1 17 June 2014 Dear Stakeholder, PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM THE KOEBERG POWER STATION INTO THE ANKERLIG POWER STATION NOTIFICATION OF A BASIC ASSESSMENT PROCESS There is a dedicated supply from the Ankerlig Power station to the Koeberg Power Station in City of Cape Town Metropolitan Municipality, in the Western Cape Province. The National Nuclear Regulator (NNR) requires that this power line is not crossed by any of other power line so as to reduce any risks to the operation of this power line. Eskom therefore proposes to deviate a portion of the existing 132kV Dassenberg-Koeberg power line (approximately 15km) from the Ankerlig Power Station to the Koeberg Power Station, Western Cape Province. The portion of the power line that will not be used will be decommissioned. The 132kV power line would be connected to a new 132kV HV yard adjacent to the now-to-be extended substation (high voltage (HV) yard) north of the Ankerlig Power Station. ENVIRONMENTAL IMPACT ASSESSMENT PROCESS In terms of the Environmental Impact Assessment (EIA) Regulations published in terms of Section 24(5) of the National Environmental Management Act (NEMA, Act No. 107 of 1998), Eskom requires authorisation from the Department of Environmental Affairs (DEA) (in consultation with the Western Cape Department of Environmental Affairs and Development Planning) for the undertaking of the proposed project. In order to obtain authorisation for this project, comprehensive, independent environmental studies must be undertaken in accordance with the EIA Regulations (GN543) and Listing Notices GN 544-546. An application for authorisation has been accepted by DEA for the proposed project under application reference number: 14/12/16/3/3/1/1182.

Upload: others

Post on 04-Aug-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

1

17 June 2014

Dear Stakeholder,

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM THE KOEBERG POWER STATION INTO THE

ANKERLIG POWER STATION

NOTIFICATION OF A BASIC ASSESSMENT PROCESS There is a dedicated supply from the Ankerlig Power station to the Koeberg Power Station in City of Cape Town Metropolitan Municipality, in the Western Cape Province. The National Nuclear Regulator (NNR) requires that this power line is not crossed by any of other power line so as to reduce any risks to the operation of this power line. Eskom therefore proposes to deviate a portion of the existing 132kV Dassenberg-Koeberg power line (approximately 15km) from the Ankerlig Power Station to the Koeberg Power Station, Western Cape Province. The portion of the power line that will not be used will be decommissioned. The 132kV power line would be connected to a new 132kV HV yard adjacent to the now-to-be extended substation (high voltage (HV) yard) north of the Ankerlig Power Station. ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of the Environmental Impact Assessment (EIA) Regulations published in terms of Section 24(5) of the National Environmental Management Act (NEMA, Act No. 107 of 1998), Eskom requires authorisation from the Department of Environmental Affairs (DEA) (in consultation with the Western Cape Department of Environmental Affairs and Development Planning) for the undertaking of the proposed project. In order to obtain authorisation for this project, comprehensive, independent environmental studies must be undertaken in accordance with the EIA Regulations (GN543) and Listing Notices GN 544-546. An application for authorisation has been accepted by DEA for the proposed project under application reference number: 14/12/16/3/3/1/1182.

Page 2: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

2

Eskom has appointed Savannah Environmental (Pty) Ltd, as the independent environmental consultant, to undertake the required Scoping Phase and EIA to identify and assess all the potential environmental impacts associated with the proposed project, and propose appropriate mitigation and management measures in an Environmental Management Programme (EMP). As part of these environmental studies, I&APs will be actively involved through the public involvement process also being undertaken by Savannah Environmental. Please find herewith the Background Information Document (BID) for the solar energy facility project. Please could you kindly confirm that you would like to be registered as and Interested and Affected Party (I&AP) on the project’s database. Please could you kindly complete the attached Stakeholder Reply Form and send it to the undersigned via fax, post or email. By registering on the database, you will receive all information relating to the project and will be provided with an opportunity to provide comment and input into the EIA process. Please could you submit your formal comments by sending written correspondence in this regard. All comments received will be submitted in the Scoping and EIA reports which will be submitted to the DEA. Comments can be made as written submission of fax, post or email. Yours sincerely, Shawn Johnston Process Facilitator (not signed via email/fax)

Page 3: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

Proof 10Begin forwarded message:

From: ShawnJohnston <[email protected]>Subject: Eskom Dassenberg-Koeberg 132kV Power Line Basic AssessmentDate: 17 June 2014 9:25:08 AM SASTTo: Shawn Johnston <[email protected]>Bcc: [email protected], CWCBR Nicole Loebenberg Loebenberg <[email protected]>, [email protected], Martin Halvorsen <[email protected]>, [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], Astrid October <[email protected]>, Ossie Oswald <[email protected]>, [email protected]

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM THE KOEBERG POWER STATION INTO THE

ANKERLIG POWER STATION

Dear Stakeholder,

Find attached the registration form, background information document and our letter clarifying the basic assessment process for the deviation of the existing 132kV Dassessneberg-Koeberg power line.

