generator assessment process - level 4

33
GAP GAP GAP GAP GAP GAP GAP GAP 4 4 4 4 4 generator assessment process generator assessment process generator assessment process generator assessment process a solution to life assessment of large generators [email protected] [email protected]

Upload: anil-panjani

Post on 05-Dec-2014

457 views

Category:

Technology


1 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Generator Assessment Process - Level 4

GAPGAPGAPGAPGAPGAPGAPGAP44444444generator assessment processgenerator assessment processgenerator assessment processgenerator assessment process

a solution to life assessment of large generators

[email protected]@gmail.com

Page 2: Generator Assessment Process - Level 4

GAPGAPGAPGAP1111 GAPGAPGAPGAP2222

GAPGAPGAPGAP****

GAPGAPGAPGAP4444 GAPGAPGAPGAP3333

GAPGAPGAPGAP****

Page 3: Generator Assessment Process - Level 4

GAPGAPGAPGAP4444 is the inspective approach to

assess the residual life of thegenerator

.

Page 4: Generator Assessment Process - Level 4

MethodologyMethodologyMethodologyMethodology

The methodology employed isconducting standard and specialelectrical tests and inspection on statorand rotor windings and accessories

Page 5: Generator Assessment Process - Level 4

UnitUnitUnitUnit ConditionConditionConditionCondition

The machine is in dismantledcondition with rotor threaded-out

InspectionInspectionInspectionInspection &&&& teststeststeststests PerformedPerformedPerformedPerformed

Physical examination

Tests and inspection

Page 6: Generator Assessment Process - Level 4

BenefitsBenefitsBenefitsBenefits

Reveals pending faults in winding

Reveals deterioration of coil insulation bycorona or end winding vibration

Establish a base line for evaluating futureinspection

Accurately assess life and futuremaintenance requirements

Record of core tightness

Preventive maintenance plan

Schedule for GAPGAPGAPGAP2222, GAPGAPGAPGAP3333 and GAPGAPGAPGAP4444

Page 7: Generator Assessment Process - Level 4

FinalFinalFinalFinal ReportReportReportReport

Standard format provided electronically

Photographs of critical areas

Dielectric absorption graph and analysis ofinsulation integrity

Results and summary of all test andmeasurements takenmeasurements taken

Location and levels of corona activity

Plots showing frequency distribution of endwinding basket

Core tightness record

EL CID test record and wedge mapping

Establishes a base-line for evaluating futureinspections and input for instituting plannedmajor maintenance activities

Page 8: Generator Assessment Process - Level 4

ExpectedExpectedExpectedExpected DowntimeDowntimeDowntimeDowntime

12-15 days

OptionOptionOptionOption

..

Page 9: Generator Assessment Process - Level 4

Life AssessmentFEM Approach

Page 10: Generator Assessment Process - Level 4

Overhangs

Turbine End

Geometrical data of the stator coils is collected to make a model by FEM method for stress analysis

Straight side

Exciter End

Overhangs

Page 11: Generator Assessment Process - Level 4
Page 12: Generator Assessment Process - Level 4

68

70

72

74

76

78

Stress/Tensile Strength (MPa)

LIFE ESTIMATION BY FEM METHOD

60

62

64

66

68

1090

1120

1150

1180

1210

1240

1270

1300

1330

1360

1390

1420

1450

1480

1510

1540

1570

1600

1630

1660

1690

1720

1750

1780

1810

1840

1870

1900

Stress/Tensile Strength (MPa)

Equivalent Operating Hours

Hundreds

Page 13: Generator Assessment Process - Level 4

Condition AssessmentRisk Assessment Approach

Page 14: Generator Assessment Process - Level 4

The following indicators are used separately toevaluate the condition of stator and rotor

• Operation and maintenance history• Physical inspection• Physical inspection• Insulation test• Generator Age

Page 15: Generator Assessment Process - Level 4

These condition indicators are initially evaluated usinginspections, tests, and measurements, which areconducted by utility staff or contractors over thecourse of time and as a part of routine maintenanceactivities.

