geotechnical assessment and design · geotechnical assessment and design bear flat cache creek...
TRANSCRIPT
Prepared for:
R.F. Binnie & Associates Ltd.
101 - 1577 7th Avenue, Prince George, BC, V2L 3P5
February 19, 2020
GEOTECHNICAL ASSESSMENT AND
DESIGN
Bear Flat Cache Creek Segment (West)
Highway 29, British Columbia
Project # KX05280503
‘Wood’ is a trading name for John Wood Group PLC and its subsidiaries
GEOTECHNICAL ASSESSMENT AND DESIGN
Bear Flat Cache Creek Segment (West)
Highway 29, British Columbia
Project # KX05280503
Prepared for: R.F. Binnie & Associates Ltd.
101 - 1577 7th Avenue, Prince George, BC, V2L 3P5
Prepared by: Wood Environment & Infrastructure Solutions,
a Division of Wood Canada Limited
3456 Opie Crescent Prince George, BC V2N 2P9
February 19, 2020
Copyright and non-disclosure notice
The contents and layout of this report are subject to copyright owned by Wood (© Wood Environment & Infrastructure Solutions)
save to the extent that copyright has been legally assigned by us to another party or is used by Wood under license. To the extent
that we own the copyright in this report, it may not be copied or used without our prior written agreement for any purpose other
than the purpose indicated in this report. The methodology (if any) contained in this report is provided to you in confidence and
must not be disclosed or copied to third parties without the prior written agreement of Wood. Disclosure of that information may
constitute an actionable breach of confidence or may otherwise prejudice our commercial interests. Any third party who obtains
access to this report by any means will, in any event, be subject to the Third Party Disclaimer set out below.
Third-party disclaimer
Any disclosure of this report to a third party is subject to this disclaimer. The report was prepared by Wood at the instruction of, and
for use by, our client named on the front of the report. It does not in any way constitute advice to any third party who is able to
access it by any means. Wood excludes to the fullest extent lawfully permitted all liability whatsoever for any loss or damage
howsoever arising from reliance on the contents of this report. We do not however exclude our liability (if any) for personal injury or
death resulting from our negligence, for fraud or any other matter in relation to which we cannot legally exclude liability.
Geotechnical Assessment and Design
Bear Flat Cache Creek Segment (West)
Project # KX05280503 | 2/19/2020 Table of Contents
Table of Contents
INTRODUCTION ................................................................................................................................................................... 1
SCOPE ....................................................................................................................................................................................... 1
GENERAL PROJECT DESCRIPTION ................................................................................................................................ 3
BACKGROUND ...................................................................................................................................................................... 4
4.1 GEOLOGY ............................................................................................................................................................... 4
SITE CONDITIONS AND DISCUSSION ......................................................................................................................... 5
5.1 SUBSURFACE GEOLOGICAL CONDITIONS ................................................................................................ 5
5.1.1 Highway 29 Realignment ................................................................................................................ 5
5.1.2 Watson Spring Boat Launch Access Road ................................................................................ 6
5.2 SHALE BEDROCK ................................................................................................................................................. 6
5.3 ACID ROCK DRAINAGE AND METAL LEACHING POTENTIAL ........................................................... 7
5.4 GROUNDWATER CONDITIONS ..................................................................................................................... 8
GEOTECHNICAL DESIGN CONSIDERATIONS & RECOMMENDATIONS ......................................................10
6.1 STRIPPING ............................................................................................................................................................10
6.2 SUBGRADE PREPARATION ............................................................................................................................10
6.3 TEMPORARY EXCAVATIONS .........................................................................................................................11
6.4 EMBANKMENT FILL CONSTRUCTION .......................................................................................................11
6.5 CUT SLOPES .........................................................................................................................................................12
6.5.1 Sta. 42+000 to Sta. 42+230 ..........................................................................................................13
6.6 GEOTEXTILE AND BIAXIAL GEOGRID SPECIFICATIONS .....................................................................13
6.7 PAVEMENT STRUCTURE .................................................................................................................................14
6.8 WASTE DISPOSAL .............................................................................................................................................14
6.9 DETAILED GEOTECHNICAL RECOMMENDATIONS BY STATION SECTION ................................15
CLOSURE ...............................................................................................................................................................................18
REFERENCES .........................................................................................................................................................................19
List of Appendices
APPENDIX A FIGURES
List of Tables
Table 5-1: Encountered Bedrock ........................................................................................................................................ 7
Table 5-2: Summary of Groundwater Monitoring ....................................................................................................... 9
Table 6-1: Non-Woven Geotextile Specifications ..................................................................................................... 13
Table 6-2: Biaxial Polypropylene Geogrid Specifications....................................................................................... 14
Table 6-3: Recommended Minimum Pavement Structure Thickness ............................................................... 14
Table 6-4: Detailed Geotechnical Recommendations by Station Section....................................................... 16
Geotechnical Assessment and Design
Bear Flat Cache Creek Segment (West)
Project # KX05280503 2/19/2020 Page 1
INTRODUCTION As part of BC Hydro’s proposed Site C Clean Energy Project, portions of the existing Highway 29
alignment between Hudson’s Hope and Charlie Lake, BC, will be flooded during normal reservoir
operation. Before filling of the reservoir, the affected portions of the highway will be relocated away from
the reservoir area. As part of the project, an access road for a boat launch is proposed south of the new
Bear Flat – Cache Creek highway alignment, in the vicinity of Watson Spring and Watson Spring Road. In
support of the project, Wood Environment & Infrastructure Solutions a Division of Wood Canada Limited
(Wood), formerly Amec Foster Wheeler, was retained by R.F. Binnie & Associates Ltd. (Binnie) to provide
geotechnical engineering services in support of proposed realignment for an approximately 4.9 km long
segment of Highway 29 located in the Cache Creek Bear Flats region along with additional geotechnical
engineering services in support of design of the boat launch. The general locations are shown in Figure 1,
and a plan of the proposed realignment and boat launch are provided on two map sheets in Figure 2. This
report has been prepared specifically in relation to the approximately 2.54 km long westernmost portion
of the alignment located on the west side of the Cache Creek valley and proposed new bridge crossing as
well as the boat launch access road.
Granular borrow investigations carried out in the vicinity of the Bear Flat Cache Creek realignment are
described in separate reporting. Additional background geotechnical information is provided in our
previous report: Preliminary Geotechnical Assessment, Proposed Bear Flat Segment, Highway 29 Definition
Design, Site C Clean Energy Project dated 5 March 2012. Results of geotechnical subsurface investigations
carried out to date are provided in our report: Geotechnical Data Report, Bear Flat Cache Creek Segment,
dated 14 August 2019. Amec Foster Wheeler also produced a Geotechnical Assessment and Design
Report: Geotechnical Assessment and Design, Highway No. 29, Bear Flat-Cache Creek, dated 21 July 2017,
for a previous L4000-Line alignment which has since been superseded.