11253 Sava….pdf (2,6 MB)

Ankerlig Da…014 (362 KB)

Reply Form.pdf (85 KB)Sincerely,

Shawn Johnston

Process Specialist

Sustainable Futures ZA

P.O. Box 749 Rondebosch 7701

Cape Town, South Africa

Tel:++27 083 325 9965

Fax: 086 510 2537

E-mail: [email protected]

From: ShawnJohnston <[email protected]>Subject: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic Assessment

Date: 21 November 2014 6:46:32 AM SAST

3 Attachments, 3 MB

Page 4: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

Proof 1Begin forwarded message:

From: ShawnJohnston <[email protected]>Subject: Eskom Dassenberg-Koeberg 132kV Power Line Basic AssessmentDate: 17 June 2014 8:59:58 AM SASTTo: Shawn Johnston <[email protected]>Bcc: [email protected], [email protected], [email protected], [email protected], [email protected], Tyron Williams <[email protected]>, Mienie Wood <[email protected]>, [email protected], [email protected], [email protected], Ahilan Kailasanathan <[email protected]>

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM THE KOEBERG POWER STATION INTO THE

ANKERLIG POWER STATION

Dear Stakeholder,

Find attached the registration form, background information document and our letter clarifying the basic assessment process for the deviation of the existing 132kV Dassessneberg-Koeberg power line.

11253 Sava….pdf (2,6 MB)

Ankerlig Da…014 (362 KB)

Reply Form.pdf (85 KB)

Sincerely,Shawn Johnston

Process Specialist

Sustainable Futures ZA

P.O. Box 749 Rondebosch 7701

Cape Town, South Africa

Tel:++27 083 325 9965

Fax: 086 510 2537

E-mail: [email protected]

From: ShawnJohnston <[email protected]>Subject: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic Assessment

Date: 21 November 2014 6:41:10 AM SAST

3 Attachments, 3 MB

Page 5: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

Proof 2Begin forwarded message:

From: ShawnJohnston <[email protected]>Subject: Eskom Dassenberg-Koeberg 132kV Power Line Basic AssessmentDate: 17 June 2014 9:00:07 AM SASTTo: Shawn Johnston <[email protected]>Bcc: Alana Duffell-Canham <[email protected]>, [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], Janet Bodenstein <[email protected]>, [email protected], [email protected]

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM THE KOEBERG POWER STATION INTO THE

ANKERLIG POWER STATION

Dear Stakeholder,

Find attached the registration form, background information document and our letter clarifying the basic assessment process for the deviation of the existing 132kV Dassessneberg-Koeberg power line.

11253 Sava….pdf (2,6 MB)

Ankerlig Da…014 (362 KB)

Reply Form.pdf (85 KB)

Sincerely,

Shawn Johnston

Process Specialist

Sustainable Futures ZA

P.O. Box 749 Rondebosch 7701

Cape Town, South Africa

Tel:++27 083 325 9965

Fax: 086 510 2537

E-mail: [email protected]

From: ShawnJohnston <[email protected]>Subject: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic Assessment

Date: 21 November 2014 6:42:30 AM SAST

3 Attachments, 3 MB

Page 6: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

Proof 3Begin forwarded message:

From: ShawnJohnston <[email protected]>Subject: Eskom Dassenberg-Koeberg 132kV Power Line Basic AssessmentDate: 17 June 2014 9:00:20 AM SASTTo: Shawn Johnston <[email protected]>Bcc: [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], Samantha Ralston <[email protected]>, [email protected], [email protected], [email protected], [email protected]

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM THE KOEBERG POWER STATION INTO THE

ANKERLIG POWER STATION

Dear Stakeholder,

Find attached the registration form, background information document and our letter clarifying the basic assessment process for the deviation of the existing 132kV Dassessneberg-Koeberg power line.

