fsawwa paper and presentation integrated master planning wpb 12012015

44
FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities Page 1 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs How Integrated Master Planning Helped the State’s Largest UV Surface Water Treatment Plant Meet Their Future Water Needs Authors: GJ Schers 1 PMP, Timothy Smith 1 PE, PMP, Scott Kelly 2 PE, Poonam Kalkat 2 PhD 1 MWH 2 City of West Palm Beach 1. Introduction The City of west Palm Beach draws its source water from Lake Okeechobee, Grassy Waters Preserve which is a pristine Everglades wetland area, and available stormwater systems. Using surface water as its source water makes this utility fairly unique in the South Florida region and requires the water treatment plant to regularly adjust the process to meet seasonal variations in water quality. Towards this goal, the City of West Palm Beach has made several priority improvements to their water treatment plant (WTP) in the past seven years (FWRC article, Dec 2013) [1]. These improvements include replacement of equipment at the end of its useful life, elimination of gaseous chemicals for staff and public safety, and modification to the control and electrical systems to provide automated plant operation and reliable power distribution as well as backup power generation systems for the plant. The WTP, located in downtown West Palm Beach, has a rated capacity of 47 MGD and utilizes a conventional treatment process consisting of coagulation, flocculation/sedimentation, filtration over dualmedia, biologicalactive rapid gravity filters, and disinfection with chloramines. Powdered activated carbon can be added to the raw water intake of the plant. A corrosion inhibitor (poly/orthophosphate blend) and fluorosilicic acid is added at the mixing metering header just upstream of the Ground Storage Tanks. See Figure 1 for a simplified process flow diagram of the existing WTP. Figure 1: Simplified Existing Treatment Plant Process Flow Diagram The WTP site structures were originally built in 1894 by Henry Flagler with major expansions in the 1920’s, 1960’s, 1990’s and 2010 and is surrounded by residential homes, highrise buildings, and businesses. Figure 2 shows an aerial photograph of the WTP with a depiction of the location and nature of each recent improvement.

Upload: gj-schers

Post on 14-Apr-2017

234 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities  Page 1 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs 

How Integrated Master Planning Helped the State’s Largest UV Surface Water 

Treatment Plant Meet Their Future Water Needs 

Authors: GJ Schers1 PMP, Timothy Smith1 PE, PMP, Scott Kelly2 PE, Poonam Kalkat2 PhD 

1 MWH 2 City of West Palm Beach 

 

1. Introduction  

The City of west Palm Beach draws its source water from Lake Okeechobee, Grassy Waters Preserve which 

is a pristine Everglades wetland area, and available stormwater systems. Using surface water as its source 

water makes this utility fairly unique in the South Florida region and requires the water treatment plant 

to regularly adjust the process to meet seasonal variations in water quality. Towards this goal, the City of 

West Palm Beach has made several priority improvements to their water treatment plant (WTP) in the 

past seven years (FWRC article, Dec 2013) [1]. These improvements include replacement of equipment at 

the end of its useful life, elimination of gaseous chemicals for staff and public safety, and modification to 

the control and electrical systems to provide automated plant operation and reliable power distribution 

as well as backup power generation systems for the plant.  

The WTP,  located  in  downtown West  Palm  Beach,  has  a  rated  capacity  of  47 MGD  and  utilizes  a 

conventional  treatment  process  consisting  of  coagulation,  flocculation/sedimentation,  filtration  over 

dual‐media, biological‐active rapid gravity filters, and disinfection with chloramines. Powdered activated 

carbon can be added to the raw water  intake of the plant. A corrosion  inhibitor (poly/orthophosphate 

blend) and fluorosilicic acid is added at the mixing metering header just upstream of the Ground Storage 

Tanks. See Figure 1 for a simplified process flow diagram of the existing WTP. 

 

 

Figure 1: Simplified Existing Treatment Plant Process Flow Diagram 

 

The WTP site structures were originally built in 1894 by Henry Flagler with major expansions in the 1920’s, 

1960’s, 1990’s and 2010 and  is  surrounded by  residential homes, high‐rise buildings, and businesses. 

Figure 2 shows an aerial photograph of the WTP with a depiction of the location and nature of each recent 

improvement. 

Page 2: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities  Page 2 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs 

 

Figure 2: Aerial picture of today’s WTP 

 

In 2013, the City decided to review the technology alternatives to strengthen the pathogen barriers as a 

requirement  of  a  2008  Consent Order with  the  Palm  Beach  County Health Department  that will  be 

discussed in more detail later in this article. The implementation of the membrane based alternative in 

the Consent Order was projected  to require an  immediate utility rate  increase. The City questioned  if 

there could be alternatives that would be less costly in terms of capital and operating costs both in the 

short and long term and would not require an immediate rate increase. The City also wanted to confirm 

that  the  facility would meet  future demands due  to an  increasing  growth  rate  in  the City while also 

quantifying replace and refurbishment (R&R) costs over the long term. 

 

Page 3: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities  Page 3 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs 

Therefore in 2014, the City initiated an integrated master planning approach to identify the present and 

future water facility needs of the City. This article outlines the basic components of this integrated master 

planning approach as listed below: 

Condition assessment and criticality analysis along with vulnerability assessment of existing WTP 

assets are outlined  in section 2. Deficiencies  identified  in  this process are  translated  into R&R 

needs for the existing WTP. 

Evaluation of treatment alternatives to meet the future requirements of the plant are discussed 

in Section 3. This includes raw and finished water quality analysis, to verify trends and changes, 

assessment  of  current  and  potential  future  regulations,  and  options  to  optimize  energy  and 

chemical  usage.  In  addition  the  assessment  evaluates  the  possibility  of  relocating  the water 

treatment system out of  the downtown area and  to  free‐up space  for  future commercial and 

residential development, an option preferred by some City commissioners.  

Opinion  of  probable  construction  costs  for  the  treatment  alternatives  considered  above  are 

outlined in section 4 along with a comparison of life cycle cost of ownership. 

 The following sections follow the same sequence of integrated master planning, as outlined above.   