This report includes a description of the scope of services, methodology, a discussion of geotechnical
engineering analysis and geotechnical recommendations developed to support the detailed design for
the proposed highway alignment on the west side of Cache Creek and boat launch access road. The
detailed design (analysis and reporting) of the bridge structure, abutments/end fills and the portion of the
alignment to the east of Cache Creek are reported separately.
SCOPE The general scope of Wood’s geotechnical field assessment for the Bear Flat Cache Creek realignment
segment and Watson Spring Boat Launch access road was as described in Work Order 5 Release 3
Highway 29 Contract Completion for the Cache Creek West (CCW) segment and the Detail and Functional
Design of a new alignment called the Cache Creek East (CCE) segment, and pursuant to the Sub-Consultant
Agreement between Binnie and Wood, dated 1 April 2018.
The geotechnical assessment included the following activities:
Attendance at project team meetings;
Review of relevant project background data;
Preparation of a site-specific health and safety plan for the fieldwork;
Field reconnaissance to identify locations and access routes for the geotechnical investigation;
Development of multiple geotechnical site investigation plans and budgets for various phases of field
investigation;
Geotechnical Assessment and Design
Bear Flat Cache Creek Segment (West)
Project # KX05280503 2/19/2020 Page 2
Preparation of various site access plans and permit support information;
Procurement and coordination of subcontractor equipment and support services for the geotechnical
investigation work including utility location, tree fallers, Level 3 medical support with emergency
transport vehicle, an excavator contractor, traffic control, multiple drill rigs, and downhole geophysical
testing subcontractors;
Coordination of the access preparation and geotechnical investigation work with concurrent activities
by others, including property considerations, surveyors, archaeology and environmental studies;
Supervision of several phases of geotechnical field investigation, including logging of ground
conditions, retention of soil samples from test pits, and retention of soil and rock core samples from
boreholes;
Supervision of the installation of groundwater instrumentation (vibrating wire piezometers) at select
locations, and follow-up monitoring;
Coordination and review of in-situ downhole geophysics data procurement;
Laboratory testing on selected soil and rock samples;
Provision of interim geotechnical data reports and draft recommendations as required; and
Compilation of this report.
Geotechnical Assessment and Design
Bear Flat Cache Creek Segment (West)
Project # KX05280503 2/19/2020 Page 3
GENERAL PROJECT DESCRIPTION The proposed approximately 4.9 km long Bear Flat Cache Creek realignment segment is referenced as
L4000O43 (Binnie draft geometric design drawings dated 17 January 2020). The subject L4000O43 Line
begins near Station 404+260 (eastern terminus of what is referred to as the Cache Creek West segment of
the new Highway 29 alignment) and runs north of and approximately parallel to the existing Highway 29
alignment. The new alignment will consist of two paved lanes. A major bridge structure is planned over
Cache Creek between approximately Sta. 406+744 to Sta. 407+334. The new highway alignment then
merges with the existing highway at approximately Station 409+144. In addition to the L4000O43 Line,
there will also be a side road (L42A10-Line, Binnie draft geometric design drawings dated 29 May 2019)
that will form an intersection at Sta. 403+590. The L42A10-Line begins at Sta. 42+000, where it will branch
south off the new highway alignment and follow a curving alignment down and generally to the east-
southeast to the Watson Spring Boat Launch parking area at approximately Sta. 42+230. Further details
pertaining to the Watson Spring Boat Launch can be found in our draft report: Geotechnical Site
Characterization, Watson Spring Boat Launch (Wood, September 2019).
This report provides a discussion and geotechnical recommendations prepared by Wood for the detailed
design of the approximately 2.54 km section of the proposed Bear Flat Cache Creek segment on the west
side of Cache Creek (i.e. from Sta. 404+200 to 406+744) as well as the proposed access road leading to
the Watson Spring Boat Launch parking area (i.e. from Sta. 42+000 to 42+230). Generally, the new
highway alignment and boat launch access road is located north of the future Site C reservoir shoreline,
along an upper fluvial terrace level within the Peace River valley.
Figure 1 depicts the general location of the project segment and the proposed boat launch access road.
Figure 2 (sheets 1 to 2) presents a detailed plan view of the new highway alignment and boat launch
access road on an orthophoto underlay. Figure 3 (sheets 1 to 6) depicts a profile view along the new
highway alignment centreline (sheets 1 to 5) and boat launch access road (sheet 6).
For more detailed descriptions of the background topographic, geology and terrain conditions along the
project segment, the reader is referred to our definition design phase reporting (Amec Foster Wheeler, 5
March 2012). Results of geotechnical subsurface investigations carried out to date are provided in our
report: Geotechnical Data Report, Bear Flat Cache Creek Segment, dated 14 August 2019.
Geotechnical Assessment and Design
Bear Flat Cache Creek Segment (West)
Project # KX05280503 2/19/2020 Page 4
BACKGROUND
4.1 GEOLOGY
Within the study region, the bedrock geology consists of Cretaceous marine sedimentary rock sequences
overlain by a series of glacial and fluvial Quaternary sediments (Hartman and Clague, 2008). The bedrock
units present include flakey and fissile shales and siltstone ascribed to the Shaftesbury Formation (part of
the Fort St. John Group), overlain by Dunvegan Formation sandstones and conglomerates (Hartman and
Clague, 2008 and Bidwell, 1999). Gates Formation sandstone (also part of the Fort St. John group) can be
found underlying the Shaftesbury Formation (Thurber, 1978). The bedding inclination of the bedrock has
been reported as near horizontal (Klohn Crippen Berger and SNC-Lavalin, 2003) in the vicinity of the
project segment, but may exhibit local undulation and variations.
The Dunvegan sandstone outcrops in upper elevation slopes within the Peace River Valley, within a
previously identified landslide feature to the east of the project segment. The contact between the
sandstone and the underlying shale is estimated to be near 670 m elevation (Thurber, 1978) at that
location, but dips downwards to the east / northeast.
The Shaftesbury shale typically is well bedded with thin, weak layers, some of which include bentonitic
clays from ashfall deposits that exhibit high plasticity and have low shear strength (Bidwell, 1999). Stability
issues in the shale have developed from weak cementation, valley rebound due to stress relief and
movement along pre-sheared or weak layers parallel to bedding. Within the Bear Flat Cache Creek project
segment, shale bedrock outcrops are apparent along both the Peace River and the Cache Creek valley
sidewall slopes between the base of the valley at about 430 m elevation up to about 475 m elevation.
Shale is assumed to underlie the terrace on which the alignment will be constructed at depths of 3 to
16 m.
The Gates Formation can consist of sandstone, shale and silty shale. It does not outcrop within the Bear
Flat project segment and is anticipated to underlie the valley bottom at an unknown depth.