11253 Sava….pdf (2,6 MB)

Ankerlig Da…014 (362 KB)

Reply Form.pdf (85 KB)

Sincerely,

Shawn Johnston

Process Specialist

Sustainable Futures ZA

P.O. Box 749 Rondebosch 7701

Cape Town, South Africa

Tel:++27 083 325 9965

Fax: 086 510 2537

E-mail: [email protected]

From: ShawnJohnston <[email protected]>Subject: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic Assessment

Date: 21 November 2014 6:43:01 AM SAST

3 Attachments, 3 MB

Page 7: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

Proof 4Begin forwarded message:

From: ShawnJohnston <[email protected]>Subject: Eskom Dassenberg-Koeberg 132kV Power Line Basic AssessmentDate: 17 June 2014 9:00:21 AM SASTTo: Shawn Johnston <[email protected]>Bcc: [email protected], [email protected], Dennis Smit <[email protected]>, [email protected], [email protected], [email protected], [email protected], [email protected]

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM THE KOEBERG POWER STATION INTO THE

ANKERLIG POWER STATION

Dear Stakeholder,

Find attached the registration form, background information document and our letter clarifying the basic assessment process for the deviation of the existing 132kV Dassessneberg-Koeberg power line.

11253 Sava….pdf (2,6 MB)

Ankerlig Da…014 (362 KB)

Reply Form.pdf (85 KB)

Sincerely,Shawn Johnston

Process Specialist

Sustainable Futures ZA

P.O. Box 749 Rondebosch 7701

Cape Town, South Africa

Tel:++27 083 325 9965

Fax: 086 510 2537

E-mail: [email protected]

From: ShawnJohnston <[email protected]>Subject: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic Assessment

Date: 21 November 2014 6:43:33 AM SAST

3 Attachments, 3 MB

Page 8: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

Proof 5Begin forwarded message:

From: ShawnJohnston <[email protected]>Subject: Eskom Dassenberg-Koeberg 132kV Power Line Basic AssessmentDate: 17 June 2014 9:02:02 AM SASTTo: Shawn Johnston <[email protected]>Bcc: [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected]

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM THE KOEBERG POWER STATION INTO THE

ANKERLIG POWER STATION

Dear Stakeholder,

Find attached the registration form, background information document and our letter clarifying the basic assessment process for the deviation of the existing 132kV Dassessneberg-Koeberg power line.

11253 Sava….pdf (2,6 MB)

Ankerlig Da…014 (362 KB)

Reply Form.pdf (85 KB)

Sincerely,

Shawn Johnston

Process Specialist

Sustainable Futures ZA

P.O. Box 749 Rondebosch 7701

Cape Town, South Africa

Tel:++27 083 325 9965

Fax: 086 510 2537

E-mail: [email protected]

From: ShawnJohnston <[email protected]>Subject: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic Assessment

Date: 21 November 2014 6:44:03 AM SAST

3 Attachments, 3 MB

Page 9: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

Proof 6Begin forwarded message:

From: ShawnJohnston <[email protected]>Subject: Eskom Dassenberg-Koeberg 132kV Power Line Basic AssessmentDate: 17 June 2014 9:13:23 AM SASTTo: Shawn Johnston <[email protected]>Bcc: [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], Edgar_John Kleinveld Kleinveld <[email protected]>, [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], Hans Linde <[email protected]>

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM THE KOEBERG POWER STATION INTO THE

ANKERLIG POWER STATION

Dear Stakeholder,

Find attached the registration form, background information document and our letter clarifying the basic assessment process for the deviation of the existing 132kV Dassessneberg-Koeberg power line.

11253 Sava….pdf (2,6 MB)

Ankerlig Da…014 (362 KB)

Reply Form.pdf (85 KB)

Sincerely,

Shawn Johnston

Process Specialist

Sustainable Futures ZA

P.O. Box 749 Rondebosch 7701

Cape Town, South Africa

Tel:++27 083 325 9965

Fax: 086 510 2537

E-mail: [email protected]

From: ShawnJohnston <[email protected]>Subject: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic Assessment

Date: 21 November 2014 6:44:35 AM SAST

3 Attachments, 3 MB

Page 10: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

Proof 7Begin forwarded message:

From: ShawnJohnston <[email protected]>Subject: Eskom Dassenberg-Koeberg 132kV Power Line Basic AssessmentDate: 17 June 2014 9:13:53 AM SASTTo: Shawn Johnston <[email protected]>Bcc: Dale Wright <[email protected]>, [email protected], [email protected], [email protected], [email protected], [email protected], Dieter Reinstorf <[email protected]>, [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected]

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM THE KOEBERG POWER STATION INTO THE

ANKERLIG POWER STATION

Dear Stakeholder,

Find attached the registration form, background information document and our letter clarifying the basic assessment process for the deviation of the existing 132kV Dassessneberg-Koeberg power line.

