gas+lift+with+nitrogen+injection+generated+in+situ
TRANSCRIPT
-
5/21/2018 GAS+LIFT+WITH+NITROGEN+INJECTION+GENERATED+IN+SITU
Copyright 2000, Society of Petroleum Engineers Inc.
This paper was prepared for presentation at the 2000 SPE International Petroleum Conferenceand Exhibition in Mexico held in Villahermosa, Mexico, 13 February 2000.
This paper was selected for presentation by an SPE Program Committee following review ofinformation contained in an abstract submitted by the author(s). Contents of the paper, aspresented, have not been reviewed by the Society of Petroleum Engineers and are subject to
correction by the author(s). The material, as presented, does not necessarily reflect anyposition of the Society of Petroleum Engineers, its officers, or members. Papers presented atSPE meetings are subject to publication review by Editorial Committees of the Society ofPetroleum Engineers. Electronic reproduction, distribution, or storage of any part of this paperfor commercial purposes without the written consent of the Society of Petroleum Engineers isprohibited. Permission to reproduce in print is restricted to an abstract of not more than 300
words; illustrations may not be copied. The abstract must contain conspicuousacknowledgment of where and by whom the paper was presented. Write Librarian, SPE, P.O.Box 833836, Richardson, TX 75083-3836, U.S.A., fax 01-972-952-9435.
ABSTRACT
Gas lift is a feasible option as an artificial lift system in a
depleted field. In the Bellota field there is no substructure
means to install any type of artificial lift system, therefore
the use of nitrogen as a gas lift source is necessary to
keep the Bellota wells producing. After evaluating
different options we implemented a nitrogen generatedin situ project using the membrane technology.
This paper analyzed the gas lift process design by using
nodal analysis and optimum allocation of nitrogen in
each well. Special emphasis and consideration was
given to this project from an economical, operational,
technical and environmental points of view. It is olso
compares this option with differents alternatives
including the traditional gas lift method using natural gas
as a source as well as the use of stored nitrogen fromstorage trucks (Tanks). Our evaluation of results
obtained from the different options investigated in this
study clearly indicates that this method is a good option
in this particular situation.
Nitrogen injection generated in situ with membr
technology can be a feasible and profitable altern
source of gas lift as shown in this study.
INTRODUCTION
Bellota Chinchorro is one of the seven producing ar
in the Southern Region of Mexico. The curr
production of this field is 105 000 STB/D of oil and
MMSCF/D of gas produced from dolomite formatio
belonging to Jurassic and Cretaceous age.
The objective of this study are the wells drilled in
Bellota field. Initial production of the bellota field sta
in 1982 reaching a peak production of 44 000 STB/D
1995. Current production is at 20 000 STB/D, ma
attributed to natural depletion. Year- to- date produc
from this field is estimated at 140 MMSTB, and
expected to produce another 50 MMSTB from calcula
total reserves.
This field is divided in two different sections. The w
that will be discussed in this gas lift application belon
the north section. These wells are currently deple
below saturation pressure. It is presumed that a gas
has been already formed in the top of the reservsince GOR has been decreasing gradually. In addit
the reservoir pressure has decline drastically makin
necessary to provide some form of artificial
assistance to keep the wells producing.
Those wells that have been converted to gas lift,
deep wells, which have so many disadvantages for
SPE 59028
GAS LIFT WITH NITROGEN INJECTION GENERATED IN SITUMiguel A. Lozada Aguilar, M.del Remedios Arredondo Monarrez, SPE, Pemex, PEP.
-
5/21/2018 GAS+LIFT+WITH+NITROGEN+INJECTION+GENERATED+IN+SITU
2 MIGUEL A. LOZADA AGUILAR, M.DEL REMEDIOS ARREDONDO MONARREZ SPE 59
artificial lift system. Some electric submergible pumps
have been tested before with poor results, and then, a
gas lift system by using nitrogen as source was installed,
since no facilities were available to handle natural gas as
a source for gas lift.
In the very beginning, storage trucks were used to
deliver nitrogen, but since this method was so
expensive, an in situ nitrogen generation project was
implemented, using the membrane technology. In this
way, it was possible to reduce 50% the total costs in
three gas lift wells.
In March 21 of 1998, gas lift started in wells Bellota 136,
138 and 158-D using nitrogen generated in situ with
membrane technology as a source.
