generation system adequacy evaluation

Upload: darshanraghu

Post on 03-Jun-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 Generation System Adequacy Evaluation

    1/85

    Objective : to determine the required amount of system

    generating capacity to ensure an adequate supply.

    1. Static Capacity Requirement :

    Long-term evaluation of the overall system requirement.

    Practice : Percentage Reserve method. Issue : comparison

    Probabilistic approaches.

    2. Operating Capacity Requirement

    Short term evaluation of the actual capacity required tomeet a given load.

    Fundamental difference: Time period

    Generation System Adequacy Evaluation

  • 8/12/2019 Generation System Adequacy Evaluation

    2/85

    Generation System Adequacy Evaluation

    The Generation and Load models arecombined to form Risk model

  • 8/12/2019 Generation System Adequacy Evaluation

    3/85

    Binomial Distribution

    P(H) + P(T) = [P(H) + P(T)]1

    P(H).P(H) + 2P(H).P(T) + P(T).P(T)= P2(H) + 2P.(H)P(T) + P2(T) = [P(H) + P(T)]2

    P3

    (H) + 3P2

    (H)P(T) + 3P(H)P2

    (T) + P3

    (T)= [P(H) + P(T)]3

    Ex. Consider a system with 4 components. Thecomponents are identical with a success

    probability of 0.9 and a failure probability of 0.1Obtain the various states in which the components

    can exist.

  • 8/12/2019 Generation System Adequacy Evaluation

    4/85

    Since there are 4 components and each one of

    them is either available OR unavailable, the

    total number of states is

    All components working

    1 component failed

    2 components failed

    3 components failed

    All components failed

  • 8/12/2019 Generation System Adequacy Evaluation

    5/85

    (S+F)4= S4+4S3F+6S2F2+4SF3+F4

    System state Individual Probability

    All components working 0.94 = 0.6561

    1 component failed 4X0.93X0.1 = 0.2961

    2 components failed 6X0.92X0.12 = 0.0486

    3 components failed 4X0.9X0.13 =0.0036

    All components failed 0.14 = 0.00011.0000

  • 8/12/2019 Generation System Adequacy Evaluation

    6/85

    If at least three components are required for

    success then

    Success Probability OR Reliability R

    R = 0.6561 + 0.2916 = 0.9477

    Failure probability of the system Q Q = 0.0486 + 0.0036 + 0.0001 = 0.0523 = 1R

  • 8/12/2019 Generation System Adequacy Evaluation

    7/85

  • 8/12/2019 Generation System Adequacy Evaluation

    8/85

    Case Units out Capacity Individual

    Probability

    Out available

    A 1 X 10 MW

    0 0 10 0.98

    1 0.02

    B 2 X 10 MW

    0 0 20 0.9604

    1 10 10 0.0392

    2 20 0 0.0004

    C 3 X 5 MW

    0 0 15 0.941192

    1 5 10 0.057624

    2 10 5 0.001176

    3 15 0 0.000008

    D 4 X 10/3 MW

    0 0 40/3 0.92236816

    1 10/3 10 0.07529536

    2 20/3 20/3 0.00230496

    3 10 10/3 0.00003136

    4 40/3 0 0.00000016

  • 8/12/2019 Generation System Adequacy Evaluation

    9/85

    Expected Load Loss

  • 8/12/2019 Generation System Adequacy Evaluation

    10/85

    Case Capacity Out

    (MW)

    Probability Load loss

    (MW)

    Expected Load Loss

    (MW)

    A 1 X 10 MW

    0 0.98 0 ---

    10 0.02 10 0.2 0.2 MW

    B 2 X 10 MW

    0 0.9604 0 ---

    10 0.0392 0 ---

    20 0.0004 10 0.004 0.004 MW

    C 3 X 5 MW

    0 0.941192 0 ----

    5 0.057524 0 -----

    10 0.001176 5 0.00588

    15 0.000008 10 0.00008 0.00596

    MW

    D 4 X 10/3 MW

    0 0.92236816 0 ------

    10/3 0.07529536 0 ------

    20/3 0.00230496 10/3 0.00768320

    10 0.00003136 20/3 0.00020907

    40/3 0.00000016 10 0.00000160 0.0078938

    7 MW

  • 8/12/2019 Generation System Adequacy Evaluation

    11/85

    Let the cost per 10 MW unit be 1 unit. The

    investment cost for the alternatives is

    Investment cost of plant

    Expected Load curtailment

    System Expected Load Loss (MW) Investment cost p.u.