11253 Sava….pdf (2,6 MB)

Ankerlig Da…014 (362 KB)

Reply Form.pdf (85 KB)

Sincerely,Shawn Johnston

Process Specialist

Sustainable Futures ZA

P.O. Box 749 Rondebosch 7701

Cape Town, South Africa

Tel:++27 083 325 9965

Fax: 086 510 2537

E-mail: [email protected]

From: ShawnJohnston <[email protected]>Subject: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic Assessment

Date: 21 November 2014 6:45:04 AM SAST

3 Attachments, 3 MB

Page 11: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

Proof 8Begin forwarded message:

From: ShawnJohnston <[email protected]>Subject: Eskom Dassenberg-Koeberg 132kV Power Line Basic AssessmentDate: 17 June 2014 9:19:14 AM SASTTo: Shawn Johnston <[email protected]>Bcc: [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected]

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM THE KOEBERG POWER STATION INTO THE

ANKERLIG POWER STATION

Dear Stakeholder,

Find attached the registration form, background information document and our letter clarifying the basic assessment process for the deviation of the existing 132kV Dassessneberg-Koeberg power line.

11253 Sava….pdf (2,6 MB)

Ankerlig Da…014 (362 KB)

Reply Form.pdf (85 KB)

Sincerely,

Shawn Johnston

Process Specialist

Sustainable Futures ZA

P.O. Box 749 Rondebosch 7701

Cape Town, South Africa

Tel:++27 083 325 9965

Fax: 086 510 2537

E-mail: [email protected]

From: ShawnJohnston <[email protected]>Subject: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic Assessment

Date: 21 November 2014 6:45:33 AM SAST

3 Attachments, 3 MB

Page 12: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

Proof 9Begin forwarded message:

From: ShawnJohnston <[email protected]>Subject: Eskom Dassenberg-Koeberg 132kV Power Line Basic AssessmentDate: 17 June 2014 9:21:49 AM SASTTo: Shawn Johnston <[email protected]>Bcc: [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected]

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM THE KOEBERG POWER STATION INTO THE

ANKERLIG POWER STATION

Dear Stakeholder,

Find attached the registration form, background information document and our letter clarifying the basic assessment process for the deviation of the existing 132kV Dassessneberg-Koeberg power line.

11253 Sava….pdf (2,6 MB)

Ankerlig Da…014 (362 KB)

Reply Form.pdf (85 KB)

Sincerely,

Shawn Johnston

Process Specialist

Sustainable Futures ZA

P.O. Box 749 Rondebosch 7701

Cape Town, South Africa

Tel:++27 083 325 9965

Fax: 086 510 2537

E-mail: [email protected]

From: ShawnJohnston <[email protected]>Subject: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic Assessment

Date: 21 November 2014 6:46:01 AM SAST

3 Attachments, 3 MB

Page 13: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

Sustainable Futures ZA P.O. Box 749 Rondebosch 7701 Cape Town South Africa Tel: +27 (0)83 3259965 Fax: 086 510 2537 E-mail: [email protected]

12 March 2015 Dear Stakeholder

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM THE KOEBERG POWER STATION INTO THE

ANKERLIG POWER STATION, WESTERN CAPE PROVINCE

NOTICE OF AVAILABILITY OF DRAFT BASIC ASSESSMENT REPORT FOR PUBLIC REVIEW

There is a dedicated power supply from the Ankerlig Power Station to the Koeberg Power Station in City of Cape Town Metropolitan Municipality, in the Western Cape Province. The National Nuclear Regulator (NNR) requires that this power line is not crossed by any other power line so as to reduce any risks to the operation of this power line. Eskom Holdings SOC Limited (Eskom) therefore proposes to deviate a portion of the existing 132kV Dassenberg-Koeberg power line (approximately 15km) from the Ankerlig Power Station to the Koeberg Power Station, Western Cape Province. The portion of the power line that will not be used will be decommissioned. The 132kV power line would be connected to a new 132kV high voltage (HV) yard adjacent to the now-to-be extended substation (HV yard) north of the Ankerlig Power Station. The following properties will be affected by the construction of the proposed power line: » Portion 2 of Farm Witzand » RE1 /2 of Farm Witzand » Portion 1 of Farm Witzand » Portion 3 of Farm Melk Post » Portion 5 of Farm Melk Post » Brakke Fontein 32 » Farm 33 » Farm 1183 » Farm 1531

Page 14: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

Sustainable Futures ZA P.O. Box 749 Rondebosch 7701 Cape Town South Africa Tel: +27 (0)83 3259965 Fax: 086 510 2537 E-mail: [email protected]

