parking & Civil Infrastructure 2,400,000         1,308,031        308,982                782,987           

Parking Structure 2,394,235         2,286,034        108,201$              ‐                         

  Total System 9,900,000$        6,230,766$       1,274,646$           2,394,586$       

Grand Total 52,015,200$      22,581,843$    6,430,689$           23,002,665$     

HOUSTON COMMUNITY COLLEGE SYSTEM2010 Maintenance Tax Notes

as of October 31, 2012

28

Page 36: Fs2012 october

Description Date Issued

 Original Bond 

Amount

Principal 

Payments

Principal 

Balance

Principal & 

Interest FY12

Final Due 

Date Call Dates

Foot‐

note

2005 Senior Lien Revenue/Refunding Bonds 04/15/05 51,285,000 (13,540,000) 37,745,000 6,676,363 04/15/20 04/15/15 (A)

2006 Junior Lien Revenue/Refunding Bonds 11/01/06 72,815,000 (15,360,000) 57,455,000 6,274,230 04/15/30 04/15/16 (A)  (B)

2008 Senior Lien Revenue Bonds 05/14/08 54,540,000 (6,115,000) 48,425,000 4,075,100 04/15/30 04/15/18 (A)

2010 Senior Lien Revenue Bonds 07/29/10 27,250,000 (875,000)           26,375,000 2,124,275 04/15/31 04/15/20 (A) 

2011 Junior Lien Revenue Refunding Bonds 03/10/11 33,940,000 (2,350,000)       31,590,000 4,150,431 04/15/25 04/15/21 (A)

2011T Senior Lien Revenue Bond 11/15/11 16,000,000 16,000,000 388,800           04/15/21 11/15/13 (A)

2003 Limited Tax Bonds 12/01/03 144,155,000 (142,960,000) 1,195,000 782,175 02/15/14 (C)

2011 Limited Tax Refunding Bonds 10/20/11 109,490,000 109,490,000 5,308,300 02/15/28 02/15/21 (C)

2006 Maintenance Tax Notes 02/01/06 12,000,000 (2,660,000) 9,340,000 890,550 02/15/26 02/15/16 (C)

2008 Maintenance Tax Notes 03/01/08 54,975,000 (7,735,000) 47,240,000 4,171,426 02/15/28 02/15/18 (C)

2009 Maintenance Tax Notes 09/01/09 13,830,000 (1,445,000) 12,385,000 1,242,569 02/15/25 02/15/19 (C)

2010 Maintenance Tax Notes 07/29/10 47,645,000 (1,840,000)       45,805,000 3,998,400        02/15/29 02/15/20 (C)

2011 Maintenance Tax Notes 03/10/11 41,560,000 (1,295,000)       40,265,000 3,293,775 02/15/31 02/15/21 (C) 

2011A Maintenance Tax Notes 10/12/11 19,590,000 19,590,000 1,583,875 02/15/31 02/15/21 (C) 

PFC Series 2005A Lease Revenue Bonds 06/01/05 11,605,000 (2,485,000) 9,120,000 837,663 04/15/28 04/15/15 (A)

PFC Series 2005C Lease Revenue Bonds 12/01/05 19,155,000 (3,155,000) 16,000,000 1,313,456 04/15/30 04/15/15 (A)

PFC Series 2006 Lease Revenue Bonds 10/01/06 36,950,000 (5,135,000) 31,815,000 2,484,773 04/15/31 04/15/16 (A)  (D)

PFC Series 2007 Lease Revenue Bonds 02/01/07 58,885,000 (6,285,000) 52,600,000 4,321,500 04/15/31 04/15/17 (A) 825,670,000 (213,235,000) 612,435,000 53,917,660

Note: This schedule represents all bonds and maintenance tax notes with outstanding principal balances as of 10/31/12; 

             previously retired debt issues are not shown (i.e. 1997, 1998, 1999, 2001, 2001A, 2003 LTD, 2005 LTD)

Footnotes:

(A)  Funded from current operations, Fund 1110

(B)  Approximately $3.4 MM annually through 8/31/17 to be funded from student technology fees, Fund 8110; remainder from 

       current operations

(C)  Funded from real estate taxes, Fund 8300

(D) $1,329,772 of interest expense to be funded from real estate taxes

Schedule of Bonds and Maintenance Tax Notes

For the Month Ended October 31, 2012

Houston Community College

29

Page 37: Fs2012 october

3101‐3100 Main 

Leasing

3102‐Conference 

Training Center 3103‐HCC‐TV 

Auxiliary

3105‐HCCS ‐ PFC 

Leasing 3110‐Auxiliary

3201‐Cafe Club 

NEO 3100 Main

3202‐Fitness 

Center‐Central

3204‐Heinen 

Theater

3207‐

International 

Initiatives

3208‐Saudi 

Consulting 

Services 3209‐Qatar Subtotal

Fund Balance 8/31/12 16,586,942$       (744,125)$         36,165$           898,968$           (7,498,516)$        (1,362,924)$        (76,298)$            33,917                (82,495)                203,712             807,349        8,802,695        

FY2013 Revenue  896,969                  9,992                    ‐                           4,606                     969,391                  92,696                    3,358                     5,855                     23,333                    ‐                             1,280,510       3,286,711           

 Salaries  54,498                    52                          111,262                  43,819                    597                        480                        3,500                      979,980           1,194,189           

 Benefits  14,817                    4                            25,008                    10,539                    3                             154,773           205,145               

 Supplies Gen Exp  6,627                      1,678                    368,937                  1,230                      435                        394                        1,822                      963                  382,085               

 Travel  9,096                      1,489                      462                  11,047                 

 Marketing Costs  ‐                            

 Rental & Leases  446                        715                          380                          1,541                   

 Contract Services  81,931                    287,825                  655                        38,910             409,322               

 Utilities  43,103                    43,103                 

 Departmental Expenses  1,531,564               270                        ‐                        1,531,834           

 Instructional & Other Materials  ‐                            

 Maintenance & Repair  600                          215                          1,291                     2,817                      4,923                   

 Indirect Cost Expenditures  23,392                    23,392                 

 Exemptions and Waivers  ‐                            

 Capital Outlay  ‐                            

 Transfer  84,736                    84,736                 

Net Income /(Loss) FY13 610,656               7,812                  ‐                        4,606                  (1,365,231)          13,336                 2,324                  2,765                  13,705                 ‐                           105,421        (604,607)          

17,197,598         (736,313)            36,165             903,574             (8,863,747)          (1,349,588)          (73,974)              36,682                (68,790)                203,712             912,770        8,198,088        