2. Condition Assessment and Criticality Analysis of Existing Assets 

The  first  step  for  integrated master planning  required  a  comprehensive  condition  assessment of  the 

existing WTP assets by visual inspections of assets as well as extensive discussions with Operations and 

Maintenance  personnel  [3].  Equipment  performance  data  was  collected  and  reviewed  to  detect 

deficiencies such as deviations from original manufacturer’s specifications. The data from inspections was 

collected and arranged  in  lists with asset names and codes, photographs, performance data, condition 

assessment rating, and repair and replacement cost for each need.  

A description of each water plant area assessment is provided below. Additionally, major findings per area 

are highlighted and some examples are included in Table 1: 

Process Evaluation: Performance of  the existing  treatment process was reviewed by analyzing historic 

water quality data, monthly operating reports, and other operational records and compared with industry 

standards and guidelines,  including  the Florida Administrative Code,  the Recommended Standards  for 

Water Works, Great  Lakes,  2012  edition,  and MWH  Best  Practice Design Guides.  In  addition  to  the 

condition assessment, a criticality analysis and vulnerability assessment was performed. The results of the 

process flow rating review of each individual process are depicted in Figure 3 and shows that a number of 

processes  including sedimentation basins, recarbonation system, washwater recovery basin, thickener, 

and calcium oxide (lime) storage do not meet the ultimate capacity of the plant though they meet the 

current plant production needs. 

Mechanical Evaluation: The condition of  the existing mechanical equipment,  such as pumps, blowers, 

compressors, piping and valves was assessed for visual defects, vibration, noise, wear and tear, and energy 

efficiency. The existing hydraulic performance of the pumps was tested by flow and pressure logging and 

the results were compared with the original shop drawing performance curves. Inspection for Health and 

Safety and Code compliance was also performed. These inspections included the safety showers/eyewash 

equipment, ventilation equipment, fire suppression, and plumbing fixtures.  

Page 4: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities  Page 4 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs 

 

Figure 3: Graphical depiction of flow rating of each individual treatment process 

 

Structural Evaluation: The structural evaluation documented concrete deterioration and rebar corrosion. 

Recorded deficiencies included visual evidence of leaks, spalling, delamination, exfoliation, and exposed, 

corroded, or deteriorated rebar. This visual inspection was then supplemented by destructive and non‐

destructive testing for the sedimentation basin and filter reinforced concrete structures consisting of in‐

place  rebound hammer  testing, Ground Penetrating Radar  (GPR) concrete scanning, and strength and 

laboratory testing of concrete core samples and steel reinforcement samples. 

Electrical Evaluation: The electrical and control systems had undergone considerable investments in the 

last seven years providing more reliable power supply to and within the site, full capacity backup power, 

and a new communications protocol and control system. Therefore the evaluation only focused on motor 

control centers, panels, and  instrumentation that were not replaced or substituted as part of the past 

upgrades.  

Architectural Evaluation: Existing buildings were reviewed in terms of building code compliance, life safety 

and general  condition. Options  to hurricane hardening of  the Operations Building were assessed and 

presented in the documents and flat roof structures were particularly subjected to a detailed review due 

to historical leakages.  

Examples of observations during the Condition Assessment for each discipline are included in Table 1. 

 

0

10

20

30

40

50

60

70

80

90

100

Rated

 Capacity of the Process (MGD)

Total Capacity per Process (all units on)Process Rating per Process (one unit out of…

Current Rating of WTP = 47 MGD

Page 5: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities  Page 5 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs 

Table 1: Examples of observations during Condition Assessments for each discipline and a typical photograph w/imaging of the structural non‐destructive investigation 

Examples of Major Findings of Condition Assessment per Discipline 

Mechanical  Electrical 

South raw water pump No. 27 needs replacement 

VFDs on raw water pumps don’t work effectively  

Sludge removal system in basins is at the end of 

useful life 

Isolation gates/valves in settled water flume and 

pipes are defective and inoperable 

Some filter and site isolation valves are nearing 

the end of useful life 

MCC for high service pumps is at end of useful life 

and parts are not available 

Some site PLCs are obsolete  

Multiple UPS systems on site; there is a need to 

centralize and make resilient 

Some remote panels should be provided with a 

secondary power feed 

Structural  Architectural 

Sections of shoreline Clear Lake eroded 

Signs of concrete deterioration in the filters and 

sedimentations basins 

Filtered water flume and underground clearwell 

show signs of leakage 

Operations Building requires hurricane hardening, 

particular in the hardware 

Flat roofs are leaking in some spots and should be 

rehabilitated or replaced 

Buildings should be reviewed in terms of life 

safety and ADA 

Just an example of the 

findings of the concrete 

non‐destructive testing: 

photograph and thermal 

imaging at same location at 

the expansion joint in the 

east sedimentation basin. 

 

The most relevant results from the criticality analysis and vulnerability assessments are presented in Table 

2. As an example,  this  table notes  that  some of  the hydraulic conduits and connections between  the 

treatment processes are either single pipelines or single reinforced concrete structures and cannot be 

taken out of operation for repair and cleaning without a full plant outage. Another example of a factor 

effecting criticality is the significant risk of flooding in both the West and East High Service Pump Stations 

due  to  hydraulic  conditions, which  can  affect mechanical  and  electrical  equipment  housed  in  these 

buildings.  

