gas+lift+with+nitrogen+injection+generated+in+situ

11
Copyright 2000, Society of Petroleum Engineers Inc. This paper was prepared for presentation at the 2000 SPE International Petroleum Conference and Exhibition in Mexico held in Villahermosa, Mexico, 1–3 February 2000. This paper was selected for presentation by an SPE Program Committee following review of information contained in an abstract submitted by the author(s). Contents of the paper, as presented, have not been reviewed by the Society of Petroleum Engineers and are subject to correction by the author(s). The material, as presented, does not necessarily reflect any position of the Society of Petroleum Engineers, its officers, or members. Papers presented at SPE meetings are subject to publication review by Editorial Committees of the Society of Petroleum Engineers. Electronic reproduction, distribution, or storage of any part of this paper for commercial purposes without the written consent of the Society of Petroleum Engineers is prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300 words; illustrations may not be copied. The abstract must contain conspicuous acknowledgment of where and by whom the paper was presented. Write Librarian, SPE, P.O. Box 833836, Richardson, TX 75083-3836, U.S.A., fax 01-972-952-9435. ABSTRACT Gas lift is a feasible option as an artificial lift system in a depleted field. In the Bellota field there is no substructure means to install any type of artificial lift system, therefore the use of nitrogen as a gas lift source is necessary to keep the Bellota wells producing. After evaluating different options we implemented a nitrogen generated in situ project using the membrane technology. This paper analyzed the gas lift process design by using nodal analysis and optimum allocation of nitrogen in each w ell. Special emphasis and cons ideration was given to this project from an economical, operational, technical and environmental points of view. It is olso compares this option with differents alternatives including the traditional gas lift method using natural gas as a source as well as the use of stored nitrogen from storage trucks (Tanks). Our evaluation of results obtained from the different options investigated in this study clearly indicates that this method is a good option in this particular situation. Nitrogen injection generated in situ with membrane technology can be a feasible and profitable alternate source of gas lift as shown in this study. INTRODUCTION Bellota – Chinchorro is one of the seven producing areas in the Southern Region of Mexico. The current production of this field is 105 000 STB/D of oil and 150 MMSCF/D of gas produced from dolomite formations, belonging to Jurassic and Cretaceous age. The objective of this study are the wells drilled in the Bellota field. Initial production of the bellota field started in 1982 reaching a peak production of 44 000 STB/D in 1995. Current produc tion is at 20 000 STB/D, mainly attributed to natural depletion. Year- to- date production from this field is estimated at 140 MMSTB, and it is expected to produce another 50 MMSTB from calculated total reserves. This field is divided in two different sections. The wells that will be discussed in this gas lift application belong to the north section. These wells are currently depleted below saturation pressure. It is presumed that a gas cap has been already formed in the top of the reservoir, since GOR has been decreasing gradually. In addition, the reservoir pre ssure has decli ne drasticall y making it necessary to provide some form of artificial lift assistance to keep the wells producing. Those wells that have been converted to gas lift, are deep wells, which have so many disadvantages for any SPE 59028 GAS LIFT WITH NITROGEN INJECTION GENERATED IN SITU Miguel A. Lozada Aguilar, M.del Remedios Arredondo Monarrez, SPE, Pemex, PEP.

Upload: pedro-perez-aparicio

Post on 12-Oct-2015

8 views

Category:

Documents


0 download

TRANSCRIPT

  • 5/21/2018 GAS+LIFT+WITH+NITROGEN+INJECTION+GENERATED+IN+SITU

    Copyright 2000, Society of Petroleum Engineers Inc.

    This paper was prepared for presentation at the 2000 SPE International Petroleum Conferenceand Exhibition in Mexico held in Villahermosa, Mexico, 13 February 2000.

