generation system adequacy evaluation
TRANSCRIPT
-
8/12/2019 Generation System Adequacy Evaluation
1/85
Objective : to determine the required amount of system
generating capacity to ensure an adequate supply.
1. Static Capacity Requirement :
Long-term evaluation of the overall system requirement.
Practice : Percentage Reserve method. Issue : comparison
Probabilistic approaches.
2. Operating Capacity Requirement
Short term evaluation of the actual capacity required tomeet a given load.
Fundamental difference: Time period
Generation System Adequacy Evaluation
-
8/12/2019 Generation System Adequacy Evaluation
2/85
Generation System Adequacy Evaluation
The Generation and Load models arecombined to form Risk model
-
8/12/2019 Generation System Adequacy Evaluation
3/85
Binomial Distribution
P(H) + P(T) = [P(H) + P(T)]1
P(H).P(H) + 2P(H).P(T) + P(T).P(T)= P2(H) + 2P.(H)P(T) + P2(T) = [P(H) + P(T)]2
P3
(H) + 3P2
(H)P(T) + 3P(H)P2
(T) + P3
(T)= [P(H) + P(T)]3
Ex. Consider a system with 4 components. Thecomponents are identical with a success
probability of 0.9 and a failure probability of 0.1Obtain the various states in which the components
can exist.
-
8/12/2019 Generation System Adequacy Evaluation
4/85
Since there are 4 components and each one of
them is either available OR unavailable, the
total number of states is
All components working
1 component failed
2 components failed
3 components failed
All components failed
-
8/12/2019 Generation System Adequacy Evaluation
5/85
(S+F)4= S4+4S3F+6S2F2+4SF3+F4
System state Individual Probability
All components working 0.94 = 0.6561
1 component failed 4X0.93X0.1 = 0.2961
2 components failed 6X0.92X0.12 = 0.0486
3 components failed 4X0.9X0.13 =0.0036
All components failed 0.14 = 0.00011.0000
-
8/12/2019 Generation System Adequacy Evaluation
6/85
If at least three components are required for
success then
Success Probability OR Reliability R
R = 0.6561 + 0.2916 = 0.9477
Failure probability of the system Q Q = 0.0486 + 0.0036 + 0.0001 = 0.0523 = 1R
-
8/12/2019 Generation System Adequacy Evaluation
7/85
-
8/12/2019 Generation System Adequacy Evaluation
8/85
Case Units out Capacity Individual
Probability
Out available
A 1 X 10 MW
0 0 10 0.98
1 0.02
B 2 X 10 MW
0 0 20 0.9604
1 10 10 0.0392
2 20 0 0.0004
C 3 X 5 MW
0 0 15 0.941192
1 5 10 0.057624
2 10 5 0.001176
3 15 0 0.000008
D 4 X 10/3 MW
0 0 40/3 0.92236816
1 10/3 10 0.07529536
2 20/3 20/3 0.00230496
3 10 10/3 0.00003136
4 40/3 0 0.00000016
-
8/12/2019 Generation System Adequacy Evaluation
9/85
Expected Load Loss
-
8/12/2019 Generation System Adequacy Evaluation
10/85
Case Capacity Out
(MW)
Probability Load loss
(MW)
Expected Load Loss
(MW)
A 1 X 10 MW
0 0.98 0 ---
10 0.02 10 0.2 0.2 MW
B 2 X 10 MW
0 0.9604 0 ---
10 0.0392 0 ---
20 0.0004 10 0.004 0.004 MW
C 3 X 5 MW
0 0.941192 0 ----
5 0.057524 0 -----
10 0.001176 5 0.00588
15 0.000008 10 0.00008 0.00596
MW
D 4 X 10/3 MW
0 0.92236816 0 ------
10/3 0.07529536 0 ------
20/3 0.00230496 10/3 0.00768320
10 0.00003136 20/3 0.00020907
40/3 0.00000016 10 0.00000160 0.0078938
7 MW
-
8/12/2019 Generation System Adequacy Evaluation
11/85
Let the cost per 10 MW unit be 1 unit. The
investment cost for the alternatives is
Investment cost of plant
Expected Load curtailment
System Expected Load Loss (MW) Investment cost p.u.