*Discretionary Funds

30

HOUSTON COMMUNITY COLLEGE SYSTEMAuxiliary Budget By Fund

as of October 31, 2012

Auxiliary Funds*

Net Fund Balance 

Page 38: Fs2012 october

HOUSTON COMMUNITY COLLEGE SYSTEMAuxiliary Budget By Fund

as of October 31, 2012

3110‐ Student 

Vending 

Commission

3111‐Auxiliary 

Student 

Services

3112‐Auxiliary 

Student Athletic 

Fee Subtotal Grand Total

Fund Balance 8/31/12 1,197,891          172,750           1,584,968          2,955,608            11,758,303        

FY2013 Revenue  9,299                    470,264             351,179                830,742                  4,117,453           

 Salaries  700                        34,352                   35,052                    35,052                 

 Benefits  6,031                     6,031                      6,031                   

 Supplies Gen Exp  2,521                    63,252                49,270                   115,043                  115,043              

 Travel  136                        730                     10,558                   11,424                    11,424                 

 Marketing Costs  ‐                               ‐                            

 Rental & Leases  ‐                               ‐                            

 Contract Services  3,200                  3,835                     7,035                      7,035                   

 Utilities  ‐                               ‐                            

 Departmental 

Expenses 

2,750                    1,500                  4,250                      4,250                   

 Instructional & 

Other Materials 

‐                               ‐                            

 Maintenance & 

Repair 

‐                               ‐                            

 Indirect Cost 

Expenditures 

‐                               ‐                            

 Exemptions and 

Waivers 

‐                               ‐                            

 Capital Outlay  1,553                    5,250                  6,803                      6,803                   

 Transfer  ‐                               ‐                            

Net Income /(Loss) FY13 1,640                  396,332           247,133             645,105               40,498                

1,199,530          569,082           1,832,101          3,600,713            11,798,801        

*Funds can only be used for services related to students

31

Net Fund Balance 

Student Auxiliary Funds ‐ Restricted*

Page 39: Fs2012 october

Federal Grantor Perform‐ Federal

Pass‐through Grantor ance CFDA Total Budget Total AwardProgram Title Period Number Expenditures Amount Amount** Ends Starts

U. S. Department of Education

Direct Programs:

Higher Education ‐ Institutional Aid 5 yrs. 84.031A 17,417               214,275            1,542,133         9/30/2014 10/1/2009

TRIO ‐ Student Support Services 5 yrs. 84.042 57,202               436,682            2,078,155         8/31/2015 9/1/2010

TRIO ‐ Upward Bound ‐ Southeast 4 yrs. 84.047 2,575                 16,669               1,172,562         ^   8/31/2012 9/1/2007

TRIO ‐ Upward Bound ‐ Southeast 5 yrs. 84.047 35,872               291,335            1,465,615          8/31/2017 9/1/2012

TRIO ‐ Upward Bound ‐ Central 5 yrs. 84.047A 53,702               410,056            2,845,845         5/31/2017 6/1/2012

Astra Stem Grant 3 yrs. 84.120A 35,516               293,375            881,873            9/30/2014 10/1/2011

Vast Academy TPSID 5 yrs. 84.407A 72,342               292,577            2,498,250         9/30/2015 10/1/2010

Pass‐Through From:

Texas Educational Agency

Adult Education ‐ State Grant Program 1 yr. 84.002 740,607            5,084,289         5,542,104         6/30/2013 7/1/2012

Adult Education ‐ State Grant Program 1 yr. 84.002 13,003               96,974               102,000            6/30/2013 7/1/2012

University of St. Thomas

Higher Education ‐ Institutional Aid 5 yrs. 84.031C 151,262            212,731            3,243,025         9/30/2016 10/1/2011

 Texas Higher Education Coordinating Board 

Vocational Education ‐ Basic Grants to States 1 yr. 84.048 46,480               1,051,987         1,051,987         8/31/2013 9/1/2012

College Access Challenge Grant Program 1 yr. 4 mos. 84.378A 15,000               26,707               208,548            8/13/2012 4/6/2011

College Access Challenge Grant Program 1 yr.  84.378A 10,359               169,803            171,798            8/13/2013 8/14/2012

Total Department of Education 1,251,337$        8,597,461$        22,803,895$     

U.S. Department of Agriculture

Direct Programs:

Hispanic Serving Institutions Education Grants 2 yrs. 10.223 2,105                 36,414               298,538            ^   8/31/2013 8/1/2009

Hispanic Serving Institutions Education Grants 2 yrs. 10.223 (0)                        26,428               244,000            ^   8/14/2013 8/15/2010

    Hispanic Serving Institutions Education Grants 2 yrs. 10.223 4,392                 135,610            445,000            ^   8/31/2013 9/1/2010

Hispanic Serving Institutions Education Grants 2 yrs. 10.223 23,515               202,726            245,000            8/31/2013 9/1/2011

Pass‐Through From:

Texas A & M University‐Corpus Christi 2 yrs 10.223 2,980                 30,435               48,700               ^   8/31/2013 9/1/2010

Total Department of Agriculture 32,992$             431,613$           1,281,238$       

* Scholarship grants are not included in this schedule.

** Award amount for the total grant period.  For example, if grant is for three years, the award amount will cover the three years.

^ No Cost Extension

32

HOUSTON COMMUNITY COLLEGE

as of October 31, 2012

Date Grant

Schedule of Federal Awards *

FY12 ‐ 13

Page 40: Fs2012 october

Federal Grantor Perform‐ Federal

Pass‐through Grantor ance CFDA Total Budget Total Award

Program Title Period Number Expenditures Amount Amount** Ends Starts

U.S. Department of Housing and Urban Development

Direct Programs:

Pass‐Through From:

Child Care Council of Greater Hous. Inc

Community Development Block Grant‐Entitlement Grant 1 yr 14.218 5,416                 3,976                 32,000               ^ 12/31/12 8/1/2011

Total Department of Housing And Urban Development 5,416$               3,976$               32,000$            

Department of Labor

DOL‐Logistics Technician Training 3yrs. 33,492$             159,097            327,404            6/30/2013 7/1/2010

Pass‐Through From:

Texas Workforce Commission

Recovery ‐ WIA Dislocated Worker Formula Grant 1 yr. 17 8,415 61,804 243,163 9/30/2012 7/1/2011

Total Department of Labor 41,907$             220,901$           570,567$          

Department of State

Pass‐Through From:

Northern Virginia Community College 1 yr 19 12,407               73,538               109,830            5/31/2013 3/8/2012

Total Department of State 12,407$             73,538$             109,830$          

National Science Foundation

Direct Programs:

 Education and Human Resources 4 yrs. 47.076 4,793                 64,204               423,300            1/31/2013 2/15/2009

Pass‐Through From:

University of Houston System

Education and Human Resources 5 yrs. 47.076 2,400                 25,212               190,000            8/31/2013 9/1/2011

Total National Science Foundation 7,193$               89,415$             613,300$          

* Scholarship grants are not included in this schedule.