The Quaternary-age sediments of the Peace River region are well exposed in the study area. Several
research papers (Matthews, 1978; Hartman and Clague, 2008) identify and describe a series of
predecessor valleys of the Peace River and its tributaries. In general, four paleovalleys have been identified
within the proposed Site C reservoir area. The paleovalleys are sometimes wider, but generally shallower
than the modern valley. The valleys are infilled with a sediment sequence that can be listed by decreasing
age as follows: pre-glacial fluvial deposits overlying the bedrock; advance phase fine-grained
glaciolacustrine soils (Glacial Lake Mathews); glacial tills of the last glaciation, late-glacial fine-grained
glaciolacustrine deposits (Glacial Lake Peace) and post-glacial deposits including fluvial sand, gravel and
silt and landslide debris.
In the Bear Flat Cache Creek project segment, a predecessor of the modern Halfway River tributary
drainage meets the ancient Peace River valley. As a result, the Peace Valley sidewall slopes within the
project area west of Cache Creek are underlain by colluvium derived from glacial sediments. East of Cache
Creek valley, the slopes are primarily underlain by similar colluvium, but shale bedrock outcrops in existing
highway cuts on the lower reaches of Cache Creek Hill.
Geotechnical Assessment and Design
Bear Flat Cache Creek Segment (West)
Project # KX05280503 2/19/2020 Page 5
SITE CONDITIONS AND DISCUSSION
5.1 SUBSURFACE GEOLOGICAL CONDITIONS
5.1.1 Highway 29 Realignment
Sta. 404+260 to 404+584: This section represents the scratch grade transition from the Cache Creek
West segment. Low cuts and embankment fills with heights less than 2 m would be excavated and
constructed along the relatively level surface of a fluvial terrace. The subsurface conditions are anticipated
to consist of up to 0.3 m of topsoil and 0.6 to 1.4 m of low to high plasticity clay and silt overlying at least
1.7 to 2.7 m of compact to very dense fluvial gravel and sand. Shale bedrock was not encountered in any
of the test holes. Groundwater was also not encountered in any of the test holes in this section.
Sta. 404+584 to 405+150: This section of the alignment entails a minor embankment fill construction of
up to 2 m in height, to be constructed along the relatively level surface of a fluvial terrace. The subsurface
conditions are anticipated to consist of up to 0.3 m of topsoil and 0.1 to 1.2 m of low to high plasticity silt
and clay overlying at least 1.1 to 3.7 m of compact to very dense gravel and sand with cobbles. Shale
bedrock underlies the gravel and sand and the bedrock surface appears to be dipping towards the south
and west. Shale is anticipated to be encountered at elevations as high as 473.4 to 474.9 m; however,
bedrock was not encountered at three locations (TH16-A-033, TP18-A-029, and TP18-A-030).
Groundwater was not encountered in any of the test pits or test holes.
Sta. 405+150 to 405+950: This section represents another area of low cuts and embankment fills with
heights less than 2 m, to be excavated and constructed on a relatively level fluvial terrace. The subsurface
conditions are anticipated to consist of up to 0.2 m of topsoil and 1.0 to 7.8 m of compact to very dense
sand and gravel with cobbles, with increasing thickness towards the east. Weathered shale and/or shale
bedrock underlies the sand and gravel at elevations ranging from 471.3 to 476.3 m. Generally, the shale
bedrock surface appears to dip towards the south. East of approximately Sta. 405+300 the bedrock
surface appears to dip towards the south and east. Groundwater was encountered in one borehole BH18-
A-055 at 6.4 m (EL. 473.8 m). An abandoned/decommissioned oil/gas drill site is present on a side slope
cut near Sta. 405+500 and BH18-A-055 and is located outside the footprint of the proposed highway.
The drill site was most likely constructed using imported fill.
Sta. 405+950 to 406+570: This section of the alignment is comprised of a side slope cut of up to 8 m on
the left (north) and up to 3 m on the right (south) side of the highway. The side slope cut is likely to
encounter 0.4 m of topsoil and 2.9 to 11.7 m of gravel and sand with cobbles. Borehole BH18-A-060 (Sta.
406+530) encountered 1.4 m of SAND below the topsoil. A relatively flat-lying weathered shale and/or shale
bedrock surface underlies the gravel and sand at depths of 3.1 to 11.9 m, and was encountered at
elevations ranging from 467.7 to 472.6 m. Groundwater was encountered in three boreholes (approx.
472.3 m in BH18-A-057; 470.6 in BH18-A-058; 470.1 m in BH18-A-059).
Sta. 406+570 to 406+744: This section comprises the western approach to the planned new bridge
across the Cache Creek valley. Embankment sections up to 4 m high would be constructed on the
relatively level surface of a fluvial terrace. The subsurface conditions are expected to consist of up to 0.4 m
of topsoil and 3.4 to 5.1 m of compact to very dense sand and gravel with cobbles. An isolated low
plasticity clay deposit with a thickness of 0.2 m was identified at a depth of 2.1 m (BH18-A-061).
Weathered bedrock and/or shale bedrock was encountered underlying the sand and gravel, the surface of
which appears to be dipping towards the south. Shale was encountered at elevations ranging from
approximately 465.4 to 468.0 m. Groundwater was encountered in one test hole TH18-A-043 at 2.1 m
(approx. 469.6 m).
Geotechnical Assessment and Design
Bear Flat Cache Creek Segment (West)
Project # KX05280503 2/19/2020 Page 6
5.1.2 Watson Spring Boat Launch Access Road
Sta. 42+030 to 42+180: The subsurface conditions are generally anticipated to be consistent across the
extent of the Watson Spring Boat Launch access road. The section between Sta. 42+000 and 42+030
represents the scratch grade transition from the Highway 29 intersection. The section of the access road
between Sta. 42+030 to 42+070 represents an area of relatively minor cuts of less than 2 m in depth
along a relatively flat fluvial terrace as well as fills up to 6 m in height along the slope of an excavated
gravel pit area. Sta. 42+070 to 42+180 represents an area of excavated cuts up to 9 m in depth. Between
Sta. 42+180 to 42+230 entails excavated cuts up to 6 m in depth and fills less than 2 m in height along
the slope located along the north side of Watson Spring Road. The subsurface conditions are anticipated
to generally consist of compact to very dense gravel and sand with cobbles to a depth of 10.5 to 11.1 m.
A low plasticity clay layer was encountered within the gravel and sand in BH18-WS-004 and BH18-WS-005
at depths ranging from 7.9 to 8.4 m with corresponding elevations of 470.8 to 471.8 m, respectively.
Weathered shale bedrock was encountered underlying the sand and gravel, the surface of which appears
to be dipping towards the east. Shale is anticipated to be encountered at elevations of approximately
468.2 to 471.1 m. Groundwater was encountered at elevations of 471.2 in BH18-WS-004 and 468.3 m in
BH18-WS-005, and appears to be locally ponded on top of the bedrock surface.
