fsawwa paper and presentation integrated master planning wpb 12012015
TRANSCRIPT
FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities Page 1 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs
How Integrated Master Planning Helped the State’s Largest UV Surface Water
Treatment Plant Meet Their Future Water Needs
Authors: GJ Schers1 PMP, Timothy Smith1 PE, PMP, Scott Kelly2 PE, Poonam Kalkat2 PhD
1 MWH 2 City of West Palm Beach
1. Introduction
The City of west Palm Beach draws its source water from Lake Okeechobee, Grassy Waters Preserve which
is a pristine Everglades wetland area, and available stormwater systems. Using surface water as its source
water makes this utility fairly unique in the South Florida region and requires the water treatment plant
to regularly adjust the process to meet seasonal variations in water quality. Towards this goal, the City of
West Palm Beach has made several priority improvements to their water treatment plant (WTP) in the
past seven years (FWRC article, Dec 2013) [1]. These improvements include replacement of equipment at
the end of its useful life, elimination of gaseous chemicals for staff and public safety, and modification to
the control and electrical systems to provide automated plant operation and reliable power distribution
as well as backup power generation systems for the plant.
The WTP, located in downtown West Palm Beach, has a rated capacity of 47 MGD and utilizes a
conventional treatment process consisting of coagulation, flocculation/sedimentation, filtration over
dual‐media, biological‐active rapid gravity filters, and disinfection with chloramines. Powdered activated
carbon can be added to the raw water intake of the plant. A corrosion inhibitor (poly/orthophosphate
blend) and fluorosilicic acid is added at the mixing metering header just upstream of the Ground Storage
Tanks. See Figure 1 for a simplified process flow diagram of the existing WTP.
Figure 1: Simplified Existing Treatment Plant Process Flow Diagram
The WTP site structures were originally built in 1894 by Henry Flagler with major expansions in the 1920’s,
1960’s, 1990’s and 2010 and is surrounded by residential homes, high‐rise buildings, and businesses.
Figure 2 shows an aerial photograph of the WTP with a depiction of the location and nature of each recent
improvement.
FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities Page 2 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs
Figure 2: Aerial picture of today’s WTP
In 2013, the City decided to review the technology alternatives to strengthen the pathogen barriers as a
requirement of a 2008 Consent Order with the Palm Beach County Health Department that will be
discussed in more detail later in this article. The implementation of the membrane based alternative in
the Consent Order was projected to require an immediate utility rate increase. The City questioned if
there could be alternatives that would be less costly in terms of capital and operating costs both in the
short and long term and would not require an immediate rate increase. The City also wanted to confirm
that the facility would meet future demands due to an increasing growth rate in the City while also
quantifying replace and refurbishment (R&R) costs over the long term.
FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities Page 3 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs
Therefore in 2014, the City initiated an integrated master planning approach to identify the present and
future water facility needs of the City. This article outlines the basic components of this integrated master
planning approach as listed below:
Condition assessment and criticality analysis along with vulnerability assessment of existing WTP
assets are outlined in section 2. Deficiencies identified in this process are translated into R&R
needs for the existing WTP.
Evaluation of treatment alternatives to meet the future requirements of the plant are discussed
in Section 3. This includes raw and finished water quality analysis, to verify trends and changes,
assessment of current and potential future regulations, and options to optimize energy and
chemical usage. In addition the assessment evaluates the possibility of relocating the water
treatment system out of the downtown area and to free‐up space for future commercial and
residential development, an option preferred by some City commissioners.
Opinion of probable construction costs for the treatment alternatives considered above are
outlined in section 4 along with a comparison of life cycle cost of ownership.
The following sections follow the same sequence of integrated master planning, as outlined above.
2. Condition Assessment and Criticality Analysis of Existing Assets
The first step for integrated master planning required a comprehensive condition assessment of the
existing WTP assets by visual inspections of assets as well as extensive discussions with Operations and
Maintenance personnel [3]. Equipment performance data was collected and reviewed to detect
deficiencies such as deviations from original manufacturer’s specifications. The data from inspections was
collected and arranged in lists with asset names and codes, photographs, performance data, condition
assessment rating, and repair and replacement cost for each need.
A description of each water plant area assessment is provided below. Additionally, major findings per area
are highlighted and some examples are included in Table 1:
Process Evaluation: Performance of the existing treatment process was reviewed by analyzing historic
water quality data, monthly operating reports, and other operational records and compared with industry
standards and guidelines, including the Florida Administrative Code, the Recommended Standards for
Water Works, Great Lakes, 2012 edition, and MWH Best Practice Design Guides. In addition to the
condition assessment, a criticality analysis and vulnerability assessment was performed. The results of the
process flow rating review of each individual process are depicted in Figure 3 and shows that a number of
processes including sedimentation basins, recarbonation system, washwater recovery basin, thickener,
and calcium oxide (lime) storage do not meet the ultimate capacity of the plant though they meet the
current plant production needs.
Mechanical Evaluation: The condition of the existing mechanical equipment, such as pumps, blowers,
compressors, piping and valves was assessed for visual defects, vibration, noise, wear and tear, and energy
efficiency. The existing hydraulic performance of the pumps was tested by flow and pressure logging and
the results were compared with the original shop drawing performance curves. Inspection for Health and
Safety and Code compliance was also performed. These inspections included the safety showers/eyewash
equipment, ventilation equipment, fire suppression, and plumbing fixtures.
FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities Page 4 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs
Figure 3: Graphical depiction of flow rating of each individual treatment process
Structural Evaluation: The structural evaluation documented concrete deterioration and rebar corrosion.
Recorded deficiencies included visual evidence of leaks, spalling, delamination, exfoliation, and exposed,
corroded, or deteriorated rebar. This visual inspection was then supplemented by destructive and non‐
destructive testing for the sedimentation basin and filter reinforced concrete structures consisting of in‐
place rebound hammer testing, Ground Penetrating Radar (GPR) concrete scanning, and strength and
laboratory testing of concrete core samples and steel reinforcement samples.
Electrical Evaluation: The electrical and control systems had undergone considerable investments in the
last seven years providing more reliable power supply to and within the site, full capacity backup power,
and a new communications protocol and control system. Therefore the evaluation only focused on motor
control centers, panels, and instrumentation that were not replaced or substituted as part of the past
upgrades.
Architectural Evaluation: Existing buildings were reviewed in terms of building code compliance, life safety
and general condition. Options to hurricane hardening of the Operations Building were assessed and
presented in the documents and flat roof structures were particularly subjected to a detailed review due
to historical leakages.
Examples of observations during the Condition Assessment for each discipline are included in Table 1.
0
10
20
30
40
50
60
70
80
90
100
Rated
Capacity of the Process (MGD)
Total Capacity per Process (all units on)Process Rating per Process (one unit out of…
Current Rating of WTP = 47 MGD
FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities Page 5 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs
Table 1: Examples of observations during Condition Assessments for each discipline and a typical photograph w/imaging of the structural non‐destructive investigation
Examples of Major Findings of Condition Assessment per Discipline
Mechanical Electrical
South raw water pump No. 27 needs replacement
VFDs on raw water pumps don’t work effectively
Sludge removal system in basins is at the end of
useful life
Isolation gates/valves in settled water flume and
pipes are defective and inoperable
Some filter and site isolation valves are nearing
the end of useful life
MCC for high service pumps is at end of useful life
and parts are not available
Some site PLCs are obsolete
Multiple UPS systems on site; there is a need to
centralize and make resilient
Some remote panels should be provided with a
secondary power feed
Structural Architectural
Sections of shoreline Clear Lake eroded
Signs of concrete deterioration in the filters and
sedimentations basins
Filtered water flume and underground clearwell
show signs of leakage
Operations Building requires hurricane hardening,
particular in the hardware
Flat roofs are leaking in some spots and should be
rehabilitated or replaced
Buildings should be reviewed in terms of life
safety and ADA
Just an example of the
findings of the concrete
non‐destructive testing:
photograph and thermal
imaging at same location at
the expansion joint in the
east sedimentation basin.
The most relevant results from the criticality analysis and vulnerability assessments are presented in Table
2. As an example, this table notes that some of the hydraulic conduits and connections between the
treatment processes are either single pipelines or single reinforced concrete structures and cannot be
taken out of operation for repair and cleaning without a full plant outage. Another example of a factor
effecting criticality is the significant risk of flooding in both the West and East High Service Pump Stations
due to hydraulic conditions, which can affect mechanical and electrical equipment housed in these
buildings.
FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities Page 6 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs
Table 2: Significant observations during the Criticality Analysis and Vulnerability Assessment
Area Area Name Single Point of Failure/Vulnerability Description Comment
02 Flocculation and
Sedimentation Basin
Single settled water reinforced concrete flume and
isolation gates which are inoperable affecting the use
of the 60" bypass piping
02 Recarbonation
System
Single carbon dioxide dosing skid feeds a single
dosing point in the recarbonation basin/settled water
flume
Use of bypass piping requires
carbon dioxide to be dosed
also in 60" bypass piping
03 Filters
Single filtered water flume and pipeline and
reinforced concrete flume does not appear to be
watertight which could provide a contamination risk
from storm water runoff and groundwater infiltration
This was also documented in
reports during 2008‐2010
period
03 Filters
Filter control panels have no secondary power feed
and Profibus configuration changes in filter area have
not been completed as per agreed plan
04 Transfer Pump
Station
Pump station has a single wet well without options
for sectional isolation
04 Transfer Pump
Station
Due to floor elevation, a failure of the transfer pumps
in the East HSP building presents a flooding risk
affecting transfer and high service pumps and
associated gear
04 Transfer Pump
Station
Single Mixing and Metering header piping, and single
pipeline cross just upstream of the ground storage
tanks
04‐05
High Service Pump
Stations (East and
West)
Due to floor elevation, the West HSP mechanical and
electrical gear can flood when the control valve to
the 1 MG clearwell fails or loses power affecting raw
water and high service pumps and gear
There have been reports of
flooding and near‐misses in
West HSP in the past
05 Ground Storage
Tank
Old 1 MG below grade clearwell does not appear to
be watertight and introduces a risk for contaminants
from storm water runoff and groundwater infiltration
06 Sludge Thickener
Single sludge thickener and sludge pump station
cannot be isolated or taken out of operation/service
for extended periods of time
De‐sludging from
sedimentation basins cannot
be delayed beyond 12 hours
3. Treatment Alternatives to Meet Future Needs
Assessing the condition of the existing plant systems and identifying areas with process capacity
limitations or systems vulnerabilities, provided a baseline for evaluation of upgrades and treatment
alternatives for modernizing the existing plant.