    1 X 10 MW 0.2 1.0

    2 X 10 MW 0.004 2.0

    3 X 5 MW 0.00596 1.5

    4 X 10/3 MW 0.00789387 1.33

    System Probability of loss

    of load

    Expected load

    curtailment hr/yr

    1 X 10 MW 0.02 175.2

    2 X 10 MW 0.0004 3.504

    3 X 5 MW 0.001184 10.37814

    4 X 10/3 MW 0.00233648 20.46756

  • 8/12/2019 Generation System Adequacy Evaluation

    12/85

    Effect of unavailability

    System 1X10 MW 2X10 MW 3X5 MW 4X10/3 MW

    Unavailabili

    ty %

    Expected Load loss, MW

    2 0.2 0.004 0.00596 0.007893874 0.4 0.016 0.02368 0.03112407

    6 0.6 0.036 0.05292 0.06909417

  • 8/12/2019 Generation System Adequacy Evaluation

    13/85

    Ex. A system consists of three 20 MW units

    with a FOR of 4%. Obtain the capacity outage

    probability table. (COPT). If a 4th unit of 40MW with an FOR of 4%, is added to the

    system, obtain the COPT on a 100 MW

    installed capacity.

  • 8/12/2019 Generation System Adequacy Evaluation

    14/85

    Table A

    Table B

    Sl. No CapacityAvailable

    Capacity out Probability

    1 60 0 0.884736

    2 40 20 0.110592

    3 20 40 0.004608

    4 0 60 0.000064

    Sl No Capacity

    available

    Capacity out Probability

    1 40 0 0.96

    2 0 40 0.04

  • 8/12/2019 Generation System Adequacy Evaluation

    15/85

    Table C

    State Capacityavailable

    Capacityout

    Howobtained

    Probability

    a 100 0 1(a),1(b) 0.8493465

    b 60 40 1(A), 2(B) 0.0353894

    c 80 20 2(A), 1(B) 0.1061683

    d 40 60 2(A), 2(B) 0.0044236

    e 60 40 3(A), 1(B) 0.0044236

    f 20 80 3(A),2(B) 0.0001843

    g 40 60 4(A),1(B) 0.0000614

    h 0 100 4(A), 2(B) 0.0000025

  • 8/12/2019 Generation System Adequacy Evaluation

    16/85

    Table D

    State Capacityavailabl

    e

    Capoacity out

    Howobtain

    ed

    Probability(state)

    Cumulative

    probability

    i 100 0 a 0.8493465 1.00

    ii 80 20 c 0.10616863 0.1506534

    iii 60 40 b+e 0.039813 0.0444851

    iv 40 60 d+g 0.004485 0.004672

    v 20 80 f 0.0001843 0.0001868

    vi 0 100 h 0.0000025 0.0000025

  • 8/12/2019 Generation System Adequacy Evaluation

    17/85

    Ex. A system consists of two 3 MW units with

    a FOR of 2%. Obtain the capacity outageprobability table. (COPT). If a 3rdunit of 5 MW

    with an FOR of 2%, is added to the system,

    obtain the COPT.