   

Page 6: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities  Page 6 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs 

Table 2: Significant observations during the Criticality Analysis and Vulnerability Assessment 

Area  Area Name  Single Point of Failure/Vulnerability Description  Comment 

02 Flocculation and 

Sedimentation Basin 

Single settled water reinforced concrete flume and 

isolation gates which are inoperable affecting the use 

of the 60" bypass piping 

 

02 Recarbonation 

System 

Single carbon dioxide dosing skid feeds a single 

dosing point in the recarbonation basin/settled water 

flume 

Use of bypass piping requires 

carbon dioxide to be dosed 

also in 60" bypass piping 

03  Filters 

Single filtered water flume and pipeline and

reinforced concrete flume does not appear to be 

watertight which could provide a contamination risk 

from storm water runoff and groundwater infiltration 

This was also documented in 

reports during 2008‐2010 

period 

03  Filters 

Filter control panels have no secondary power feed 

and Profibus configuration changes in filter area have 

not been completed as per agreed plan 

  

04 Transfer Pump 

Station 

Pump station has a single wet well without options 

for sectional isolation   

04 Transfer Pump 

Station 

Due to floor elevation, a failure of the transfer pumps 

in the East HSP building presents a flooding risk 

affecting transfer and high service pumps and 

associated gear 

 

04 Transfer Pump 

Station 

Single Mixing and Metering header piping, and single 

pipeline cross just upstream of the ground storage 

tanks 

  

04‐05 

High Service Pump 

Stations (East and 

West) 

Due to floor elevation, the West HSP mechanical and 

electrical gear can flood when the control valve to 

the 1 MG clearwell fails or loses power affecting raw 

water and high service pumps and gear 

There have been reports of 

flooding and near‐misses in 

West HSP in the past 

05 Ground Storage 

Tank 

Old 1 MG below grade clearwell does not appear to 

be watertight and introduces a risk for contaminants 

from storm water runoff and groundwater infiltration 

 

06  Sludge Thickener 

Single sludge thickener and sludge pump station 

cannot be isolated or taken out of operation/service 

for extended periods of time 

De‐sludging from 

sedimentation basins cannot 

be delayed beyond 12 hours 

  

3. Treatment Alternatives to Meet Future Needs 

Assessing  the  condition  of  the  existing  plant  systems  and  identifying  areas  with  process  capacity 

limitations  or  systems  vulnerabilities,  provided  a  baseline  for  evaluation  of  upgrades  and  treatment 

alternatives for modernizing the existing plant. 

The existing process has been successful in meeting the primary and secondary drinking water standards 

and  regulations  over  the  last  eight  years.  However,  in  2007,  a  series  of  bacteriological  hits  in  the 

distribution system led to two boil water notifications. Investigations by Public Utilities department staff, 

regulators, and consulting engineers led to the discovery of an improperly sealed interconnect not shown 

on  as‐built  drawings, which  allowed  filtered,  chlorinated water  to  bypass  the  storage  tanks without 

providing the contact time necessary for bacteriological and virus kill prior to distribution. Subsequently, 

Page 7: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities  Page 7 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs 

the regulator  (the Palm Beach County Department of Health) and the City entered  into an agreement 

(Consent Order) to upgrade the City’s WTP by 2018. 

In addition  the Utility wanted  to address  the concern of always being able  to meet both  the Stage 1 

Disinfection and Disinfection Byproduct (D/DBP) and Long‐Term (2) Enhanced Surface Water Treatment 

Rule  (ESWTR)  requirements,  i.e. meeting  the  Total Organic  Carbon  (TOC)  removal  and  pathogen  log 

inactivation requirements, while not exceeding the maximum disinfectant residual level of chloramines 

and  disinfection  byproduct  levels  of  trihalomethanes  (THM)  and  haloacetic  acids  (HAA).  These 

requirements are summarized in Table 3. 

Table 3: EPA Rules affecting on‐going operation 

Rule  Contaminant or Treatment 

Requirement 

Limit 

Stage  1  D/DBP  Rule:  Maximum 

Contaminant Levels (MCL) 

THM

HAA 

80 µg/L 

60 µg/L 

Stage  1  D/DBP  Rule:  Maximum  Residual 

Disinfectant Levels (MRDL) 

Chloramine 4 mg/L 

Stage 1 D/DBP Rule: Required Removal of 

TOC 

TOC removal >=40% 

Surface Water  Treatment  Rules  (Original, 

Interim and Long‐Term) 

Virus inactivation

Giardia inactivation 

Filtered water turbidity 

Cryptosporidium inactivation 

4 log 

3 log 

<0.3 NTU 95%, <1.0 NTU 100% 

2 log 

 

While the criticality and vulnerability assessment identified current deficiencies in the water treatment 

process and opportunities for improvements, it did not address future regulatory drivers including: final 

Contaminant Candidate List 4 (CCL‐4), final Third Determination of CCL‐3, proposed Carcinogenic Volatile 

Organic Compound (cVOC), Lead and Copper Rule Long‐Term Revisions (LCR‐LTR) and Perchlorate Rules, 

and Third Six‐Year Review. 

Following the stipulations in the Consent Order and based on the future regulations mentioned above, 

the  City  determined  that  the  future  water  treatment  process  should  include  additional  pathogen 

protection and additional taste and odor (T&O) control. The considered processes to provide additional 

treatment for pathogens and T&O  included activated carbon treatment (either granular or powdered), 

anion  exchange,  low  pressure  membrane  filtration,  high‐rate  clarification,  and  ultraviolet  light 

disinfection. Other processes, while potentially effective for additional treatment as outlined above, were 

discarded for a variety of reasons. For example, ozone for T&O control would have resulted in elevated 

bromate levels in the finished water, close to or even above the standard of 10 µg/L [5]. 

A short description of each alternative is provided below, while a more detailed process description and 

simplified Process Flow Diagrams (PFD’s) are presented in Figure 4:  

Alternative 1: PAC‐UV: Alternative 1 maintains the existing lime softening process with the addition of a 

dedicated  powdered  activated  carbon  (PAC)  contact  chamber  on  the  raw  water  for  T&O  control. 

Additional pathogen protection is provided with ultraviolet (UV) light disinfection process downstream of 

the filters. 

Alternative 2: IX‐UF‐GAC: Alternative 2  is  located on a 4.5‐acre vacant  lot on the existing WTP site and 

uses new processes  in  suspended  anion  exchange  (IX), ultrafiltration  (UF) membrane  treatment,  and 

granular  activated  carbon  (GAC)  absorption.  Additional  pathogen  protection  is  provided  with  the 

Page 8: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities  Page 8 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs 

membranes and the extended free chlorine contact time. T&O control is provided with GAC Absorption 

through an extended empty bed contact time. 

Alternative 3: IX‐UF‐GAC (ECR Site): Alternative 3 is in essence the same process as Alternative 2, however 

it is located on a Greenfield site near the East Central Regional (ECR) Water Reclamation Facility (WRF). 