5.2 SHALE BEDROCK
In general, where bedrock was encountered during the investigation, it consisted of shale attributed to the
Shaftesbury Formation (part of the Fort. St. John Group). The Shaftesbury shale typically is well bedded
with thin, weak layers, some of which may include bentonitic clays from ashfall deposits that exhibit high
plasticity and have low shear strength. Stability issues in the shale have developed from weak
cementation, valley rebound due to stress relief and movement along pre-sheared or weak layers parallel
to bedding (Amec Foster Wheeler, 5 March 2012). It is anticipated that the planned earthworks between
Sta. 42+180 to 42+230 along the Watson Spring Boat Launch access road will encounter shale bedrock. It
is not expected that shale bedrock will be encountered by the proposed new highway alignment
earthworks. The shale bedrock locations and elevations encountered by drilling relative to the L4000O43-
Line and L42A10-Line (Station and Offsets) are summarized in Table 5.1, below.
In general, at the interface between the overburden and shale bedrock, the shale was weak, highly
weathered and in many instances resembled residual clay soil. Based on previous experience in the area,
portions of the Shaftesbury shale can be highly sensitive to moisture changes when exposed/disturbed
and can rapidly decompose to a clay-like soil. The shale bedrock is generally not considered suitable for
highway embankment fill construction without special consideration (low slope angles, careful placement,
encapsulation to prevent moisture driven decomposition, etc.).
Geotechnical Assessment and Design
Bear Flat Cache Creek Segment (West)
Project # KX05280503 2/19/2020 Page 7
Table 5-1: Encountered Bedrock
ID Station Offset
(m)
Bedrock Depth
(m)
Bedrock Elevation
(m)
HIGHWAY 29 REALIGNMENT
TP18-A-031 407+331 -12 1.8 473.4
TP18-A-032 407+393 -8 1.7 474.9
BH18-A-054 407+435 40 1.1 476.3
TP18-A-033 407+540 -16 3.2 475.2
BH18-A-055 407+677 2 7.8 472.4
BH18-A-056 407+803 3 7.4 471.3
BH18-A-057 407+896 -22 11.9 467.7
BH18-A-058 407+996 -43 4.8 468.7
BH18-A-059 408+002 -2 7.4 468.5
BH18-A-060 408+129 -4 3.1 472.6
TH18-A-043 408+258 -36 3.7 468.0
TH18-A-044 408+261 92 3.8 466.8
BH18-A-062 408+377 39 5.3 465.4
WATSON SPRING BOAT LAUNCH ACCESS ROAD
BH18-WS-004 42+090.2 -8.9 11.1 469.0
BH18-WS-005 42+141.2 -10.2 10.5 468.2
5.3 ACID ROCK DRAINAGE AND METAL LEACHING POTENTIAL
In general, shale bedrock is anticipated to be below the limits of planned earthworks for the highway
design alignment, however, is anticipated to be encountered in portions of the boat launch access road.
To assess the shale’s potential for acid rock drainage (ARD) and metal leaching (ML), two core samples
were previously selected from two drill holes completed near the western bridge abutment area for a
previous downstream alignment (BH16-A-015, at an approximate depth 7.6 m / elevation of 462 m and
DH11-51, at approximate depth of 7.1 m / elevation of 461.9 m). The samples were crushed and sent to
SGS Canada Inc. (SGS) in Burnaby, BC for acid-base accounting (ABA) analysis and multi-element analyses,
and to SGS in Lakefield, Ontario for quantitative X-ray diffraction by Rietveld Refinement. The laboratory
results can be found in the Geotechnical Data Report (Wood, August 2019).
ABA (acid-based accounting) results indicated that the pH values of the samples were 6.82 and 7.8 for
BH16-A-015 and DH11-51, respectively, with the total concentrations of sulphur at 0.52% and 0.48%. The
acid potential (AP) values (based on the sulphide content) were 11.3 and 12.2 tonnes CaCO3 per 1000
tonnes of material, and the modified Sobek Neutralization Potential (NP) values were 3.4 and 32.7 tonnes
CaCO3 per 1000 tonnes of material respectively.
The neutralization potential ratio (NPR) is a measure of the proportion of NP to AP (NPR = NP/AP). The
NPR value for BH16-A-015 was 0.3, while for DH11-51 it was 2.68. Based on the NPR criteria outlined in
the guidance document Technical Circular Letter T-04/13 (MoTI, 15 September 2013), the sample from
BH16-A-15 was classified as having a high potential to produce ARD. The sample from DH11-15 was
classified as non-acid generating with low potential to produce ARD. While both samples contained pyrite
(1.2 to 1.3%), only DH11-51 had appreciable carbonate (calcite, siderite) which would provide offsetting
neutralization potential. This high variation between the two samples found in relatively close proximity
and at similar elevations suggests that the ARD & ML potential will most likely be highly variable and
dependent on local mineralogy within each shale layer. Accordingly, it will be onerous and likely
impractical to screen and separate non-acid generating layers from shale that is or has the potential to be
acid generating. Consequently, it is conservatively considered that all the shale bedrock, if encountered,
should be considered as potentially acid generating, and where excavated should be disposed of in an
Geotechnical Assessment and Design
Bear Flat Cache Creek Segment (West)
Project # KX05280503 2/19/2020 Page 8
environmentally appropriate manner. Should significant surface exposures of shale remain after
excavation, they could likely be appropriately treated by backfill cover.
5.4 GROUNDWATER CONDITIONS
Vibrating wire piezometers were installed to provide information on the long-term groundwater conditions
for both the boat launch access road and highway realignment areas. The details of the vibrating wire
piezometers, along with maximum and minimum piezometric levels in 2016, 2018, and 2019 are provided
in Table 5-2. Further information on the instrumentation installation can be found in the Geotechnical Data
Report (Wood, August 2019).
Geotechnical Assessment and Design
Bear Flat Cache Creek Segment (West)
Project # KX05280503 | 2/18/2020 Page 9
Table 5-2: Summary of Groundwater Monitoring
Hole ID Station Offset Piezometer
No.
Elevation
Ground/Tip
(m)
Measured
Piezometric Level
in 2016
Measured
Piezometric Level
in 2018
Measured
Piezometric Level
in 2019
Highway 29 Realignment
BH16-A-013 407+412 269R
BH16-A-013A 470.1/464.9 465.4 – 465.7 465.7 466.0
BH16-A-013B 470.1/445.4 462.1 – 465.6 463.0 462.6
BH16-A-013C 470.1/429.0 442.9 – 444.1 443.4 443.3
BH16-A-015 407+996 43L BH16-A-015 463.0 433.4 – 434.9 - -
Watson Spring Boat Launch Access Road
BH18-WS-005 42+141.2 10.2L BH18-WS-005A 478.7/470.9 - 470.3 470.0
BH18-WS-005B 478.7/468.2 - 468.8 – 469.3 469.0
Geotechnical Assessment and Design
Bear Flat Cache Creek Segment (West)
Project # KX05280503| 2/19/2020 Page 10
GEOTECHNICAL DESIGN CONSIDERATIONS &
RECOMMENDATIONS Based on the office and field investigations to date, there does not appear to be any significant
geohazards or geotechnical conditions that would preclude the construction of the L4000O43 alignment.
