    QUESTION: After the Product Backlog has

    been created by the Product Owner at thebeginning of a project, items cannot be added to

    it or removed from itANSWER: FalseEXPLANATION: The Product Owner can

    change the Product Backlog at any time. (What

    they cannot add to is the Teams target in thecurrent Sprint.)

  • 8/12/2019 Game of Scrum

    2/39

    QUESTION: All communication between theTeam and Product Owner is required to go

    through the ScrumMasterANSWER: False

    EXPLANATION: Direct, open communication

    between the Team and the Product Owner is

    encouraged, as long as it doesnt disrupt the

    Team

  • 8/12/2019 Game of Scrum

    3/39

    QUESTION: Product Backlog Items the Teamdoes not complete in a Sprint automatically get

    added into the next SprintANSWER: False

    EXPLANATION: Product Backlog Items the

    Team does not complete in a Sprint

    automatically get put back to the Product

    Backlog, and prioritized by the Product Owner

  • 8/12/2019 Game of Scrum

    4/39

    QUESTION: During the Sprint, Team members

    are permitted to switch tasks with each otherANSWER: TrueEXPLANATION: The Team is free to organize

    the work of the Sprint in any way it chooses.

  • 8/12/2019 Game of Scrum

    5/39

    QUESTION: Every single person on the Team isrequired to have all the development skills

    necessary to produce done Product Backlog

    Items design, coding, testing, etc.ANSWER: FalseEXPLANATION: The Team as a whole must

    have those skills, but each individual member is

    not required to have all of them.

  • 8/12/2019 Game of Scrum

    6/39

    QUESTION: The Sprint Review should be

    attended by the Team, Product Owner,

    ScrumMaster, as well as other stakeholders (likecustomers or end users)ANSWER: TrueEXPLANATION: The Sprint Review should beattended by anyone whose opinion or input

    would be useful to the Product Owner in the

    inspection of whats been produced, or theadaptation of the Product Backlog.

  • 8/12/2019 Game of Scrum

    7/39

    QUESTION: In Scrum, most of the testing is

    completed at the end of the project, just beforethe releaseANSWER: FalseEXPLANATION: Leaving important testing until

    the end of a project creates significant risk. In

    Scrum, we do as much testing as possible each

    Sprint, in order to minimize or eliminate thetesting that is left until the end of the project.

  • 8/12/2019 Game of Scrum

    8/39

    QUESTION: In Scrum, as much testing as

    possible is done during each Sprint, to ensurethat defects are found and fixed as early as

    possibleANSWER: TrueEXPLANATION: In Scrum, we try to do as

    much testing as possible each Sprint, in order to

    minimize the testing that is left until the end ofthe project

  • 8/12/2019 Game of Scrum

    9/39

    QUESTION: In Scrum, the system architectureis finalized at the beginning of the projectANSWER: FalseEXPLANATION: In Scrum, the systemarchitecture is started at the beginning of a

    project, but it continues to evolve during the

    project, as new requirements emerge, and as the

    Team discovers improvements

  • 8/12/2019 Game of Scrum

    10/39

    QUESTION: In the Sprint Planning meeting, the

    Product Owner tells the Team how much theyneed to target in the SprintANSWER: FalseEXPLANATION: In the Sprint Planning meeting,the Team decides how much they can target in

    the Sprint, free of pressure from the Product

    Owner.

  • 8/12/2019 Game of Scrum

    11/39

    QUESTION: In the Sprint Retrospective the

    Team, ScrumMaster and Product Owner discusshow to improve their process, practices and

    way of workingANSWER: True

    EXPLANATION: The purpose of the Sprint

    Retrospective is for the Team, ScrumMaster and

    Product Owner to collaborate and find ways to

    improve their process, practices, and way of

    working, within the Scrum framework.

  • 8/12/2019 Game of Scrum

    12/39

    QUESTION: It is recommended that customers,

    end users, and other stakeholders be invited tothe Sprint ReviewANSWER: TrueEXPLANATION: The purpose of the Sprint

    Review is to inspect and adapt the product

    thats being built, and inviting customers, end

    users, and other stakeholders to join will givemore and better insights.

  • 8/12/2019 Game of Scrum

    13/39

    QUESTION: It is recommended that

    management should attend the Daily ScrumMeetingANSWER: FalseEXPLANATION: The purpose of the DailyScrum Meeting is for the Team to update each

    other on progress, and make blocks visible to

    everyone, inside a 15-minute timebox. If

    management attends, it may disrupt this.