The existing process has been successful in meeting the primary and secondary drinking water standards
and regulations over the last eight years. However, in 2007, a series of bacteriological hits in the
distribution system led to two boil water notifications. Investigations by Public Utilities department staff,
regulators, and consulting engineers led to the discovery of an improperly sealed interconnect not shown
on as‐built drawings, which allowed filtered, chlorinated water to bypass the storage tanks without
providing the contact time necessary for bacteriological and virus kill prior to distribution. Subsequently,
FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities Page 7 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs
the regulator (the Palm Beach County Department of Health) and the City entered into an agreement
(Consent Order) to upgrade the City’s WTP by 2018.
In addition the Utility wanted to address the concern of always being able to meet both the Stage 1
Disinfection and Disinfection Byproduct (D/DBP) and Long‐Term (2) Enhanced Surface Water Treatment
Rule (ESWTR) requirements, i.e. meeting the Total Organic Carbon (TOC) removal and pathogen log
inactivation requirements, while not exceeding the maximum disinfectant residual level of chloramines
and disinfection byproduct levels of trihalomethanes (THM) and haloacetic acids (HAA). These
requirements are summarized in Table 3.
Table 3: EPA Rules affecting on‐going operation
Rule Contaminant or Treatment
Requirement
Limit
Stage 1 D/DBP Rule: Maximum
Contaminant Levels (MCL)
THM
HAA
80 µg/L
60 µg/L
Stage 1 D/DBP Rule: Maximum Residual
Disinfectant Levels (MRDL)
Chloramine 4 mg/L
Stage 1 D/DBP Rule: Required Removal of
TOC
TOC removal >=40%
Surface Water Treatment Rules (Original,
Interim and Long‐Term)
Virus inactivation
Giardia inactivation
Filtered water turbidity
Cryptosporidium inactivation
4 log
3 log
<0.3 NTU 95%, <1.0 NTU 100%
2 log
While the criticality and vulnerability assessment identified current deficiencies in the water treatment
process and opportunities for improvements, it did not address future regulatory drivers including: final
Contaminant Candidate List 4 (CCL‐4), final Third Determination of CCL‐3, proposed Carcinogenic Volatile
Organic Compound (cVOC), Lead and Copper Rule Long‐Term Revisions (LCR‐LTR) and Perchlorate Rules,
and Third Six‐Year Review.
Following the stipulations in the Consent Order and based on the future regulations mentioned above,
the City determined that the future water treatment process should include additional pathogen
protection and additional taste and odor (T&O) control. The considered processes to provide additional
treatment for pathogens and T&O included activated carbon treatment (either granular or powdered),
anion exchange, low pressure membrane filtration, high‐rate clarification, and ultraviolet light
disinfection. Other processes, while potentially effective for additional treatment as outlined above, were
discarded for a variety of reasons. For example, ozone for T&O control would have resulted in elevated
bromate levels in the finished water, close to or even above the standard of 10 µg/L [5].
A short description of each alternative is provided below, while a more detailed process description and
simplified Process Flow Diagrams (PFD’s) are presented in Figure 4:
Alternative 1: PAC‐UV: Alternative 1 maintains the existing lime softening process with the addition of a
dedicated powdered activated carbon (PAC) contact chamber on the raw water for T&O control.
Additional pathogen protection is provided with ultraviolet (UV) light disinfection process downstream of
the filters.
Alternative 2: IX‐UF‐GAC: Alternative 2 is located on a 4.5‐acre vacant lot on the existing WTP site and
uses new processes in suspended anion exchange (IX), ultrafiltration (UF) membrane treatment, and
granular activated carbon (GAC) absorption. Additional pathogen protection is provided with the
FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities Page 8 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs
membranes and the extended free chlorine contact time. T&O control is provided with GAC Absorption
through an extended empty bed contact time.
Alternative 3: IX‐UF‐GAC (ECR Site): Alternative 3 is in essence the same process as Alternative 2, however
it is located on a Greenfield site near the East Central Regional (ECR) Water Reclamation Facility (WRF).
Once relocated, the existing WTP site would be redeveloped for residential and/or commercial use.
Additional pathogen protection is provided with membranes and an extended free chlorine contact time.
T&O control is provided with GAC Absorption with an extended empty bed contact time.
Alternative 4: ENH.COAG‐ACT‐UF (Riviera Beach Site): Alternative 4 includes Actiflo‐Carb® and
ultrafiltration membrane treatment, and is located on a new site in Riviera Beach. The existing WTP site
would be redeveloped for residential and/or commercial development. Additional pathogen protection is
provided with the membranes and extended free chlorine contact time. T&O control is provided with
continuous PAC pre‐treatment integrated with the Actiflo® clarification process.
4. Cost of Alternatives and Financing Options
The R&R needs for each treatment alternative are different due to the different approaches towards the
use of existing assets. The plant upgrades needs for each alternative are also different due to the use of
different treatment processes to meet the objectives.
For each alternatives, capital, operating and life cycle cost estimates were prepared, as outlined below.
Capital Cost Estimates for Plant Upgrades
Planning level capital cost estimates (CAPEX) for each alternative were developed. A contingency
allowance of 30% is considered in the cost estimates of which 20% was included in the cost estimate and
the other 10% was allocated by the City in the City’s reserve. The CAPEX estimates follow Class 5 Opinion
of Probable Construction Costs (OPCC) as defined by the Association for the Advancement of Cost
Engineering International (AACEI), Recommended Practice No. 18R‐97. This level of cost is a planning level
order of magnitude cost with an expected accuracy range of ‐20% to ‐50% below and 30% to 100% above.