    Also obtain the COPT in the increments of 5

    MW

  • 8/12/2019 Generation System Adequacy Evaluation

    18/85

    Table 1. COPT for two units

    Table 2. COPT with 5 MW unit in service

    Capacity Out Probability

    0 0.9604

    3 0.0392

    6 0.0004

    Capacity Out Probability

    0+0 = 0 MW (0.9604) X (0.98) = 0.941192

    3 + 0 = 3 MW (0.0392) X (0.98) = 0.038416

    6 + 0 = 6 MW (0.0004) X (0.98) = 0.000392

    = 0.980000

  • 8/12/2019 Generation System Adequacy Evaluation

    19/85

    Table 3. COPT with 5 MW out of service

    Table 4. COPT with all the units

    Capacity Out Probability

    0+5 = 5MW (0.9604) X (0.02) = 0.019208

    3 + 5 = 8 MW (0.0392) X (0.02) = 0.000784

    6 + 5 = 11 MW (0.0004) X (0.02) = 0.000008

    = 0.020000

    Capacity Out Probability Cumulative Probability

    0 0.941192 1.000000

    3 0.038416 0.058808

    5 0.019208 0.020392

    6 0.000392 0.001184

    8 0.000784 0.000792

    11 0.000008 0.000008

  • 8/12/2019 Generation System Adequacy Evaluation

    20/85

    Table 5. Rounded table

    Capacity Out Probability0 0.9565584

    5 0.0428848

    10 0.0005552

    15 0.0000016

  • 8/12/2019 Generation System Adequacy Evaluation

    21/85

    Comparison of percentage reserve margin and

    largest unit reserve criteria

  • 8/12/2019 Generation System Adequacy Evaluation

    22/85

    system 1, 24 x 10 MW units each having a FOR of 0.01

    system 2. 12 x 20 MW units each having a FOR of 0.01

    system 3, 12 x 20 MW units each having a FOR of 0.03

    system 4,22 x 10 MW units each having a FOR of 0.01

  • 8/12/2019 Generation System Adequacy Evaluation

    23/85

  • 8/12/2019 Generation System Adequacy Evaluation

    24/85

  • 8/12/2019 Generation System Adequacy Evaluation

    25/85

  • 8/12/2019 Generation System Adequacy Evaluation

    26/85

    Loss of Load Indices

    The generation system model is convolvedwith an appropriate load model to produce a

    system risk index. The risk indices depends

    upon the nature of load model.

  • 8/12/2019 Generation System Adequacy Evaluation

    27/85

    Sample types of load models

    Daily peak load variation curve.

    Each day is represented by its daily peak load.

    Individual peak loads arranged in descending manner

    forming a cumulative modeldaily peak load variation

    curve.

    Load duration curve.

    Individual hourly loads are used.

    Area under the curve represents the energy required in

    the given period.

  • 8/12/2019 Generation System Adequacy Evaluation

    28/85

    Loss of Load Expectation (LOLE)

    The expected number of days in the specified

    period in which the daily peak load will exceedthe available capacity.

    Capacity Outageloss of generation which may or may notresult in a loss of load. This depends on the generatingcapacity reserve margin.

    Loss of loadoccur only when the capability of thegenerating capacity remaining in service is exceeded by thesystem load.

    The applicable system capacity outage probability

    table is combined with the system loadcharacteristics to give an expected risk of loss ofload.

  • 8/12/2019 Generation System Adequacy Evaluation

    29/85

    Where

    Ci= available capacity on day I LI = forecast peak load on day I

    Pi(CiLi) = probability of loss of load on day i.( obtained from the capacity outage cumulative probability table)

  • 8/12/2019 Generation System Adequacy Evaluation

    30/85

    Ex. A system consists of two units of 25 MW each and one unit of 50

    MW with a FOR 0.02.Obtain LOLE with the load data given in table 1below.

  • 8/12/2019 Generation System Adequacy Evaluation

    31/85

    Capacity Out Cumulative Probability

    0 1.00000025 0.058808

    50 0.020392

    75 0.000792

    100 0.000008

    Table 2

  • 8/12/2019 Generation System Adequacy Evaluation

    32/85

    LOLE from daily peak load variation curve.

    Qk- magnitude of kth outage in the system COPT

    tknumber of time units in the study interval that an outage of magnitude Qkwould result in a loss of load.

    The load model is a represented by a continuous curve for 365 days.

  • 8/12/2019 Generation System Adequacy Evaluation

    33/85

    Pkcumulative outage probability for capacitystate Qk

  • 8/12/2019 Generation System Adequacy Evaluation

    34/85

    Ex. Consider a system containing five 40 MW units each with a FOR of 0.01. theCOPT for the system is given in the table 3. The system load model is representedby the daily peak load variation curve shown in the figure. Obtain LOLE if theforecast peak load is 160 MW

  • 8/12/2019 Generation System Adequacy Evaluation

    35/85

    100 % means 365 days on the x - axis and 160 MW on the

    y - axis.