** Award amount for the total grant period.  For example, if grant is for three years, the award amount will cover the three years.

33

as of October 31, 2012

HOUSTON COMMUNITY COLLEGE

Schedule of Federal Awards *

Date Grant

FY12 ‐ 13

Page 41: Fs2012 october

Federal Grantor Perform‐ Federal

Pass‐through Grantor ance CFDA Total Budget Total Award

Program Title Period Number Expenditures Amount Amount** Ends Starts

U. S. Department of Energy

Energy Sector Grant (SECO) 8 mos 81.041 37,180               63,836 460,480 ^  9/30/2012 5/10/2010

Solar Energy Technical Program 13 mos 81.087 24,776 591,069            750,000            12/30/14 11/1/2012

Total U. S. Department of Energy 61,956$             654,905$           1,210,480$       

U. S. Department of Health and Human Services

Direct Programs:

Head Start 5 yrs. 93.600 15,204 34,617               936,660            9/29/2013 9/30/2008

Head Start 5 yrs. 93.600 8,791 187,332            936,660            9/29/2013 9/30/2008

Pass‐Through From:

Texas Education Agency

Temporary Assistance for Needy Families 1 yr. 93.558 10,178               10,200               208,614            8/31/2012 9/1/2011

Temporary Assistance for Needy Families 1 yr. 93.558 24,243               244,749            244,749            8/31/2013 9/1/2012

YMCA of Greater Houston

Refugee and Entrant Assistance ‐ Targeted Assistance Grants 1 yr. 93.584 21,048               82,578               374,938            9/30/2012 10/1/2011

Refugee and Entrant Assistance ‐ Targeted Assistance Grants 1 yr. 93.584 14,170               85,527               374,938            9/30/2013 10/1/2012

Pitt Community College

Health Information Tech Professionals 2 yrs. 93.721 62,347               461,664            1,287,568         4/1/2013 4/2/2010

University of Texas at Austin

Block Grants for Prevention and Treatment of Substance Abus 1 yr. 93.959 ‐                           9,015                 22,000               9/29/2012 9/30/2011

Total Department of Health and Human Services 155,980$           1,115,681$        4,386,127$       

U. S. Department of Homeland Security

Direct Programs:

 Homeland Security 2 yrs. 97.062 5,090                 58,856               250,000            ^ 12/31/12 9/1/2010

Total Department of Homeland Security 5,090$               58,856$             250,000$          

Total  Federal Financial Assistance 1,574,278$        11,246,346$      31,257,437$     

* Scholarship grants are not included in this schedule.

**Award amount for the total grant period.  For example, if grant is for three years, the award amount will cover the three years.

^ No Cost Extension

HOUSTON COMMUNITY COLLEGE

Schedule of Federal Awards *

as of October 31, 2012

FY12 ‐ 13

34

Date Grant

Page 42: Fs2012 october

Perform‐

ance Total Budget Total Award

Program Title ‐ State Grantor Period Expenditures Amount Amount** Ends Starts

Texas Education Agency

Adult Education 1 yr. 24,620$             24,615$             1,165,635$        8/31/2012 9/1/2011

Adult Education 1 yr. 194,735            1,165,635         1,165,635         8/31/2013 9/1/2012

Drop‐Out Recovery Program 18mos 960                     43,998               194,000            2/28/2013 8/1/2011

Drop‐Out Recovery Performance Pay 1 yr. 9,679                 181,750            181,750            until expended 6/1/2011

Temporary Assistance for Needy Families 1 yr. 16,311               16,869               111,445            8/31/2012 9/1/2011

    Temporary Assistance for Needy Families 1 yr. 14,578               131,283            131,283            8/31/2013 9/1/2012

       Total Texas Education Agency 260,882$           1,564,151$        2,949,748$       

Texas Higher Education Coordinating Board

Adult Basic Education Innovation Grant 1 yr. 58,400$             158,314            500,000            8/31/2013 9/1/2012

Collegiate G‐Force Mentorship 1 yr. ‐                           27,148               50,000               8/31/2013 9/1/2009

First Year Experience 13 mos. 4,952                 8,709                 50,000               until expended 7/18/2011

Nursing Shortage Reduction Program 4 yrs. ‐                           112,280            157,314            8/31/2014 9/1/2010

Nursing Shortage Under 70 Program 1 yr. 616                     383,891            383,891            8/31/2013 9/1/2012

Rider 58 ATCP School Grant 8 1/2 mos. ‐                           13,960               46,360               until expended 12/18/2009

Pass‐Through From:

University of Tex Health Science Center

Navigator Grant 1 yr. 14,213               51,452               129,195            ^ 11/30/2012 6/1/2011

       Total Texas Higher Education Coordinating Board 78,181$             755,754$           1,316,760$       

Texas Workforce Commission

Skills Development ‐ Skills for Small Business Initiatives 1 yr. ‐                           18,791               20,000               5/31/2013 6/1/2012

The Methodist 14 mos. 2,337                 902,965            902,965            10/31/2013 8/20/2012

Pass‐Through From:

       Total Texas Workforce Commission 2,337$               921,756$           922,965$          

Total State Financial Assistance 341,401$           3,241,660$        5,189,473$       

* Scholarship grants are not included in this schedule.**Award amount for the total grant period.  For example, if grant is for three years, the award amount will cover the three years.

