ft. detrick defense medical logistics center buildinggy g ... · – rd i sredesign summary –...

33
Ft. Detrick Defense Medical Logistics Center Building Systems Redesign Architectural Engineering Mechanical Option April 16, 2008 Senior Thesis Presentation Domenica Ferraro Penn State University

Upload: others

Post on 04-Aug-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick Defense Medical Logistics CenterBuilding Systems Redesigng y g

Architectural EngineeringMechanical Option

April 16, 2008Senior Thesis Presentation

Domenica FerraroPenn State University

Page 2: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

OutlineB k d– Background

– Existing Mechanical SystemsR d i S– Redesign Summary

– Redesign Goals– Mechanical Depth Study– Architectural/Site Breadth Study– Electrical Breadth Study– Conclusions and Recommendations

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 3: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

BackgroundSizeSize

129,960 ft2

CostCost$26.5 Million

FunctionOffice

OccupantsTop Medical Planning Organizations within the Department of Defense, representing the Army, Navy, Air Force, and Marines

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 4: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

BackgroundAT/FPAT/FP

Anti-Terrorism/Force Protection

SPiRiTSPiRiTSustainable Project Rating Tool

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 5: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Existing Mechanical SystemChilled Water System•2 Water-Cooled Chillers at 220 tons each•42°F Leaving Water Temperature•Serves Cooling Coils of AHU-1 thru 6•Serves Cooling Coils of AHU-1 thru 6

Personal Photo Taken 2/23/08

Hot Water System•2 Gas-Fired Boilers at 2160 MBH each•Serves AHU heating coils VAV reheat coils and

Personal Photo Taken 2/23/08

Serves AHU heating coils, VAV reheat coils, and Unit Heaters

Personal Photo Taken 2/23/08

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 6: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Existing Mechanical System

Airside

•6 VAV Air Handling6 VAV Air Handling Units

•Water Heating and C li C ilCooling Coils

•VAV Hot Water Reheat Boxes

Personal Photo Taken 2/23/08

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Personal Photo Taken 2/23/08

Page 7: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Existing Mechanical SystemFirst Floor Second Floor Third Floor

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 8: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Redesign Goals

1. Decrease Space2 I E Effi i2. Increase Energy Efficiency3. Maintain Affordability4. Maintain Occupant Safety 5. Improve Sustainability5. Improve Sustainability

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 9: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Redesign SummaryM h i l D th St d• Mechanical Depth Study – DOAS/Chilled Beams/High-Induction Diffusers

• Architectural/Site Breadth Study– Constructed Wetland for On-Site Wastewater TreatmentConstructed Wetland for On-Site Wastewater Treatment

• Electrical Breadth StudyElectrical Breadth Study– Impact of Mechanical Redesign on Electrical System

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 10: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Mechanical Depth StudyDedicated Outdoor Air System (DOAS)

• Enthalpy Wheel• Enthalpy Wheel – Recovers Energy– Save on Utility Cost

Innovent Dedicated Outdoor Air Unit

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 11: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Mechanical Depth StudyDedicated Outdoor Air System (DOAS)

• 100% Outdoor AirVot (current design) Vot 100% OA (∑Voz) Difference

Outdoor Air Savings from DOAS-1

• 100% Outdoor Air– Smaller Volume of Air

Required

AHU‐1 4460 2843AHU‐3 4975 2235AHU‐5 4670 2120Total 14,105 7198 6907

– Contaminants Not RecirculatedVot (current design) Vot 100% OA (∑Voz) Difference

AHU‐2 4210 1773AHU‐4 4550 2092AHU 6 4985 2584

Outdoor Air Savings from DOAS-2

AHU‐6 4985 2584Total 13,745 6449 7296

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 12: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Mechanical Depth Study

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 13: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Mechanical Depth StudyChilled Beams

• Passive System• Passive System– Cool by Convection and

Radiation– Remove Sensible Loads– No Additional Energy to

Operate

http://www.aeieng.com/services/sustainable/chilledbeam.htm

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 14: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Mechanical Depth StudyHigh-Induction Diffusers

• Cooling Supply Air• Cooling Supply Air Temperature = 48°F– Diffusers encourage mixing of

air– Prevent “dumping” of cold air

Nailor High-Induction Diffuser

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 15: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Mechanical Depth StudyGoal 1 – Decrease Space

• Existing System6 M h i l R– 6 Mechanical Rooms

– 5.2% Lost Rentable Space

• Redesigned SystemRedesigned System- 2 Mechanical Rooms- 3.3% Lost Rentable Space

2• Owner saves 2392 ft2 –2% of Total Area

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 16: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Mechanical Depth StudyGoal 2 – Increase Energy Efficiency

