GEO Work Plan Symposium 2012, 30 April – 2 May 2012, Geneva, Switzerland “Building Synergies Across the GEO Work Plan” ID-02 Developing Institutional and Individual Capacity Andiswa Mlisa Task Leads and Contributors

Upload: alison-jackson

Post on 13-Jan-2016

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: GEO Work Plan Symposium 2012, 30 April – 2 May 2012, Geneva, Switzerland “Building Synergies Across the GEO Work Plan” ID-02 Developing Institutional and

GEO Work Plan Symposium 2012, 30 April – 2 May 2012, Geneva, Switzerland

“Building Synergies Across the GEO Work Plan”

ID-02 Developing Institutional and Individual Capacity

Andiswa Mlisa

Task Leads and Contributors

Page 2: GEO Work Plan Symposium 2012, 30 April – 2 May 2012, Geneva, Switzerland “Building Synergies Across the GEO Work Plan” ID-02 Developing Institutional and

Response to GEOSS Strategic Target: Build the capacity of individuals, institutions and infrastructures to benefit from and contribute to GEOSS, particularly in developing countries.

Expected Achievements by 2015 • Establish regional capacity-building networks: Organize and reinforce

international networks (incl. training opportunity networks) for the use and provision of Earth observations. Improve coordination of these networks through the GEO Portal and existing initiatives.

• Create conditions for expanding GEO capacity building activities and improving their effectiveness across Societal Benefit Areas.

• Develop qualitative and quantitative Performance Indicators for measuring the efficacy of institutional and individual capacity building programs

• Strengthen regional and national capabilities to employ geographic information systems and remote sensing for environmental monitoring and decision-making

Page 3: GEO Work Plan Symposium 2012, 30 April – 2 May 2012, Geneva, Switzerland “Building Synergies Across the GEO Work Plan” ID-02 Developing Institutional and

Recent Progress and Key Outputs for 2012

• Training and research components of large funded projects with GEO signature and other ->

• EU FP7 DEVCOCAST (Africa & Latin Am): a success story 2007-2011

• EU EDF AMESD (Africa, SADC, IGAD)• EU FP7 EO2Heaven (Europe; Africa)• EU FP7 CEOP-AEGIS (Asia)• TIGER2 CBF (Africa with ESA)New recently launched:• EU FP7 AGRICAB (N,S,W,N Africa)• UN WFP-CO Ethiopia (food security)• NL NUFFIC NICHE-ZAF (South Africa;

UWC, Cape town)• NL NUFFIC NICHE-VNM (Ha Noi, VNM)SUBMITTED:• Ethiopia IWRM, coop. with e.g. Cornell

Univ., to NSF, USAID…• More..

Page 4: GEO Work Plan Symposium 2012, 30 April – 2 May 2012, Geneva, Switzerland “Building Synergies Across the GEO Work Plan” ID-02 Developing Institutional and

Recent Progress and Key Outputs for 2012• Software portal:

– Software to handle and process the GEONETCast and ESA DDS data received is now freely available through the newly established “Earth Observation” community (http://52north.org).

• Capacity building portal:– Further information, hands on exercises and sample

data is now freely available at the ITC “GNC pages”

(http://www.itc.nl/Pub/WRS/WRS-GEONETCast)

• Registered component of GEO GCI

Page 5: GEO Work Plan Symposium 2012, 30 April – 2 May 2012, Geneva, Switzerland “Building Synergies Across the GEO Work Plan” ID-02 Developing Institutional and

Recent Progress and Key Outputs for 2012• TerraMA2 - Version 3.0 to be released in July 2012

http://www.dpi.inpe.br/terrama2/english/index.php)– May 21-25, 2012: In Portuguese, 40 hours, at INPE– Mini-courses during Brazilian Symposium on Natural Disasters.

• TerraAmazon (http://www3.funcate.org.br/geo//available/wiki-v01-TerraAmazon/pmwiki.php/Main/Home)– Jan 23- Feb 2, 2012: IV International Course on Tropical Forest

Monitoring. Spanish Speaking Countries: Barbados, Belize, Granada and Jamaica

– Jun 11 – 29, 2012: V International Course on Tropical Forest Monitoring. Spanish Speaking Countries: Costa Rica, El Salvador, Nicaragua, Panama.