Date Grant

as of October 31, 2012

Schedule of State Awards *

FY12 ‐ 13

35

HOUSTON COMMUNITY COLLEGE

Page 43: Fs2012 october

Program Title ‐ Private Grantor Period Expenditures Budget Award Amount** Ends Starts

21st Century FY 12 10 mos. ‐                           1                         984                    10/31/2012 1/3/2012

Achieving the Dream ‐ Intiative 1 yr.‐cont. ‐                           9,433                 20,000               until expended 12/1/2009

Achieving the Dream ‐ Gates Foundation 3 yrs. 25,087               262,135            743,000            ^12/31/2012 7/1/2009

Adult Education/We Can Work 1 yr. ‐                           ‐                         11,500               until expended 1/1/2010

American Chemical Society 8 mos 70                       248                    500                    until expended 9/1/2011

AT&T High School Success Grant 1 yr. 7 mos. ‐                           25,216               35,000               until expended 1/31/2010

Bank of America  2 yrs. ‐                           316                    50,000               until expended 5/1/2008

Baylor Summer Interns 1 yr. ‐                      1,638                 60,000               until expended 5/1/2010

Brown Foundation 1 yr.‐cont. ‐                      ‐                         100,000            until expended 2/1/2008

Bulletproof Vest Partnership Program 1 yr.‐cont. ‐                      ‐                         5,345                 until expended 9/1/2004

Capital Idea project 1 yr. 1,609                 73,794               341,000            until expended 8/1/2010

Carnegie FDTN 1 yr 4,501                 30,901               67,500               12/31/2012 1/1/2012

Citibank ‐ College Connection Program 1 yr. ‐                      20,475               41,718               until expended 8/15/2007

Civic Ventures 1 yr. 1 mo. ‐                      1,246                 25,000               until expended 7/1/2010

Dow Male Minority Initiative Summer Prog. 1 yr. ‐                      12,588               23,986               1/2/2013 1/2/2012

Early College High School (Southeast) ‐ Gates/Dell 5 yrs. ‐                           6,779                 400,000            until expended 6/10/2005

Financial Empowerment Strat. Student Success 2 yrs. 1,181                 60,808               63,050               12/31/2013 1/1/2012

Goldman Sachs Grant ‐ Phase I 5 yrs. 125,856            765,458            1,786,121         5/31/2016 1/3/2011

Gulf Coast Pass 3 yrs. 8,754                 227,625            318,750            12/31/2014 1/1/2012

Hammill FDTN ‐ Veterans Grants 2 yrs. ‐                           11                      18,191               until expended 9/1/2010

Houston Endowment Grant 3 yrs. ‐                           814                    267,000            until expended 11/16/2005

Houston Pathways Initiative 2 yrs. 15,054               345,471            1,580,000         8/31/2013 3/26/2009

Interlocal Metro (PSI) 10 yrs. ‐                           45,000               200,000            8/23/2017 8/23/2008

Interlocal Stafford ‐ City of Stafford 1 yr. 6,400                 71,986               149,011            until expended 10/1/2010

KBR Veterans Orientation 1 yr.‐cont. ‐                           5,540                 19,685               until expended 9/1/2008

Kresge Fdtn‐Coordinator/Evaluation 1 yr. 10,681               17,221               82,450               until expended 9/1/2011

Kresge Fdtn‐Parent Academy 1 yr. 1,887                 40,254               89,320               until expended 9/1/2011

Kresge Fdtn‐Veterans Grant 1 yr. 17,972               51,298               128,230            until expended 9/1/2011

MDRC ‐ Learning Community Demonstration Grant ‐ Northeast 4 yrs. ‐                           26,495               60,233               until expended 11/1/2007

MDRC ‐ Learning Community Demonstration Grant ‐ Southeast 4 yrs. ‐                           738                    75,000               until expended 11/1/2007

MDRC ‐ Learning Community Demonstration Grant ‐ Central 4 yrs. ‐                           385                    33,000               until expended 11/1/2007

Metlife Caregiving for Older Americans 1 yr.‐cont. ‐                           18,012               23,855               until expended 7/1/2007

Microsoft Elevate America 1 yr. ‐                           31,985               34,969               3/20/2013 3/20/2012

* Scholarship grants are not included in this schedule.

** Award amount for the total grant period.  For example, if grant is for three years, the award amount will cover the three years.

FY12 ‐ 13

36

HOUSTON COMMUNITY COLLEGE

Schedule of Local Government and Private Awards *

as of October 31, 2012

Page 44: Fs2012 october

Program Title ‐ Private Grantor Period Expenditures Budget Award Amount** Ends Starts

Mobile Go Center ‐ Valero 1 yr.‐cont. ‐                           494                    7,293                 until expended 9/1/2007

National Articulation & Transfer Network Council(NATN) 1 yr.‐cont. ‐                           29,273               29,273               until expended 4/1/2005

North Forest GED Preparation 3 mos 241                     6,799                 25,000               until expended 10/1/2011

St. Luke's Episcopal Health Charities Immunization Fellowship 2 yrs. ‐                           4,178                 142,650            until expended 9/10/2008

Susan B Komen Breast Cancer Initiative 1 yr. ‐                           6,610                 123,230            until expended 4/1/2010

Texas Pioneer Foundation Grant 1 yr. 162                     2,851                 23,117               12/31/2012 1/26/2012

Vast Job Developer 1 yr. 1,380                 20,299               94,898               until expended 11/1/2009

Verizon Foundation Grant 1 yr. ‐                           510                    12,510               until expended 1/1/2010

Walmart ‐ Minority Male Initiative 1 yr. ‐                           25,215               40,000               until expended 9/1/2009

Washington Mutual 1 yr.‐cont. ‐                           16,717               31,700               until expended 9/1/2006Total Private Financial Assistance 220,835$           2,266,817$        7,384,069$       

* Scholarship grants are not included in this schedule.

** Award amount for the total grant period.  For example, if grant is for three years, the award amount will cover the three years.