Once  relocated,  the  existing WTP  site would  be  redeveloped  for  residential  and/or  commercial  use. 

Additional pathogen protection is provided with membranes and an extended free chlorine contact time. 

T&O control is provided with GAC Absorption with an extended empty bed contact time. 

Alternative  4:  ENH.COAG‐ACT‐UF  (Riviera  Beach  Site):  Alternative  4  includes  Actiflo‐Carb®  and 

ultrafiltration membrane treatment, and is located on a new site in Riviera Beach. The existing WTP site 

would be redeveloped for residential and/or commercial development. Additional pathogen protection is 

provided with  the membranes and extended  free chlorine contact  time. T&O control  is provided with 

continuous PAC pre‐treatment integrated with the Actiflo® clarification process.  

 

4. Cost of Alternatives and Financing Options 

The R&R needs for each treatment alternative are different due to the different approaches towards the 

use of existing assets. The plant upgrades needs for each alternative are also different due to the use of 

different treatment processes to meet the objectives. 

For each alternatives, capital, operating and life cycle cost estimates were prepared, as outlined below. 

Capital Cost Estimates for Plant Upgrades 

Planning  level  capital  cost  estimates  (CAPEX)  for  each  alternative  were  developed.  A  contingency 

allowance of 30% is considered in the cost estimates of which 20% was included in the cost estimate and 

the other 10% was allocated by the City in the City’s reserve. The CAPEX estimates follow Class 5 Opinion 

of  Probable  Construction  Costs  (OPCC)  as  defined  by  the  Association  for  the  Advancement  of  Cost 

Engineering International (AACEI), Recommended Practice No. 18R‐97. This level of cost is a planning level 

order of magnitude cost with an expected accuracy range of ‐20% to ‐50% below and 30% to 100% above. 

A  summary  of  the  CAPEX  is  included  in  Figure  5.  The  CAPEX  for  Alternatives  3  and  4  includes  the 

conveyance  to and  from  the new sites and demolition of structures at  the existing WTP, removal and 

disposal of construction debris off site, remediation of the drinking water sludge area to prepare the site 

for  new  residential,  and  commercial  construction.  It  also  contains  the market  value  of  the  26  acres 

property  of  the  existing WTP  site, which  becomes  vacant when  a  replacement WTP  is  built  and  is 

operational at a new site.   As shown, the onsite alternatives were more cost‐effective than the off‐site 

alternatives. Alternative 1 PAC‐UV has the lowest CAPEX at $33.5 million, with Alternative 2 IX‐UF‐GAC (at 

existing site) the next most cost‐effective option with an additional CAPEX of $74.2 million. Alternatives 3 

and 4 (the off‐site alternatives) are at least $250 million more expensive than Alternative 1. From the off‐

site alternatives, Alternative 4 ACTIFLOCARB‐UF (at Riviera Beach)  is more cost‐effective mainly due to 

the reduced CAPEX for the raw water and finished water conveyance. 

Page 9: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities  Page 9 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs 

Alternative 1 (at WTP site) PAC improvements involve new auger, slurry mixer and dosing lines to the new PAC basin. Continued use of sedimentation basins will ultimately involve re‐rating by providing additional valving, extending flocculation zone, and providing lamella plate settling units and replacing the sludge removal system. Recarbonation will be provided in settled water flume and settled water pipe. Existing rapid gravity filters (RGF) will be provided with new media. Filter effluent will be combined requiring additional isolation valves and pipelines. A new transfer pump station will be provided to convey flow through the new UV installation to the existing mixing and metering header. The new UV system and associated equipment will be housed in a new building. Finished water will be dosed with free chlorine downstream of the UV system before chloramine formation at the existing mixing and metering header. The existing filtered water flume and buried clearwell will be demolished. 

Alternative 2 (at WTP site) A new IX process will be included to remove the organics. UF membranes will be provided for suspended solids and pathogens removal and will be housed in a new building. The membranes will be located downstream of IX, while existing dual media filters will be converted to GAC absorbers by changing the media. The 32 re‐purposed filters will be retrofit with plastic underdrain block with an IMS cap allowing for deeper media depth and covered with retractable FRP covers. Similarly to Alternative 1, effluent from the GAC contactors will be combined and transferred to a new reinforced concrete chlorine contact basin to provide a free chlorine contact time providing virus and Giardia inactivation control. Chloramines will be used as secondary disinfectant. This alternative will involve the excavation of unsuitable soils from the vacant lot and will eliminate existing filtered water flume and buried clearwell. 

Alternative 3 (West, near ECR site) The process is an exact match of Alternative 2. UF membranes will be constructed for suspended solids and pathogens removal and will be housed in a new building. New GAC adsorbers will be constructed using pressurized vessels instead of open reinforced concrete structures. Free chlorine will be used for primary disinfection and chloramines for maintaining a residual in the distribution system. This alternative requires the repurpose of the existing vacant 26‐acre site on the south side of Jog road, east of the City well field. 

Alternative 4 (East, Riviera Beach site) A new enhanced coagulation process integrated with PAC pretreatment will be provided to remove source water organics and T&O. UF membranes will be constructed for remaining suspended solids and pathogens removal and will be housed in a new building. The membranes are located downstream of the Actiflo® Carb process and safety strainer. A new chlorine contact basin will be constructed to provide free chlorine contact time for virus and Giardia inactivation. Chloramines will be used as a secondary disinfectant. The proposed 8.5‐acre treatment site is west of the FPL power facility in Riviera Beach. Raw water will be pumped approximately 3.75 miles north from the existing WTP site and finished water will be pumped back to existing site. 