  • 8/12/2019 Generation System Adequacy Evaluation

    36/85

    LOLE using individual probability

    The LOLE is 0.0412413 % of the time baseunit. With 365 days year, the LOLE will be

    0.150410 days.

  • 8/12/2019 Generation System Adequacy Evaluation

    37/85

    LOLE using Cumulative Probability

    Capacity out Capacity In Cumulative

    Probability

    Time interval

    Tk

    LOLE

    0 200 1.000000 0 ----------

    40 160 0.049009 0 ----------

    80 120 0.000980 41.7 0.0408660

    120 80 0.000009 41.7 0.0003753

    0.0412413 %

    Table 4. The LOLE obtained is identical to the value obtained with

    the value obtained with individual probability.

  • 8/12/2019 Generation System Adequacy Evaluation

    38/85

    Examples A power system contains the following generating capacity.

    3 X 40 MW hydro units FOR = 0.005

    1 X 50 MW thermal units FOR = 0.02

    1 X 60 MW thermal unit FOR = 0.02

    The annual daily peak load variation curve is given by astraight line from the 100 % to the 40% point. Calculate the

    loss of load expectation for the following peak load values.a. 150 MW

    b. 160 MW

    c. 170 MW

    d. 180 MWe. 190 MW

    f. 200 MW.

    S i i i S di

  • 8/12/2019 Generation System Adequacy Evaluation

    39/85

    Table 5. Variation in risk as a function of peak load

    Sensitivity Studies

  • 8/12/2019 Generation System Adequacy Evaluation

    40/85

    Fig 1. Variation in risk with system peak load, drawn on a semi log sheet

  • 8/12/2019 Generation System Adequacy Evaluation

    41/85

    Table 6 . Effect of FOR and System Peak Load

  • 8/12/2019 Generation System Adequacy Evaluation

    42/85

    The system used is very small hence the effect ofgenerating unit unavailability is quitepronounced. The effect for a big system with

    large units having high FORs is shown in the fig. 2

    The total installed capacity of the system is 10100MW

    The largest units have 300 MW and 500 MWcapacity with FOR varying from 4 % to 13%.

    The risk profile is almost a straight line.

    This is because, a large system with a wide range

    of unit sizes has a more continuous COPTresulting in a smoother risk profile.

  • 8/12/2019 Generation System Adequacy Evaluation

    43/85

    Fig 2. LOLE as a function of FOR

  • 8/12/2019 Generation System Adequacy Evaluation

    44/85

    The system peak load carrying capability (PLCC)

    The PLCC at a risk level of 0.1 day/year is 9006 MW for FOR of 0.04. Table

    7 shows the change in PLCC for FOR values from 0.04 to 0.13. the decrease

    in PLCC is 815 MW.

    FOR % PLCC (MW) Difference (MW) Cumulative difference MW

    4 9006 ------ ------

    5 8895 111 111

    6 8793 102 213

    7 8693 100 313

    8 8602 91 404

    9 8513 89 493

    10 8427 86 57911 8345 82 661

    12 8267 78 739

    13 8191 76 815

    Table 7 . Changes in PLCC

  • 8/12/2019 Generation System Adequacy Evaluation

    45/85

    If the forecast peak load is 9000 MW and the

    FOR of the large units are 0.13, an additional

    capacity of approximately 1000 MW has to beinstalled.

    The investment has to be therefore increased

    to meet the new demand. This clearly shows the consequences of the

    unit unavailability in terms of additional

    capacity.

  • 8/12/2019 Generation System Adequacy Evaluation

    46/85

  • 8/12/2019 Generation System Adequacy Evaluation

    47/85

    Capacity Expansion Analysis

    Time required for designing, construct and commissioning a

    large power station takes normally 510 years.