37

         HOUSTON COMMUNITY COLLEGE ‐ Schedule of Local Government and Private Awards *

Schedule of Local Government and Private Awards * continued

as of October 31, 2012

FY12 ‐ 13

Page 45: Fs2012 october

CHANCELLOR

1         

DEPUTY CHANCELLOR

12       

VICE CHANCELLOR INSTRUCTION

2         

VICE CHANCELLOR STUDENT SUCCESS

6         

VICE CHANCELLOR INFORMATION TECHNOLOGY

1         

New Postions

Transcript Evaluator

Replacement‐External ‐        

‐        

NewPosition‐Internal

‐        

NewPosition‐External 4       

Interim ‐           

Leslie Dye

Randi Sprouse

‐        

Kimberly Davis Oct

New Position‐Hired External

1       

Application Dev

Instructional Designer

Dir., Outreach & Student Development

Replacement‐Internal

Scott Godley

NewPosition‐External

New Position‐Hired External

1       

NewPosition‐Internal NewPosition‐External1       

Larke Clishe

Mona Terrell Registrar

Outreach & Student Dev

Transcript Evaluator

Workforce Initiatives Program Manager

New Position‐Hired External

Replacement‐External

Oct

Instructional

Registrar

Transcript Evaluator

Henry Thomas

Oct

Transcript Evaluator

6       

Repl Shantay Grays‐Hired External

4        2       Replacement‐Internal

New Position‐Hired External

Paul Donaldson

NewPosition‐Internal

Sep     

New Position‐Hired External

Oct

Registrar

VC Instr

Wanda Taft

Interim

Repl David Lin‐Hired Internal

Interim ‐           Deputy Chancell

Student Information Svcs Advisor Repl Laura Collins‐Hired External Sep     

Antonio Hill

Oct

Oct

Oct

Registrar

Repl Deshaunta Stewart‐Hired Internal

Aracelia Saucedo

Interim Dir., Resource & Economic Dev New Position‐Budget 12‐13‐Hired Internal

OctPolice Department

Repl John Chen‐Hired External‐TempManagerHR‐Compensation

James Lindsey

Oct

Houston College Community

2012‐2013 Positions

Employee Name Department Month

SepBarlett Sheinberg Resource & Economic Dev

CommentsJob Title

Interim 1          ‐         NewPosition‐External‐         ‐        

Edwin Johnson Police Department

My'Keshia Robinson

Ules Harris

Executive Secretary

Police Department

Oct

Security Officer Repl Kenneth Bridges‐Hired External

Oct

NewPosition‐Internal ‐        Replacement‐InternalChancellor Replacement‐External

Patricia Thompson

Sep

Police Department Corporal Repl Timothy Ramirez‐Hired Internal

Repl Willie Rostan‐Hired External Oct

Repl Anthony Maxie‐Hired Internal

Repl Alice Binkley‐Hired Internal

Security Officer

Maria Alarcon

Sep

Police Department Corporal New Position‐Budger 11‐12‐Hired Internal Sep

Police Department

Shirley Voisin

Repl Victor Fisher‐Hired External

Police Department

Tobin Anderson

Navidad Martinez

Sep

Corporal

Oct

Corporal New Position‐Budger 11‐12‐Hired Internal

Security Officer Repl Grayland Jones‐Hired External

Repl Majid Iqbal‐Hired ExternalPolice Department Security Officer

Accounts Payable Accounting Specialist

Business Affairs

Police Department

Security OfficerKatherine McCabe

Repl Norma Jackson‐Hired Internal

Oct

NewPosition‐InternalReplacement‐ExternalVCSS

SepSystem Analyst

2       ‐         ‐           Replacement‐Internal

‐           ‐        VCIT ‐        Replacement‐ExternalReplacement‐Internal NewPosition‐External Interim

38

‐        

Page 46: Fs2012 october

CENTRAL

4         

NORTHWEST

13       

NORTHEAST

9         

New Postions

Construction

Oct

Repl Mallikarjun Shintri‐Hired External‐Temp Oct

Oct

COO

New Position‐Hired External

NewPosition‐External 1       

Dean Instruction

Repl Samuel sannl‐Hired External

Repl Bonnie Gallup‐Hired External‐Temp

2       

NORTHEAST

Technician Services

Student Services

Sep

William Nicholson

Oct

Thomas Tankersley

Sep

Northwest

Bharat Sutaria

Nellie Bradley

Repl Carlana Brooks‐Hired External‐Temp

Fine Arts

Admissions

1          Interim

Instructor

Steven Cohan

Sep Eva Foster English

Repl Kimberly Crocker Montgomery‐Hire External‐Temp

Oct

Senior Advisor Oct

Student Life Coordinator

Student Services

Instructor

‐        

Oct

Repl Joaquin Torres‐Hired External‐Temp

1       

Sep

Ronald Dewlen

Instructor Repl Homer Stewart‐Hired External‐Temp

Retention Specialist Repl Joseph Willis‐Hired Internal

Lesley Savoy‐Green Enrollment Services AssociateStudent Services Repl Alonia Whitmore‐Hired Internal

New Position‐Budget 12‐13‐Hired Internal

Instructor

Betty Keller

Repl John Jagdish‐Hired External‐Temp

Office Manager

Sep

Sep

David Jones

Instructor

SepIfeanyi Oramulu

Replacement‐Internal Replacement‐External3        5        NewPosition‐Internal ‐           1        Interim‐        NewPosition‐External

Hosein Tahvillian Electronic Engineering

NewPosition‐Internal

Repl Barbara Smith‐Hired Internal

Student Services Oct

Nicki Norman

Electronic Engineering Instructor Repl Nicky Haddock‐Hired External Sep

Repl Pratap Talusani‐Hired External

Student Services

Student Services

Advising Manager

Technology

Technology

‐           

Hardware/Software Technician

Repl Rima Adil‐Hired External‐Temp

Instructional

Sep

Replacement‐Internal InterimReplacement‐External

Repl Lois Avery‐Hired External

Khansaa Almansor

Sep 

10    

Rima Adil

Repl Manhal Chbat‐Hired External‐Temp

1       

Testing AssociateInstruction‐Testing

Public Relations

Oct

Instructor

New Position‐Budget 12‐13‐Hired External

Laleh Golestani

InstructorEngineering

Enrollment Service Assistant

Sandra Brooks Enrollment Service Assistant Repl Makeba Brown‐Hired External‐Temp

Sep 

NewPosition‐External 1       

Christine Moore

Instructor

Director of Public Relations

Student Services Interim Dean of Student Dev

Oct

Oct

Repl Johnny Watson‐Hired External‐Temp

Cashier II

Paul Brady

Anthony Hilliard

Central NewPosition‐Internal

Sep 

Anika Chowdhury

Repl Nellie Bradley‐Hired Internal‐Temp

Accounting

New Position‐Budget 12‐13‐Hired Internal

Sep 

Replacement‐Internal ‐        

Community Outreach CoordinatorCOO

Lusinda Eshelman

Sep 

Replacement‐External

Biology

Repl Cheryl Johnson‐Hired Internal

OctDora Whiteside

Repl Denny Smith‐Hired ExternalSonya Sneed

Houston College Community

2012‐2013 Positions

Employee Name Department Job Title Comments Month

Student Services ADA Counselor

Jason Wilson

39

James Connery

Repl Stella Villarreal‐Hired External‐Temp

Instructor

Student Services

Page 47: Fs2012 october

SOUTHWEST

5         

SOUTHEAST

3         

COLEMAN

4          

EXTENDED LEARNING, DIVISION OF‐          

Adm. Totals Replacement‐Internal Replacement‐External NewPosition‐Internal NewPosition‐External Interim 22       

College Totals Replacement‐Internal Replacement‐External NewPosition‐Internal NewPosition‐External Interim 38       

Grand Total Replacement‐Internal Replacement‐External NewPosition‐Internal NewPosition‐External Interim 60       