However, the lower end of the proposed L42A10 boat launch access road will encounter groundwater,
potentially acid generating shale bedrock, and will be in close proximity to the steep lower valley slope
that may retrogress under the effects of reservoir inundation and erosion. Interception of groundwater by
the road excavation may affect the flow of the adjacent Watson Spring. For further discussion of the
reservoir shoreline slope stability issue and recommendations, refer to our draft report: Geotechnical Site
Characterization, Watson Spring Boat Launch (Wood, September 2019).
Section 6.1 through Section 6.9 provide geotechnical recommendations that are generally applicable for
the design and construction of the new highway alignment and boat launch access road. A summary of
recommendations specific to various station ranges is provided in Section 6.9. Recommendations for the
highway alignment are based on specific base mapping data provided to Wood on 9 Jan 2018 and design
alignment L4000O43 provided on 17 Jan2019 by Binnie. Recommendations for the boat launch access
road are based on the Option 1 L42A10-Line provided on 29 May 2019 by Binnie. The following
recommendations also reference the Ministry of Transportation and Infrastructure’s 2016 version of the
Standard Specifications for Highway Construction (SS2016), which is assumed will be used for the project
construction, unless updated prior to construction.
6.1 STRIPPING
For design, unless indicated otherwise, a minimum average stripping depth of 300 mm should be
assumed at the base of the proposed fills. Additional areas (e.g. existing ditches, colluvial slopes and wet
areas) will require deeper stripping and/or sub-excavation of soft, wet, weakened and organic soils that
are unsuitable for fill foundations. All stripped foundation subgrades should be reviewed prior to fill
placement by a geotechnical engineer or their representative to confirm that underlying soft, wet,
weakened and organic soils have been appropriately removed and that conditions are as anticipated in
this report. Some additional details regarding stripping and/or sub-excavation specific to various project
station ranges are provided in Section 6.9 below.
6.2 SUBGRADE PREPARATION
For the purposes of fill construction, the following subgrade preparation procedure is recommended:
Remove all unsuitable materials such as loose-fill, organic materials, stripping, and softened soils
from the subgrade surface. Location-specific guidance for additional sub-excavation (in excess of
stripping) of subgrade soils is provided in Section 6.9. A geotechnical engineer should review all
prepared subgrade prior to placement of fill (and/or geotextile separators, where applicable) to
confirm that unsuitable soils have been adequately removed.
Crown the subgrade to promote drainage by providing a minimum cross fall of 2% as soon as
possible following exposure of the subgrade soils. This will help minimize softening of the fine-
grained subgrade materials due to infiltration of surface water from precipitation events that occur
following exposure of the subgrade.
Minimize disturbance of the subgrade by limiting vehicle and construction traffic over the prepared
subgrade surface. If the subgrade surface is disturbed and becomes softened, removal of softened
soils and replacement with suitable fill will be required.
Geotechnical Assessment and Design
Bear Flat Cache Creek Segment (West)
Project # KX05280503| 2/19/2020 Page 11
Deposits of unsuitable subgrade soils that are too deep to be practically removed will require
additional subgrade improvements as directed by a geotechnical engineer at the time of
construction. Subgrade improvements may consist of (but are not limited to) use of geotextile
separator(s), biaxial geogrid layer(s), granular backfills and/or other methods.
6.3 TEMPORARY EXCAVATIONS
Temporary excavations greater than 1.2 m in depth, where worker entry is required should be constructed
in accordance with the current Part 20.78 through 20.95 of the Occupational Health and Safety Regulation
as per WorkSafeBC. The construction contractor, however, is ultimately responsible for the safety of
temporary excavation slopes. Should excavations encounter groundwater, flatter slopes than those
recommended by WorkSafeBC could be required. Excavations greater than 1.2 m in depth with steeper
slopes and those subject to seepage or sloughing should not be entered unless they are shored, braced
or sloped as approved by the contractor’s geotechnical engineer.
6.4 EMBANKMENT FILL CONSTRUCTION
New embankment fills along the highway alignment are estimated to be less than 4 m high. Maximum fill
slopes of 3H:1V are recommended between Sta. 404+260 to 405+150, unless the underlying fine silt and
clay soil cap (0.4 to 1.4 m thick where present) is removed to expose granular subgrade. Maximum fill
slopes of 2H:1V could be used elsewhere, i.e. between Sta. 405+150 to 405+950 and Sta. 406+570 to
406.744. New embankment fills along the boat launch access road are estimated to be constructed to a
maximum height of 6 m. A maximum fill slope of 2H:1V is recommended.
The maximum slope recommendations of 3H:1V and 2H:1V are also based on the embankment being
constructed on a properly prepared subgrade approved by a geotechnical engineer, and the fill consisting
primarily of Type D granular borrow as defined in SS 2016.
The following general recommendations are provided for fill construction.
All fill foundation preparation, fill placement and fill compaction operations should be observed by
qualified geotechnical engineering field personnel to confirm that the construction is in accordance
with the recommendations in this report and SS 2016.
Existing organic materials, loose-fill and/or otherwise unsuitable soils should be removed from under
the footprint of any new fills and from the outside face of the existing fill slopes prior to placing the
new fill.
Fill materials should consist of inorganic granular soil with moisture contents near (±1%) of the
optimum moisture content (as determined by laboratory moisture-density testing) such that they are
conducive to good compaction. In general, the following two granular fill types are recommended for
indicated uses:
Clean Granular Fill (CGF) – to be used for all embankment/berm fills constructed below an elevation of
466 m, the lower or back 1 m of fills placed on or against groundwater seepage zones.
♦ Material is to be free of organics and other detritus and has less than 5 % passing the
0.075 mm sieve.
♦ Maximum particle size as large as 300 mm can be used, provided that adequate lift thickness
and compaction is achieved before placement of the next lift. The contractor must
demonstrate via test strips and test excavations that they have the equipment, methodology
and are achieving compaction nominally equivalent to 95 % (Standard Proctor Maximum Dry
Geotechnical Assessment and Design
Bear Flat Cache Creek Segment (West)
Project # KX05280503| 2/19/2020 Page 12
Density as per the current version of ASTM D 698), with no observable segregation or
deflection and no rutting greater than 10 mm under construction traffic loading.
Type D Granular Fill – to be used for all other fill locations, where internal drainage is not required as
described above.
♦ Material gradation shall meet SS 2016 Section 201.44 and consist of predominately granular
material with a maximum 300 mm particle size that contains a maximum of 20% fines
(material passing the 0.075 mm sieve) and is free of organics and other detritus material.
Fills that will overlie seepage zones from existing fill or natural slopes will require field review by a
geotechnical engineer. These areas should be treated on a case by case basis and may need to be
treated by placement of a granular drainage blanket from the base of the excavation to a minimum of
2.0 m above the seepage area.
Fills underlain by groundwater seepage zones should be founded on a minimum 0.5 m thickness (as
measured above the high-water level or original ground surface, as determined by the geotechnical
engineer) of clean granular fill. A layer of non-woven geotextile (as defined in Section 6.6) should be
placed on the prepared subgrade before placement of granular drainage fill. Geotextile should also be
placed over granular drainage fill where finer-grained fill (i.e. having greater than 5% fines) will be
placed over the cleaner drainage fill.