Numerical scores are assigned to each stator androtor condition indicator, which are then weighted androtor condition indicator, which are then weighted andsummed to determine the Stator and Rotor ConditionIndices.

The lower of the two indices is selected to representthe overall Generator Condition Index.

Page 16: Generator Assessment Process - Level 4

An additional stand-alone indicator is used to reflectthe quality of the information available for scoring thegenerator condition indicators.

In some cases, data may be missing, out-of-date, orof questionable integrity.

Any of these situations could affect the accuracy ofAny of these situations could affect the accuracy ofthe associated condition indicator scores as well asthe validity of the overall Condition Index.

Given the potential impact of poor or missing data,the Data Quality Indicator is used as a means ofevaluating and recording confidence in the finalGenerator Condition Index.

Page 17: Generator Assessment Process - Level 4

Additional information regarding generator condition may benecessary to improve the accuracy and reliability of theGenerator Condition index.

Therefore, in addition to the Tier 1 condition indicators, thisappendix describes a “toolbox” of Tier 2 inspections, tests, andmeasurements that may be applied to the Stator and RotorCondition Indices, depending on the specific issue or problembeing addressed. Tier 2 tests are considered non-routine.

However, if Tier 2 data is readily available, it may be used toHowever, if Tier 2 data is readily available, it may be used tosupplement the Tier 1 assessment. Alternatively, Tier 2 testsmay be deliberately performed to address Tier 1 findings.

Results of the Tier 2 analysis may either increase or decreasethe score of the Generator Condition Index.

The Data Quality Indicator score may also be revised during theTier 2 assessment to reflect the availability of additionalinformation or test data.

Page 18: Generator Assessment Process - Level 4

Condition AssessmentStator

Page 19: Generator Assessment Process - Level 4

Operation & Maintenance History

Physical Inspection

Insulation Test

Generator Age

Page 20: Generator Assessment Process - Level 4

DC Ramped Voltage Test

Partial Discharge Measurement

Dissipation Factor Measurement

Ozone Monitoring

Black Out TestBlack Out Test

High Potential Withstand Test

Stator Core Inspection

Wedge Tightness Evaluation

Core Loop Test

Page 21: Generator Assessment Process - Level 4

ELCID Test

Corona Probe Test

Coupling Resistance Test

Bump test

Capacitance MeasurementCapacitance Measurement

Core Bolt Insulation Resistance

Winding Conductor Resistance Measurement

Impedance Measurement

Winding Dissection

Page 22: Generator Assessment Process - Level 4

10987654321

Stator Condition Index

10987654321

Page 23: Generator Assessment Process - Level 4

10740

Stator Data Quality Index

10740

Page 24: Generator Assessment Process - Level 4

Condition AssessmentRotor

Page 25: Generator Assessment Process - Level 4

Operation & Maintenance History

Physical Inspection

Insulation Test

Generator Age

Page 26: Generator Assessment Process - Level 4

High Potential Withstand Test

Rotor Core Inspection

AC Pole Drop Test

AC Impedance Test

Winding Resistance Measurement

RSO Test

Page 27: Generator Assessment Process - Level 4

10987654321

Rotor Condition Index

10987654321

Page 28: Generator Assessment Process - Level 4

10740

Rotor Data Quality Index

10740

Page 29: Generator Assessment Process - Level 4

Condition AssessmentGenerators

Page 30: Generator Assessment Process - Level 4

10987654321

Generator Condition Index

10987654321

Page 31: Generator Assessment Process - Level 4

10740

Generator Data Quality Index

10740

Page 32: Generator Assessment Process - Level 4
Page 33: Generator Assessment Process - Level 4

شكرا

THANK YOU

������ ����

ध�यवाद

شکریہ ادا کيا ہے

��������شكرا

ந�றி

ಧನ��ಾದಗಳ

����