    Consider a plant with five 40 MW units whose COPT is shown

    in table 8

    Table 8

  • 8/12/2019 Generation System Adequacy Evaluation

    48/85

    It is decided to add additional 50 MW units

    with FOR 0.01, to meet a projected load

    growth of 10 %.

    The question- In what years must the units be

    committed in order to meet the accepted

    system risk level? Table 9 shows the change in risk level for with

    the sequential addition of 50 MW units.

    Table 9 The change in risk level with sequential addition of 50 MW units

  • 8/12/2019 Generation System Adequacy Evaluation

    49/85

    Table 9. The change in risk level with sequential addition of 50 MW units

    System Peak

    Load (MW)

    LOLE (days/year)

    200 MW 250 MW 300 MW 350 MW

    100 0.001210 ---- ---- ----

    120 0.002005 ---- ---- ----

    140 0.08686 0.001301 ---- ----

    160 0.1506 0.002625 ---- ----

    180 3.447 0.06858 ---- ----

    200 6.083 0.1505 0.002996 ----

    220 ---- 2.058 0.03615 ----

    240 ---- 4.853 0.1361 0.002980

    250 ---- 6.083 0.1800 0.004034

    260 ---- ---- 0.6610 0.01175280 ---- ---- 3.566 0.1075

    300 ---- ---- 6.082 0.2904

    320 ---- ---- ---- 2.248

    340 ---- ---- ---- 4.880

    350 ---- ---- ---- 6.083

  • 8/12/2019 Generation System Adequacy Evaluation

    50/85

    Year number Forecast peak load (MW)

    1 160

    2 176

    3 193.6

    4 213.0

    5 234.3

    6 257.5

    7 283.1

    8 311.4

    Table 10. Load growth at 10 %

    Fig 3. Variation in risk with unit additions.

  • 8/12/2019 Generation System Adequacy Evaluation

    51/85

    If it i t d th t i t ll d it f

  • 8/12/2019 Generation System Adequacy Evaluation

    52/85

    If it is accepted that an installed capacity of

    200 MW is adequate for a system peak load of

    160 MW, the risk criterion is 0.15 days/year.

    Choosing this risk criterion, the timing of unit

    additions can be obtained.

    The actual choice of the risk value is amanagement decision.

    In the present case, 50 MW additions can be

    made in the years 2,4 and 6 The expansion is shown in the table 11.

    T bl 11 G ti i lt

  • 8/12/2019 Generation System Adequacy Evaluation

    53/85

    Table 11. Generation expansion results

    Year Unit added (MW) System capacity

    (MW)

    Peak Load

    (MW)

    LOLE

    (days/year)1 ----- 200 160 0.15

    2 ----- 200 176 2.9

    50 250 176 0.058

    3 ----- 250 193.6 0.11

    4 ----- 250 213 0.73

    50 300 213 0.011

    5 ----- 300 234.3 0.11

    6 ----- 300 257.4 0.55

    50 350 257.4 0.009

    7 ----- 350 283.1 0.125

    8 ----- 350 311.4 0.96

    b i ff

  • 8/12/2019 Generation System Adequacy Evaluation

    54/85

    Perturbation Effects

    Large units have relatively low cost per KW installed.

    Large units have better heat rates than the smaller units.

    However, the impact on the system reliability by adding a

    large unit should be considered when carrying out economic

    evaluation of alternate sizes.

    This effect is considered in Increased Peak Load CarryingCapacity due to unit additions. (IPLCC)

    The IPLCC values with each 50 MW unit at a system risk level

    of 0.1 is shown in table 12.

    Table 12 IPLCC for five unit system

  • 8/12/2019 Generation System Adequacy Evaluation

    55/85

    Table 12. IPLCC for five unit system.

    System Capacity

    (MW)

    Available peak load

    (MW)

    Increase in PLCC (MW)

    Individual Cumulative

    200 144 0 0

    250 186 42 42300 232 46 88

    350 279 47 135

  • 8/12/2019 Generation System Adequacy Evaluation

    56/85

    Consider a large system with 2010 MW

    units. The total installed capacity = 200 MW

    With the criterion of loss of largest unit , thissystem can carry a 190 peak load.