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

In terms of the Environmental Impact Assessment (EIA) Regulations published in terms of Section 24(5) of the National Environmental Management Act (NEMA, Act No. 107 of 1998), Eskom requires authorisation from the National Department of Environmental Affairs (DEA) (in consultation with the Western Cape Department of Environmental Affairs and Development Planning) for the undertaking of the proposed project. In order to obtain authorisation for this project, comprehensive, independent environmental studies must be undertaken in accordance with the EIA Regulations (GN543) and Listing Notices GN 544-546 (as amended). An application for authorisation has been accepted by DEA for the proposed project under application reference number: 14/12/16/3/3/1/1182. A Draft Basic Assessment Report for the proposed deviation of 132kV Dassenberg-Koeberg power line has been prepared by Savannah Environmental and is available for public review. The review period is from 13 March – 16 April 2015. Please could you kindly submit your formal comments by sending written correspondence in this regard. You are invited to review the report at one of the following locations: » Koeberg Public Library (Merchant Walk, Duynefontein, Melkbosstrand, 7441) » Wesfleur Public Library (Wesfleur Circle, Atlantis, 7349) » Koeberg Visitor Centre » www.savannahSA.com CD copies are available on request

Please submit written comment on or before 16 April 2015. All comments received will be included within the Final Basic Assessment Report which will be submitted to the DEA. Comments can be made as written submission via fax, post or e-mail. Our team welcomes your participation and looks forward to your involvement throughout this process. Kind Regards

Shawn Johnston

Process Specialist

Sustainable Futures ZA

Page 15: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

1

Jo-Anne Thomas

From: ShawnJohnston <[email protected]>

Sent: 31 March 2015 09:02

To: Jo-Anne Thomas

Subject: Fwd: Proposed Deviation of the Existing 132kV Dassenberg-Koeberg Power Line

from Koeberg Power Station into Ankerlig Power Station

Attachments: Dassenberg-Koeberg 132kV BA.pdf; Untitled attachment 01597.htm

Proof 1

Begin forwarded message:

From: ShawnJohnston <[email protected]>

Subject: Proposed Deviation of the Existing 132kV Dassenberg-Koeberg Power Line from Koeberg Power Station into Ankerlig Power Station

Date: 11 March 2015 6:09:14 PM SAST

To: Shawn Johnston <[email protected]>

Bcc: [email protected], [email protected], Janet Bodenstein <[email protected]>, [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected]

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM

THE KOEBERG POWER STATION INTO THE ANKERLIG POWER STATION, WESTERN CAPE

PROVINCE

Dear Stakeholder,

Attached find our letter clarifying the release of the Draft Basic Assessment Report for the deviation of the

existing 132kV Dassenberg-Koeberg power line from

Koeberg Power Station into Ankerlig Power Station.

Page 16: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

1

Jo-Anne Thomas

From: ShawnJohnston <[email protected]>

Sent: 31 March 2015 09:02

To: Jo-Anne Thomas

Subject: Fwd: Proposed Deviation of the Existing 132kV Dassenberg-Koeberg Power Line

from Koeberg Power Station into Ankerlig Power Station

Attachments: Dassenberg-Koeberg 132kV BA.pdf; Untitled attachment 01591.htm

Proof 2

Begin forwarded message:

From: ShawnJohnston <[email protected]>

Subject: Proposed Deviation of the Existing 132kV Dassenberg-Koeberg Power Line from Koeberg Power Station into Ankerlig Power Station

Date: 11 March 2015 6:09:19 PM SAST

To: Shawn Johnston <[email protected]>

Bcc: Alana Duffell-Canham <[email protected]>, Ahilan Kailasanathan <[email protected]>, [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected]

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM

THE KOEBERG POWER STATION INTO THE ANKERLIG POWER STATION, WESTERN CAPE

PROVINCE

Dear Stakeholder,

Attached find our letter clarifying the release of the Draft Basic Assessment Report for the deviation of the

existing 132kV Dassenberg-Koeberg power line from

Koeberg Power Station into Ankerlig Power Station.