1 X 10 MW 0.2 1.0
2 X 10 MW 0.004 2.0
3 X 5 MW 0.00596 1.5
4 X 10/3 MW 0.00789387 1.33
System Probability of loss
of load
Expected load
curtailment hr/yr
1 X 10 MW 0.02 175.2
2 X 10 MW 0.0004 3.504
3 X 5 MW 0.001184 10.37814
4 X 10/3 MW 0.00233648 20.46756
-
8/12/2019 Generation System Adequacy Evaluation
12/85
Effect of unavailability
System 1X10 MW 2X10 MW 3X5 MW 4X10/3 MW
Unavailabili
ty %
Expected Load loss, MW
2 0.2 0.004 0.00596 0.007893874 0.4 0.016 0.02368 0.03112407
6 0.6 0.036 0.05292 0.06909417
-
8/12/2019 Generation System Adequacy Evaluation
13/85
Ex. A system consists of three 20 MW units
with a FOR of 4%. Obtain the capacity outage
probability table. (COPT). If a 4th unit of 40MW with an FOR of 4%, is added to the
system, obtain the COPT on a 100 MW
installed capacity.
-
8/12/2019 Generation System Adequacy Evaluation
14/85
Table A
Table B
Sl. No CapacityAvailable
Capacity out Probability
1 60 0 0.884736
2 40 20 0.110592
3 20 40 0.004608
4 0 60 0.000064
Sl No Capacity
available
Capacity out Probability
1 40 0 0.96
2 0 40 0.04
-
8/12/2019 Generation System Adequacy Evaluation
15/85
Table C
State Capacityavailable
Capacityout
Howobtained
Probability
a 100 0 1(a),1(b) 0.8493465
b 60 40 1(A), 2(B) 0.0353894
c 80 20 2(A), 1(B) 0.1061683
d 40 60 2(A), 2(B) 0.0044236
e 60 40 3(A), 1(B) 0.0044236
f 20 80 3(A),2(B) 0.0001843
g 40 60 4(A),1(B) 0.0000614
h 0 100 4(A), 2(B) 0.0000025
-
8/12/2019 Generation System Adequacy Evaluation
16/85
Table D
State Capacityavailabl
e
Capoacity out
Howobtain
ed
Probability(state)
Cumulative
probability
i 100 0 a 0.8493465 1.00
ii 80 20 c 0.10616863 0.1506534
iii 60 40 b+e 0.039813 0.0444851
iv 40 60 d+g 0.004485 0.004672
v 20 80 f 0.0001843 0.0001868
vi 0 100 h 0.0000025 0.0000025
-
8/12/2019 Generation System Adequacy Evaluation
17/85
Ex. A system consists of two 3 MW units with
a FOR of 2%. Obtain the capacity outageprobability table. (COPT). If a 3rdunit of 5 MW
with an FOR of 2%, is added to the system,
obtain the COPT.
Also obtain the COPT in the increments of 5
MW
-
8/12/2019 Generation System Adequacy Evaluation
18/85
Table 1. COPT for two units
Table 2. COPT with 5 MW unit in service
Capacity Out Probability
0 0.9604
3 0.0392
6 0.0004
Capacity Out Probability
0+0 = 0 MW (0.9604) X (0.98) = 0.941192
3 + 0 = 3 MW (0.0392) X (0.98) = 0.038416
6 + 0 = 6 MW (0.0004) X (0.98) = 0.000392
= 0.980000
-
8/12/2019 Generation System Adequacy Evaluation
19/85
Table 3. COPT with 5 MW out of service
Table 4. COPT with all the units
Capacity Out Probability
0+5 = 5MW (0.9604) X (0.02) = 0.019208
3 + 5 = 8 MW (0.0392) X (0.02) = 0.000784
6 + 5 = 11 MW (0.0004) X (0.02) = 0.000008
= 0.020000
Capacity Out Probability Cumulative Probability
0 0.941192 1.000000
3 0.038416 0.058808
5 0.019208 0.020392
6 0.000392 0.001184
8 0.000784 0.000792
11 0.000008 0.000008
-
8/12/2019 Generation System Adequacy Evaluation
20/85
Table 5. Rounded table
Capacity Out Probability0 0.9565584
5 0.0428848
10 0.0005552
15 0.0000016
-
8/12/2019 Generation System Adequacy Evaluation
21/85
Comparison of percentage reserve margin and
largest unit reserve criteria
-
8/12/2019 Generation System Adequacy Evaluation
22/85
system 1, 24 x 10 MW units each having a FOR of 0.01
system 2. 12 x 20 MW units each having a FOR of 0.01
system 3, 12 x 20 MW units each having a FOR of 0.03
system 4,22 x 10 MW units each having a FOR of 0.01
-
8/12/2019 Generation System Adequacy Evaluation
23/85
-
8/12/2019 Generation System Adequacy Evaluation
24/85
-
8/12/2019 Generation System Adequacy Evaluation
25/85
-
8/12/2019 Generation System Adequacy Evaluation
26/85
Loss of Load Indices
The generation system model is convolvedwith an appropriate load model to produce a
system risk index. The risk indices depends
upon the nature of load model.