300

Weekday Cooling Load - June

150

200

250

300

Cooling

0

50

100

150Tons Current Design

DOAS/CB

0 4 8 12 16 20 24

Hour

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 17: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Mechanical Depth StudyGoal 2 – Increase Energy Efficiency

1000

Weekday Heating Load - January

500600700800900

1000

Heating

0100200300400500

MBH Current DesignDOAS/CB

0 4 8 12 16 20 24

Hour

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 18: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Mechanical Depth StudyGoal 3 – Maintain Affordability

Utility Rates ‐ Baltimore Gas and ElectricUtility Type Rate Type Summer Charge  Winter Charge y yp yp g g

Electric Consumption On Peak $0.07/kWh $0.055/kWh

Electric Consumption Off Peak $0.044/kWh $0.04/kWh

Electric Demand On Peak $10.22/kW $4.94/kW

Electric Demand Off Peak $4.94/kW $4.94/kW

$

• Existing System Energy Cost: $164,529/yearR d i d S t E C t $136 252/

Gas Consumption ‐ $0.4165/therm

• Redesigned System Energy Cost: $136,252/year• Yearly Savings: $28,277

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 19: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Mechanical Depth StudyGoal 3 – Maintain Affordability

Initial Cost ComparisonEquipment Existing System Redesign DOAS/CB Difference

Diffusers (493) $20 460 $21 300 ‐$840Diffusers (493) $20,460  $21,300  ‐$840VAV Boxes (164) $87,740  $ ‐ $87,740 Chilled Beams (1460) $ ‐ $276,750  ‐$276,750VAV AHUs (6) $187,800  $ ‐ $187,800 DOAS Units (2) $ ‐ $86,000  ‐$86,000

$ $ $

• Existing System First Cost: $296,000R d i d S t Fi t C t $384 050

Total $296,000  $384,050  ‐$88,050

• Redesigned System First Cost: $384,050• First Cost Increase: $88,050

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 20: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Mechanical Depth Study

• Existing System Life Cycle Cost: $1,696,733

Goal 3 – Maintain Affordability

• Redesigned System First Cost: $1,544,041• 20-Year Life Cycle Cost Savings: $152,692y g

– Payback Period: only 3.9 years

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 21: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Mechanical Depth StudyGoal 4 – Maintain Occupant Safety

• Simulation of contaminant released in

1st Floor 2nd Floor 3rd Floor

outdoor air intake (star)• Concentration of contaminants 30

minutes following release

Existing System

• Existing system has higher initial concentration on first floor

– Smaller ZonesRest of contamination due to leakage– Rest of contamination due to leakage

Redesigned System

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 22: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Mechanical Depth StudyGoal 4 – Maintain Occupant Safety

• Redesign takes 300000

Concentration vs. TimeClassroom 129

approximately 2 hours longer to clear the building

200000

250000

300000

ContaminantConcentration

50000

100000

150000Concentration

(#/m^3)

0

50000

4:00 8:00 12:00 16:00 20:00 0:00

Time of Day

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 23: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Mechanical Depth StudyGoal 4 – Maintain Occupant Safety

• Acute Exposure Guideline Level (AEGL)0.016

Concentration vs. Time - Classroom 129Acute Exposure

– Describe risk from one-time exposure to contaminants

• Contaminant selected arbitrarily, only i d d di l l i

0.01

0.012

0.014

Occupant

ExistingRedesign

intended to display relative concentration between 2 cases

• Redesign never reaches dangerous l l 2 iff i

0.002

0.004

0.006

0.008Occupant Exposure

(ppm)

AEGL 2

level – 2 hour difference is not critical

0

0:00

:00

0:00

:10

0:30

:00

1:00

:00

1:30

:00

2:00

:00

2:30

:00

3:00

:00

3:30

:00

4:00

:00

4:30

:00

5:00

:00

5:30

:00

6:00

:00

6:30

:00

7:00

:00

7:30

:00

8:00

:00

Time

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 24: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Mechanical Depth Study

Existing Systemi i i

Redesigned System

Goal 5 – Improve Sustainability

• 43 points – SPiRiT Silver• Need 7 points for SPiRiT Gold

• Uses 17.2% less energy than baseline system

• 1 point awarded for every 2.5% reduction of energy

• 6 more points can be obtained, but still need one more…

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 25: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Architectural/Site Breadth Study