Drainage from under an embankment area should be directed to an exposed face of a ditch or a sub-
drain system but should not be directed over the face of potentially unstable or erodible slopes
without additional armouring and/or riprap.
6.5 CUT SLOPES
Some shallow cuts up to 2 m and relatively minor ditch cuts of up to 2 m will be required for the currently
proposed highway alignment. Between Sta. 405+950 to 406+570 larger ditch cuts up to 8 m will be at the
left side (north) of the highway will be required. The required cuts between Sta. 404+260 to 404+584 are
expected to encounter mainly glaciofluvial and alluvial soils (BCMoTI Type D excavation) that are generally
anticipated to be unsuitable for use in the construction of new highway embankments (Type D borrow).
Cuts located between Sta. 404+584 and 406+570 are also anticipated to encounter primarily coarse-
grained fluvial and alluvial soils.
For detailed design, the following recommendations are provided:
Unless otherwise specified in Section 6.9, use a maximum cut slope angle of 3H:1V.
Cuts that encounter seepage require field review by a geotechnical engineer and may need to be
protected from piping erosion by the placement of a granular drainage blanket on the face of the
slope from the base of the ditch to a minimum of 2 m above the seepage zone.
Fine-grained soil from cuts within the project alignment are unsuitable for re-use and should be
considered waste.
Coarse-grained soil from cuts may be used for construction borrow purposes provided laboratory
testing is conducted on sampled material, and results confirm construction borrow material
specifications are met.
Cut areas should be hydro-seeded with an appropriate vegetation seed mix as soon as possible
after soil disturbance is complete.
Geotechnical Assessment and Design
Bear Flat Cache Creek Segment (West)
Project # KX05280503| 2/19/2020 Page 13
6.5.1 Sta. 42+000 to Sta. 42+230
A maximum slope of 2H:1V is recommended for cuts within coarse-grained material, and 1.5H:1V for cuts
within shale bedrock. Where bedrock is exposed there is potential acid rock drainage and metal leaching.
Where bedrock is exposed and/or wasted it should be treated as potentially acid generating. Should
significant surface exposures of shale remain after excavation, they could likely be appropriately treated
by backfill cover as needed.
It is also anticipated that the lower portions of cuts will encounter significant groundwater, likely perched
on the underlying bedrock. This groundwater has the potential to cause piping failures in face of cuts in
sand and gravel. It is therefore recommended that such groundwater areas be covered with granular
drainage blankets, which could also be tied into granular cover treatment for exposed potentially acid
generating shale bedrock. It is recommended that buried trench drains be installed along the ditch line
through these areas to direct groundwater away from the subgrade. Further details and a typical section
will be developed as detailed design proceeds.
Further to the groundwater issue, it is anticipated that interception of groundwater by the boat launch
access road may affect the groundwater discharge currently known as Watson Spring. Depending on the
future required use of Watson Spring, this may or may not be a concern. If flow disruption is a concern,
then a specific and detailed hydrogeologic assessment of the potential interaction between the road
works drainage and the spring will be required.
6.6 GEOTEXTILE AND BIAXIAL GEOGRID SPECIFICATIONS
Where non-woven geotextiles are required, the recommended specifications listed in Table 6-1, below
should be used.
Table 6-1: Non-Woven Geotextile Specifications
1. Elongation > 50%, as per ASTM D4632
2. Based on minimum average roll values (as per ASTM C 4759) in the weaker principal direction
3. Based on maximum average roll values
Where geogrid is required for local subgrade improvement during construction, the recommended
specifications for a biaxial polypropylene geogrid are provided in Table 6-2, below.
Property Test Method Class 1 Class 2
Material Type Non-Woven1 Non-Woven1
Grab Tensile Strength2 ASTM D 4632 ≥ 900 N ≥ 700 N
Sewn Seam Strength2 ASTM D 4632 ≥ 810 ≥ 630 N
Tear Strength2 ASTM D 4533 ≥ 350 ≥ 250 N
Puncture Strength2 ASTM D 6241 ≥ 1925 ≥ 1375 N
Permittivity ASTM D4491 ≥ 0.2 sec-1 ≥ 0.1 sec-1
Apparent Opening Size3 ASTM D 4751 < 0.43 mm < 0.22 mm
Recommended Application + 50 kg class riprap
drainage layers
subgrade separation
- 50 kg class riprap
Geotechnical Assessment and Design
Bear Flat Cache Creek Segment (West)
Project # KX05280503| 2/19/2020 Page 14
Table 6-2: Biaxial Polypropylene Geogrid Specifications
Property Test Method Value
Tensile Strength @ 5% Strain, Machine Direction1 ASTM D 6637 ≥ 11.8 kN/m
Tensile Strength @ 5% Strain, Cross Machine Direction1 ASTM D 6637 ≥ 18.8 kN/m
Maximum Aperture Size 50 mm
Minimum Aperture Size 15 mm
Flexural Stiffness1 ASTM D 7748 ≥ 700 g-cm
Roll Width 4.0 +/- 0.1 m 1. Based on minimum average roll values (as per ASTM C4759).
6.7 PAVEMENT STRUCTURE
The recommended pavement structure is dependent on the nature of the soil subgrade that will be
encountered (in cuts) or constructed (fills). Table 6-3 provides a recommended pavement structure for the
new highway alignment and boat launch access road, for two different subgrade conditions (Type A for
well-drained granular subgrades, Type B for poorly drained and/or fine-grained subgrades).
Table 6-3: Recommended Minimum Pavement Structure Thickness
It is currently anticipated that the recommended Type B structure would be used for the entire alignment
segment. In cases where subgrade fill meets the gradation for SGSB, the thinner Type A structure could
be used. It is anticipated that granular soils, as well as weathered shale bedrock, will be encountered
during planned earthworks for the boat launch access road. Generally, a Type A structure should be
suitable to use for most of the boat launch access road. However, in areas where groundwater and
weathered shale will be encountered, a Type B structure is recommended. Additionally, a groundwater
interception subdrain may be required along upgradient ditch lines.
6.8 WASTE DISPOSAL
The following procedures are recommended for general siting and placing waste from unsuitable or
surplus soil materials generated by the project. Specific disposal scenarios different from below should be
assessed on a case by case basis by a geotechnical engineer.
Waste materials should only be placed on slopes with a gradient of 10° (approx. 5.7H:1V) or less
and should not be placed in the vicinity of the crests of other slopes where they could have a de-
stabilising influence.
Do not site waste areas within or near environmentally sensitive locations such as riparian zones,
seepage zones, or where the waste will cause ponding of water or redirection of drainage patterns
(including ditches).
Waste materials should be placed with a maximum slope of 3H:1V, and to a maximum height of
3 m. Place the waste in maximum 1 m thick lifts and level with tracked equipment, as required.