A summary of the CAPEX is included in Figure 5. The CAPEX for Alternatives 3 and 4 includes the
conveyance to and from the new sites and demolition of structures at the existing WTP, removal and
disposal of construction debris off site, remediation of the drinking water sludge area to prepare the site
for new residential, and commercial construction. It also contains the market value of the 26 acres
property of the existing WTP site, which becomes vacant when a replacement WTP is built and is
operational at a new site. As shown, the onsite alternatives were more cost‐effective than the off‐site
alternatives. Alternative 1 PAC‐UV has the lowest CAPEX at $33.5 million, with Alternative 2 IX‐UF‐GAC (at
existing site) the next most cost‐effective option with an additional CAPEX of $74.2 million. Alternatives 3
and 4 (the off‐site alternatives) are at least $250 million more expensive than Alternative 1. From the off‐
site alternatives, Alternative 4 ACTIFLOCARB‐UF (at Riviera Beach) is more cost‐effective mainly due to
the reduced CAPEX for the raw water and finished water conveyance.
FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities Page 9 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs
Alternative 1 (at WTP site) PAC improvements involve new auger, slurry mixer and dosing lines to the new PAC basin. Continued use of sedimentation basins will ultimately involve re‐rating by providing additional valving, extending flocculation zone, and providing lamella plate settling units and replacing the sludge removal system. Recarbonation will be provided in settled water flume and settled water pipe. Existing rapid gravity filters (RGF) will be provided with new media. Filter effluent will be combined requiring additional isolation valves and pipelines. A new transfer pump station will be provided to convey flow through the new UV installation to the existing mixing and metering header. The new UV system and associated equipment will be housed in a new building. Finished water will be dosed with free chlorine downstream of the UV system before chloramine formation at the existing mixing and metering header. The existing filtered water flume and buried clearwell will be demolished.
Alternative 2 (at WTP site) A new IX process will be included to remove the organics. UF membranes will be provided for suspended solids and pathogens removal and will be housed in a new building. The membranes will be located downstream of IX, while existing dual media filters will be converted to GAC absorbers by changing the media. The 32 re‐purposed filters will be retrofit with plastic underdrain block with an IMS cap allowing for deeper media depth and covered with retractable FRP covers. Similarly to Alternative 1, effluent from the GAC contactors will be combined and transferred to a new reinforced concrete chlorine contact basin to provide a free chlorine contact time providing virus and Giardia inactivation control. Chloramines will be used as secondary disinfectant. This alternative will involve the excavation of unsuitable soils from the vacant lot and will eliminate existing filtered water flume and buried clearwell.
Alternative 3 (West, near ECR site) The process is an exact match of Alternative 2. UF membranes will be constructed for suspended solids and pathogens removal and will be housed in a new building. New GAC adsorbers will be constructed using pressurized vessels instead of open reinforced concrete structures. Free chlorine will be used for primary disinfection and chloramines for maintaining a residual in the distribution system. This alternative requires the repurpose of the existing vacant 26‐acre site on the south side of Jog road, east of the City well field.
Alternative 4 (East, Riviera Beach site) A new enhanced coagulation process integrated with PAC pretreatment will be provided to remove source water organics and T&O. UF membranes will be constructed for remaining suspended solids and pathogens removal and will be housed in a new building. The membranes are located downstream of the Actiflo® Carb process and safety strainer. A new chlorine contact basin will be constructed to provide free chlorine contact time for virus and Giardia inactivation. Chloramines will be used as a secondary disinfectant. The proposed 8.5‐acre treatment site is west of the FPL power facility in Riviera Beach. Raw water will be pumped approximately 3.75 miles north from the existing WTP site and finished water will be pumped back to existing site.
Figure 4: Simplified diagram and a description of each of the treatment alternatives
50 mgd
Clear Lake
ChlorineAmmonia
CausticFerric Sulfate, Acid
PAC
Actiflo –Carb®Offsite
Storage
Polymer,
Microsand
UF
FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities Page 10 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs
Figure 5: Graphical depiction of CAPEX for each of the alternatives
Annual Allocation for R&R Needs
The MWH team conducted field inspections and assessments of the existing plant assets as described
before. In addition the team defined the refurbishment and rehabilitation (R&R) needs of the
infrastructure that would need to be maintained as part of the long term solution to upgrade the WTP
with either UV disinfection (Alternative 1) or UF membrane (Alternatives 2‐4) technologies. The two
alternatives at the existing site (Alternatives 1 and 2) have different R&R needs based on the existing
processes and structures remaining in service. Similarly, the offsite alternatives (Alternatives 3 and 4)
require only urgent repairs until the new plant is operational as reflected in the early R&R costs.
CAPEX estimates for R&R needs were developed for the next 10 years (Periods 2015‐2019 and 2020‐2024)
with the same planning level accuracy as the Plant Upgrades CAPEX estimates. The R&R needs for the
following 20 years (Period 2025‐2044) were estimated and included in the assessment for completeness,
and were kept the same between the options. The CAPEX numbers were subsequently amortized to an
annual allocation. The results are presented in Figure 6.