    This paper was selected for presentation by an SPE Program Committee following review ofinformation contained in an abstract submitted by the author(s). Contents of the paper, aspresented, have not been reviewed by the Society of Petroleum Engineers and are subject to

    correction by the author(s). The material, as presented, does not necessarily reflect anyposition of the Society of Petroleum Engineers, its officers, or members. Papers presented atSPE meetings are subject to publication review by Editorial Committees of the Society ofPetroleum Engineers. Electronic reproduction, distribution, or storage of any part of this paperfor commercial purposes without the written consent of the Society of Petroleum Engineers isprohibited. Permission to reproduce in print is restricted to an abstract of not more than 300

    words; illustrations may not be copied. The abstract must contain conspicuousacknowledgment of where and by whom the paper was presented. Write Librarian, SPE, P.O.Box 833836, Richardson, TX 75083-3836, U.S.A., fax 01-972-952-9435.

    ABSTRACT

    Gas lift is a feasible option as an artificial lift system in a

    depleted field. In the Bellota field there is no substructure

    means to install any type of artificial lift system, therefore

    the use of nitrogen as a gas lift source is necessary to

    keep the Bellota wells producing. After evaluating

    different options we implemented a nitrogen generatedin situ project using the membrane technology.

    This paper analyzed the gas lift process design by using

    nodal analysis and optimum allocation of nitrogen in

    each well. Special emphasis and consideration was

    given to this project from an economical, operational,

    technical and environmental points of view. It is olso

    compares this option with differents alternatives

    including the traditional gas lift method using natural gas

    as a source as well as the use of stored nitrogen fromstorage trucks (Tanks). Our evaluation of results

    obtained from the different options investigated in this

    study clearly indicates that this method is a good option

    in this particular situation.

    Nitrogen injection generated in situ with membr

    technology can be a feasible and profitable altern

    source of gas lift as shown in this study.

    INTRODUCTION

    Bellota Chinchorro is one of the seven producing ar

    in the Southern Region of Mexico. The curr

    production of this field is 105 000 STB/D of oil and

    MMSCF/D of gas produced from dolomite formatio

    belonging to Jurassic and Cretaceous age.

    The objective of this study are the wells drilled in

    Bellota field. Initial production of the bellota field sta

    in 1982 reaching a peak production of 44 000 STB/D

    1995. Current production is at 20 000 STB/D, ma

    attributed to natural depletion. Year- to- date produc

    from this field is estimated at 140 MMSTB, and

    expected to produce another 50 MMSTB from calcula

    total reserves.

    This field is divided in two different sections. The w

    that will be discussed in this gas lift application belon

    the north section. These wells are currently deple

    below saturation pressure. It is presumed that a gas

    has been already formed in the top of the reservsince GOR has been decreasing gradually. In addit

    the reservoir pressure has decline drastically makin

    necessary to provide some form of artificial

    assistance to keep the wells producing.

    Those wells that have been converted to gas lift,

    deep wells, which have so many disadvantages for

    SPE 59028

    GAS LIFT WITH NITROGEN INJECTION GENERATED IN SITUMiguel A. Lozada Aguilar, M.del Remedios Arredondo Monarrez, SPE, Pemex, PEP.

  • 5/21/2018 GAS+LIFT+WITH+NITROGEN+INJECTION+GENERATED+IN+SITU

    2 MIGUEL A. LOZADA AGUILAR, M.DEL REMEDIOS ARREDONDO MONARREZ SPE 59

    artificial lift system. Some electric submergible pumps

    have been tested before with poor results, and then, a

    gas lift system by using nitrogen as source was installed,

    since no facilities were available to handle natural gas as

    a source for gas lift.

    In the very beginning, storage trucks were used to

    deliver nitrogen, but since this method was so

    expensive, an in situ nitrogen generation project was

    implemented, using the membrane technology. In this

    way, it was possible to reduce 50% the total costs in

    three gas lift wells.

    In March 21 of 1998, gas lift started in wells Bellota 136,

    138 and 158-D using nitrogen generated in situ with

    membrane technology as a source.