Figure 4: Simplified diagram and a description of each of the treatment alternatives

50 mgd 

Clear Lake 

ChlorineAmmonia

CausticFerric Sulfate, Acid 

PAC 

Actiflo –Carb®Offsite 

Storage 

Polymer, 

Microsand

UF

 

 

Page 10: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities  Page 10 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs 

 

Figure 5: Graphical depiction of CAPEX for each of the alternatives  

Annual Allocation for R&R Needs 

The MWH team conducted  field  inspections and assessments of  the existing plant assets as described 

before.  In  addition  the  team  defined  the  refurbishment  and  rehabilitation  (R&R)  needs  of  the 

infrastructure that would need to be maintained as part of the  long term solution to upgrade the WTP 

with  either UV disinfection  (Alternative 1) or UF membrane  (Alternatives  2‐4)  technologies.  The  two 

alternatives at  the existing site  (Alternatives 1 and 2) have different R&R needs based on  the existing 

processes and structures  remaining  in  service. Similarly,  the offsite alternatives  (Alternatives 3 and 4) 

require only urgent repairs until the new plant is operational as reflected in the early R&R costs. 

CAPEX estimates for R&R needs were developed for the next 10 years (Periods 2015‐2019 and 2020‐2024) 

with the same planning  level accuracy as the Plant Upgrades CAPEX estimates. The R&R needs for the 

following 20 years (Period 2025‐2044) were estimated and included in the assessment for completeness, 

and were kept the same between the options. The CAPEX numbers were subsequently amortized to an 

annual allocation. The results are presented in Figure 6. 

   

Alternative 1 ‐PAC‐UV

(at existing site)

Alternative 2 ‐IX‐UF‐GAC

(at existing site)

Alternative 3 ‐IX‐UF‐GAC (near ECR)

Alternative 4 ‐Actiflo‐Carb‐UF

(at RivieraBeach)

Other Fees $5.6 $18.0 $61.2 $51.3

Site Property Value $0.0 $0.0 ‐$33.2 ‐$33.2

Site Works, Power, Demolition $4.3 $14.0 $76.7 $69.4

Treatment $23.6 $75.1 $96.1 $92.6

Pump Stations, Storage,Conveyance

$0.0 $0.7 $161.9 $109.2

‐$100

‐$50

$0

$50

$100

$150

$200

$250

$300

$350

$400

$450

2018 CAPEX

 Cost

(in M

illions)

Other Fees

Site Property Value

Site Works, Power,DemolitionTreatment

Pump Stations,Storage, Conveyance $33.6

$107.7

$362.7

$289.3

Page 11: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities  Page 11 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs 

 

Figure 6: Annual Cost of R&R needs 

 

Operating Cost Estimates 

Estimates  of  Operating  Expenses  (OPEX)  were  evaluated  on  the  basis  of  energy,  chemicals,  labor, 

maintenance  and  repair,  sludge  hauling  and  disposal,  liquid  waste  disposal  to  sewer  and  other 

miscellaneous items. Energy costs include pumping for primary and secondary flow streams, mixers, lime 

slakers, sludge collection, UV power draw, and other electrical consumers at the WTP. Energy costs also 

include the conveyance to and from the offsite location for Alternatives 3 and 4. Chemicals include PAC, 

IX resin, sodium chloride, unslaked lime, ferric sulfate, sulfuric acid, micro‐sand, cationic polymer, carbon 

dioxide, membrane  cleaning  chemicals, GAC  regeneration  or  replacement, UV  cleaning  acid,  sodium 

hypochlorite, aqueous ammonia,  sodium hydroxide  (or  caustic  soda), poly/orthophosphate  (corrosion 

inhibitor), hydrofluorosilicic acid (fluoride), and anionic polymer. Labor costs include burden costs for full‐

time  equivalent  (FTE)  estimates  for  supervisors,  operators,  technicians,  and  administrative  assistants 

based on requirements of 60‐699.310 F.A.C. Category I or Category II staffing requirements and the 2014 

organizational staffing plans for the City’s WTP. Sludge disposal costs include lime sludge or ferric sludge 

thickening and dewatering, storage, hauling, and disposal. Sewer disposal costs include disposal of liquid 

wastes into the sewer including filter press filtrate, Washwater lamella separator sludge, and ion exchange 

waste brine. Miscellaneous operating  costs are  items not  specifically  called out above  like diesel  fuel 

usage,  hired  labor  and  technicians  and  other maintenance materials,  and  calibration  chemicals  for 

instruments. Unit costs for each of the above operating cost categories were obtained from the City or 

from vendors. The operating costs for 2018 are summarized in Figure 7. 

 

Alternative 1 ‐PAC‐UV

(at existing site)

Alternative 2 ‐IX‐UF‐GAC

(at existing site)

Alternative 3 ‐IX‐UF‐GAC (near ECR)

Alternative 4 ‐Actiflo‐Carb‐UF

(at RivieraBeach)

Annual R&R CIP 2015‐2019 $2.8 $2.3 $0.9 $0.9

Annual R&R CIP 2020‐2024 $6.4 $1.7 $0.0 $0.0

Annual R&R CIP 2025‐2044 Est. $4.8 $4.8 $4.8 $4.8

$0.0

$1.0

$2.0

$3.0

$4.0

$5.0

$6.0

$7.0

Annual R&R Costs

(in M

illions)

Annual R&R CIP2015‐2019

Annual R&R CIP2020‐2024

Annual R&R CIP2025‐2044 Est.

Page 12: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities  Page 12 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs 

 

Figure 7: Graphical depiction of OPEX for each of the alternatives, compared with the existing situation, for the year 2018 at a flow of 27.5 MGD 

 

The annual OPEX in 2018 for the existing water treatment plant is forecast at approximately $15.2 million. 

For Alternative 1 PAC‐UV the annual OPEX is forecast to increase to $15.4 million due to the addition of 

PAC and UV treatment and for Alternative 2 IX‐UF‐GAC (at existing site) and Alternative 3 IX‐UF‐GAC (near 

ECR)  these  costs  are  forecast  to  reduce  to  $12.5  and  $12.1 million,  respectively, mainly  due  to  the 

reduction of the use of coagulation chemicals and disposal of sludge. For Alternative 4 ACTIFLOCARB‐UF 

(at Riviera Beach) the annual OPEX is forecast to remain the same as the existing water treatment plant. 

Life Cycle Cost Estimates 

The summary of  the  life cycle costs estimates, expressed  in Net Present Value  (NPV), are provided  in 

Figure 8. The Net Present Value calculations assume an estimated construction completion date in 2018 

to meet the Consent Order deadline. The CAPEX of the Plant Upgrades and the annual expenditure of R&R 

and the operating costs were presented in the sections before. 

