georgia transportation summit 2017 - microsoft...georgia transportation summit 2017 staying the...
TRANSCRIPT
Staying the Course for Success
1
Meg Pirkle, PE, Chief EngineerGeorgia Transportation Summit 2017
Staying the Course: Program Goals
1
• Sustain Increased Delivery of the Capital Program
– Capital Roadway Projects
– Maintenance Projects
– Bridge Projects
• Build Engineering Support for Innovative and Major Mobility Projects
• Initiatives and Innovations to support program delivery and improve quality
Procurement Trends (A&E)
FY 13 FY 14 FY 15 FY 16 FY 17 FY 18 to date
# of Contracts 434 418 399 561 855 252
Total Contract $$ $157M $175M $177M $286M $357M $165M
TFA 2015
(as of 9/30/17)
$-
$50,000,000
$100,000,000
$150,000,000
$200,000,000
$250,000,000
$300,000,000
$350,000,000
$400,000,000
FY13 FY14 FY15 FY16 FY17 FY18
Total Contract $
• Construction
– Construction Management and CEI (Regional)
• GDOT District 1
• GDOT District 3
• GDOT District 4
• Intermodal
– Aviation Program Management
– Rail Program On-Call Services
– Statewide Rail Plan Update
2018 Planned Contracts/Needs
• Transportation Investment Act Program (TIA)
– Construction Management and CEI
• Band 3 Projects
– Possible Program Management for New TIA Regions
• Middle Georgia and Southern Georgia Regions
• We’ll know in May 2018!!
2018 Planned Contracts/Needs
• Materials & Testing
– Statewide On-Call Physical-Chemical Testing for Lab Services
• Planning
– Statewide Transportation Plan (SWTP) Update
– I-85 Corridor Study – DeKalb/Gwinnett County
2018 Planned Contracts/Needs
• Transportation Data
– Video Log Data Collection (Statewide)
• Engineering Services (2 Regional)
– Plan Review
• Utilities
– Utility Coordination Services (Statewide)
2018 Planned Contracts/Needs
• Maintenance
– Management, Engineering and Inspection (MEI) (3 Regional)
– Comprehensive Maintenance Contract, I-95
• Traffic Operations
– Signal and ITS Design (3 Regional)
– Operational Improvement Program Support,
Analysis and Design (2 Regional)
2018 Planned Contracts/Needs
• Program Delivery
– General Engineering Services Contract (2 Regional)
– ROW Acquisition (Project Specific)
• Rome-Cartersville Development Corridor
• Other projects
2018 Planned Contracts/Needs
2018 Design Contracts: Widen/Reconstruct
0012759 ClaytonI-75 SB CD SYSTEM FROM I-285 TO SR 331 (At the
Forest Parkway Interchange)
0013524 ClaytonSR 85 FROM CS 925/ADAMS DRIVE TO I-75;
INCLUDING INTERCHANGE AT FOREST PKWY
0008668 GilmerSR 282 REALIGNMENT FROM CS 563/PROGRESS DR
TO SR 515 AT CROSS ST
0013579 SumterSR 30/US 280 FROM CR 307/FELDER STREET TO CR
311/LAMAR ROAD
Jefferson,
Warren0013576
SR 17 FROM QUAKER RD/JEFFERSON TO NORTH OF
SR 296/WARREN (INCLUDES RELOCATION)
2018 Design Contracts: Bridge Bundles
0015532 Banks SR 51 @ HUDSON RIVER IN HOMER
0015543 Elbert SR 77 @ COLDWATER CREEK 9.5 MI N OF ELBERTON
0015551 Hall SR 60 @ CHATTAHOOCHEE RIVER IN GAINESVILLE
0015557 MadisonSR 8/SR 174 @ HUDSON RIVER 8.8 MI N OF
DANIELSVILLE
0015547 GilmerSR 515/US 76 @ BIG TURNIPTOWN CREEK IN
ELLIJAY
0015556 LumpkinSR 9/US 19 @ CHESTATEE RIVER 10.25 MI NE OF
DAHLONEGA
0015567 Union SR 60 @ SUCHES CREEK 13.1 MI SW OF BLAIRSVILLE
Bridge Bundle Contract 2
Bridge Bundle Contract 1
2018 Design Contracts: Bridge Bundles
0015555 LincolnSR 79 @ BROAD RIVER 15.7 MI NW OF
LINCOLNTON
0015560 Newton SR 81 @ YELLOW RIVER IN PORTERDALE
0015568 Walton SR 83 @ POLECAT CREEK 1 MI NW OF GOOD HOPE