• TerraHidro (website under development): Tool built on TerraLib´s library, designed to develop distributed hydrological models, using elevation and hydrological data. Engagement with DEM project to be developed with CEOS WGCapD (Working Group on Capacity Building and Data Democracy).

Page 6: GEO Work Plan Symposium 2012, 30 April – 2 May 2012, Geneva, Switzerland “Building Synergies Across the GEO Work Plan” ID-02 Developing Institutional and

Recent Progress and Key Outputs for 2012

• EO & Geoinformation for Climate Change Adaptation: Malawi 2011 (Z_GIS, COOPI, UNDP); Uganda, Mozambique (supported by Austria)

• EC FP7 EnerGEO Summer Schools (Z_GIS Austria) linking EN-01 and Ecosystem Monitoring SBA – Salzburg/Austria 2011, – Brazil (INPE) 2012, – Kampala/Uganda 2013

• 2012 – Further define measurement framework for GEO capacity building performance indicators and undertake annual assessment

• Development and improvement of open-source software and open systems (Brazilian contribution)

• New releases to be released and training courses (TerraLib and family)

Page 7: GEO Work Plan Symposium 2012, 30 April – 2 May 2012, Geneva, Switzerland “Building Synergies Across the GEO Work Plan” ID-02 Developing Institutional and

Linkages with other Tasks

• Potential collaboration with all tasks• ID-05: Resource Mobilization• IN-03: GCI

– GCI: Connect GEONetCab portal inside GCI (open source and best practices inventories)

– GCI: Training activity involving the GCI and registry of components.

– Outreach on GEO Portal (to be designed• IN-04: Communication infrastructure and networks• EN-01: Ecosystem Monitoring (EnerGEO summer schools)• CEOS WGCapD (Working Group on Capacity Building and Data

Democracy): development of an International Online Certificate Program in Remote Sensing, to be organized by CEOS Space Agencies.

• AfriGEOSS: Connect activities with AfriGEOSS

Page 8: GEO Work Plan Symposium 2012, 30 April – 2 May 2012, Geneva, Switzerland “Building Synergies Across the GEO Work Plan” ID-02 Developing Institutional and

Available Resource (Contributors)

• GEONETCAST (systems and networks)• GEO-Net-CaB: Regional studies on earth observation

markets and capacity building (Nov 2009-2012)• SEOCA: GEO capacity building in Central Asia• AGRICAB Project: A framework for enhancing EO

capacity for Agriculture and Forest Management in Africa as a contribution to GEOSS

• AfroMaison: Africa at meso-scale: Adaptive and integrated tools and strategies on natural resources management (Mar 2011 - 2014)

• OBSERVE: Strengthening and development of EO activities for the environment in the Balkan area

Page 9: GEO Work Plan Symposium 2012, 30 April – 2 May 2012, Geneva, Switzerland “Building Synergies Across the GEO Work Plan” ID-02 Developing Institutional and

Available Resource (Contributors)

• BalkanGEONet: Balkans in Global Observation• CLIVAR - Climate Variability Research Program• REGATTA (UNEP project funded by Spain)• CEOP–AEGIS• EnviroGRIDS (April 2009 - 2013)• EcoArm2ERA (Dec 2011 - 2014)• Swiss FNRS SCOPES ARPEGEO (Sep 2011 - 2013)• FP7 EnerGEO Summer Schools (Z_GIS Austria) • FP7 EO2Heaven (Europe; Africa)

Page 10: GEO Work Plan Symposium 2012, 30 April – 2 May 2012, Geneva, Switzerland “Building Synergies Across the GEO Work Plan” ID-02 Developing Institutional and

Issues and Gaps

• Efficiency in using existing resources through coordination • Provision of information in the Task Component Sheets on

capacity building activities• Engagement with SBAs

Page 11: GEO Work Plan Symposium 2012, 30 April – 2 May 2012, Geneva, Switzerland “Building Synergies Across the GEO Work Plan” ID-02 Developing Institutional and

Ideas for Accelerating Work Plan Implementation

• Commitment by all in Task Teams to actively participate and provide information timeously

• Terminology and role clarification (Task, Component, Priority Activitions, Leads, Contributors)

– All inclusive nature of GEO maybe there is room for an ‘observer’ role

• The process of collating information from Task Leads/Contributors can be improved to minimize effort in translating it to the task sheet – progress report template

• Consensus on level of detail to be provided in the task sheet (task team level)

• More frequent progress reporting to enable adequate coordination