NPV costs are forecasted starting in year 2018 to coincide with project completion. The NPV shown for 

year 0 represents cumulative expenditures for years 2015 through 2018. The existing WTP NPV includes 

2.5 million dollars  (2018 $) per  year  for R&R. CAPEX, R&R  and OPEX  costs  for  the  existing WTP  and 

Alternatives 1‐4 are  illustrated as stacked graphs  in Figure 8. The alternatives utilizing the existing site 

(e.g. Alternatives 1 and 2) have a lower NPV than the offsite alternatives (e.g. Alternatives 3 and 4). From 

the onsite alternatives, PAC‐UV (Alternative 1)  is more cost effective  in the first 15 years of operation, 

Existing

Alternative 1 ‐PAC‐UV

(at existingsite)

Alternative 2 ‐IX‐UF‐GAC(at existing

site)

Alternative 3 ‐IX‐UF‐GAC (near ECR)

Alternative 4 ‐Actiflo‐Carb‐UF

(at RivieraBeach)

Other OPEX $3.91 $3.91 $3.91 $3.91 $3.91

Waste to Sewer $0.10 $0.10 $0.20 $0.19 $0.11

Sludge $0.96 $0.96 $0.00 $0.00 $0.90

Labor $4.47 $4.47 $4.19 $3.63 $3.63

Chemicals $4.38 $4.38 $2.22 $2.22 $4.24

Energy $1.40 $1.44 $1.54 $1.70 $1.83

$0.00

$2.00

$4.00

$6.00

$8.00

$10.00

$12.00

$14.00

$16.00

$18.00

2018 OPEX

 Cost 

(in M

illions)

Other OPEX

Waste toSewerSludge

Labor

Chemicals

Energy

Page 13: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities  Page 13 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs 

however after year 15, IX‐UF‐GAC (Alternative 2) becomes more cost effective, mainly due to the lower 

OPEX. From  the off‐site alternatives, ACTIFLO‐CARB‐UF  (at Riviera Beach)  (Alternative 4)  is more  cost 

effective in the first 22 years of operation but after year 22, IX‐UF‐GAC (near ECR) (Alternative 3) becomes 

more cost effective. 

 

Figure 8: Graphical depiction of NPV for each of the alternatives  

Financing Options and Impact on Rates 

Several financing options were considered for each treatment alternative because of the differences in the initial CAPEX needs. A financial summary is provided in Table 4. The credit rating of the City of West Palm Beach is slightly different for each rating agency, but is general around ‘AA’ (double A). The utility department has already a relatively high debt, translated in the current rate being in the top quadrant of all utilities rates in Florida, compared to the City’s own targets: 

Debt outstanding to net plant ratio is 49.6% (target <50%) 

Debt per customer is $2,579 (target <$1,800) 

Affordability to customers is 2.48% (target of <2.00%) 

Based  on  the  existing  debt  situation  not meeting  targets,  the  City  expressed  an  interest  to  pursue opportunities to look at alternative financing options, if possible and feasible. Such alternative option was considered for alternative 1, with the relatively low initial capital needs. The available funds in the City’s Utility Reserve Fund would suffice to cover the  initial CAPEX needs. Alternative financing options were considered but found not feasible for Alternatives 2 and 3, and the capital necessary to fund the CAPEX needs would  need  to  be  raised  through  the  issuance  of  new  bonding.  Private  financing would  fund Alternative 4. This option also assumed that the ownership and operations of the new assets would be in 

$0

$100

$200

$300

$400

$500

$600

$700

$800

$900

$1,000

0 5 10 15 20 25 30

Cumulative Net Present Value

(2018 M

illions)

Years in Operation

Alternative 1 PAC‐UV(at existing site)

Alternative 2 IX‐UF‐GAC(at existing site)

Alternative 3 IX‐UF‐GAC (near ECR)

Alternative 4 Actiflo‐Carb‐UF(at Riviera Beach)

Existing

Page 14: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities  Page 14 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs 

private hands under a 30‐year concession agreement between the City and the private company. The financial implications on utility rates for all alternatives were estimated based on current best knowledge of capital needs, financing costs and yearly operations costs. 

The Utility Department management brought the results of the study, as presented in Table 4, to a City Commission meeting for decision making. Extensive discussions transpired on details of the alternatives, but in the end the City decided to move forward with Alternative 1 as it would not degrade the Utilities debt position and would not require an immediate utility rate increase.  The project team is moving ahead with the design and ground breaking for construction is expected in late spring of 2016. 

Table 4: Summary of Financing Options and Parameters for Alternatives 

  Alternative 1 

PAC‐UV (at existing site) 

Alternative 2 

IX‐UF‐GAC (at existing site) 

Alternative 3  

IX‐UF‐GAC (near ECR) 

Alternative 4 

Actiflo‐Carb‐UF‐GAC (at Riviera 

Beach) 

CAPEX  $33.6m $107.7m $362.7m  $289.3m

R&R 2015‐2019  $2.8m/yr $2.3m/yr $0.9m/yr  $0.9m/yr

Financing option considered for CAPEX and R&R ‘15‐‘19 

City’s Utility reserve and book 

balance 

Utility bonds from market 

Utility bonds from market 

Private funding through external contract ops 

R&R 2020‐2024  $6.4m/yr $1.7m/yr $0.0m/yr  $0.0m/yr

Financing option considered for R&R ‘20‐‘24 

Pay as you go (from yearly 

budget surplus) 

Pay as you go (from yearly 

budget surplus) 

Not applicable  Not applicable

Expected immediate increase of utility rate 

No increase 3% 35% 23%

Expected annual increase of utility rate (4‐year average) due to R&R needs 

2.0% 1.5% 1.0% 1.5%

 

5. Conclusions 

In summary, this integrated master planning approach to the City’s water treatment plant, included an 

assessment of the current condition of assets, performance review of process systems and a criticality 

and vulnerability assessment. The existing plant asset condition and performance information was linked 

with the needs of future treatment  improvements to ensure that the true total cost of ownership and 

final  treatment  concepts  were  considered  during  project  planning  and  alternatives  evaluation.  The 

presentation of an integrated master planning methodology using a case study for the City of West Palm 

Beach may  be  used  by  other  utilities  planning major  repairs  and  improvements  to  their  treatment 

facilities. A similar systematic and comprehensive approach can also be helpful  in evaluating financing 

options, including the potential for using Utility’s Reserve and pay as you go approach to utility upgrades. 