0015540 Crisp SR 7/US 41 @ CEDAR CREEK 1.5 MI S OF CORDELE
0015552 Houston SR 7 @ FLAT CREEK 3.5 MI SW OF PERRY
0015553 Houston SR 7/SR 127/US 41 @ BIG INDIAN CREEK IN PERRY
0015563 Randolph SR 41 @ BARGE CREEK 12 MI NE OF CUTHBERT
Bridge Bundle Contract 3
Bridge Bundle Contract 4
2018 Design Contracts: Bridge Bundles
0015558 Meriwether SR 41 @ COLEMAN CREEK 4 MI S OF LUTHERSVILLE
0015559 MuscogeeSR 520/US 280 @ CHATTAHOOCHEE RIVER IN
COLUMBUS
0015564 TalbotSR 22 @ SOUTH FORK UPATOI CREEK 1 MILE E OF
GENEVA
0015565 Talbot SR 22 @ RICHLAND CREEK 6.7 MI E OF TALBOTTON
0015566 Talbot SR 190 @ NS #718623W 2.5 MI W OF MANCHESTER
Bridge Bundle Contract 5
2018 Design Contracts: Bridge Bundles
0015534 Bartow SR 3/US 41 NB @ SR 293 IN EMERSON
0015535 Bartow SR 3/US 41 SB @ SR 293/CS #340429D IN EMERSON
0015539 ChattoogaSR 48 @ RACCOON CREEK 3 MI W OF
SUMMERVILLE
0015544 Floyd SR 293 @ DYKES CREEK 5.4 MI E OF ROME
0015561 Polk SR 101 @ EUHARLEE CREEK TRIB IN ROCKMART
Bridge Bundle Contract 6
2018 Design Contracts: Bridge Bundles
0015538 Catoosa SR 3 @ PEAVINE CREEK 3.7 M E OF FT OGLETHORPE
0015541 DadeSR 58 @ SQUIRREL TOWN CREEK 4 MI NE OF
TRENTON
0015542 Dade SR 136 @ LOOKOUT CREEK
0015546 Fulton SR 14 @ NS #718047H IN ATLANTA
Bridge Bundle Contract 7
Bridge Bundle Contract 8
MMIP Schedule
Program and MMIP Consultant Opportunities
18
Design-Build Project Opportunities
Additional projects will be added to
the DB program as they are identified
I-20 Moveable Barrier
SR 53 Bridge
I-20 SavannahRiver Bridge
SR 135 Bridge
I-16 Widening
Project Project ID CST FY
FY 18 Bridges Various 2018
I-20 Moveable Barrier 0015244 2019
SR 53 Bridge 0010212 2019
I-20 Savannah River Bridge 210327- 2019
SR 135 Bridge 0007037 2019
I-16/I-95 Interchange/
Widening
0012758
0012757
0013727
2018
Design-Build Project Opportunities
19
FY 18 Locations are subject to change.
Development FY 18 Bridges
Under Contract
FY 16 Bridges
I-85 Bridges
FY 17 Bridges
Web Based Applications
• e-Construction
• Contract Authorization Tracking System (CATS)
• CMIS
New!
• Georgia Permitting Application System (GPAS)
• GDOT IT in the lobby today to assist
• Jeff Hill, GDOT CIO, 404-217-5504
GDOT’s culture of INNOVATION
• Accelerated Bridge Construction
• 3D Modeling for Design
• Streamedlined Agency Coordination
Accelerated Bridge Construction
GDOT’s culture of INNOVATION
SR 299 bridge over Interstate 24 in Dade County
56-hours Onsite Construction Time Vs. of 9 months Road Closure
Accelerated Bridge Construction
GDOT’s culture of INNOVATION
SR 299 bridge over Interstate 24 in Dade County
SR 211 Bridge over Beech Creek59 Days Road closures vs. 8 miles long detour for 9 months
3D Modeling for Roadway Design
GDOT’s Culture of INNOVATION
• Detail and visualization of elements
• Avoid delays/supplemental agreements
• Increased accuracy for quantities and estimates
• Goal: 3D model as a deliverable in Final Plans Submission beginning January 2019
• GDOT/FHWA NEPA Reevaluation Memorandum of Agreement
• GDOT/FHWA Programmatic Agreement for Carbon Monoxide Analyses
GDOT’s Culture of INNOVATION
Coordination for future improved processes underway:
• Buffer Variance coordination with EPD and 404 permitting with USACE
• Remove from critical path in project schedule
• GDOT/FHWA coordination towards
Abbreviated FONSI
GDOT’s Culture of INNOVATION
www.dot.ga.gov
If you want to experience significant
progress toward your goal, you need to be
intentional about the work you’re doing
every day…