Over all Total

New Postions

Micalyn Flagg

Jose Cruz

Kelli Caraway

COO

Ashley Nichols

Daniel Guzman

Southeast

Southwest

Christine Moore

Brandi Gaza

Oct

Instructor

Senior Advisor

1        ‐        NewPosition‐External3        NewPosition‐Internal

Repl Adballah Cherif‐Hired External‐TempLorraine Donovan

Student Dev/Advising

Oct

‐           

Oct

New Position‐Hired External

Financial Aid

Nancy Garcia

Christy Muniz

Replacement‐External

11     33     6        8        2          

3        1          

NewPosition‐Internal 1        NewPosition‐External

‐         NewPosition‐Internal ‐         NewPosition‐External ‐         Interim ‐           

5        4       

2        5        1          6       

Interim ‐           2       

Ex. Learning

‐        

Replacement‐Internal

Replacement‐External

‐        

1       

Replacement‐External

60    

25    

Replacement‐InternalColeman

8       

Instructor

Interim ‐           

SepChlinical Simulation Lab Technician

Caroline Couto‐Ortiz

Charmaine Lewinson‐Evans

Repl Verlicia Pope‐Hired External

Student Services

‐        Replacement‐Internal

Repl Sharon McCowan‐Hired External

Health Science SepNew Position‐Budget 12‐13‐Hired ExternalDental Hygiene Operations Assistant

Simulation Center

Sep

Sep

3       

Oct

Advisor

‐        Replacement‐External

Natural Sciences

NewPosition‐Internal

Vocaitonal Nursing

‐        

Instructor

New Position‐Budget 12‐13‐Hired Internal

NewPosition‐External

Repl Pearlie Watts‐Hired ExternalVocaitonal Nursing

Instructor

1       Replacement‐Internal

Secretary II

Repl Vivian Flores‐Hired External

Senior Advisor New Position‐Budget 12‐13‐Hired Internal

Repl Margie Ricks‐Hired External‐Temp

Financial Aid Associate

Interim

English

Oct

OctStudent Dev/Advising

Academic

Oct

Sep

New Position‐Budget 12‐13‐Hired Internal

2012‐2013 Positions

Employee Name Department Job Title

Houston College Community

Campus Service Technician Repl Belinda Defalco‐Hired Internal

Comments Month

40

Page 48: Fs2012 october

HOUSTON COMMUNITY COLLEGEFTE Comparison Year‐To‐Date Thru October 31, 2012 by Type(Full‐Time Employee Equivalent) 

FACULTY FTE

Faculty SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 1,361    1,514   

2011‐2012 1,451    1,582    1,598    1,564    823       1,530    1,573    1,598    1,576    1,003    1,098    955      

STAFF FTE

Staff/Lib/Cou SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 1,401    1,426   

2011‐2012 1,429    1,415    1,425    1,327    1,407    1,429    1,396    1,404    1,410    1,397    1,391    1,429   

F

T

E

F

T

E

41

 ‐

 200

 400

 600

 800

 1,000

 1,200

 1,400

 1,600

 1,800

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 200

 400

 600

 800

 1,000

 1,200

 1,400

 1,600

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

Page 49: Fs2012 october

CENTRAL COLLEGEFTE Comparison Year‐To‐Date Thru October 31, 2012 by Type(Full‐Time Employee Equivalent) 

FACULTY FTE

Faculty SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 238       270      

2011‐2012 254       293       296       293       159       279       298       300       291       184       204       178      

STAFF FTE

Staff/Lib/Cou SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 155       159      

2011‐2012 161       158       165       145       155       163       157       157       158       156       154       161      

42

F

T

E

F

T

E

 ‐

 50

 100

 150

 200

 250

 300

 350

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 20

 40

 60

 80

 100

 120

 140

 160

 180

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

Page 50: Fs2012 october

COLEMAN COLLEGEFTE Comparison Year‐To‐Date Thru October 31, 2012 by Type(Full‐Time Employee Equivalent) 

FACULTY FTE

Faculty SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 108       107      

2011‐2012 115       112       113       109       82          109       107       110       110       99          98          84         

STAFF FTE

Staff/Lib/Cou SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 56          55         

2011‐2012 58          58          59          55          56          58          55          55          57          54          54          55         

F

T

E

F

T

E

43

 ‐

 20

 40

 60

 80

 100

 120

 140

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 10

 20

 30

 40

 50

 60

 70

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

Page 51: Fs2012 october

NORTHWEST COLLEGEFTE Comparison Year‐To‐Date Thru October 31, 2012 by Type(Full‐Time Employee Equivalent) 

FACULTY FTE

Faculty SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 281       310      

2011‐2012 267       292       293       307       155       323       330       334       335       198       224       190      

STAFF FTE

Staff/Lib/Cou SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 131       135      

2011‐2012 104       106       108       108       129       138       122       129       130       132       131       138      

F

T

E

F

T

E

44

 ‐

 50

 100

 150

 200

 250

 300

 350

 400

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 20

 40

 60

 80

 100

 120

 140

 160

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

Page 52: Fs2012 october

NORTHEAST COLLEGEFTE Comparison Year‐To‐Date Thru October 31, 2012 by Type(Full‐Time Employee Equivalent) 

FACULTY FTE

Faculty SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 187       208      

2011‐2012 200       211       216       207       112       204       212       212       211       129       137       124      

STAFF FTE

Staff/Lib/Cou SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 126       125      

2011‐2012 127       126       128       118       121       128       124       127       126       126       126       128      

F

T

E

F

T

E

45

 ‐

 50

 100

 150

 200

 250

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 20

 40

 60

 80

 100

 120

 140

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

Page 53: Fs2012 october

SOUTHWEST COLLEGEFTE Comparison Year‐To‐Date Thru October 31, 2012 by Type(Full‐Time Employee Equivalent) 

FACULTY FTE

Faculty SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 318       385      

2011‐2012 380       433       435       422       183       377       382       386       382       229       252       217      

STAFF FTE

Staff/Lib/Cou SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 152       154      

2011‐2012 185       184       182       145       146       155       144       150       152       151       147       153      

46

F

T

E

F

T

E

 ‐

 50

 100

 150

 200

 250

 300

 350

 400

 450

 500

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 20

 40

 60

 80

 100

 120

 140

 160

 180

 200

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

Page 54: Fs2012 october

SOUTHEAST COLLEGEFTE Comparison Year‐To‐Date Thru October 31, 2012 by Type(Full‐Time Employee Equivalent) 

FACULTY FTE

Faculty SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 130       160      

2011‐2012 143       168       173       169       77          161       178       183       179       101       120       95         

STAFF FTE

Staff/Lib/Cou SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 96          103      

2011‐2012 99          96          97          86          94          98          91          95          96          99          96          101      