In the City of West Palm Beach’s case, once the true cost of ownership was determined, the City was able 

to  eliminate  a  planned  utility  bond  issuance, was  able  to  forgo  two  previous  scheduled  utility  rate 

increases, and fund water facility projects through existing and future internally generated funds with no 

additional debt to the City. 

    

Page 15: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities  Page 15 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs 

Literature [1] GJ Schers et al, City of West Palm Beach Makes Priority Improvements to Aging Water Treatment Plant, 

published in FWRC 2013 

[2] Scott D. Kelly et al, City of West Palm Beach diverse source water system, Paper presented at FSAWWA 

2014 

[3] MWH WA‐28.1 Task 9.2 Field Inspection and Condition Assessment at the City’s WTP Facilities, Final 

Report, July 2014. 

{4] MWH (sub: Amec) WA‐28.1 Task 9.2 Concrete Condition Assessment of the City of West Palm Beach 

WTP, July 2014. 

[5] MWH WA‐28.1 Task 9.3 Capital Investment Program (CIP) for the City’s WTP, Final Report, July 2014. 

[6] MWH WA‐31 Task 2 Evaluation of Water Treatment Alternatives, Final Report, January 2015 

Page 16: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

How Integrated Master Planning Helped the State’s Largest UV Surface Water Treatment Plant Meet Their Future Water Needs

December 1, 2015

Poonam Kalkat, PHDTimothy J. Smith, PE

Page 17: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

Overview

• Facility background

• Why an integrated master planning approach?

o Criticality analysis, condition and vulnerability assessments

o Evaluation of treatment alternatives

o Cost alternatives and financing options

• Conclusion

2

Page 18: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

3

Facility Background

Page 19: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

4

Facility Background

Simplified Existing Treatment Plant Process Flow Diagram

Page 20: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

5

Page 21: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

In 2007, a series of bacteriological hits in the distribution system led to boiled water notifications. Subsequently, the regulator and the City entered Consent Order to upgrade the City’s WTP by 2018.

6

Why an integrated master planning approach?

2008 Consent Order• Strengthen the pathogen barriers in

their treatment process

• Membrane technologies original selected to provide this barrier

o Rising costs

o Change in administration

Other Options?• Were there other alternatives that

would achieve the same objective with lower short and long term costs?

• Since a new plant was not necessarily the solution, the existing facilities needed to be evaluated

o Meet future growth needs?

o R&R costs reasonable?

Page 22: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

2014, the City initiated an integrated master planning approach consisting of:

• Criticality analysis and condition assessment along with vulnerability assessment of existing WTP assets

• Evaluation of treatment alternatives to meet consent requirement and future requirements of the plant

• Lifecycle cost alternatives and financing options for the various alternatives

7

Why an integrated master planning approach?

Page 23: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

8

Page 24: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

Process Evaluation: Performance of the existing treatment process was reviewed by analyzing historic water quality data, monthly operating reports, and other operational records and compared with industry standards and guidelines.

9

Criticality Analysis – Overall Plant Process

Page 25: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

Criticality Analysis – Overall Plant Process

Graphical depiction of flow rating of each individual treatment process

10

0

10

20

30

40

50

60

70

80

90

100

Rat

ed C

apac

ity o

f the

Pro

cess

(M

GD

)

Total Capacity per Process (all units on)

Process Rating per Process (one unit out ofoperation)

Current Rating of WTP = 47 MGD

A number of processes did not meet the ultimate capacity of the plant though they meet the current plant production needs.

Page 26: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

Criticality Analysis and Condition Assessment of Existing Assets

Analysis and Assessment

• Visual inspections

• Interviews with operations staff

• Collection/Review of equipment performance data

• Existing asset data included:– Asset names/codes

– Age/service life

– Photographs

– Performance data

– Condition assessment rating

– Repair and replacement cost

11

Page 27: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

Criticality Analysis and Condition Assessment of Existing Assets

More than 500 assets were analyzed

12

Page 28: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

13

Condition Assessment – Mechanical, Structural, and Electrical

Mechanical Evaluation Structural Evaluation Electrical Evaluation

• pumps• blowers • compressors • piping and valves

• concrete deterioration• rebar corrosion• Leaks, spalling, and

delamination• exfoliation

• motor control centers

• panels• instrumentation

Each assessed for visual defects, vibration, noise, wear and tear, and energy efficiency.

Supplemented by destructive and nondestructive testing

The electrical and control systems had undergone considerable investments in the last seven years

Page 29: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

Architectural Evaluation: Existing buildings were reviewed in terms of building code compliance, life safety and general condition. Options to hurricane hardening of the Operations Building were assessed and presented in the documents and flat roof structures were particularly subjected to a detailed review due to historical leakages.

14

Condition Assessment – Code compliance and life safety

Page 30: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

15

Example of Major finding of Condition Assessment

Mechanical Electrical

South raw water pump No. 27 is failing VFDs on raw water pumps don’t work Sludge removal system in basins at end of life Isolation gates/valves in settled water flume and pipes are

defective and inoperable Some filter and site isolation valves are nearing the end of

useful life

MCC for high service pumps is at end of life and parts are not available

Some site PLCs are obsolete Multiple UPS systems on site; there is a need to centralize and

make resilient Some remote panels should be provided with a secondary power

feed

Structural Architectural

Sections of shoreline Clear Lake eroded Signs of concrete deterioration in the filters and

sedimentations basins Filtered water flume and underground clearwelll are leaking

Operations Building requires hurricane hardening, particular in the hardware

Flat roofs are leaking in some spots and should be rehabilitated or replaced

Buildings should be reviewed in terms of life safety and ADA

Example of the findings of the concrete non‐destructive testing: thermal imaging at the expansion joint in the east sedimentation basin.