  • 8/12/2019 Game of Scrum

    14/39

    QUESTION: Items at the top of the Product Backlog

    are typically smaller in size and have more detail than

    those at the bottomANSWER: TrueEXPLANATION: On a regular basis, the Product

    Owner and Team collaborate to groom the ProductBacklog. Product Backlog Grooming involves looking

    at the next 2-3 Sprints worth of Product Backlog,

    breaking the larger Product Backlog Items into smaller

    pieces, and getting a more detailed understanding ofthe requirements.

  • 8/12/2019 Game of Scrum

    15/39

  • 8/12/2019 Game of Scrum

    16/39

    QUESTION: It is recommended that the Sprint

    Review be limited just to the Product Owner,Team and ScrumMasterANSWER: FalseEXPLANATION: The purpose of the SprintReview is to inspect and adapt the product

    thats being built, and inviting customers, end

    users, and other stakeholders to participate will

    give more and better insights

  • 8/12/2019 Game of Scrum

    17/39

    QUESTION: The Definition of Done is

    different for every single Product Backlog Item.

    ANSWER: FalseEXPLANATION: The Definition of Done

    should be relevant to most of the items on theProduct Backlog. (There may however be a

    small number of Product Backlog Items which

    because of their unique characteristics require a

    one-off Definition of Done.)

  • 8/12/2019 Game of Scrum

    18/39

    QUESTION: The Definition of Done isdecided solely by the Product Owner.ANSWER: FalseEXPLANATION: The Definition of Done isdecided by the Team in collaboration with the

    Product Owner, based on the needs of the

    release, and the capabilities of the Team.

  • 8/12/2019 Game of Scrum

    19/39

    QUESTION: Team members are only required

    to go to the Daily Scrum Meeting if they have

    blocks to reportANSWER: FalseEXPLANATION: The Daily Scrum Meeting is

    mandatory for all members of the Team who

    are not on leave that day.

  • 8/12/2019 Game of Scrum

    20/39

    QUESTION: The purpose of the Sprint Review

    is to see working product, find improvements tomake to the product, and know where we are

    relative to the goals of the releaseANSWER: TrueEXPLANATION: The main purpose of the

    Sprint Review is to see working product, find

    improvements to make to the product, and

    know where we are relative to the goals of the

    release

  • 8/12/2019 Game of Scrum

    21/39

    QUESTION: The Product Backlog is a list of

    tasks to be completed in the current SprintANSWER: FalseEXPLANATION: The list of tasks to be

    completed in the current Sprint is the SprintBacklog. The Product Backlog is an ordered list

    of features, functionality, and other work that

    needs to be completed in the future.

  • 8/12/2019 Game of Scrum

    22/39

    QUESTION: The Product Owner can change

    the future Product Backlog based on what theyobserve or feedback they receive in the Sprint

    ReviewANSWER: TrueEXPLANATION: The Product Owner can

    change the future Product Backlog at any time.

    What they cannot change is the Teams target inthe current Sprint

  • 8/12/2019 Game of Scrum

    23/39

    QUESTION: The Product Owner decides the

    Product Backlog content and prioritization, and

    the Team decides how much to target in theSprintANSWER: TrueEXPLANATION: The Product Owner decides

    the Product Backlog content and prioritization,

    and the Team decides how much to target in the

    Sprint. The Team should provide input to theProduct Owner on the content and

    prioritization of the Product Backlog

  • 8/12/2019 Game of Scrum

    24/39

    QUESTION: The Product Owner is allowed to

    make a change to the target of the Sprint, butonly if the Team agreesANSWER: FalseEXPLANATION: The Product Owner is not

    allowed to change the target of the Sprint; their

    only options are to terminate the current Sprint

    and start a new one, or wait until the nextSprint

  • 8/12/2019 Game of Scrum

    25/39

    QUESTION: The Product Owner must remaincompletely silent in the Sprint Planning MeetingANSWER: FalseEXPLANATION: The Product Owner is allowed

    to speak freely during the Sprint Planning

    Meeting (unless they are doing so in a way that

    is harmful or disruptive.)

  • 8/12/2019 Game of Scrum

    26/39

    QUESTION: Product Backlog Grooming is for

    getting a better understanding of features in the

    current Sprint

    ANSWER: FalseEXPLANATION: Product Backlog Grooming

    involves looking ahead to the next 2-3 Sprintsworth of Product Backlog, breaking the larger

    Product Backlog Items into smaller pieces, and

    getting a more details understanding of therequirements.