Page 17: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

1

Jo-Anne Thomas

From: ShawnJohnston <[email protected]>

Sent: 31 March 2015 09:03

To: Jo-Anne Thomas

Subject: Fwd: Proposed Deviation of the Existing 132kV Dassenberg-Koeberg Power Line

from Koeberg Power Station into Ankerlig Power Station

Attachments: Dassenberg-Koeberg 132kV BA.pdf; Untitled attachment 01573.htm

Proof 3

Begin forwarded message:

From: ShawnJohnston <[email protected]>

Subject: Proposed Deviation of the Existing 132kV Dassenberg-Koeberg Power Line from Koeberg Power Station into Ankerlig Power Station

Date: 11 March 2015 6:11:14 PM SAST

To: Shawn Johnston <[email protected]>

Bcc: [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], Hans Linde <[email protected]>, CWCBR Nicole Loebenberg Loebenberg <[email protected]>, [email protected], [email protected], Martin Halvorsen <[email protected]>, [email protected], [email protected]

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM

THE KOEBERG POWER STATION INTO THE ANKERLIG POWER STATION, WESTERN CAPE

PROVINCE

Dear Stakeholder,

Attached find our letter clarifying the release of the Draft Basic Assessment Report for the deviation of the

existing 132kV Dassenberg-Koeberg power line from

Koeberg Power Station into Ankerlig Power Station.

Page 18: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

1

Jo-Anne Thomas

From: ShawnJohnston <[email protected]>

Sent: 31 March 2015 09:03

To: Jo-Anne Thomas

Subject: Fwd: Proposed Deviation of the Existing 132kV Dassenberg-Koeberg Power Line

from Koeberg Power Station into Ankerlig Power Station

Attachments: Dassenberg-Koeberg 132kV BA.pdf; Untitled attachment 01585.htm

proof 4

Begin forwarded message:

From: ShawnJohnston <[email protected]>

Subject: Proposed Deviation of the Existing 132kV Dassenberg-Koeberg Power Line from Koeberg Power Station into Ankerlig Power Station

Date: 11 March 2015 6:15:00 PM SAST

To: Shawn Johnston <[email protected]>

Bcc: [email protected], Dieter Reinstorf <[email protected]>, [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected]

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM

THE KOEBERG POWER STATION INTO THE ANKERLIG POWER STATION, WESTERN CAPE

PROVINCE

Dear Stakeholder,

Attached find our letter clarifying the release of the Draft Basic Assessment Report for the deviation of the

existing 132kV Dassenberg-Koeberg power line from

Koeberg Power Station into Ankerlig Power Station.

Page 19: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

1

Jo-Anne Thomas

From: ShawnJohnston <[email protected]>

Sent: 31 March 2015 09:03

To: Jo-Anne Thomas

Subject: Fwd: Proposed Deviation of the Existing 132kV Dassenberg-Koeberg Power Line

from Koeberg Power Station into Ankerlig Power Station

Attachments: Dassenberg-Koeberg 132kV BA.pdf; Untitled attachment 01579.htm

proof 5

Begin forwarded message:

From: ShawnJohnston <[email protected]>

Subject: Proposed Deviation of the Existing 132kV Dassenberg-Koeberg Power Line from Koeberg Power Station into Ankerlig Power Station

Date: 11 March 2015 6:16:59 PM SAST

To: Shawn Johnston <[email protected]>

Bcc: [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], Edgar_John Kleinveld Kleinveld <[email protected]>, [email protected]

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM

THE KOEBERG POWER STATION INTO THE ANKERLIG POWER STATION, WESTERN CAPE

PROVINCE

Dear Stakeholder,

Attached find our letter clarifying the release of the Draft Basic Assessment Report for the deviation of the

existing 132kV Dassenberg-Koeberg power line from

Koeberg Power Station into Ankerlig Power Station.

Page 20: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

1

Jo-Anne Thomas

From: ShawnJohnston <[email protected]>

Sent: 31 March 2015 09:03

To: Jo-Anne Thomas

Subject: Fwd: Proposed Deviation of the Existing 132kV Dassenberg-Koeberg Power Line

from Koeberg Power Station into Ankerlig Power Station

Attachments: Dassenberg-Koeberg 132kV BA.pdf; Untitled attachment 01567.htm

Proof 6

Begin forwarded message:

From: ShawnJohnston <[email protected]>

Subject: Proposed Deviation of the Existing 132kV Dassenberg-Koeberg Power Line from Koeberg Power Station into Ankerlig Power Station

Date: 11 March 2015 6:17:44 PM SAST

To: Shawn Johnston <[email protected]>

Bcc: [email protected], [email protected], [email protected], Dennis Smit <[email protected]>, [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], Tyron Williams <[email protected]>, Mienie Wood <[email protected]>, [email protected], [email protected], [email protected]

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM

THE KOEBERG POWER STATION INTO THE ANKERLIG POWER STATION, WESTERN CAPE

PROVINCE

Dear Stakeholder,

Attached find our letter clarifying the release of the Draft Basic Assessment Report for the deviation of the

existing 132kV Dassenberg-Koeberg power line from

Koeberg Power Station into Ankerlig Power Station.