Page 31: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

16

Page 32: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

Existing plant systems and additional treatment alternatives were evaluated

• To identify process capacity limitations or systems vulnerabilities

• For meeting future regulatory drivers

• Based on consent order requirements, above criteria and feasibility of implementation the following processes were shortlisted:

– Anion exchange

– Low pressure membrane filtration

– High‐rate clarification

– Ultraviolet light disinfection

Being a surface water plant, activated carbon systems (either granular or powdered) were included for Taste and Odor treatment.

17

Basis of Evaluation of Treatment Alternatives

Page 33: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

Alternative 1: PAC‐UV

18

Treatment Alternatives – PAC-UV

Existing Lime softening process

PAC-T&O control

UV-Additional pathogen protection

Existing site and processes used

Page 34: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

Alternative 2: IX‐UF‐GAC

19

Treatment Alternatives – IX-UF-GAC

IX,UF membrane (Additional pathogen

protection)

CL contact-Additional pathogen protection

GAC-T&O control

New processes built in a vacant section of the existing site

Page 35: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

Alternative 3: IX‐UF‐GAC (Offsite)

20

Treatment Alternatives – IX-UF-GAC (offsite)

IX,UF membrane (Additional pathogen

protection)

GAC-T&O control

CL contact-Additional pathogen protection

New site and processes-need underground utilities to and from new site. Option for redeveloping existing site for residential and/or commercial use.

Page 36: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

Alternative 4: ENH.COAG‐ACT‐UF (Offsite)

21

Treatment Alternatives – ENH.COAG-ACT-UF (offsite)

50 mgd

Clear Lake 

ChlorineAmmonia

CausticFerric Sulfate, AcidPAC

Actiflo –Carb®Offsite 

Storage

Polymer, 

Microsand

UF

Actiflo‐Carb®, UF membrane (Additional pathogen protection)

PAC-T&O control

New site and processes-need underground utilities to and from new site. Option for redeveloping existing site for residential and/or commercial use.

Page 37: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

22

Page 38: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

23

Alternatives Capital Cost Comparison

Alternative 1 -PAC-UV

(at existing site)

Alternative 2 - IX-UF-GAC

(at existing site)

Alternative 3 - IX-UF-GAC

(near ECR)

Alternative 4 -Actiflo-Carb-UF

(at Riviera Beach)

Other Fees $5.6 $18.0 $61.2 $51.3

Site Property Value $0.0 $0.0 -$33.2 -$33.2

Site Works, Power, Demolition $4.3 $14.0 $76.7 $69.4

Treatment $23.6 $75.1 $96.1 $92.6

Pump Stations, Storage, Conveyance $0.0 $0.7 $161.9 $109.2

-$100

-$50

$0

$50

$100

$150

$200

$250

$300

$350

$400

$45020

18 C

AP

EX

Co

st(i

n M

illio

ns)

Other Fees

Site Property Value

Site Works, Power,Demolition

Treatment

Pump Stations, Storage,Conveyance $33.6

$107.7

$362.7

$289.3

Page 39: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

24

Alternatives R&R Cost Comparison

Alternative 1 - PAC-UV

(at existing site)

Alternative 2 - IX-UF-GAC

(at existing site)

Alternative 3 - IX-UF-GAC

(near ECR)

Alternative 4 - Actiflo-Carb-UF

(at Riviera Beach)

Annual R&R CIP 2015-2019 $2.8 $2.3 $0.9 $0.9

Annual R&R CIP 2020-2024 $6.4 $1.7 $0.0 $0.0

Annual R&R CIP 2025-2044 Est. $4.8 $4.8 $4.8 $4.8

$0.0

$1.0

$2.0

$3.0

$4.0

$5.0

$6.0

$7.0A

nn

ual

R&

R C

ost

s(i

n M

illio

ns)

Annual R&R CIP 2015-2019

Annual R&R CIP 2020-2024

Annual R&R CIP 2025-2044 Est.

Page 40: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

25

Alternatives Operating Cost Comparison

ExistingAlternative 1 - PAC-

UV(at existing site)

Alternative 2 - IX-UF-GAC

(at existing site)

Alternative 3 - IX-UF-GAC

(near ECR)

Alternative 4 -Actiflo-Carb-UF

(at Riviera Beach)

Other OPEX $3.91 $3.91 $3.91 $3.91 $3.91

Waste to Sewer $0.10 $0.10 $0.20 $0.19 $0.11

Sludge $0.96 $0.96 $0.00 $0.00 $0.90

Labor $4.47 $4.47 $4.19 $3.63 $3.63

Chemicals $4.38 $4.38 $2.22 $2.22 $4.24

Energy $1.40 $1.44 $1.54 $1.70 $1.83

$0.00

$2.00

$4.00

$6.00

$8.00

$10.00

$12.00

$14.00

$16.00

$18.00

2018

OP

EX

Co

st

(in

Mill

ion

s)

Other OPEX

Waste to Sewer

Sludge

Labor

Chemicals

Energy

Page 41: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

26

Alternatives Lifecycle Cost Comparison

$0.00

$100.00

$200.00

$300.00

$400.00

$500.00

$600.00

$700.00

$800.00

$900.00

$1,000.00

0 5 10 15 20 25 30

Cu

mu

lati

ve N

et P

rese

nt

Val

ue

(201

8 M

illio

ns)

Years in Operation

Alternative 1 PAC-UV(at existing site)Alternative 2 IX-UF-GAC(at existing site)Alternative 3 IX-UF-GAC (near ECR)Alternative 4 Actiflo-Carb-UF(at Riviera Beach)Existing

Page 42: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

27

Summary of Financing Options and Parameters for Alternatives

Page 43: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

Not membranes!

Alternative 1 PAC-UV as it would not degrade the Utilities debt position and would not require an immediate utility rate increase.

The project team is moving ahead with the design and ground breaking for construction is expected in late spring of 2016.

28

…and the winner is?

Page 44: FSAWWA Paper and Presentation Integrated master planning WPB 12012015

Questions?

29