    PRINCIPIA OF MEMBRANE EQUIPMENT FOR

    NITROGEN GENERATION

    Nitrogen generation through membrane equipment is

    carried out by pumping an air current into membrane,

    which due to its especial material design let the air to be

    separated into nitrogen and oxygen mainly. This is

    achieved basically because the oxygen flows faster than

    nitrogen through it, being expulsed to the atmosphere,

    as long as the nitrogen is absorbed into the membrane

    to be delivered to the next compression stage. Before

    the separation process, air composition is 78% of

    nitrogen, 21% of oxygen and 1% of rear gases;

    Neverdeless just after the separation process, gas

    mixture will be expulsed into the atmosphere with 40% of

    oxygen content, and the one that has been absorbed

    into the membrane has from 95% to 98% of nitrogencontent.

    Membranes are built up from a polymeric thin cap, which

    has special physical properties that make the separation

    efficiency to have a variation base on: pressure,

    temperature, permeability, membrane aria and

    selectivity. Since 1987, when they have been reported

    for its use in petroleum industry, they have evolved u

    now, having 60% of better permeability and 30%

    better selectivity, besides, a significant reduction

    consumption energy has been achieved (Figure No.1

    Equipment to be installed on location together w

    membrane unit is the following: two air compress

    pack, an air nitrogen compressor pack, flow meter

    and additional equipment. A brief functional descrip

    for each component is given next to it.

    a).- Two air compressor pack.

    This pack has the function of comprise the air, wh

    comes from the atmosphere to be deliver into the n

    compression stage. Air pressure is increased fr

    atmosphere pressure to 200 PSIG. Those

    compressors handle 5.6 MMSCF/D with 1100 HP

    potency.

    b).- Air nitrogen compressor pack.

    This pack has the function to raise the air pressure t

    comes from the previous stage to be deliver into

    membrane unit at 400 PSIG, and it has also the func

    to increase the pressure of nitrogen which comes f

    membrane unit in two stages, one of them from 4

    PSIG to 900 PSIG and the other one from 900 PSIG

    2000 PSIG, to be deliver into the gas line for gas

    purpose.

    c).- Membrane unit.

    This pack has the function of separate 5.6 MMSCF/D

    air to obtain 2 MMSCF/D of nitrogen with 95% to 98%

    quality. This unit is built up of 36 cylinders, the ones

    the membrane element inside of them.

    d).- Flow meter unit.

    This unit has the function of measure the amountnitrogen that is deliver into the gas line for gas lift.

    e).- Additional equipment.

    This equipment helps in order to let the main equipm

    accomplish its function. Some of the most import

    devices are: filter system, coolers, start on compres

    energy plant and fuel storage.

  • 5/21/2018 GAS+LIFT+WITH+NITROGEN+INJECTION+GENERATED+IN+SITU

    SPE 59028 GAS LIFT WITH NITROGEN INJECTION GENERATED IN SITU

    GAS LIFT NETWORK AND WELLS CONVERSION

    Those three wells, which will be converted from natural

    flow to gas lift, were drilled in the same location, thereby

    gas lift line construction was cheap and quickly, as

    distance from each well was no longer tan 500 FT. It

    was also necessary to install flow meter and regulation

    valves for each well. The nitrogen generation equipment

    was installed in the same location (figure No. 2).

    In the other hand, in order to make the wells conversion

    cheaper, it was concluded that no workover rigs should

    be necessary, as operation conditions for each well

    permitted start the wells on production just by injecting

    gas in one point, that means not to use any upper

    injection valve. In this way a puncher charge was shot,

    taking in account the equivalent diameter for an specific

    drop drown from casing pressure to tubing pressure.

    This was achieved basically, because a high pressure

    was available in the gas line (2000 PSIG).