Page 21: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

1

Jo-Anne Thomas

From: ShawnJohnston <[email protected]>

Sent: 31 March 2015 09:03

To: Jo-Anne Thomas

Subject: Fwd: Proposed Deviation of the Existing 132kV Dassenberg-Koeberg Power Line

from Koeberg Power Station into Ankerlig Power Station

Attachments: Dassenberg-Koeberg 132kV BA.pdf; Untitled attachment 01561.htm

Proof 7

Begin forwarded message:

From: ShawnJohnston <[email protected]>

Subject: Proposed Deviation of the Existing 132kV Dassenberg-Koeberg Power Line from Koeberg Power Station into Ankerlig Power Station

Date: 11 March 2015 6:19:16 PM SAST

To: Shawn Johnston <[email protected]>

Bcc: [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], Samantha Ralston <[email protected]>, [email protected], [email protected], [email protected], [email protected]

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM

THE KOEBERG POWER STATION INTO THE ANKERLIG POWER STATION, WESTERN CAPE

PROVINCE

Dear Stakeholder,

Attached find our letter clarifying the release of the Draft Basic Assessment Report for the deviation of the

existing 132kV Dassenberg-Koeberg power line from

Koeberg Power Station into Ankerlig Power Station.

Page 22: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

1

Jo-Anne Thomas

From: ShawnJohnston <[email protected]>

Sent: 31 March 2015 09:04

To: Jo-Anne Thomas

Subject: Fwd: Proposed Deviation of the Existing 132kV Dassenberg-Koeberg Power Line

from Koeberg Power Station into Ankerlig Power Station

Attachments: Dassenberg-Koeberg 132kV BA.pdf; Untitled attachment 01555.htm

proof 9

Begin forwarded message:

From: ShawnJohnston <[email protected]>

Subject: Proposed Deviation of the Existing 132kV Dassenberg-Koeberg Power Line from Koeberg Power Station into Ankerlig Power Station

Date: 11 March 2015 6:21:46 PM SAST

To: Shawn Johnston <[email protected]>

Bcc: [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], Samantha Ralston <[email protected]>, [email protected], [email protected], [email protected], [email protected]

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM

THE KOEBERG POWER STATION INTO THE ANKERLIG POWER STATION, WESTERN CAPE

PROVINCE

Dear Stakeholder,

Attached find our letter clarifying the release of the Draft Basic Assessment Report for the deviation of the

existing 132kV Dassenberg-Koeberg power line from

Koeberg Power Station into Ankerlig Power Station.

Page 23: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

1

Jo-Anne Thomas

From: ShawnJohnston <[email protected]>

Sent: 31 March 2015 09:04

To: Jo-Anne Thomas

Subject: Fwd: Proposed Deviation of the Existing 132kV Dassenberg-Koeberg Power Line

from Koeberg Power Station into Ankerlig Power Station

Attachments: Dassenberg-Koeberg 132kV BA.pdf; Untitled attachment 01549.htm

Proof 8

Begin forwarded message:

From: ShawnJohnston <[email protected]>

Subject: Proposed Deviation of the Existing 132kV Dassenberg-Koeberg Power Line from Koeberg Power Station into Ankerlig Power Station

Date: 11 March 2015 6:20:17 PM SAST

To: Shawn Johnston <[email protected]>

Bcc: [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], Dale Wright <[email protected]>, Donald Matjuda <[email protected]>, Deon Jeannes <[email protected]>, [email protected], [email protected], [email protected], [email protected]

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM

THE KOEBERG POWER STATION INTO THE ANKERLIG POWER STATION, WESTERN CAPE

PROVINCE

Dear Stakeholder,

Attached find our letter clarifying the release of the Draft Basic Assessment Report for the deviation of the

existing 132kV Dassenberg-Koeberg power line from

Koeberg Power Station into Ankerlig Power Station.