Alternative 1 ‐PAC‐UV
(at existing site)
Alternative 2 ‐IX‐UF‐GAC
(at existing site)
Alternative 3 ‐IX‐UF‐GAC (near ECR)
Alternative 4 ‐Actiflo‐Carb‐UF
(at RivieraBeach)
Other Fees $5.6 $18.0 $61.2 $51.3
Site Property Value $0.0 $0.0 ‐$33.2 ‐$33.2
Site Works, Power, Demolition $4.3 $14.0 $76.7 $69.4
Treatment $23.6 $75.1 $96.1 $92.6
Pump Stations, Storage,Conveyance
$0.0 $0.7 $161.9 $109.2
‐$100
‐$50
$0
$50
$100
$150
$200
$250
$300
$350
$400
$450
2018 CAPEX
Cost
(in M
illions)
Other Fees
Site Property Value
Site Works, Power,DemolitionTreatment
Pump Stations,Storage, Conveyance $33.6
$107.7
$362.7
$289.3
FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities Page 11 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs
Figure 6: Annual Cost of R&R needs
Operating Cost Estimates
Estimates of Operating Expenses (OPEX) were evaluated on the basis of energy, chemicals, labor,
maintenance and repair, sludge hauling and disposal, liquid waste disposal to sewer and other
miscellaneous items. Energy costs include pumping for primary and secondary flow streams, mixers, lime
slakers, sludge collection, UV power draw, and other electrical consumers at the WTP. Energy costs also
include the conveyance to and from the offsite location for Alternatives 3 and 4. Chemicals include PAC,
IX resin, sodium chloride, unslaked lime, ferric sulfate, sulfuric acid, micro‐sand, cationic polymer, carbon
dioxide, membrane cleaning chemicals, GAC regeneration or replacement, UV cleaning acid, sodium
hypochlorite, aqueous ammonia, sodium hydroxide (or caustic soda), poly/orthophosphate (corrosion
inhibitor), hydrofluorosilicic acid (fluoride), and anionic polymer. Labor costs include burden costs for full‐
time equivalent (FTE) estimates for supervisors, operators, technicians, and administrative assistants
based on requirements of 60‐699.310 F.A.C. Category I or Category II staffing requirements and the 2014
organizational staffing plans for the City’s WTP. Sludge disposal costs include lime sludge or ferric sludge
thickening and dewatering, storage, hauling, and disposal. Sewer disposal costs include disposal of liquid
wastes into the sewer including filter press filtrate, Washwater lamella separator sludge, and ion exchange
waste brine. Miscellaneous operating costs are items not specifically called out above like diesel fuel
usage, hired labor and technicians and other maintenance materials, and calibration chemicals for
instruments. Unit costs for each of the above operating cost categories were obtained from the City or
from vendors. The operating costs for 2018 are summarized in Figure 7.
Alternative 1 ‐PAC‐UV
(at existing site)
Alternative 2 ‐IX‐UF‐GAC
(at existing site)
Alternative 3 ‐IX‐UF‐GAC (near ECR)
Alternative 4 ‐Actiflo‐Carb‐UF
(at RivieraBeach)
Annual R&R CIP 2015‐2019 $2.8 $2.3 $0.9 $0.9
Annual R&R CIP 2020‐2024 $6.4 $1.7 $0.0 $0.0
Annual R&R CIP 2025‐2044 Est. $4.8 $4.8 $4.8 $4.8
$0.0
$1.0
$2.0
$3.0
$4.0
$5.0
$6.0
$7.0
Annual R&R Costs
(in M
illions)
Annual R&R CIP2015‐2019
Annual R&R CIP2020‐2024
Annual R&R CIP2025‐2044 Est.
FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities Page 12 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs
Figure 7: Graphical depiction of OPEX for each of the alternatives, compared with the existing situation, for the year 2018 at a flow of 27.5 MGD
The annual OPEX in 2018 for the existing water treatment plant is forecast at approximately $15.2 million.
For Alternative 1 PAC‐UV the annual OPEX is forecast to increase to $15.4 million due to the addition of
PAC and UV treatment and for Alternative 2 IX‐UF‐GAC (at existing site) and Alternative 3 IX‐UF‐GAC (near
ECR) these costs are forecast to reduce to $12.5 and $12.1 million, respectively, mainly due to the
reduction of the use of coagulation chemicals and disposal of sludge. For Alternative 4 ACTIFLOCARB‐UF
(at Riviera Beach) the annual OPEX is forecast to remain the same as the existing water treatment plant.
Life Cycle Cost Estimates
The summary of the life cycle costs estimates, expressed in Net Present Value (NPV), are provided in
Figure 8. The Net Present Value calculations assume an estimated construction completion date in 2018
to meet the Consent Order deadline. The CAPEX of the Plant Upgrades and the annual expenditure of R&R
and the operating costs were presented in the sections before.