-
8/12/2019 Generation System Adequacy Evaluation
27/85
Sample types of load models
Daily peak load variation curve.
Each day is represented by its daily peak load.
Individual peak loads arranged in descending manner
forming a cumulative modeldaily peak load variation
curve.
Load duration curve.
Individual hourly loads are used.
Area under the curve represents the energy required in
the given period.
-
8/12/2019 Generation System Adequacy Evaluation
28/85
Loss of Load Expectation (LOLE)
The expected number of days in the specified
period in which the daily peak load will exceedthe available capacity.
Capacity Outageloss of generation which may or may notresult in a loss of load. This depends on the generatingcapacity reserve margin.
Loss of loadoccur only when the capability of thegenerating capacity remaining in service is exceeded by thesystem load.
The applicable system capacity outage probability
table is combined with the system loadcharacteristics to give an expected risk of loss ofload.
-
8/12/2019 Generation System Adequacy Evaluation
29/85
Where
Ci= available capacity on day I LI = forecast peak load on day I
Pi(CiLi) = probability of loss of load on day i.( obtained from the capacity outage cumulative probability table)
-
8/12/2019 Generation System Adequacy Evaluation
30/85
Ex. A system consists of two units of 25 MW each and one unit of 50
MW with a FOR 0.02.Obtain LOLE with the load data given in table 1below.
-
8/12/2019 Generation System Adequacy Evaluation
31/85
Capacity Out Cumulative Probability
0 1.00000025 0.058808
50 0.020392
75 0.000792
100 0.000008
Table 2
-
8/12/2019 Generation System Adequacy Evaluation
32/85
LOLE from daily peak load variation curve.
Qk- magnitude of kth outage in the system COPT
tknumber of time units in the study interval that an outage of magnitude Qkwould result in a loss of load.
The load model is a represented by a continuous curve for 365 days.
-
8/12/2019 Generation System Adequacy Evaluation
33/85
Pkcumulative outage probability for capacitystate Qk
-
8/12/2019 Generation System Adequacy Evaluation
34/85
Ex. Consider a system containing five 40 MW units each with a FOR of 0.01. theCOPT for the system is given in the table 3. The system load model is representedby the daily peak load variation curve shown in the figure. Obtain LOLE if theforecast peak load is 160 MW
-
8/12/2019 Generation System Adequacy Evaluation
35/85
100 % means 365 days on the x - axis and 160 MW on the
y - axis.
-
8/12/2019 Generation System Adequacy Evaluation
36/85
LOLE using individual probability
The LOLE is 0.0412413 % of the time baseunit. With 365 days year, the LOLE will be
0.150410 days.
-
8/12/2019 Generation System Adequacy Evaluation
37/85
LOLE using Cumulative Probability
Capacity out Capacity In Cumulative
Probability
Time interval
Tk
LOLE
0 200 1.000000 0 ----------
40 160 0.049009 0 ----------
80 120 0.000980 41.7 0.0408660
120 80 0.000009 41.7 0.0003753
0.0412413 %
Table 4. The LOLE obtained is identical to the value obtained with
the value obtained with individual probability.
-
8/12/2019 Generation System Adequacy Evaluation
38/85
Examples A power system contains the following generating capacity.
3 X 40 MW hydro units FOR = 0.005
1 X 50 MW thermal units FOR = 0.02
1 X 60 MW thermal unit FOR = 0.02
The annual daily peak load variation curve is given by astraight line from the 100 % to the 40% point. Calculate the
loss of load expectation for the following peak load values.a. 150 MW
b. 160 MW
c. 170 MW
d. 180 MWe. 190 MW
f. 200 MW.
S i i i S di
-
8/12/2019 Generation System Adequacy Evaluation
39/85
Table 5. Variation in risk as a function of peak load
Sensitivity Studies
-
8/12/2019 Generation System Adequacy Evaluation
40/85
Fig 1. Variation in risk with system peak load, drawn on a semi log sheet
-
8/12/2019 Generation System Adequacy Evaluation
41/85
Table 6 . Effect of FOR and System Peak Load
-
8/12/2019 Generation System Adequacy Evaluation
42/85
The system used is very small hence the effect ofgenerating unit unavailability is quitepronounced. The effect for a big system with
large units having high FORs is shown in the fig. 2
The total installed capacity of the system is 10100MW
The largest units have 300 MW and 500 MWcapacity with FOR varying from 4 % to 13%.