  • 8/12/2019 Game of Scrum

    27/39

    QUESTION: The Product Owner should create

    the Product Backlog with input from any and all

    of the following: customers, end users,stakeholders, and the TeamANSWER: TrueEXPLANATION: To create and prioritize the

    Product Backlog effectively, the Product Owner

    will need lots of input and advice from

    customers and end users, stakeholders, andespecially from the Team. A great ScrumMaster

    will help facilitate this.

  • 8/12/2019 Game of Scrum

    28/39

    QUESTION: The purpose of the Daily Scrum

    Meeting is for the Team to update the ProductOwner and Management on progress and

    blocksANSWER: FalseEXPLANATION: The purpose of the Daily

    Scrum Meeting is for the Team to update each

    other on progress and blocks. After the

    meeting, the ScrumMaster will help with

    removing the blocks.

  • 8/12/2019 Game of Scrum

    29/39

    QUESTION: The purpose of the Sprint Backlog

    and Burndown Chart is to enable theScrumMaster to monitor the TeamANSWER: FalseEXPLANATION: The Team is responsible forself-organizing to achieve the target they set for

    the Sprint, and the purpose of the Sprint

    Backlog and Burndown Chart is to enable the

    Team to self-organize and give them continuous

    visibility during the Sprint.

  • 8/12/2019 Game of Scrum

    30/39

    QUESTION: The ScrumMaster offers theirassistance only when a Team member asks for

    help.ANSWER: FalseEXPLANATION: The ScrumMaster should offer

    assistance any time they see an opportunity to

    serve the Team

  • 8/12/2019 Game of Scrum

    31/39

    QUESTION: The Team works together in theSprint Planning Meeting to decide how much to

    target in the SprintANSWER: True

    EXPLANATION: The Team works together in

    the Sprint Planning Meeting to decide how

    much to target in the Sprint, and that target is

    shared among the members of the Team.

  • 8/12/2019 Game of Scrum

    32/39

    QUESTION: The ScrumMaster is responsiblefor assigning tasks to the TeamANSWER: FalseEXPLANATION: The Team is responsible forself-organizing, and this includes together

    deciding who should work on which tasks

    during the Sprint

  • 8/12/2019 Game of Scrum

    33/39

    QUESTION: The Product Backlog is an ordered

    list of features, functionality, and other workthat needs to be completed in the futureANSWER: TrueEXPLANATION: The Product Backlog is anordered list of features, functionality, and other

    work that needs to be completed in the future,

    to maximize ROI

  • 8/12/2019 Game of Scrum

    34/39

    QUESTION: The ScrumMaster is responsible

    for making sure everyone knows and followsthe practices of ScrumANSWER: TrueEXPLANATION: One of the first things aScrumMaster will do is teach Scrum to the

    Team, Product Owner, and stakeholders.

    Everyone needs to understand the principlesand practices of Scrum, for it to be successful.

  • 8/12/2019 Game of Scrum

    35/39

    QUESTION: The ScrumMaster is responsible

    for managing the Team to hit its target at theend of the SprintANSWER: FalseEXPLANATION: The ScrumMaster does notmanage the Team the Team is responsible for

    self-organizing during the Sprint. If they fail to

    do this effectively, it will be visible, and theScrumMaster should help them learn how.

  • 8/12/2019 Game of Scrum

    36/39

    QUESTION: The ScrumMaster is responsiblefor protecting the Team from outside

    distractions, disruption, or interferenceANSWER: TrueEXPLANATION: The ScrumMaster is

    responsible for serving as a bodyguard for the

    Team, protecting them from outside

    distractions, disruption, or interference

  • 8/12/2019 Game of Scrum

    37/39

    QUESTION: The Sprint Backlog tracks howlong each Team member has spent so far on

    each taskANSWER: FalseEXPLANATION: The Sprint Backlog tracks how

    much work remains for each task being worked

    on or planned for in the Sprint.

  • 8/12/2019 Game of Scrum

    38/39

    QUESTION: The Sprint Planning Meeting istimeboxed to 8 hours for a 1 month Sprint, and

    4 hours for a 2 week SprintANSWER: TrueEXPLANATION: The Sprint Planning Meeting is

    timeboxed to these lengths to ensure that

    planning is completed in a reasonable amount of

    time, and to help the Team learn to do this.

  • 8/12/2019 Game of Scrum

    39/39

    QUESTION: The Sprint Retrospective is only

    required if the Team is having difficulties;otherwise, it is optionalANSWER: FalseEXPLANATION: No Sprint is perfect, and aSprint Retrospective is mandatory for every

    Sprint, to enable the Team, Product Owner, and

    ScrumMaster to identify improvements to ourway of working in future Sprints.