NPV costs are forecasted starting in year 2018 to coincide with project completion. The NPV shown for
year 0 represents cumulative expenditures for years 2015 through 2018. The existing WTP NPV includes
2.5 million dollars (2018 $) per year for R&R. CAPEX, R&R and OPEX costs for the existing WTP and
Alternatives 1‐4 are illustrated as stacked graphs in Figure 8. The alternatives utilizing the existing site
(e.g. Alternatives 1 and 2) have a lower NPV than the offsite alternatives (e.g. Alternatives 3 and 4). From
the onsite alternatives, PAC‐UV (Alternative 1) is more cost effective in the first 15 years of operation,
Existing
Alternative 1 ‐PAC‐UV
(at existingsite)
Alternative 2 ‐IX‐UF‐GAC(at existing
site)
Alternative 3 ‐IX‐UF‐GAC (near ECR)
Alternative 4 ‐Actiflo‐Carb‐UF
(at RivieraBeach)
Other OPEX $3.91 $3.91 $3.91 $3.91 $3.91
Waste to Sewer $0.10 $0.10 $0.20 $0.19 $0.11
Sludge $0.96 $0.96 $0.00 $0.00 $0.90
Labor $4.47 $4.47 $4.19 $3.63 $3.63
Chemicals $4.38 $4.38 $2.22 $2.22 $4.24
Energy $1.40 $1.44 $1.54 $1.70 $1.83
$0.00
$2.00
$4.00
$6.00
$8.00
$10.00
$12.00
$14.00
$16.00
$18.00
2018 OPEX
Cost
(in M
illions)
Other OPEX
Waste toSewerSludge
Labor
Chemicals
Energy
FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities Page 13 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs
however after year 15, IX‐UF‐GAC (Alternative 2) becomes more cost effective, mainly due to the lower
OPEX. From the off‐site alternatives, ACTIFLO‐CARB‐UF (at Riviera Beach) (Alternative 4) is more cost
effective in the first 22 years of operation but after year 22, IX‐UF‐GAC (near ECR) (Alternative 3) becomes
more cost effective.
Figure 8: Graphical depiction of NPV for each of the alternatives
Financing Options and Impact on Rates
Several financing options were considered for each treatment alternative because of the differences in the initial CAPEX needs. A financial summary is provided in Table 4. The credit rating of the City of West Palm Beach is slightly different for each rating agency, but is general around ‘AA’ (double A). The utility department has already a relatively high debt, translated in the current rate being in the top quadrant of all utilities rates in Florida, compared to the City’s own targets:
Debt outstanding to net plant ratio is 49.6% (target <50%)
Debt per customer is $2,579 (target <$1,800)
Affordability to customers is 2.48% (target of <2.00%)
Based on the existing debt situation not meeting targets, the City expressed an interest to pursue opportunities to look at alternative financing options, if possible and feasible. Such alternative option was considered for alternative 1, with the relatively low initial capital needs. The available funds in the City’s Utility Reserve Fund would suffice to cover the initial CAPEX needs. Alternative financing options were considered but found not feasible for Alternatives 2 and 3, and the capital necessary to fund the CAPEX needs would need to be raised through the issuance of new bonding. Private financing would fund Alternative 4. This option also assumed that the ownership and operations of the new assets would be in
$0
$100
$200
$300
$400
$500
$600
$700
$800
$900
$1,000
0 5 10 15 20 25 30
Cumulative Net Present Value
(2018 M
illions)
Years in Operation
Alternative 1 PAC‐UV(at existing site)
Alternative 2 IX‐UF‐GAC(at existing site)
Alternative 3 IX‐UF‐GAC (near ECR)
Alternative 4 Actiflo‐Carb‐UF(at Riviera Beach)
Existing
FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities Page 14 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs
private hands under a 30‐year concession agreement between the City and the private company. The financial implications on utility rates for all alternatives were estimated based on current best knowledge of capital needs, financing costs and yearly operations costs.
The Utility Department management brought the results of the study, as presented in Table 4, to a City Commission meeting for decision making. Extensive discussions transpired on details of the alternatives, but in the end the City decided to move forward with Alternative 1 as it would not degrade the Utilities debt position and would not require an immediate utility rate increase. The project team is moving ahead with the design and ground breaking for construction is expected in late spring of 2016.
Table 4: Summary of Financing Options and Parameters for Alternatives
Alternative 1
PAC‐UV (at existing site)
Alternative 2
IX‐UF‐GAC (at existing site)
Alternative 3
IX‐UF‐GAC (near ECR)
Alternative 4
Actiflo‐Carb‐UF‐GAC (at Riviera
Beach)
CAPEX $33.6m $107.7m $362.7m $289.3m
R&R 2015‐2019 $2.8m/yr $2.3m/yr $0.9m/yr $0.9m/yr
Financing option considered for CAPEX and R&R ‘15‐‘19
City’s Utility reserve and book
balance
Utility bonds from market
Utility bonds from market
Private funding through external contract ops
R&R 2020‐2024 $6.4m/yr $1.7m/yr $0.0m/yr $0.0m/yr
Financing option considered for R&R ‘20‐‘24
Pay as you go (from yearly
budget surplus)
Pay as you go (from yearly
budget surplus)
Not applicable Not applicable
Expected immediate increase of utility rate
No increase 3% 35% 23%
Expected annual increase of utility rate (4‐year average) due to R&R needs
2.0% 1.5% 1.0% 1.5%
5. Conclusions
In summary, this integrated master planning approach to the City’s water treatment plant, included an
assessment of the current condition of assets, performance review of process systems and a criticality
and vulnerability assessment. The existing plant asset condition and performance information was linked
with the needs of future treatment improvements to ensure that the true total cost of ownership and
final treatment concepts were considered during project planning and alternatives evaluation. The
presentation of an integrated master planning methodology using a case study for the City of West Palm
Beach may be used by other utilities planning major repairs and improvements to their treatment
facilities. A similar systematic and comprehensive approach can also be helpful in evaluating financing
options, including the potential for using Utility’s Reserve and pay as you go approach to utility upgrades.
In the City of West Palm Beach’s case, once the true cost of ownership was determined, the City was able
to eliminate a planned utility bond issuance, was able to forgo two previous scheduled utility rate
increases, and fund water facility projects through existing and future internally generated funds with no
additional debt to the City.
