gas quality potential constraints on flows from the zeebrugge area

9
Gas Quality Potential constraints on flows from the Zeebrugge area 5 November 2009

Upload: nicki

Post on 05-Jan-2016

21 views

Category:

Documents


1 download

DESCRIPTION

Gas Quality Potential constraints on flows from the Zeebrugge area. 5 November 2009. What’s changed since 2006: Wobbe Index?. Zeepipe (ZPT) Gas from Norway. Nordstream II Russian Gas (2012-13) Rich gas. Terminal LNG. GRAV Gas from Norway via Emden (2014). Zelzate (ZEL) - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Gas Quality  Potential constraints on flows from the Zeebrugge area

Gas Quality Potential constraints on flows

from the Zeebrugge area

5 November 2009

Page 2: Gas Quality  Potential constraints on flows from the Zeebrugge area

2

What’s changed since 2006: Wobbe Index?

IUK

Zeepipe (ZPT) Gas from Norway

Terminal LNG

Eynatten (EYN) Gas from

German/Russian

GRAVGas from

Norway via Emden(2014)

Zelzate (ZEL) Gas from Netherlands

(2010)

Line pack

OKSOKS VTN

510005150052000525005300053500540005450055000

ZPT WI

52000525005300053500540005450055000555005600056500

LNG WI

49500500005050051000515005200052500530005350054000

EYN WI

Nordstream IIRussian Gas

(2012-13)Rich gas

Page 3: Gas Quality  Potential constraints on flows from the Zeebrugge area

3

IUK

Zeepipe (ZPT) Gas from Norway

Terminal LNG

Eynatten (EYN) Gas from

German/Russian

GRAVGas from

Norway via Emden(2014)

Zelzate (ZEL) Gas from Netherlands

(2010)

Line pack

OKSOKS VTN

0

5

10

15

20

25

30

35

40

LNG Flows

0

5

10

15

20

25

30

EYN Flows

0

5

10

15

20

25

30

35

40

45

ZPT Flows

What’s changed since 2006: Volumes?

Page 4: Gas Quality  Potential constraints on flows from the Zeebrugge area

4

Eynatten gas flows 2001-2009

Page 5: Gas Quality  Potential constraints on flows from the Zeebrugge area

5

Page 6: Gas Quality  Potential constraints on flows from the Zeebrugge area

6

Use of LPack (Dam OKS)

0

100 000

200 000

300 000

400 000

500 000

600 000

700 000

800 000

900 000

1 000 000

Q m

³(n

)/h

52

52,5

53

53,5

54

54,5

WI kJ/m

³(n

)

Injections into VTN of Norwegian gasIn m³(n)/h

GS(M)R upper limit

Wobbe IndexThreshold for injection

Wobbe Index ZPT

Page 7: Gas Quality  Potential constraints on flows from the Zeebrugge area

7

Looking ahead

• Views on Fluxys’ arguments– Does this story raise your concerns about gas supplies from the

Zeebrugge area going forward?– What would be the implications for your business if flows from

Zeebrugge become less reliable?• Pre-Xmas Workshop on gas quality

– Would you be interested in attending a workshop facilitated by Ofgem regarding gas quality (18th November 9-12)?

– Topics that could potentially be covered at the workshop include: • Revisiting work to assess the magnitude of the risk• Discussing the appropriate investment response (previously proposed hybrid

approach, other possible infrastructure investment)• Considering barrier that hindered market interest of the previous tender

process and possible remedies.

Page 8: Gas Quality  Potential constraints on flows from the Zeebrugge area

8

Contacts

• For technical information regarding the Zeebrugge area contact:– Laurent Remy

• FLUXYS – International Business & LNG• Tel: +32 2 282 7450• [email protected]

• Ofgem’s contact officer is:– Antony Miller

• Tel: +44 (0)20 7901 0506• Email: [email protected]

Page 9: Gas Quality  Potential constraints on flows from the Zeebrugge area

9