    EQUIPMENT DESIGN

    In order to design the equipment dimensions, it was

    necessary to use three different software: nodal

    analysis, gas lift design and equal slope method to

    allocate the amount of gas for each well.

    Based on the results getting from the equal slope

    method and gas lift design software, it was concluded

    that 2 MMSCF/D of N2 will be necessary to be injected

    in those three wells, and 1600 PSIG will be required on

    surface pressure; thereby, according to manufacture

    specifications, one equipment for 2 MMSCF/D and 2000PSIG was selected for this purpose (figure 3 and 4).

    Gas lift design criteria was to find out the deepest

    injection point, thereby, with static conditions was

    possible to start the wells on production with 2000

    PSIG of surface pressure. Injection points were

    located just above of packers, due basically, that

    reservoir pressure was low enough, end in the o

    hand, wells productivity index were high enough

    reach dynamic conditions with only one gas injec

    point. Thanks to those conditions mentioned befo

    it was possible to shoot the tubing by using punc

    charges, rather than use workover rigs to pul

    tubing string and put it back with gas lift valves.

    Due basically, that there wasnt any availa

    surface control valve for high pressure, it w

    necessary to install chocks in order to allocate

    optima amount of gas for each well; thereby it w

    necessary to design the right diameter for each

    of them, using Bernulli equation.

    ECONOMICAL ANALYSIS

    a) Assumptions for different scenarios

    In order to asses the feasibility of this project, th

    scenarios were madein a period of time of five years:

    1) build up a gas lift network in order to use natural

    as a source, installing compressors in the locatio

    increase gas pressure to that one which

    necessary for each well.

    2) Inject nitrogen as a gas lift source by using stor

    trucks.

    3) Inject nitrogen as a gas lift source, by generatin

    with membrane technology, with leasing option.

    4) Inject nitrogen as a gas lift source, by generatin

    with membrane technology, with purchase option

    Those assumptions used for this analysis are referee

    July, 1998 (table No.1).

    The economical premises are defined as following:

    Oil price: It is refereed to July 1998.

    Production race: For comparison purpose, accord

    to allocation of gas for each well, getting from eq

    slope method, it was possible to increase 3

  • 5/21/2018 GAS+LIFT+WITH+NITROGEN+INJECTION+GENERATED+IN+SITU

    4 MIGUEL A. LOZADA AGUILAR, M.DEL REMEDIOS ARREDONDO MONARREZ SPE 59

    STB/D by injecting 2 MMSCF/D of nitrogen, and

    4125 STB/D by injecting 2 MMSCF/D of natural gas.

    Discount rate: It was used that one from Pemex

    projects, which is 10%.

    Initial investment: Initial investment was considered

    in this way:

    For gas lift network option, it was considered to

    built up 13 miles of gas lift line of 6 in. and 3 in..

    For membranes leasing option, it was

    considered to invest on nitrogen line from

    membrane equipment to each well.

    For membrane purchase option, it was

    considered to invest on nitrogen line from

    membrane equipment to each well.

    For storage trucks option for nitrogen injection,

    there wasnt any investment.

    Operational costs: In order to obtain those costs, it

    was considered the production increase for each

    option, as well as the total operational costs for each

    option, getting, in this way the cost for each

    produced barrel.

    Operational costs for that to build up gas lift

    network, is an addition of: differential costbetween to buy 2 MMSCF/D of natural gas and

    to sell the same amount of sour gas; leasing of

    compressors to increase gas pressure from gas

    line pressure to that which is required to inject in

    to the well; and comprising costs to inject sour

    gas toward sweeter station; which yield

    657.8+48+184.2 = 1249 USD/D.

    Operational cost for that to leasing storage

    trucks for injecting 2 MMSCF/D of nitrogen is

    equal to 18,650 USD/D.

    Operational cost for leasing membranes to

    generate 2 MMSCF/D of nitrogen is equal to 11,

    275 USD/D

    Operational cost for membrane purchase is a

    to that of comprising costs in gas lift netw

    option, which is equal to 184.2 USD/STB.