The risk profile is almost a straight line.
This is because, a large system with a wide range
of unit sizes has a more continuous COPTresulting in a smoother risk profile.
-
8/12/2019 Generation System Adequacy Evaluation
43/85
Fig 2. LOLE as a function of FOR
-
8/12/2019 Generation System Adequacy Evaluation
44/85
The system peak load carrying capability (PLCC)
The PLCC at a risk level of 0.1 day/year is 9006 MW for FOR of 0.04. Table
7 shows the change in PLCC for FOR values from 0.04 to 0.13. the decrease
in PLCC is 815 MW.
FOR % PLCC (MW) Difference (MW) Cumulative difference MW
4 9006 ------ ------
5 8895 111 111
6 8793 102 213
7 8693 100 313
8 8602 91 404
9 8513 89 493
10 8427 86 57911 8345 82 661
12 8267 78 739
13 8191 76 815
Table 7 . Changes in PLCC
-
8/12/2019 Generation System Adequacy Evaluation
45/85
If the forecast peak load is 9000 MW and the
FOR of the large units are 0.13, an additional
capacity of approximately 1000 MW has to beinstalled.
The investment has to be therefore increased
to meet the new demand. This clearly shows the consequences of the
unit unavailability in terms of additional
capacity.
-
8/12/2019 Generation System Adequacy Evaluation
46/85
-
8/12/2019 Generation System Adequacy Evaluation
47/85
Capacity Expansion Analysis
Time required for designing, construct and commissioning a
large power station takes normally 510 years.
Consider a plant with five 40 MW units whose COPT is shown
in table 8
Table 8
-
8/12/2019 Generation System Adequacy Evaluation
48/85
It is decided to add additional 50 MW units
with FOR 0.01, to meet a projected load
growth of 10 %.
The question- In what years must the units be
committed in order to meet the accepted
system risk level? Table 9 shows the change in risk level for with
the sequential addition of 50 MW units.
Table 9 The change in risk level with sequential addition of 50 MW units
-
8/12/2019 Generation System Adequacy Evaluation
49/85
Table 9. The change in risk level with sequential addition of 50 MW units
System Peak
Load (MW)
LOLE (days/year)
200 MW 250 MW 300 MW 350 MW
100 0.001210 ---- ---- ----
120 0.002005 ---- ---- ----
140 0.08686 0.001301 ---- ----
160 0.1506 0.002625 ---- ----
180 3.447 0.06858 ---- ----
200 6.083 0.1505 0.002996 ----
220 ---- 2.058 0.03615 ----
240 ---- 4.853 0.1361 0.002980
250 ---- 6.083 0.1800 0.004034
260 ---- ---- 0.6610 0.01175280 ---- ---- 3.566 0.1075
300 ---- ---- 6.082 0.2904
320 ---- ---- ---- 2.248
340 ---- ---- ---- 4.880
350 ---- ---- ---- 6.083
-
8/12/2019 Generation System Adequacy Evaluation
50/85
Year number Forecast peak load (MW)
1 160
2 176
3 193.6
4 213.0
5 234.3
6 257.5
7 283.1
8 311.4
Table 10. Load growth at 10 %
Fig 3. Variation in risk with unit additions.
-
8/12/2019 Generation System Adequacy Evaluation
51/85
If it i t d th t i t ll d it f
-
8/12/2019 Generation System Adequacy Evaluation
52/85
If it is accepted that an installed capacity of
200 MW is adequate for a system peak load of
160 MW, the risk criterion is 0.15 days/year.
Choosing this risk criterion, the timing of unit
additions can be obtained.
The actual choice of the risk value is amanagement decision.
In the present case, 50 MW additions can be
made in the years 2,4 and 6 The expansion is shown in the table 11.
T bl 11 G ti i lt
-
8/12/2019 Generation System Adequacy Evaluation
53/85
Table 11. Generation expansion results
Year Unit added (MW) System capacity
(MW)
Peak Load
(MW)
LOLE
(days/year)1 ----- 200 160 0.15
2 ----- 200 176 2.9
50 250 176 0.058
3 ----- 250 193.6 0.11
4 ----- 250 213 0.73
50 300 213 0.011
5 ----- 300 234.3 0.11
6 ----- 300 257.4 0.55
50 350 257.4 0.009
7 ----- 350 283.1 0.125
8 ----- 350 311.4 0.96
b i ff
-
8/12/2019 Generation System Adequacy Evaluation
54/85
Perturbation Effects
Large units have relatively low cost per KW installed.