PRINCIPIA OF MEMBRANE EQUIPMENT FOR
NITROGEN GENERATION
Nitrogen generation through membrane equipment is
carried out by pumping an air current into membrane,
which due to its especial material design let the air to be
separated into nitrogen and oxygen mainly. This is
achieved basically because the oxygen flows faster than
nitrogen through it, being expulsed to the atmosphere,
as long as the nitrogen is absorbed into the membrane
to be delivered to the next compression stage. Before
the separation process, air composition is 78% of
nitrogen, 21% of oxygen and 1% of rear gases;
Neverdeless just after the separation process, gas
mixture will be expulsed into the atmosphere with 40% of
oxygen content, and the one that has been absorbed
into the membrane has from 95% to 98% of nitrogencontent.
Membranes are built up from a polymeric thin cap, which
has special physical properties that make the separation
efficiency to have a variation base on: pressure,
temperature, permeability, membrane aria and
selectivity. Since 1987, when they have been reported
for its use in petroleum industry, they have evolved u
now, having 60% of better permeability and 30%
better selectivity, besides, a significant reduction
consumption energy has been achieved (Figure No.1
Equipment to be installed on location together w
membrane unit is the following: two air compress
pack, an air nitrogen compressor pack, flow meter
and additional equipment. A brief functional descrip
for each component is given next to it.
a).- Two air compressor pack.
This pack has the function of comprise the air, wh
comes from the atmosphere to be deliver into the n
compression stage. Air pressure is increased fr
atmosphere pressure to 200 PSIG. Those
compressors handle 5.6 MMSCF/D with 1100 HP
potency.
b).- Air nitrogen compressor pack.
This pack has the function to raise the air pressure t
comes from the previous stage to be deliver into
membrane unit at 400 PSIG, and it has also the func
to increase the pressure of nitrogen which comes f
membrane unit in two stages, one of them from 4
PSIG to 900 PSIG and the other one from 900 PSIG
2000 PSIG, to be deliver into the gas line for gas
purpose.
c).- Membrane unit.
This pack has the function of separate 5.6 MMSCF/D
air to obtain 2 MMSCF/D of nitrogen with 95% to 98%
quality. This unit is built up of 36 cylinders, the ones
the membrane element inside of them.
d).- Flow meter unit.
This unit has the function of measure the amountnitrogen that is deliver into the gas line for gas lift.
e).- Additional equipment.
This equipment helps in order to let the main equipm
accomplish its function. Some of the most import
devices are: filter system, coolers, start on compres
energy plant and fuel storage.
-
5/21/2018 GAS+LIFT+WITH+NITROGEN+INJECTION+GENERATED+IN+SITU
SPE 59028 GAS LIFT WITH NITROGEN INJECTION GENERATED IN SITU
GAS LIFT NETWORK AND WELLS CONVERSION
Those three wells, which will be converted from natural
flow to gas lift, were drilled in the same location, thereby
gas lift line construction was cheap and quickly, as
distance from each well was no longer tan 500 FT. It
was also necessary to install flow meter and regulation
valves for each well. The nitrogen generation equipment
was installed in the same location (figure No. 2).
In the other hand, in order to make the wells conversion
cheaper, it was concluded that no workover rigs should
be necessary, as operation conditions for each well
permitted start the wells on production just by injecting
gas in one point, that means not to use any upper
injection valve. In this way a puncher charge was shot,
taking in account the equivalent diameter for an specific
drop drown from casing pressure to tubing pressure.
This was achieved basically, because a high pressure
was available in the gas line (2000 PSIG).
EQUIPMENT DESIGN
In order to design the equipment dimensions, it was
necessary to use three different software: nodal
analysis, gas lift design and equal slope method to
allocate the amount of gas for each well.
Based on the results getting from the equal slope
method and gas lift design software, it was concluded
that 2 MMSCF/D of N2 will be necessary to be injected
in those three wells, and 1600 PSIG will be required on
surface pressure; thereby, according to manufacture
specifications, one equipment for 2 MMSCF/D and 2000PSIG was selected for this purpose (figure 3 and 4).
Gas lift design criteria was to find out the deepest
injection point, thereby, with static conditions was
possible to start the wells on production with 2000
PSIG of surface pressure. Injection points were
located just above of packers, due basically, that
reservoir pressure was low enough, end in the o
hand, wells productivity index were high enough
reach dynamic conditions with only one gas injec
point. Thanks to those conditions mentioned befo
it was possible to shoot the tubing by using punc
charges, rather than use workover rigs to pul
tubing string and put it back with gas lift valves.