    Field depletion: it was taken that one w

    represents field performance.

    b) Interpretation of economical indicators.

    Some of the indicators shown here are quite far good

    any petroleum project, basically because the h

    production rate to be expected (table 2). So

    comments are summarized as following:

    - Giving the risk approach form internal rate of re

    all of the four option are excellent, as it is unlikel

    reach the same value for discount rate in any ban

    - Regarding to investment efficiency all the values

    quite high, so it means that all the four options

    profitable.

    - Pay back period is very short for every option

    cash flow will be available since the early stages.

    - Net present value could be the indicator to

    considered for making a good decision, since op

    1 and 4 represent the highest values, and they a

    represent an important difference between

    others options.

    - As net present value for option 1 and 4 are q

    similar, best option should be that which has so

    else benefits; whether environmental, technica

    operational aspects concerns.

    TECHNICAL, OPERATIONAL AND ENVIRONMENT

    ISSUES

    Technical comparisons:

    According to equal slope method, figure 6 sh

    how injecting the same amount of gas, whet

    nitrogen or gas at the same depth, it is possible

    obtain 400 STB/D more injecting natural gas t

    nitrogen. The explanation of this is because nitro

  • 5/21/2018 GAS+LIFT+WITH+NITROGEN+INJECTION+GENERATED+IN+SITU

    SPE 59028 GAS LIFT WITH NITROGEN INJECTION GENERATED IN SITU

    is heavier than natural gas, thereby getting a higher

    gradient all along the tubing; therefore, the higher

    flowing bottom hole pressure, the lower liquid rate

    based on productivity index ecuation. For this

    specific case a 10% production rate increase could

    be achieved (figure 5).

    In the other hand, shows how the higher nitrogen

    weigth in the annulus, the surface requirements

    pressure is lower from that with natural gas injection,

    therefore less potency is required. For this particular

    case it is expecting to reduce 10% of total costs due

    to potency reduction (figure 6).

    Operational and environmental comparisons:

    Nitrogen is an unfinished source available in the

    atmosphere, thereby its use doesnt have to deal

    with hydrocarbon exploitation.

    Nitrogen plants can be installed in the most

    convenient place, as they dont need natural gas

    supply.

    As nitrogen is an inert gas, safety problems are

    reduced enormously.

    Petrochemical plants can only handle 3% of impurityas a total amount of gas, thereby nitrogen uses as a

    gas lift source is constrained by the total processed

    gas. For this particular case the impurity percentage

    was no higher than 0.5%.

    As it is known nitrogen generated with membrane

    technology has from 5 to 2% of impurities, mainly

    oxygen. Somewhere during membrane operation,

    there were some corrosion problems in the process

    facilities, but unfortunately by that time it was

    necessary to stop membrane operation for budget

    reasons, without giving the chance to evaluate

    oxygen impact on this problem, specially because

    sour gas is produced in those wells. So this is a big

    concern as this technology is a good option for this

    particular case, anyway, if it was true, it is poss

    to use chemical products to avoid this phenomen

    CONCLUSIONS

    Nitrogen injection as a gas lift source is feasible

    it is an unfinished and available source in

    atmosphere.

    Nitrogen injection as a gas lift source has a sim

    profitability as that with natural gas injection.

    At this moment with the current conditions on

    leasing contract, it is more profitable for PEMEX

    buy and install its own plant.

    It is possible to save 10% of potency injec

    nitrogen rather than natural gas.

    There is a significant reduction on risks, as nitro

    is an inert gas, besides of that a significant reduc

    of gas line mileage is achieved.

    Reduction of 10% of production rate is expected

    a result of inject nitrogen rather than natural gas.

    Further investigation will be needed to evaluate

    nitrogen impurities on corrosion problems.

    The amount of nitrogen used for gas liftconstrained by the total gas handled

    petrochemical plant, which shouldnt be no hig

    than 3%.