FSAWWA Fall Conf. Track Tue 2A Management Tools for Water Utilities Page 15 of 15 How Integrated Master Planning Helped UV Surface WTP Meet Future Water Needs
Literature [1] GJ Schers et al, City of West Palm Beach Makes Priority Improvements to Aging Water Treatment Plant,
published in FWRC 2013
[2] Scott D. Kelly et al, City of West Palm Beach diverse source water system, Paper presented at FSAWWA
2014
[3] MWH WA‐28.1 Task 9.2 Field Inspection and Condition Assessment at the City’s WTP Facilities, Final
Report, July 2014.
{4] MWH (sub: Amec) WA‐28.1 Task 9.2 Concrete Condition Assessment of the City of West Palm Beach
WTP, July 2014.
[5] MWH WA‐28.1 Task 9.3 Capital Investment Program (CIP) for the City’s WTP, Final Report, July 2014.
[6] MWH WA‐31 Task 2 Evaluation of Water Treatment Alternatives, Final Report, January 2015
How Integrated Master Planning Helped the State’s Largest UV Surface Water Treatment Plant Meet Their Future Water Needs
December 1, 2015
Poonam Kalkat, PHDTimothy J. Smith, PE
Overview
• Facility background
• Why an integrated master planning approach?
o Criticality analysis, condition and vulnerability assessments
o Evaluation of treatment alternatives
o Cost alternatives and financing options
• Conclusion
2
3
Facility Background
4
Facility Background
Simplified Existing Treatment Plant Process Flow Diagram
5
In 2007, a series of bacteriological hits in the distribution system led to boiled water notifications. Subsequently, the regulator and the City entered Consent Order to upgrade the City’s WTP by 2018.
6
Why an integrated master planning approach?
2008 Consent Order• Strengthen the pathogen barriers in
their treatment process
• Membrane technologies original selected to provide this barrier
o Rising costs
o Change in administration
Other Options?• Were there other alternatives that
would achieve the same objective with lower short and long term costs?
• Since a new plant was not necessarily the solution, the existing facilities needed to be evaluated
o Meet future growth needs?
o R&R costs reasonable?
2014, the City initiated an integrated master planning approach consisting of:
• Criticality analysis and condition assessment along with vulnerability assessment of existing WTP assets
• Evaluation of treatment alternatives to meet consent requirement and future requirements of the plant
• Lifecycle cost alternatives and financing options for the various alternatives
7
Why an integrated master planning approach?
8
Process Evaluation: Performance of the existing treatment process was reviewed by analyzing historic water quality data, monthly operating reports, and other operational records and compared with industry standards and guidelines.
9
Criticality Analysis – Overall Plant Process
Criticality Analysis – Overall Plant Process
Graphical depiction of flow rating of each individual treatment process
10
0
10
20
30
40
50
60
70
80
90
100
Rat
ed C
apac
ity o
f the
Pro
cess
(M
GD
)
Total Capacity per Process (all units on)
Process Rating per Process (one unit out ofoperation)
Current Rating of WTP = 47 MGD
A number of processes did not meet the ultimate capacity of the plant though they meet the current plant production needs.
Criticality Analysis and Condition Assessment of Existing Assets
Analysis and Assessment
• Visual inspections
• Interviews with operations staff
• Collection/Review of equipment performance data
• Existing asset data included:– Asset names/codes
– Age/service life
– Photographs
– Performance data
– Condition assessment rating
– Repair and replacement cost
11
Criticality Analysis and Condition Assessment of Existing Assets
More than 500 assets were analyzed
12
13
Condition Assessment – Mechanical, Structural, and Electrical
Mechanical Evaluation Structural Evaluation Electrical Evaluation
• pumps• blowers • compressors • piping and valves
• concrete deterioration• rebar corrosion• Leaks, spalling, and
delamination• exfoliation
• motor control centers
• panels• instrumentation
Each assessed for visual defects, vibration, noise, wear and tear, and energy efficiency.
Supplemented by destructive and nondestructive testing
The electrical and control systems had undergone considerable investments in the last seven years
Architectural Evaluation: Existing buildings were reviewed in terms of building code compliance, life safety and general condition. Options to hurricane hardening of the Operations Building were assessed and presented in the documents and flat roof structures were particularly subjected to a detailed review due to historical leakages.
14
Condition Assessment – Code compliance and life safety
15
Example of Major finding of Condition Assessment
Mechanical Electrical
South raw water pump No. 27 is failing VFDs on raw water pumps don’t work Sludge removal system in basins at end of life Isolation gates/valves in settled water flume and pipes are
defective and inoperable Some filter and site isolation valves are nearing the end of
useful life
MCC for high service pumps is at end of life and parts are not available
Some site PLCs are obsolete Multiple UPS systems on site; there is a need to centralize and
make resilient Some remote panels should be provided with a secondary power
feed
Structural Architectural
Sections of shoreline Clear Lake eroded Signs of concrete deterioration in the filters and
sedimentations basins Filtered water flume and underground clearwelll are leaking
Operations Building requires hurricane hardening, particular in the hardware
Flat roofs are leaking in some spots and should be rehabilitated or replaced
Buildings should be reviewed in terms of life safety and ADA
Example of the findings of the concrete non‐destructive testing: thermal imaging at the expansion joint in the east sedimentation basin.
16
Existing plant systems and additional treatment alternatives were evaluated
• To identify process capacity limitations or systems vulnerabilities
• For meeting future regulatory drivers
• Based on consent order requirements, above criteria and feasibility of implementation the following processes were shortlisted:
– Anion exchange
– Low pressure membrane filtration
– High‐rate clarification
– Ultraviolet light disinfection
Being a surface water plant, activated carbon systems (either granular or powdered) were included for Taste and Odor treatment.