F

T

E

F

T

E

47

 ‐

 20

 40

 60

 80

 100

 120

 140

 160

 180

 200

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 20

 40

 60

 80

 100

 120

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 20

 40

 60

 80

 100

 120

 140

 160

 180

 200

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 20

 40

 60

 80

 100

 120

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 20

 40

 60

 80

 100

 120

 140

 160

 180

 200

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 20

 40

 60

 80

 100

 120

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

Page 55: Fs2012 october

Division of Extended Learning (DOEL)FTE Comparison Year‐To‐Date Thru October 31, 2012 by Type(Full‐Time Employee Equivalent) 

FACULTY FTE

Faculty SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 90          67         

2011‐2012 85          69          68          56          55          72          63          67          64          59          57          64         

STAFF FTE

Staff/Lib/Cou SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 79          81         

2011‐2012 78          79          79          75          79          80          77          79          79          79          78          81         

F

T

E

F

T

E

48

 ‐

 10

 20

 30

 40

 50

 60

 70

 80

 90

 100

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 10

 20

 30

 40

 50

 60

 70

 80

 90

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

Page 56: Fs2012 october

DISTRICTFTE Comparison Year‐To‐Date Thru October 31, 2012 by Type(Full‐Time Employee Equivalent) 

FACULTY FTE

Faculty SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 8            7           

2011‐2012 7            4            4            1            ‐             5            4            5            3            4            4            3           

STAFF FTE

Staff/Lib/Cou SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

2012‐2013 606       612      

2011‐2012 616       609       608       595       627       609       625       612       614       601       605       612      

F

T

E

F

T

E

49

 ‐

 1

 2

 3

 4

 5

 6

 7

 8

 9

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 100

 200

 300

 400

 500

 600

 700

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

Page 57: Fs2012 october

HOUSTON COMMUNITY COLLEGEDuplicated Headcount Comparison Year‐To‐Date Thru October 31, 2012 by Type

FACULTY HEADCOUNT

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

12‐13 FT 787       795      

12‐13 PT 1,992    2,361   

12‐13 Total Fac 2,779    3,156    ‐             ‐             ‐             ‐             ‐             ‐             ‐             ‐             ‐             ‐            

11‐12 FT 792       797       793       788       793       785       784       782       783       768       757       794      

11‐12 PT 1,911    2,334    2,390    2,331    275       2,387    2,391    2,351    2,367    1,075    1,372    679      

11‐12 Total Fac 2,703    3,131    3,183    3,119    1,068    3,172    3,175    3,133    3,150    1,843    2,129    1,473   

STAFF HEADCOUNT

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

12‐13 FT 1,238    1,250   

12‐13 PT 840       833      

12‐13 Total Staff 2,078    2,083    ‐             ‐             ‐             ‐             ‐             ‐             ‐             ‐             ‐             ‐            

11‐12 FT 1,256    1,256    1,238    1,235    1,253    1,242    1,249    1,235    1,240    1,201    1,240    1,250   

11‐12 PT 877       879       883       839       629       822       834       828       846       767       790       790      

11‐12 Total Staff 2,133    2,135    2,121    2,074    1,882    2,064    2,083    2,063    2,086    1,968    2,030    2,040   

50

 

S

t

a

f

f

 

Headcount

 

F

a

c

u

l

t

y

Headcount

 ‐

 500

 1,000

 1,500

 2,000

 2,500

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

 ‐

 200

 400

 600

 800

 1,000

 1,200

 1,400

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

Page 58: Fs2012 october

HOUSTON COMMUNITY COLLEGEUnduplicated* Headcount Comparison Year‐To‐Date Thru October 31, 2012 by Type

UNDUPLICATED HEADCOUNT

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

12‐13 Total  4,475    4,446   

11‐12 Total  4,543    4,902    4,917    4,833    2,891    4,728    4,814    4,805    4,806    3,373    3,575    3,303   

* Includes Full‐time and Part‐time Faculties, Librarians, Counselors, and Staffs 

51

Unduplicated* Headcount

 ‐

 500

 1,000

 1,500

 2,000

 2,500

 3,000

 3,500

 4,000

 4,500

 5,000

SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG

Page 59: Fs2012 october

Non‐current assets:

Restricted cash 6,804$                  

Restricted investment in trust accounts 2,298,886

Lease receivable from HCCS 172,194,009        

Deferred charges ‐ bond issuance costs 2,046,534            

Capital Assets:

Land ‐                         

Other Structures ‐                         

Furniture & equipment ‐                         

Leasehold improvements ‐                         

Construction in process 791,957            

791,957                

TOTAL ASSETS 177,338,190$      

Current liabilities:

Accounts payable ‐ HCC 60,979$                

Accounts payable 19,982                  

Accrued liabilities ‐ interest ‐                             

Current bond payable 3,880,000            

Total current liabilities 3,960,961$          

Non‐current liabilities:

Deposits 440                       

Arbitrage payable ‐                             

Unearned interest income (23 years) ‐ HCC 70,298,500          

Premium on bonds 2,209,548            

Bonds payable 105,655,000        

Total non‐current liabilities 178,163,488$      

TOTAL LIABILITIES 182,124,449        

TOTAL NET ASSETS ‐ restricted (4,786,259)$         

PFC 1

Houston Community College ‐ Public Facility CorporationStatement of Net Assets

Cash Basis ‐ Interim Period

as of October 31, 2012

ASSETS

LIABILITIES

Page 60: Fs2012 october

Cash Flows from Capital Financing Activities

Receipt from HCCS for lease payment 2,538,004$     

Purchases of capital assets (815,068)          

Payment on capital debt ‐ principal and interest (2,538,696)      

Net cash provided (used by) in financing activities (815,760)          

Cash Flows from Investing Activities

  Interest income 738

Increase (decrease) in restricted cash and 

restricted investment in trust accounts (815,022)          

Restricted cash and restricted investment in 

trust accounts ‐ beginning of year 3,120,712        

Restricted cash and restricted investment in 

trust accounts ‐ end of period 2,305,690$     

Houston Community College System Public Facility CorporationStatement of Cash Flows

Cash Basis ‐ Interim Period

Two Month Ended as of October 31, 2012

PFC 2

Page 61: Fs2012 october

Total Budget to 

Date

Total Revenues 

/  Expenditures 

To Date

Encumbrances 

To Date Unexpended

Sources of funds:

Proceeds from 

2005C Lease Revenue Bond 19,155,000$   

Discount (170,064)        Land Purchase (4,212,644)    Bond Issuance Cost (606,201)        Interest Expense (524,785)        

13,641,306$  Interest Income 1,003,532      Vendor Contract Refund 102,706         Transfer to Payment Account (1,354,990)    

Funds Available 13,392,554$  

Uses of funds:4,092$             4,092$             ‐$ ‐$                   

11,550,643    11,550,643    ‐                      ‐                    Maintenance 393,940          141,479          252,461         ‐                    

6,443              6,443              ‐                    563,928          563,928          ‐                    

7,200              7,200              ‐                      ‐                    27,403            26,326            1,077              ‐                    24,940            24,940            ‐                    44,695            44,695            ‐                      ‐                    

596,787          596,787          ‐                      ‐                    

172,483            8,100                164,383         

Grand Total Uses 13,392,554$   12,974,634$   253,537$        164,383$     

Net Available ‐$                     

  PFC requires GMP before inception.