    REFERENCES

    - Nodal analysis software, PIPESIM, Baker Jard

    and Associates Limited.

    - The technology of artificial lift methods volume

    kermit Brown.

    - Gas lift optimitation and design software GL

    Cealc.

    - Temas selectos sobre bombeo neumtico contin

    Colegio de Ingenieros Petroleros de Mxico.

  • 5/21/2018 GAS+LIFT+WITH+NITROGEN+INJECTION+GENERATED+IN+SITU

    6 MIGUEL A. LOZADA AGUILAR, M.DEL REMEDIOS ARREDONDO MONARREZ SPE 59

    - Optimizacin de la distribucin de gas en la red de

    bombeo neumtico del campo Cunduacn

    Oxiacaque, AIPM, Miguel Angel Lozada Aguilar y

    Maria del Remedios Arredondo M.

    - Technical and operational manual of membrane

    plants.

  • 5/21/2018 GAS+LIFT+WITH+NITROGEN+INJECTION+GENERATED+IN+SITU

    SPE 59028 GAS LIFT WITH NITROGEN INJECTION GENERATED IN SITU

    Figure 1

    Figure 2

    MEMBRANE DIAGRAM

    FIBER

    NITROGEN

    AIR FEED

    WASTE OXYGEN VENTWASTE OXYGEN VENT

    FIELD MEMBRANE DIAGRAM

    BELLOTA 158-D

    WELL

    BELLOTA 138

    WELL

    BELLOTA 136

    WELL

    MEMBRANE EQUIPMENTGAS METER

    M

    EM

    BRAN

    E

    COMPRESSOR

    COMPRESSOR

    COMPRESSOR

    FLOW LINE

    NITROGEN LINE

    PROCESS

    FACILITIES

  • 5/21/2018 GAS+LIFT+WITH+NITROGEN+INJECTION+GENERATED+IN+SITU

    8 MIGUEL A. LOZADA AGUILAR, M.DEL REMEDIOS ARREDONDO MONARREZ SPE 59

    Figure 3

    Figure 4

    WELL PERFORMANCE WITH NITROGEN INJECTION

    0

    20 0

    40 0

    60 0

    80 0

    1000

    1200

    1400

    1600

    1800

    0 0.2 0.4 0.6 0.8 1

    NITROGEN INJECTION RATE(MMSCF/D )

    LIQ

    UIDR

    ATE(

    STB/D)

    BELLOTA 13 6

    BELLOTA 138

    BELLOTA 158-D

    Iny.P.=1437 PSIG

    Iny. P.=1380 PSIG

    Iny.P.=1671PSIG

    EQUAL SLOPE METHOD

    CHARACATERISTIC CURVE FOR THREE WELLS WITH NITROGEN INJECTION

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    4500

    0 0.25 0.5 0.75 1 1.25 1.5 1.75 2 2.25 2.5

    Nitrogen injection rate (MM SCF/D)

    Liquidrate(STB/D)

    41004100

  • 5/21/2018 GAS+LIFT+WITH+NITROGEN+INJECTION+GENERATED+IN+SITU

    SPE 59028 GAS LIFT WITH NITROGEN INJECTION GENERATED IN SITU

    Figure 5

    Figure 6

    E Q U A L S L O P E M E T H O D

    N A T U R A L G A S V S . N I T R O G E N I N J E C T I O N C O M P A R I S O N

    0

    5 0 0

    1 0 0 0

    1 5 0 0

    2 0 0 0

    2 5 0 0

    3 0 0 0

    3 5 0 0

    4 0 0 0

    4 5 0 05 0 0 0

    0 0.25 0.5 0 .75 1 1.25 1.5 1 .75 2 2. 25 2.5

    G A S I N J E C T I O N R A T E ( M M S C F / D )

    LIQUIDR

    ATE

    (STB/D)