17
Basis of Evaluation of Treatment Alternatives
Alternative 1: PAC‐UV
18
Treatment Alternatives – PAC-UV
Existing Lime softening process
PAC-T&O control
UV-Additional pathogen protection
Existing site and processes used
Alternative 2: IX‐UF‐GAC
19
Treatment Alternatives – IX-UF-GAC
IX,UF membrane (Additional pathogen
protection)
CL contact-Additional pathogen protection
GAC-T&O control
New processes built in a vacant section of the existing site
Alternative 3: IX‐UF‐GAC (Offsite)
20
Treatment Alternatives – IX-UF-GAC (offsite)
IX,UF membrane (Additional pathogen
protection)
GAC-T&O control
CL contact-Additional pathogen protection
New site and processes-need underground utilities to and from new site. Option for redeveloping existing site for residential and/or commercial use.
Alternative 4: ENH.COAG‐ACT‐UF (Offsite)
21
Treatment Alternatives – ENH.COAG-ACT-UF (offsite)
50 mgd
Clear Lake
ChlorineAmmonia
CausticFerric Sulfate, AcidPAC
Actiflo –Carb®Offsite
Storage
Polymer,
Microsand
UF
Actiflo‐Carb®, UF membrane (Additional pathogen protection)
PAC-T&O control
New site and processes-need underground utilities to and from new site. Option for redeveloping existing site for residential and/or commercial use.
22
23
Alternatives Capital Cost Comparison
Alternative 1 -PAC-UV
(at existing site)
Alternative 2 - IX-UF-GAC
(at existing site)
Alternative 3 - IX-UF-GAC
(near ECR)
Alternative 4 -Actiflo-Carb-UF
(at Riviera Beach)
Other Fees $5.6 $18.0 $61.2 $51.3
Site Property Value $0.0 $0.0 -$33.2 -$33.2
Site Works, Power, Demolition $4.3 $14.0 $76.7 $69.4
Treatment $23.6 $75.1 $96.1 $92.6
Pump Stations, Storage, Conveyance $0.0 $0.7 $161.9 $109.2
-$100
-$50
$0
$50
$100
$150
$200
$250
$300
$350
$400
$45020
18 C
AP
EX
Co
st(i
n M
illio
ns)
Other Fees
Site Property Value
Site Works, Power,Demolition
Treatment
Pump Stations, Storage,Conveyance $33.6
$107.7
$362.7
$289.3
24
Alternatives R&R Cost Comparison
Alternative 1 - PAC-UV
(at existing site)
Alternative 2 - IX-UF-GAC
(at existing site)
Alternative 3 - IX-UF-GAC
(near ECR)
Alternative 4 - Actiflo-Carb-UF
(at Riviera Beach)
Annual R&R CIP 2015-2019 $2.8 $2.3 $0.9 $0.9
Annual R&R CIP 2020-2024 $6.4 $1.7 $0.0 $0.0
Annual R&R CIP 2025-2044 Est. $4.8 $4.8 $4.8 $4.8
$0.0
$1.0
$2.0
$3.0
$4.0
$5.0
$6.0
$7.0A
nn
ual
R&
R C
ost
s(i
n M
illio
ns)
Annual R&R CIP 2015-2019
Annual R&R CIP 2020-2024
Annual R&R CIP 2025-2044 Est.
25
Alternatives Operating Cost Comparison
ExistingAlternative 1 - PAC-
UV(at existing site)
Alternative 2 - IX-UF-GAC
(at existing site)
Alternative 3 - IX-UF-GAC
(near ECR)
Alternative 4 -Actiflo-Carb-UF
(at Riviera Beach)
Other OPEX $3.91 $3.91 $3.91 $3.91 $3.91
Waste to Sewer $0.10 $0.10 $0.20 $0.19 $0.11
Sludge $0.96 $0.96 $0.00 $0.00 $0.90
Labor $4.47 $4.47 $4.19 $3.63 $3.63
Chemicals $4.38 $4.38 $2.22 $2.22 $4.24
Energy $1.40 $1.44 $1.54 $1.70 $1.83
$0.00
$2.00
$4.00
$6.00
$8.00
$10.00
$12.00
$14.00
$16.00
$18.00
2018
OP
EX
Co
st
(in
Mill
ion
s)
Other OPEX
Waste to Sewer
Sludge
Labor
Chemicals
Energy
26
Alternatives Lifecycle Cost Comparison
$0.00
$100.00
$200.00
$300.00
$400.00
$500.00
$600.00
$700.00
$800.00
$900.00
$1,000.00
0 5 10 15 20 25 30
Cu
mu
lati
ve N
et P
rese
nt
Val
ue
(201
8 M
illio
ns)
Years in Operation
Alternative 1 PAC-UV(at existing site)Alternative 2 IX-UF-GAC(at existing site)Alternative 3 IX-UF-GAC (near ECR)Alternative 4 Actiflo-Carb-UF(at Riviera Beach)Existing
27
Summary of Financing Options and Parameters for Alternatives
Not membranes!
Alternative 1 PAC-UV as it would not degrade the Utilities debt position and would not require an immediate utility rate increase.
The project team is moving ahead with the design and ground breaking for construction is expected in late spring of 2016.
28
…and the winner is?
Questions?
29