Page 24: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

1

Jo-Anne Thomas

From: ShawnJohnston <[email protected]>

Sent: 31 March 2015 09:04

To: Jo-Anne Thomas

Subject: Fwd: Proposed Deviation of the Existing 132kV Dassenberg-Koeberg Power Line

from Koeberg Power Station into Ankerlig Power Station

Attachments: Dassenberg-Koeberg 132kV BA.pdf; Untitled attachment 01532.htm

Proof 10

Begin forwarded message:

From: ShawnJohnston <[email protected]>

Subject: Proposed Deviation of the Existing 132kV Dassenberg-Koeberg Power Line from Koeberg Power Station into Ankerlig Power Station

Date: 11 March 2015 6:24:17 PM SAST

To: Shawn Johnston <[email protected]>

Bcc: [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], Justine Wyngaardt <[email protected]>, [email protected], [email protected], [email protected]

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM

THE KOEBERG POWER STATION INTO THE ANKERLIG POWER STATION, WESTERN CAPE

PROVINCE

Dear Stakeholder,

Attached find our letter clarifying the release of the Draft Basic Assessment Report for the deviation of the

existing 132kV Dassenberg-Koeberg power line from

Koeberg Power Station into Ankerlig Power Station.

Page 25: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

1

Jo-Anne Thomas

From: ShawnJohnston <[email protected]>

Sent: 31 March 2015 09:04

To: Jo-Anne Thomas

Subject: Fwd: Proposed Deviation of the Existing 132kV Dassenberg-Koeberg Power Line

from Koeberg Power Station into Ankerlig Power Station

Attachments: Dassenberg-Koeberg 132kV BA.pdf; Untitled attachment 01543.htm

Proof 11

Begin forwarded message:

From: ShawnJohnston <[email protected]>

Subject: Proposed Deviation of the Existing 132kV Dassenberg-Koeberg Power Line from Koeberg Power Station into Ankerlig Power Station

Date: 11 March 2015 6:26:08 PM SAST

To: Shawn Johnston <[email protected]>

Bcc: [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], Astrid October <[email protected]>, Ossie Oswald <[email protected]>, [email protected], [email protected], Patrick Dowling <[email protected]>

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM

THE KOEBERG POWER STATION INTO THE ANKERLIG POWER STATION, WESTERN CAPE

PROVINCE

Dear Stakeholder,

Attached find our letter clarifying the release of the Draft Basic Assessment Report for the deviation of the

existing 132kV Dassenberg-Koeberg power line from

Koeberg Power Station into Ankerlig Power Station.

Page 26: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

1

Jo-Anne Thomas

From: ShawnJohnston <[email protected]>

Sent: 31 March 2015 09:05

To: Jo-Anne Thomas

Subject: Fwd: Proposed Deviation of the Existing 132kV Dassenberg-Koeberg Power Line

from Koeberg Power Station into Ankerlig Power Station

Attachments: Dassenberg-Koeberg 132kV BA.pdf; Untitled attachment 01526.htm

Proof 12

Begin forwarded message:

From: ShawnJohnston <[email protected]>

Subject: Proposed Deviation of the Existing 132kV Dassenberg-Koeberg Power Line from Koeberg Power Station into Ankerlig Power Station

Date: 11 March 2015 6:27:10 PM SAST

To: Shawn Johnston <[email protected]>

Bcc: [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], Justine Wyngaardt <[email protected]>, [email protected], [email protected], [email protected]

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM

THE KOEBERG POWER STATION INTO THE ANKERLIG POWER STATION, WESTERN CAPE

PROVINCE

Dear Stakeholder,

Attached find our letter clarifying the release of the Draft Basic Assessment Report for the deviation of the

existing 132kV Dassenberg-Koeberg power line from

Koeberg Power Station into Ankerlig Power Station.

Page 27: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM THE KOEBERG POWER STATION INTO THE ANKERLIG POWER STATION WESTERN CAPE PROVINCE (DEA REF: 14/12/16/3/3/1/1182)

NOTIFICATION OF AVAILABILITY OF DRAFT BASIC ASSESSMENT REPORT FOR PUBLIC REVIEW: PROOF OF DISTRIBUTION 13-03-2015

Page 28: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)

PROPOSED DEVIATION OF THE EXISTING 132KV DASSENBERG-KOEBERG POWER LINE FROM THE KOEBERG POWER STATION INTO THE ANKERLIG POWER STATION WESTERN CAPE PROVINCE (DEA REF: 14/12/16/3/3/1/1182)

NOTIFICATION OF AVAILABILITY OF DRAFT BASIC ASSESSMENT REPORT FOR PUBLIC REVIEW: PROOF OF DISTRIBUTION 13-03-2015

Page 29: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)
Page 30: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)
Page 31: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)
Page 32: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)
Page 33: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)
Page 34: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)
Page 35: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)
Page 36: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)
Page 37: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)
Page 38: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)
Page 39: Fwd: Eskom Dassenberg-Koeberg 132kV Power Line Basic … · 2018-04-04 · application reference number: 14/12/16/3/3/1/1182. 2 Eskom has appointed Savannah Environmental (Pty)