Large units have better heat rates than the smaller units.
However, the impact on the system reliability by adding a
large unit should be considered when carrying out economic
evaluation of alternate sizes.
This effect is considered in Increased Peak Load CarryingCapacity due to unit additions. (IPLCC)
The IPLCC values with each 50 MW unit at a system risk level
of 0.1 is shown in table 12.
Table 12 IPLCC for five unit system
-
8/12/2019 Generation System Adequacy Evaluation
55/85
Table 12. IPLCC for five unit system.
System Capacity
(MW)
Available peak load
(MW)
Increase in PLCC (MW)
Individual Cumulative
200 144 0 0
250 186 42 42300 232 46 88
350 279 47 135
-
8/12/2019 Generation System Adequacy Evaluation
56/85
Consider a large system with 2010 MW
units. The total installed capacity = 200 MW
With the criterion of loss of largest unit , thissystem can carry a 190 peak load.
The initial load carrying capability is different
than the 5 unit system The addition of each 50 MW unit has a
different IPLCC
Initial PLCC penalty
-
8/12/2019 Generation System Adequacy Evaluation
57/85
Table 13. IPLCC for 20 unit system.
System Capacity
(MW)
Available peak load
(MW)
Increase in PLCC (MW)
Individual Cumulative
200 184 0 0250 202 18 18
300 250 48 66
350 298 48 114
S h d l d O t
-
8/12/2019 Generation System Adequacy Evaluation
58/85
Scheduled Outages
If the units are removed from the service for periodic
inspection/maintenance, the capacity availableduring this period is not the same as that during the
other period.
Hence a single COPT is not applicable.
The year is divided into several periods and the LOLE
is calculated for each period.
The annual risk index is obtained as
Modified capacity model is obtained by creating new
COPT for each capacity condition.
-
8/12/2019 Generation System Adequacy Evaluation
59/85
-
8/12/2019 Generation System Adequacy Evaluation
60/85
If a new unit is added to the system, the same can be
added to the capacity model also.
If the actual in-service date of the new unit isuncertain, it can be represented by a probability
distribution function and LOLE is obtained as
-
8/12/2019 Generation System Adequacy Evaluation
61/85
Alternate method
A th lt t th d
-
8/12/2019 Generation System Adequacy Evaluation
62/85
Another alternate method
Most realistic approach is to obtain the COPT by considering the
-
8/12/2019 Generation System Adequacy Evaluation
63/85
Most realistic approach is to obtain the COPT by considering theunits actually available in a given period.
Other methods give a higher risk value which increases withincreased maintenance capacity.
Maintenance Scheduling.
While scheduling the maintenance, the important point to be
considered is that, the reliability of a system becomes poorer if aunit with low FOR is removed from service.
Approaches for maintenance scheduling:
1. To reduce the total installed capacity by the expected capacity lossrather than by the actual unit capacity and then schedulemaintenance on a constant reserve base.
2. Determine the decrease of PLCC at the appropriate risk level foreach individual unit on maintenance and then using these values,schedule is prepared on a constant reserve basis.
Evaluation methods on period basis
-
8/12/2019 Generation System Adequacy Evaluation
64/85
Evaluation methods on period basis. Annual risk index can be obtained by using any of the three
methods
1. Monthly (or period) basis considering maintenance2. Annual basis neglecting maintenance
3. Worst period basis.
Monthly approach : Constant capacity for the period is assumed.
Appropriate COPT is combined with the load model. The annual risk is the sum of the 12 monthly risks.
If the capacity on maintenance is not constant during the month,the month is divided into several intervals during which thecapacity is constant.
The COPT, modified by removing the units on maintenance foreach separate interval, is combined with monthly peak and loadcharacteristic using the interval as its time base.
A l h l ti i t
-
8/12/2019 Generation System Adequacy Evaluation
65/85
Annual approach neglecting maintenance:
The annual forecast peak load and the systemload characteristics are combined with thesystem COPT.
Basic assumption: a constant capacity exists forthe entire period.
Justification: The year can be divided into a peak load season and a
light load season.
The planned maintenance can be scheduled entirely
during the light load season. The contribution of light load season to the annual
risk is quite low and hence a constant capacity can beassumed.