Due basically, that there wasnt any availa
surface control valve for high pressure, it w
necessary to install chocks in order to allocate
optima amount of gas for each well; thereby it w
necessary to design the right diameter for each
of them, using Bernulli equation.
ECONOMICAL ANALYSIS
a) Assumptions for different scenarios
In order to asses the feasibility of this project, th
scenarios were madein a period of time of five years:
1) build up a gas lift network in order to use natural
as a source, installing compressors in the locatio
increase gas pressure to that one which
necessary for each well.
2) Inject nitrogen as a gas lift source by using stor
trucks.
3) Inject nitrogen as a gas lift source, by generatin
with membrane technology, with leasing option.
4) Inject nitrogen as a gas lift source, by generatin
with membrane technology, with purchase option
Those assumptions used for this analysis are referee
July, 1998 (table No.1).
The economical premises are defined as following:
Oil price: It is refereed to July 1998.
Production race: For comparison purpose, accord
to allocation of gas for each well, getting from eq
slope method, it was possible to increase 3
-
5/21/2018 GAS+LIFT+WITH+NITROGEN+INJECTION+GENERATED+IN+SITU
4 MIGUEL A. LOZADA AGUILAR, M.DEL REMEDIOS ARREDONDO MONARREZ SPE 59
STB/D by injecting 2 MMSCF/D of nitrogen, and
4125 STB/D by injecting 2 MMSCF/D of natural gas.
Discount rate: It was used that one from Pemex
projects, which is 10%.
Initial investment: Initial investment was considered
in this way:
For gas lift network option, it was considered to
built up 13 miles of gas lift line of 6 in. and 3 in..
For membranes leasing option, it was
considered to invest on nitrogen line from
membrane equipment to each well.
For membrane purchase option, it was
considered to invest on nitrogen line from
membrane equipment to each well.
For storage trucks option for nitrogen injection,
there wasnt any investment.
Operational costs: In order to obtain those costs, it
was considered the production increase for each
option, as well as the total operational costs for each
option, getting, in this way the cost for each
produced barrel.
Operational costs for that to build up gas lift
network, is an addition of: differential costbetween to buy 2 MMSCF/D of natural gas and
to sell the same amount of sour gas; leasing of
compressors to increase gas pressure from gas
line pressure to that which is required to inject in
to the well; and comprising costs to inject sour
gas toward sweeter station; which yield
657.8+48+184.2 = 1249 USD/D.
Operational cost for that to leasing storage
trucks for injecting 2 MMSCF/D of nitrogen is
equal to 18,650 USD/D.
Operational cost for leasing membranes to
generate 2 MMSCF/D of nitrogen is equal to 11,
275 USD/D
Operational cost for membrane purchase is a
to that of comprising costs in gas lift netw
option, which is equal to 184.2 USD/STB.
Field depletion: it was taken that one w
represents field performance.
b) Interpretation of economical indicators.
Some of the indicators shown here are quite far good
any petroleum project, basically because the h
production rate to be expected (table 2). So
comments are summarized as following:
- Giving the risk approach form internal rate of re
all of the four option are excellent, as it is unlikel
reach the same value for discount rate in any ban
- Regarding to investment efficiency all the values
quite high, so it means that all the four options
profitable.
- Pay back period is very short for every option
cash flow will be available since the early stages.
- Net present value could be the indicator to
considered for making a good decision, since op
1 and 4 represent the highest values, and they a
represent an important difference between
others options.
- As net present value for option 1 and 4 are q
similar, best option should be that which has so
else benefits; whether environmental, technica
operational aspects concerns.
TECHNICAL, OPERATIONAL AND ENVIRONMENT
ISSUES
Technical comparisons:
According to equal slope method, figure 6 sh
how injecting the same amount of gas, whet
nitrogen or gas at the same depth, it is possible
obtain 400 STB/D more injecting natural gas t
nitrogen. The explanation of this is because nitro
-
5/21/2018 GAS+LIFT+WITH+NITROGEN+INJECTION+GENERATED+IN+SITU
SPE 59028 GAS LIFT WITH NITROGEN INJECTION GENERATED IN SITU
is heavier than natural gas, thereby getting a higher
gradient all along the tubing; therefore, the higher
flowing bottom hole pressure, the lower liquid rate
based on productivity index ecuation. For this
specific case a 10% production rate increase could
be achieved (figure 5).
In the other hand, shows how the higher nitrogen
weigth in the annulus, the surface requirements
pressure is lower from that with natural gas injection,
therefore less potency is required. For this particular
case it is expecting to reduce 10% of total costs due
to potency reduction (figure 6).