Constructed Wetland

Goal 5 – Improve Sustainability

• Satisfies SPiRiT credit 2.C2 –Innovative use of wastewater technology

• Use planting beds of wetland vegetation to treat noxious effluents/sewage

• Free water surface – most affordable

http://www.dep.state.pa.us/Images/

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 26: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Architectural/Site Breadth StudyGoal 5 – Improve Sustainability

http://www unep org/geo/yearbook/yb2003/images/fresh img g 40 jpg

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

http://www.unep.org/geo/yearbook/yb2003/images/fresh_img_g_40.jpg

Page 27: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Architectural/Site Breadth Study

Constructed Wetland

Goal 5 – Improve Sustainability

Construction Cost Summary ‐ FWS Constructed Wetland

E ti /C ti $8 668 80• Building uses 24,300 gal/day

(max. occupancy)• 4300 ft2, 3 ft deep

Excavation/Compaction $8,668.80

Soil/Gravel $2,786.40

Liner $12,267.90

Plants $5,495.40

Plumbing $9 481 50

• Adds $38,700 to first costPlumbing $9,481.50

Total $38,700.00

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 28: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Architectural/Site Breadth StudyGoal 5 – Improve Sustainability

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 29: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Electrical Breadth StudyGoal 3 – Maintain Affordability

Cost of Electrical AdditionsAdded Qty. Cost per 100 LF LF Total Cost 

#10 Wi 6 59 50 36 $129 • Equipment reduction means#10 Wire 6 59.50 36 $129 25 A Breaker 6 ‐ ‐ $4,074 

Total $4,203 

Cost of Electrical Subtractions

Equipment reduction means power reduction

• Panelboard DP5 can be eliminated• Reduces first cost by $17 065

Subtracted Qty. Cost per 100 LF LF Total Cost #3 Wire 6 196.00 100 $1,176 #4 Wire 12 166.50 64 $1,279 #12 Wire 18 47.90 128 $1,104 70 A Breaker 6 $4 818

• Reduces first cost by $17,065• Total cost additions from

breadth: $21,63570 A Breaker 6 ‐ ‐ $4,818 80 A Breaker 12 ‐ ‐ $4,818 15 A Breaker 18 ‐ ‐ $4,074 Panel DP5 1 ‐ ‐ $4,000 

Total $21,268 

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 30: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Conclusions and Recommendations• Total First Cost of Redesign: $384,050 + $21,635 = $405,685• Total 20-Year Life Cycle Cost Savings: $131,058

P b k i d till l 5 2– Payback period still only 5.2 years

• Owner would pay $109,685 more up-front, but would save $131,058 after 20 yearsy

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 31: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Conclusions and RecommendationsG l MGoals Met:1. Decrease Space

– YES. DOAS units take up 2% less space than existing AHUs

2. Increase Energy Efficiency– YES. Smaller quantity of air to condition; Enthalpy wheel provides energy recovery

3. Maintain Affordability– YES. Higher first cost pays back in 5.2 years with savings on energy.

4. Maintain Occupant Safety – YES. DOAS takes longer to clear the building, but the building never reaches a

iti l l lcritical level.

5. Improve Sustainability– YES. 6 credits from mechanical redesign + 1 credit from wetland = 7 credits needed

for SPiRiT GoldArchitectural Engineering

Mechanical OptionDomenica Ferraro

Penn State UniversityApril 16, 2008Senior Thesis Presentation

for SPiRiT Gold.

Page 32: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Acknowledgements

Project Sponsor: Lou Mittleman

Dave Casciano

Faculty Advisor: Dr. William Bahnfleth

Justin BemDave CascianoTodd Garing

Darren AndersonJohn Morris

Justin BemMike RoyerNick Kutchi

Lou and Julie FerraroMichael Schwarz Brian Hoover

Architectural EngineeringMechanical Option

Domenica FerraroPenn State University

April 16, 2008Senior Thesis Presentation

Page 33: Ft. Detrick Defense Medical Logistics Center Buildinggy g ... · – Rd i SRedesign Summary – Redesign Goals – Mechanical Depth Study – Architectural/Site Breadth Study –

Ft. Detrick DMLCFrederick, MDFrederick, MD

Questions?G l MGoals Met:1. Decrease Space

– YES. DOAS units take up 2% less space than existing AHUs

2. Increase Energy Efficiency– YES. Smaller quantity of air to condition; Enthalpy wheel provides energy recovery

3. Maintain Affordability– YES. Higher first cost pays back in 5.2 years with savings on energy.

4. Maintain Occupant Safety – YES. DOAS takes longer to clear the building, but the building never reaches a

iti l l lcritical level.

5. Improve Sustainability– YES. 6 credits from mechanical redesign + 1 credit from wetland = 7 credits needed

for SPiRiT GoldArchitectural Engineering

Mechanical OptionDomenica Ferraro

Penn State UniversityApril 16, 2008Senior Thesis Presentation

for SPiRiT Gold.