Total Proceeds from Bond

Houston Community College ‐ Public Facility CorporationPublic Safety Instituteas of October 31, 2012

PFC 3

Bank Service ChargesConstruction

Waste Water Management *Geo Technical Services*

Survey*Architect

Engineering ServicesFFE

Contingency

 * Included in GMP 

Site Infrasturcture

Page 62: Fs2012 october

Total Budget to 

Date

Total Revenues 

/  Expenditures 

to Date

Encumbrances    

to Date Unexpended

Sources of funds:

Proceeds from 

 2005 A Bonds  11,605,000$   

 Premium Received             492,931 

 Accrued Interest Received               53,425 

 Interest Income                    998 

 Bond Issuance Costs           (391,474)

 Repayment of Loans     (11,392,147)

Funds Available 368,733$        

Uses of funds:

Debt Service 53,425$            53,425$          ‐$                        ‐$                       

Renovation & Construction  169,759            169,759          ‐                          ‐                         

Demolish & Renovate Office 56,244              56,244            ‐                          ‐                         

Furniture & Fixtures 46,857              46,857            ‐                          ‐                         

Legal Fees 42,448              42,448            ‐                         

Grand Total Uses 368,733$         368,733$       ‐$                        ‐$                      

Net Available ‐$                     

Note 1: PFC requires GMP before inception.

Houston Community College ‐ Public Facility CorporationWestgate (Katy)

as of October 31, 2012

PFC 4

Page 63: Fs2012 october

Total Budget to 

Date

Total Revenues 

/  Expenditures 

To Date

Encumbrances 

To Date Unexpended

Sources of funds:

Principal Amount on Bonds 36,950,000$   

Discount on Bonds (546,238)          

Underwriter's Discount (209,273)

Accrued Interest on Bonds 98,080             

Amount Available 36,292,569$   

Issuance Costs (490,131)          

 Accrued and Capitalized Interest (1,449,023)      

Repair and Replacement (1,000,000)      

Title Fees Capitalized (81,379)            

Amount Available for Project 33,272,036$   

Repayment to HCC (188,006)          

Project Account Balance 33,084,030$   

Administrative & Legal Fees (29,486)            

Interest Income 836,330           

Transfer Cost Issuance 85,509             

Interest Expense on Notes (135,299)          

Funds Available 33,841,084$  

Uses of funds:

Land & Building 17,807,972$    17,807,972$    ‐$                     ‐$                

Maintenance Rehabilitation & 

Deferred Maintenance

12,856,469      12,856,469      ‐                  

CPMS PGAL 211,959            211,959            ‐                  

Facilities Space Programming 214,620            214,620            ‐                  

Furniture, Fixtures & Equipment 1,040,112         1,006,277         14,273            19,562       

Site Infrastructure 971,369            854,984            4,859               111,526     

Architect and Engineering 517,509            428,355            4,632               84,522       

Repair & Maintenance Contingency   ‐ 

per bond requirement

221,074            83,089              2,000               135,985     

Grand Total Uses 33,841,084$   33,463,726$   25,764$          351,595$  

Net Available ‐$                     

  PFC requires GMP before inception.

Houston Community College ‐ Public Facility CorporationHayes Road ‐ Alief Project

as of October 31, 2012

PFC 5

Page 64: Fs2012 october

Total Budget to 

Date

Total Revenues 

/  Expenditures 

To Date

Encumbrances 

To Date Unexpended

Sources of funds:

Principal Amount of 2007 Series Bonds 58,885,000$   

Premium on Bonds 3,094,498        

Underwriter's Discount (346,244)          

Accrued Interest Income‐ Bonds 173,733           

Total Amount Available 61,806,987$   

Issuance Cost (839,837)          

Accrued  and Capitalized Interest (4,632,122)      

Repair and Maintenance Account ‐                        

Amount Available for Project 56,335,028$   

Interest Income on Trust Account 2,496,540        

Interest Expense on Notes (414,601)          

Transfer to Trustee Payment Account (4,712,985)      

Vendor Contract Refunds 230,035           

Sale of Land 569,890           

Funds Available 54,503,907$  

Uses of funds:

Land & Building 10,671,234$    10,671,234$    ‐$                     ‐$                    

Construction Cost‐ Building 18,200,000      18,200,000      ‐                       ‐                      

Construction‐Demolition 494,972            ‐                         ‐                       494,972         

Constuction‐ Site 640,988            630,793            10,194            ‐                      

Site Improvement 14,221,039      13,804,804      416,235          ‐                      

Site Demolition & Abatement 791,298            791,298            ‐                      

CPMS PGAL 1,391,958         1,391,958         ‐                       ‐                      

Site and Infrastructure Design 2,334,840         2,334,840         ‐                       ‐                      

Facilities Space Programming 29,274              29,274              ‐                       ‐                      

Architect and Engineering 1,256,727         1,256,727         ‐                      

Furniture, Fixtures & Equipment 1,828,332         1,818,281         10,051            ‐                      

Library 66,564              66,182              382                 ‐                      

Inspections 214,981            214,981            ‐                       ‐                      

Design Geotech 17,500              17,500              ‐                       ‐                      

Material Testing  24,503              24,503              ‐                       ‐                      

Communications IT‐ PGAL 253,614            253,614            ‐                      

IT Telephone & Communications 790,467            790,467            ‐                      

Surveying  62,398              59,124              3,274              ‐                      

Administrative Expenses 34,505              34,505              ‐                      

Preconstruction Costs 886,377            886,377            ‐                      

Contingency 292,338            186                    ‐                       292,154         

Grand Total Uses 54,503,907$   53,276,647$   440,135$       787,126$     

  PFC requires GMP before inception.

as of October 31, 2012

PFC 6

Houston Community College ‐ Public Facility CorporationNorthline Mall Project