Operational and environmental comparisons:
Nitrogen is an unfinished source available in the
atmosphere, thereby its use doesnt have to deal
with hydrocarbon exploitation.
Nitrogen plants can be installed in the most
convenient place, as they dont need natural gas
supply.
As nitrogen is an inert gas, safety problems are
reduced enormously.
Petrochemical plants can only handle 3% of impurityas a total amount of gas, thereby nitrogen uses as a
gas lift source is constrained by the total processed
gas. For this particular case the impurity percentage
was no higher than 0.5%.
As it is known nitrogen generated with membrane
technology has from 5 to 2% of impurities, mainly
oxygen. Somewhere during membrane operation,
there were some corrosion problems in the process
facilities, but unfortunately by that time it was
necessary to stop membrane operation for budget
reasons, without giving the chance to evaluate
oxygen impact on this problem, specially because
sour gas is produced in those wells. So this is a big
concern as this technology is a good option for this
particular case, anyway, if it was true, it is poss
to use chemical products to avoid this phenomen
CONCLUSIONS
Nitrogen injection as a gas lift source is feasible
it is an unfinished and available source in
atmosphere.
Nitrogen injection as a gas lift source has a sim
profitability as that with natural gas injection.
At this moment with the current conditions on
leasing contract, it is more profitable for PEMEX
buy and install its own plant.
It is possible to save 10% of potency injec
nitrogen rather than natural gas.
There is a significant reduction on risks, as nitro
is an inert gas, besides of that a significant reduc
of gas line mileage is achieved.
Reduction of 10% of production rate is expected
a result of inject nitrogen rather than natural gas.
Further investigation will be needed to evaluate
nitrogen impurities on corrosion problems.
The amount of nitrogen used for gas liftconstrained by the total gas handled
petrochemical plant, which shouldnt be no hig
than 3%.
REFERENCES
- Nodal analysis software, PIPESIM, Baker Jard
and Associates Limited.
- The technology of artificial lift methods volume
kermit Brown.
- Gas lift optimitation and design software GL
Cealc.
- Temas selectos sobre bombeo neumtico contin
Colegio de Ingenieros Petroleros de Mxico.
-
5/21/2018 GAS+LIFT+WITH+NITROGEN+INJECTION+GENERATED+IN+SITU
6 MIGUEL A. LOZADA AGUILAR, M.DEL REMEDIOS ARREDONDO MONARREZ SPE 59
- Optimizacin de la distribucin de gas en la red de
bombeo neumtico del campo Cunduacn
Oxiacaque, AIPM, Miguel Angel Lozada Aguilar y
Maria del Remedios Arredondo M.
- Technical and operational manual of membrane
plants.
-
5/21/2018 GAS+LIFT+WITH+NITROGEN+INJECTION+GENERATED+IN+SITU
SPE 59028 GAS LIFT WITH NITROGEN INJECTION GENERATED IN SITU
Figure 1
Figure 2
MEMBRANE DIAGRAM
FIBER
NITROGEN
AIR FEED
WASTE OXYGEN VENTWASTE OXYGEN VENT
FIELD MEMBRANE DIAGRAM
BELLOTA 158-D
WELL
BELLOTA 138
WELL
BELLOTA 136
WELL
MEMBRANE EQUIPMENTGAS METER
M
EM
BRAN
E
COMPRESSOR
COMPRESSOR
COMPRESSOR
FLOW LINE
NITROGEN LINE
PROCESS