    4 1 0 04 5 0 0

    N A T U R A L G A S

    N I T R O G E N

    S U R F A C E R E Q U I R E M E N T S P R E S S U R E

    N A T U R A L G A S V S . N I T R O G E N C O M P A R I S O N

    1 5 0 0

    2 0 0 0

    2 5 0 0

    3 0 0 0

    3 5 0 0

    4 0 0 0

    4 5 0 0

    5 0 0 0

    5 5 0 0

    7 0 0 9 5 0 1 2 0 0 1 4 5 0 1 7 0 0 1 9 5 0

    P r e s s u r e ( P s i)

    Depth(m

    )

    N I T R O G E N N A T U R A L G A S

  • 5/21/2018 GAS+LIFT+WITH+NITROGEN+INJECTION+GENERATED+IN+SITU

    10 MIGUEL A. LOZADA AGUILAR, M.DEL REMEDIOS ARREDONDO MONARREZ SPE 59

    Table 1

    Table 2

    BASIS FOR ECONOMICAL ANALYSIS

    OPTIONOPTION CONCEPTCONCEPT PRICE PERPRICE PER

    BARRELBARREL

    (USD)(USD)

    PRODUCTIONPRODUCTION

    INCREASEINCREASE

    (STB/D)(STB/D)

    DISCOUNTDISCOUNT

    RATE (%)RATE (%)

    CAPITALCAPITAL

    INVESTMENTINVESTMENT

    (USD)(USD)

    OPERATIONALOPERATIONAL

    COSTS (USD/STB)COSTS (USD/STB)

    FIELDFIELD

    DEPLETIDEPLETI

    ON (%)ON (%)

    GAS LIFTGAS LIFT

    NETWORKNETWORK

    NITROGENNITROGEN

    INJ. WITHINJ. WITH

    STORAGESTORAGE

    TRUCKSTRUCKS

    MEMBRANEMEMBRANE

    LEASINGLEASING

    MEMBRANEMEMBRANE

    PURCHASEPURCHASE

    22

    33

    44

    11 1010

    1010

    1010

    1010

    41254125

    37253725

    37253725

    37253725

    1010

    1010

    1010

    1010

    1010

    1010

    1010

    1010

    0.30280.3028

    5.00065.0006

    3.0273.027

    0.0490.049

    1253,0001253,000

    150,000150,000

    1710,9601710,960

    00

    PROFITABILITY INDICATORS

    OPTIONOPTION CONCEPTCONCEPT NET PRESENTNET PRESENT

    VALUE (DLS)VALUE (DLS)

    INVESTMENTINVESTMENT

    EFFICIENCYEFFICIENCY

    EFFICIENCYEFFICIENCY

    RATE (%)RATE (%)

    INTERNALINTERNALRATE OFRATE OF

    RETURN (%)RETURN (%)

    PROFITABILI-PROFITABILI-

    TY RATETY RATE

    (%)(% )

    PAY OUTPAY OUT

    TIMETIME

    (YEARS)(YEARS)

    GAS LIFTGAS LIFT

    NETWORKNETWORK

    NITROGENNITROGEN

    INJECTIONINJECTION

    WITHWITH

    STORAGESSTORAGES

    TRUCKSTRUCKS

    MEMBRANEMEMBRANE

    LEASINGLEASING

    MEMBRANEMEMBRANE

    PURCHASEPURCHASE

    22

    33

    44

    11 44380,05844380,058

    29,481,60729,481,607

    40575,59240575,592

    3636

    10,00010,000

    19 819 8

    2525

    8282

    34 734 7

    11 611 6

    7474

    0.08650.0865

    0. 01580. 0158

    0.12810.1281

    90 090 0

    539353,083539353,083

    49954995

    0.030.03

    11551155

    63106310

    78 078 0

    678996,700678996,70021221,89021221,890 1.47 x 101.47 x 10

    -7-7