Worst Period Basis
-
8/12/2019 Generation System Adequacy Evaluation
66/85
Worst Period Basis:
The load level in a particular season or month
may be so high that the same may dominatethe annual figure.
The risk value for that month is calculated.
The annual risk level is obtained bymultiplying this risk value by 12.
Usually the worst period is December.
12 December Basis.
Load Forecast Uncertainty
-
8/12/2019 Generation System Adequacy Evaluation
67/85
Load Forecast Uncertainty
Assumption that the actual peak load will
differ from the forecast peak load with zeroprobability, is extremely unlikely to happen in
the actual practice, as the forecast is actually
predicted on past experience.
Method 1: This uncertainty can be described
by a probability distribution, whose
parameters can be determined from past
experience, future load modeling.
The load forecast probability is divided into
-
8/12/2019 Generation System Adequacy Evaluation
68/85
The load forecast probability is divided into
several class intervals.
LOLE is computed for each load by multiplying
the class interval and the probability of the load
existing.
The uncertainty is well described by a normal
distribution.
The distribution mean is the forecast peak load.
The distribution is divided into a discrete number
of class intervals.
The load representing the class interval mid point
is taken as the probability for that class interval.
E A t i t f t l 5 MW it
-
8/12/2019 Generation System Adequacy Evaluation
69/85
Ex. A system consists of twelve 5 MW units,
each with a FOR of 0.01. the forecast peak
load is 50 MW. The COPT can be obtained
The uncertainty is normally distributed using a
seven step approximation.
-
8/12/2019 Generation System Adequacy Evaluation
70/85
Period = 1 month = 30 days = 720 hours.
Standard deviation is 2% of the forecast peak
load = 1 MW. Monthly load-duration curve is represented by a
straight line .
The LOLE is obtained as
Probability of load X LOLE (hours/month for the load)
Method 2
-
8/12/2019 Generation System Adequacy Evaluation
71/85
Method 2
Conditional Load Duration Curves
-
8/12/2019 Generation System Adequacy Evaluation
72/85
Conditional Load Duration Curves
Modified Load Duration Curve
-
8/12/2019 Generation System Adequacy Evaluation
73/85
-
8/12/2019 Generation System Adequacy Evaluation
74/85
LOLE
-
8/12/2019 Generation System Adequacy Evaluation
75/85
In general
LOLE is affected by
Generation unit unavailability (FOR)
Load Forecast uncertainty.
Hence the calculated value is only approximate.
The actual distribution of LOLE can be obtained by Monte
Carlo simulation
Loss of Energy Indices
-
8/12/2019 Generation System Adequacy Evaluation
76/85
Loss of Energy Indices
The area under the load duration curve
represents the energy utilized during thespecified period and can be used to
determine the expected energy not supplied
due to insufficient installed capacity.
-
8/12/2019 Generation System Adequacy Evaluation
77/85
-
8/12/2019 Generation System Adequacy Evaluation
78/85
The normalized LOEE is obtained as
Where E is the total energy under load duration curve.
The energy index of Reliability EIR is
EIR = 1LOEE pu
-
8/12/2019 Generation System Adequacy Evaluation
79/85
Consider the LDC for a period of 100 hours and the generating unit capacity
shown in the table
-
8/12/2019 Generation System Adequacy Evaluation
80/85
The total energy in the period is 4575 MWh.If there were no units, the Expected Energy Not Supplied
(EENS) is 4575 MWH. If the system contained only unit 1, the
EENS is obtained as
-
8/12/2019 Generation System Adequacy Evaluation
81/85
EENS with units 1 & 2
-
8/12/2019 Generation System Adequacy Evaluation
82/85
EENS with units 1,2 & 3
-
8/12/2019 Generation System Adequacy Evaluation
83/85
The expected energy produced by unit 3 is 401.764.08 = 337.6 MWh
Summary of EENS
-
8/12/2019 Generation System Adequacy Evaluation
84/85
Summary of EENS
The expected energy not supplied is therefore 64.08
MWh. The energy index of reliability EIR is obtained asEIR = 1(64.08/4575) = 0.985993
A generating contains three 25 MW
-
8/12/2019 Generation System Adequacy Evaluation
85/85
A generating contains three 25 MW
generating units each with a 4 % FOR and one
30 MW unit with 5 % FOR. If the peak load fora 100 day period is 75 MW, what is the LOLE
and EIR for this period? Assume that
appropriate load characteristics is a straight
line from the 100 % point to 60 % point.