    The initial load carrying capability is different

    than the 5 unit system The addition of each 50 MW unit has a

    different IPLCC

    Initial PLCC penalty

  • 8/12/2019 Generation System Adequacy Evaluation

    57/85

    Table 13. IPLCC for 20 unit system.

    System Capacity

    (MW)

    Available peak load

    (MW)

    Increase in PLCC (MW)

    Individual Cumulative

    200 184 0 0250 202 18 18

    300 250 48 66

    350 298 48 114

    S h d l d O t

  • 8/12/2019 Generation System Adequacy Evaluation

    58/85

    Scheduled Outages

    If the units are removed from the service for periodic

    inspection/maintenance, the capacity availableduring this period is not the same as that during the

    other period.

    Hence a single COPT is not applicable.

    The year is divided into several periods and the LOLE

    is calculated for each period.

    The annual risk index is obtained as

    Modified capacity model is obtained by creating new

    COPT for each capacity condition.

  • 8/12/2019 Generation System Adequacy Evaluation

    59/85

  • 8/12/2019 Generation System Adequacy Evaluation

    60/85

    If a new unit is added to the system, the same can be

    added to the capacity model also.

    If the actual in-service date of the new unit isuncertain, it can be represented by a probability

    distribution function and LOLE is obtained as

  • 8/12/2019 Generation System Adequacy Evaluation

    61/85

    Alternate method

    A th lt t th d

  • 8/12/2019 Generation System Adequacy Evaluation

    62/85

    Another alternate method

    Most realistic approach is to obtain the COPT by considering the

  • 8/12/2019 Generation System Adequacy Evaluation

    63/85

    Most realistic approach is to obtain the COPT by considering theunits actually available in a given period.

    Other methods give a higher risk value which increases withincreased maintenance capacity.

    Maintenance Scheduling.

    While scheduling the maintenance, the important point to be

    considered is that, the reliability of a system becomes poorer if aunit with low FOR is removed from service.

    Approaches for maintenance scheduling:

    1. To reduce the total installed capacity by the expected capacity lossrather than by the actual unit capacity and then schedulemaintenance on a constant reserve base.

    2. Determine the decrease of PLCC at the appropriate risk level foreach individual unit on maintenance and then using these values,schedule is prepared on a constant reserve basis.

    Evaluation methods on period basis

  • 8/12/2019 Generation System Adequacy Evaluation

    64/85

    Evaluation methods on period basis. Annual risk index can be obtained by using any of the three

    methods

    1. Monthly (or period) basis considering maintenance2. Annual basis neglecting maintenance

    3. Worst period basis.

    Monthly approach : Constant capacity for the period is assumed.

    Appropriate COPT is combined with the load model. The annual risk is the sum of the 12 monthly risks.

    If the capacity on maintenance is not constant during the month,the month is divided into several intervals during which thecapacity is constant.

    The COPT, modified by removing the units on maintenance foreach separate interval, is combined with monthly peak and loadcharacteristic using the interval as its time base.

    A l h l ti i t

  • 8/12/2019 Generation System Adequacy Evaluation

    65/85

    Annual approach neglecting maintenance:

    The annual forecast peak load and the systemload characteristics are combined with thesystem COPT.

    Basic assumption: a constant capacity exists forthe entire period.

    Justification: The year can be divided into a peak load season and a

    light load season.

    The planned maintenance can be scheduled entirely

    during the light load season. The contribution of light load season to the annual

    risk is quite low and hence a constant capacity can beassumed.

    Worst Period Basis

  • 8/12/2019 Generation System Adequacy Evaluation

    66/85

    Worst Period Basis:

    The load level in a particular season or month

    may be so high that the same may dominatethe annual figure.

    The risk value for that month is calculated.

    The annual risk level is obtained bymultiplying this risk value by 12.

    Usually the worst period is December.

    12 December Basis.

    Load Forecast Uncertainty

  • 8/12/2019 Generation System Adequacy Evaluation

    67/85

    Load Forecast Uncertainty

    Assumption that the actual peak load will

    differ from the forecast peak load with zeroprobability, is extremely unlikely to happen in

    the actual practice, as the forecast is actually

    predicted on past experience.

