GEOSCIENCES AND ENGINEERING DIVISION
QUALITY ASSURANCE PROCEDURE
Title: QAP-017 DRAWING CONTROL
Proc. QAP-017
- Revision 1 Chg 1
- Page 1 of 3
EFFECTIVITY AND APPROVAL
Revision 9 of this procedure became effective on August 25, 2005. This procedure consists of the pages and changes listed below.
Page No. All
Change 1
Date Effective 5/12/2010
Change 1: Reflects QA title change
Supersedes Procedure No. Q Prepared by
I GEOSCIENCES AND ENGINEERING DIVISION I QAP-017 I 1
QUALITY ASSURANCE PROCEDURE Page 2 of 3
QAP-017 DRAWING CONTROL
1. PURPOSE
The purpose of this procedure is to describe the measures for preparing, reviewing, approving, changing, and distributing drawingskketches of items, equipment, and specimens used in Geosciences and Engineering Division (Division) activities. This procedure addresses requirements of the Quality Assurance Manual (QAM), Section 6, Document Control.
2.
2.1
2.2
2.3
3.
3.1
3.1.1
3.1.2
3.2
RESPONSlBl LIT1 ES
Division Quality Assurance (QA) is responsible for maintaining drawings and assigning drawing numbers.
Technical staff are responsible for preparing drawings in accordance with this procedure.
The responsible manager and QA staff are responsible for reviewing and approving drawings.
PROCEDURE
Drawing Initiation
The drawing originator :shall request a drawing number (see 3.1.2) from QA staff. QA staff shall maintain a drawing number log book providing project number, drawing number, revision, date, title, and requester.
Unique numbers shall be created by using the appropriate project number and a sequence of numbers s,o that each drawing is uniquely identified. Drawing revisions shall be indicated by sequential letters (i.e., A, B, etc.) added to the base drawing number.
Drawing Format and Content
The drawing shall contain sufficient detail for the end user to perform an activity without ambiguity or question. The drawing shall include appropriate quantitative and qualitative acceptance criteria (e.g., tolerances). Each drawing shall contain signature and date blocks for the drawing initiator and drawing reviewers (see 3.3).
3.3 Review and Approval
After completion, the drawing shall be reviewed and approved by the responsible manager and QA staff. I
I
GEOSCIENCES AND ENGINEERING DIVISION 1 Proc. QAP-017 Revision1 ChgJ
Page 3 of 3 QUALITY ASSURANCE PROCEDURE
3.4 Drawing Change Control
When a drawing change is necessary, the following steps are required.
.
. 3.5
3.5.1
3.5.2
4.
A drawing revision number should be obtained from QA staff and the revision shall be logged into the drawing number log book.
Revised drawings shall be reviewed and approved as specified in Section 3.3.
Distribution
The drawing initiator shall distribute drawings and drawing changes as needed. As a minimum, drawings and drawing changes shall be distributed to the point of use. If multiple (copies are distributed, the requester shall maintain a list identifying the personneVorganizations that received the drawing.
The drawing initiator shall also distribute the drawing revision that affects work in progress on a timely basis so that the correct revision is used.
RECORDS
Original drawings and revisions, and the drawing log book shall be maintained in accordance with QAP-012, Quality Assurance Records.