FACILITIES
-
5/21/2018 GAS+LIFT+WITH+NITROGEN+INJECTION+GENERATED+IN+SITU
8 MIGUEL A. LOZADA AGUILAR, M.DEL REMEDIOS ARREDONDO MONARREZ SPE 59
Figure 3
Figure 4
WELL PERFORMANCE WITH NITROGEN INJECTION
0
20 0
40 0
60 0
80 0
1000
1200
1400
1600
1800
0 0.2 0.4 0.6 0.8 1
NITROGEN INJECTION RATE(MMSCF/D )
LIQ
UIDR
ATE(
STB/D)
BELLOTA 13 6
BELLOTA 138
BELLOTA 158-D
Iny.P.=1437 PSIG
Iny. P.=1380 PSIG
Iny.P.=1671PSIG
EQUAL SLOPE METHOD
CHARACATERISTIC CURVE FOR THREE WELLS WITH NITROGEN INJECTION
0
500
1000
1500
2000
2500
3000
3500
4000
4500
0 0.25 0.5 0.75 1 1.25 1.5 1.75 2 2.25 2.5
Nitrogen injection rate (MM SCF/D)
Liquidrate(STB/D)
41004100
-
5/21/2018 GAS+LIFT+WITH+NITROGEN+INJECTION+GENERATED+IN+SITU
SPE 59028 GAS LIFT WITH NITROGEN INJECTION GENERATED IN SITU
Figure 5
Figure 6
E Q U A L S L O P E M E T H O D
N A T U R A L G A S V S . N I T R O G E N I N J E C T I O N C O M P A R I S O N
0
5 0 0
1 0 0 0
1 5 0 0
2 0 0 0
2 5 0 0
3 0 0 0
3 5 0 0
4 0 0 0
4 5 0 05 0 0 0
0 0.25 0.5 0 .75 1 1.25 1.5 1 .75 2 2. 25 2.5
G A S I N J E C T I O N R A T E ( M M S C F / D )
LIQUIDR
ATE
(STB/D)
4 1 0 04 5 0 0
N A T U R A L G A S
N I T R O G E N
S U R F A C E R E Q U I R E M E N T S P R E S S U R E
N A T U R A L G A S V S . N I T R O G E N C O M P A R I S O N
1 5 0 0
2 0 0 0
2 5 0 0
3 0 0 0
3 5 0 0
4 0 0 0
4 5 0 0
5 0 0 0
5 5 0 0
7 0 0 9 5 0 1 2 0 0 1 4 5 0 1 7 0 0 1 9 5 0
P r e s s u r e ( P s i)
Depth(m
)
N I T R O G E N N A T U R A L G A S
-
5/21/2018 GAS+LIFT+WITH+NITROGEN+INJECTION+GENERATED+IN+SITU
10 MIGUEL A. LOZADA AGUILAR, M.DEL REMEDIOS ARREDONDO MONARREZ SPE 59
Table 1
Table 2
BASIS FOR ECONOMICAL ANALYSIS
OPTIONOPTION CONCEPTCONCEPT PRICE PERPRICE PER
BARRELBARREL
(USD)(USD)
PRODUCTIONPRODUCTION
INCREASEINCREASE
(STB/D)(STB/D)
DISCOUNTDISCOUNT
RATE (%)RATE (%)
CAPITALCAPITAL
INVESTMENTINVESTMENT
(USD)(USD)
OPERATIONALOPERATIONAL
COSTS (USD/STB)COSTS (USD/STB)
FIELDFIELD
DEPLETIDEPLETI
ON (%)ON (%)
GAS LIFTGAS LIFT
NETWORKNETWORK
NITROGENNITROGEN
INJ. WITHINJ. WITH
STORAGESTORAGE
TRUCKSTRUCKS
MEMBRANEMEMBRANE
LEASINGLEASING
MEMBRANEMEMBRANE
PURCHASEPURCHASE
22
33
44
11 1010
1010
1010
1010
41254125
37253725
37253725
37253725
1010
1010
1010
1010
1010
1010
1010
1010
0.30280.3028
5.00065.0006
3.0273.027
0.0490.049
1253,0001253,000
150,000150,000
1710,9601710,960
00
PROFITABILITY INDICATORS
OPTIONOPTION CONCEPTCONCEPT NET PRESENTNET PRESENT
VALUE (DLS)VALUE (DLS)
INVESTMENTINVESTMENT
EFFICIENCYEFFICIENCY
EFFICIENCYEFFICIENCY
RATE (%)RATE (%)
INTERNALINTERNALRATE OFRATE OF
RETURN (%)RETURN (%)
PROFITABILI-PROFITABILI-
TY RATETY RATE
(%)(% )
PAY OUTPAY OUT
TIMETIME
(YEARS)(YEARS)
GAS LIFTGAS LIFT
NETWORKNETWORK
NITROGENNITROGEN
INJECTIONINJECTION
WITHWITH
STORAGESSTORAGES
TRUCKSTRUCKS
MEMBRANEMEMBRANE
LEASINGLEASING
MEMBRANEMEMBRANE
PURCHASEPURCHASE
22
33
44
11 44380,05844380,058
29,481,60729,481,607
40575,59240575,592
3636
10,00010,000
19 819 8
2525
8282
34 734 7
11 611 6
7474
0.08650.0865
0. 01580. 0158
0.12810.1281
90 090 0
539353,083539353,083
49954995
0.030.03
11551155
63106310
78 078 0
678996,700678996,70021221,89021221,890 1.47 x 101.47 x 10
-7-7