    Method 1: This uncertainty can be described

    by a probability distribution, whose

    parameters can be determined from past

    experience, future load modeling.

    The load forecast probability is divided into

  • 8/12/2019 Generation System Adequacy Evaluation

    68/85

    The load forecast probability is divided into

    several class intervals.

    LOLE is computed for each load by multiplying

    the class interval and the probability of the load

    existing.

    The uncertainty is well described by a normal

    distribution.

    The distribution mean is the forecast peak load.

    The distribution is divided into a discrete number

    of class intervals.

    The load representing the class interval mid point

    is taken as the probability for that class interval.

    E A t i t f t l 5 MW it

  • 8/12/2019 Generation System Adequacy Evaluation

    69/85

    Ex. A system consists of twelve 5 MW units,

    each with a FOR of 0.01. the forecast peak

    load is 50 MW. The COPT can be obtained

    The uncertainty is normally distributed using a

    seven step approximation.

  • 8/12/2019 Generation System Adequacy Evaluation

    70/85

    Period = 1 month = 30 days = 720 hours.

    Standard deviation is 2% of the forecast peak

    load = 1 MW. Monthly load-duration curve is represented by a

    straight line .

    The LOLE is obtained as

    Probability of load X LOLE (hours/month for the load)

    Method 2

  • 8/12/2019 Generation System Adequacy Evaluation

    71/85

    Method 2

    Conditional Load Duration Curves

  • 8/12/2019 Generation System Adequacy Evaluation

    72/85

    Conditional Load Duration Curves

    Modified Load Duration Curve

  • 8/12/2019 Generation System Adequacy Evaluation

    73/85

  • 8/12/2019 Generation System Adequacy Evaluation

    74/85

    LOLE

  • 8/12/2019 Generation System Adequacy Evaluation

    75/85

    In general

    LOLE is affected by

    Generation unit unavailability (FOR)

    Load Forecast uncertainty.

    Hence the calculated value is only approximate.

    The actual distribution of LOLE can be obtained by Monte

    Carlo simulation

    Loss of Energy Indices

  • 8/12/2019 Generation System Adequacy Evaluation

    76/85

    Loss of Energy Indices

    The area under the load duration curve

    represents the energy utilized during thespecified period and can be used to

    determine the expected energy not supplied

    due to insufficient installed capacity.

  • 8/12/2019 Generation System Adequacy Evaluation

    77/85

  • 8/12/2019 Generation System Adequacy Evaluation

    78/85

    The normalized LOEE is obtained as

    Where E is the total energy under load duration curve.

    The energy index of Reliability EIR is

    EIR = 1LOEE pu

  • 8/12/2019 Generation System Adequacy Evaluation

    79/85

    Consider the LDC for a period of 100 hours and the generating unit capacity

    shown in the table

  • 8/12/2019 Generation System Adequacy Evaluation

    80/85

    The total energy in the period is 4575 MWh.If there were no units, the Expected Energy Not Supplied

    (EENS) is 4575 MWH. If the system contained only unit 1, the

    EENS is obtained as

  • 8/12/2019 Generation System Adequacy Evaluation

    81/85

    EENS with units 1 & 2

  • 8/12/2019 Generation System Adequacy Evaluation

    82/85

    EENS with units 1,2 & 3

  • 8/12/2019 Generation System Adequacy Evaluation

    83/85

    The expected energy produced by unit 3 is 401.764.08 = 337.6 MWh

    Summary of EENS

  • 8/12/2019 Generation System Adequacy Evaluation

    84/85

    Summary of EENS

    The expected energy not supplied is therefore 64.08

    MWh. The energy index of reliability EIR is obtained asEIR = 1(64.08/4575) = 0.985993

    A generating contains three 25 MW

  • 8/12/2019 Generation System Adequacy Evaluation

    85/85

    A generating contains three 25 MW

    generating units each with a 4 % FOR and one

    30 MW unit with 5 % FOR. If the peak load fora 100 day period is 75 MW, what is the LOLE

    and EIR for this period? Assume that

    appropriate load characteristics is a straight

    line from the 100 % point to 60 % point.