Do not site waste piles adjacent to existing and proposed road fills, where practicable. Waste piles
placed adjacent to road fills are often encountered during future road widening and upgrading
projects, frequently leading to costly removal (and schedule delays) during construction.
Subgrade Type Pavement
Structure Asphalt (AP)
Crushed Base
Course SGSB
Well Drained Granular Soils (sand
and gravel <10% fines) A 125 mm 300 mm 300 mm
Poorly Drained or Fine-Grained
Soils (>10% fines) B 125 mm 300 mm 600 mm
Geotechnical Assessment and Design
Bear Flat Cache Creek Segment (West)
Project # KX05280503| 2/19/2020 Page 15
Waste piles placed adjacent to road fills should not block drainage from existing fills and should be
kept at least 1 m below existing or proposed road pavement structure subgrade and/or any other
granular fills that are likely to transmit drainage.
Contour the waste material to promote surface drainage. To maintain positive drainage from the
fill surface while allowing for a long-term settlement of the loosely placed fill, use a minimum 10%
cross fall slopes to crown the waste material.
Use appropriate short-term measures to control off-site transport of fines in runoff (such as silt
fencing). Maintain the short-term controls until effective long-term measures (such as vegetation
cover) are established.
Subject to relevant environmental and land use requirements, disposal of surplus excavation material
(waste) is not anticipated to be a geotechnical concern, especially if deposited on fluvial terrace areas and/or
below the reservoir inundation level. Surplus material should not be disposed along the Cache Creek valley
slope crest, the main Peace River Valley sidewall slope located above and to the north of the proposed
alignment and/or along the crests of the terrace slopes down towards the Peace River to the south, as these
areas may be unstable.
6.9 DETAILED GEOTECHNICAL RECOMMENDATIONS BY STATION
SECTION
A summary of geotechnical conditions encountered, and station-specific recommendations are provided
in Table 6-4 on the following pages.
Geotechnical Assessment and Design
Bear Flat Cache Creek Segment (West)
Project # KX05280503| 2/19/2020 Page 16
Table 6-4: Detailed Geotechnical Recommendations by Station Section
Station Range Reference Geometric
Design Configuration
Representative
Geotechnical
Investigation
Anticipated Subsurface Conditions Geotechnical Recommendations From To
403+590 See Watson Spring Boat Launch Access Road
HIGHWAY 29 REALIGNMENT
404+260 404+584
Scratch Grade Transition from
the Cache Creek West Segment
Low Cuts and Fills < 2 m
depth/height
TP16-A-031
TH16-A-032
Upper 0.1 to 0.3 m: TOPSOIL.
Below TOPSOIL: 0.6 to 1.4 m of SILT/CLAY.
Below SILT/CLAY: SAND and GRAVEL with cobbles to depths ranging from at least 3.4
to 3.7 m below ground surface.
Shale bedrock was not encountered.
Groundwater not encountered.
Stripping: Typically, 0.3 m, maybe locally deeper.
Subgrade to be reviewed and approved by a geotechnical engineer.
Max Fill Slopes 3H:1V if SILT/CLAY left in-situ. If sub-excavation of SILT/CLAY (0.6
to 1.4 m) undertaken Max Fill Slopes 1.5H:1V. Use granular fill.
Max Cut Slopes 3H:1V in SILT/CLAY.
Estimated Waste: 100%
404+584 405+150 Fill up to 2 m in height
TH16-A-033
TP18-A-029
TP18-A-030
TP18-A-031
TP18-A-032
Upper 0.1 to 0.3 m: TOPSOIL.
Below TOPSOIL: 0.1 to 1.2 m of SILT/CLAY, decreasing thickness to the east.
Below SILT/CLAY: 1.1 to 3.7 m SAND and GRAVEL with cobbles over SHALE BEDROCK.
Bedrock was encountered in two test pits.
Bedrock: TP18-A-031 (1.8 m – EL. 474.4 m), TP18-A-032 (1.7 m – EL. 474.9 m
Groundwater not encountered.
Stripping: Typically, 0.1 to 0.3 m.
Subgrade to be reviewed and approved by a geotechnical engineer.
Max Fill Slopes: 3H:1V. Use granular fill.
Max Fill Slopes 3H:1V if SILT/CLAY left in-situ. If sub-excavation of SILT/CLAY (0.1
to 1.4 m) undertaken Max Fill Slopes 1.5H:1V.
Max Ditch Cut Slopes: 3H:1V in SILT/CLAY.
Estimated Waste: 100%
405+150 405+950 Low Cuts and Fills < 2 m
depth/height
BH18-A-054
TP18-A-033
TP18-A-034
BH18-A-055
TP18-A-035
TP18-A-036
TP18-A-037
BH18-A-056
Upper 0.1 to 0.2 m: TOPSOIL.
Below TOPSOIL: 1.0 to 7.8 m of SAND and GRAVEL with cobbles over SHALE
BEDROCK, increasing thickness to the east.
Bedrock was encountered in three boreholes and one test pit.
Bedrock: BH18-A-054 (1.1 m – EL. 476.3 m), TP18-A-033 (3.2 m – EL. 475.2, BH18-A-
055 (7.8 m – EL, 472.4 m), and BH18-A-056 (7.4 m – 471.3 m),
Groundwater was encountered in one borehole BH18-A-055 (6.4 m – EL. 473.8 m).
Stripping: Typically, 0.1 to 0.2 m, maybe locally deeper.
Subgrade to be reviewed and approved by a geotechnical engineer.
Max Fill Slopes 2H:1V. Use granular fill.
Max Cut Slopes: 1.5H:1V in granular soils.
Estimated Waste: 5%.
405+950 406+570
Cuts up to 8 m in height on left
and up to 3 m in height on right
of highway.
TP18-A-038
TP18-A-039
TP18-A-040
TP18-A-041
TP18-A-042
BH18-A-057
BH18-A-058
BH18-A-059
BH18-A-060
Upper 0.1 to 0.4 m TOPSOIL.
Below TOPSOIL: 2.9 to 11.7 m SAND and GRAVEL with cobbles over SHALE BEDROCK.
Bedrock was encountered in four boreholes. Borehole BH18-A-060 encountered 1.m
of SAND below the topsoil.
Bedrock: BH18-A-057 (11.9 m – EL. 464.7 m), BH18-A-058 (4.8 m – EL 468.7 m), BH18-
A-059 (7.4 m – EL. 468.5 m), and BH18-A-060 (3.1 m – EL. 472.6 m)
Groundwater encountered in some locations (approx. 472.3 m in BH18-A-057; 470.6 in
BH18-A-058; 470.1 m in BH18-A-059)
Stripping: Typically, 0.1 to 0.4 m.
Max Cut Slopes 1.5H:1V in SAND and GRAVEL.
Max Cut Slope 2H:1V in SAND.
Potential for additional granular borrow if cuts are expanded.
Estimated Waste: 5%
406+570 406+744.010 Fills up to 4 m in height
TH18-A-043
TH18-A-044
BH18-A-061
BH18-A-062
Upper 0.1 to 0.4 m: TOPSOIL.
Below TOPSOIL: 3.4 to 5.1 m SAND and GRAVEL with cobbles over SHALE BEDROCK.
BH18-A-061 encountered 0.2 m of low plasticity clay at 2.1 m.
Bedrock was encountered in two test holes and one borehole.
Bedrock: TH18-A-043 (3.7 m – EL. 468 m), TH18-A-044 (3.8 m – EL 466.8 m), and BH18-
A-062 (5.3 m – EL. 465.4 m).
Groundwater was encountered in one test hole TH18-A-043 (2.1 m - EL. 469.6 m).
Stripping: Typically, 0.1 to 0.3 m.
Subgrade to be reviewed and approved by a geotechnical engineer.
Max Fill Slopes 2H:1V. Use granular fill.
Geotechnical Assessment and Design
Bear Flat Cache Creek Segment (West)
Project # KX05280503| 2/19/2020 Page 17
Station Range Reference Geometric
Design Configuration
Representative
Geotechnical
Investigation
Anticipated Subsurface Conditions Geotechnical Recommendations From To
WATSON SPRING BOAT LAUNCH ACCESS ROAD
42+000 42+030
Scratch Grade Transition from
the Highway 29 intersection
Low Cuts and Fills < 1 m
depth/height
TP16-A-0251
Upper 2.7 m GRAVEL with cobbles.
Below GRAVEL: >2.0 m GRAVEL and SAND with cobbles.
Bedrock not encountered.
Groundwater not encountered.
Stripping: Approximately 0.3 m
Max Cut Slopes: 1.5H:1V in granular soils.
Max Fill Slopes: 2H:1V. Use granular fills.
Estimated Waste: 5%
42+030 42+070
Left: Minor drainage cuts < 2 m
in depth.
Right: Fills up to 6 m in height
BH18-WS-0041
BH18-WS-0051
Upper 7.9 to 8.4 m: GRAVEL and SAND with cobbles.
Below GRAVEL and SAND: 0.8 to 1.2 m of low plasticity CLAY.
Below CLAY: 1.5 to 1.8 m of GRAVEL and SAND over SHALE BEDROCK.
Bedrock at elevation 469.0 to 468.2 m.
Groundwater encountered at approximately 471.2 m in BH18-WS-004 and 468.3 m in
BH18-WS-005.
Max Cut Slopes: 1.5H:1V in granular soils.
Max Fill Slopes: 2H:1V. Use granular fills.
Estimated Waste: 5%
42+070 42+180 Cuts up to 9 m in depth BH18-WS-004
BH18-WS-005
Upper 7.9 to 8.4 m: GRAVEL and SAND with cobbles.
Below GRAVEL and SAND: 0.8 to 1.2 m of low plasticity CLAY.
Below CLAY: 1.5 to 1.8 m of GRAVEL and SAND over SHALE BEDROCK.
Bedrock was encountered in two boreholes.
Bedrock: BH18-WS-004 (11.1 m – EL. 469.0 m), and BH18-WS-005 (10.5 m – EL
468.2 m),
Groundwater encountered at approximately 471.2 m in BH18-WS-004 and 468.3 m in
BH18-WS-005.
Max Cut Slopes: 2.0H:1V in granular soils.
Use 1.5H:1V in weathered shale bedrock.
Requires sub drainage and drainage blanket on slope face over groundwater
discharge areas on slope face (Sta. 42+145 to Sta. 42+180).Bedrock exposure in
lower portion of cut will require treatment as potentially acid generating
(Sta. 42+150 to Sta. 42+180)
GEOTECHNICAL ENGINEER TO REVIEW SUBGRADE AT THE TIME OF
CONSTRUCTION.
Estimated Waste: 10%
42+180 42+230 Left: Minor fills < 2 m in height
Right: Cuts up to 7 m in depth TP18-WS-0021
Upper 0.5 m: GRAVEL, sandy, over SHALE BEDROCK.
Bedrock was encountered in one test pit.
Bedrock: TP18-WS-002 (10.5 m – EL. 468.2 m),
Groundwater not encountered at nearest test pit which is approximately 45 m west of
this section of highway.
Max Cut Slopes: 2.0H:1V in granular soils.
Use 1.5H:1V in weathered shale bedrock. Max Fill Slopes: 2H:1V. Use granular fills.
Requires sub drainage and drainage blanket on slope face over groundwater
discharge areas on slope face (Sta. 42+180 to Sta. 42+230).
Bedrock exposure in lower portion of cut will require treatment as potentially acid
generating (Sta. 42+180 to Sta. 42+230)
GEOTECHNICAL ENGINEER TO REVIEW SUBGRADE AT THE TIME OF
CONSTRUCTION.
Estimated Waste: 50%
1. Nearest exploratory hole, may not be representative of ground conditions on the access road.
Geotechnical Assessment and Design
Bear Flat Cache Creek Segment (West)
Project # KX05280503| 2/19/2020 Page 19
REFERENCES Amec Foster Wheeler. (5 March 2012). Preliminary Geotechnical Assessment Proposed Bear Flat Segment
Highway 29 Definition Design.
Amec Foster Wheeler. (19 January 2017). Gravel Investigation – Lower Cache Creek Gravel Borrow
Prospect Highway 29: Bear Flat – Cache Creek.
Amec Foster Wheeler. (27 January 2017, revised 20 April 2018). Gravel Resource Assessment Peaceview Pit
Prospect Highway 29 Bear Flat to Cache Creek.
Amec Foster Wheeler. (21 July 2017). Geotechnical Assessment and Design Highway No. 29 Bear Flat –
Cache Creek.
Bidwell, A.K., May 1999, “The Engineering Geology of the Fort St. John Area”, Master of Engineering
Report, University of Alberta.
Hartman, G.M.D. and Clague, J.J., 25 June 2008, “Quaternary Stratigraphy and Glacial History of the Peace
River Valley, Northeast British Columbia”, Canadian Journal of Earth Science, Volume 45, pages
549-564.
Klohn Crippen Berger and SNC-Lavalin Inc., January 2003, “Peace Cascade Development, Prefeasibility for
a Cascade of Low Consequence Structures as an Alternative to Site C”, Technical Report.
Wood Environment and Infrastructure Solutions. (14 Aug 2019). Geotechnical Data Report Highway 29,
Bear Flat Cache Creek Segment.
Appendix A
Figures
E
L4000O43 DesignAlignment
Hwy 29
Lower Cache CreekGravel Borrow Prospect
Ha l f
w a y R i ve
r
CacheCreekEast
CacheCreekWest Watson Spring
Boat LaunchPeaceview PitProspect
C a c h e C r e e k
C h a r l i eL a k e
P e a c eR i v e r
Notes:1. L4000O43 centreline alignment provided by R.F. Binnie & Associates CAD file 'ACAD-20200108 - Plan.dwg', received 27 January 2020.2. Watson Spring boat launch location provided by Moffat & Nichol CAD file '959806-FIG-01.dwg', received 22 May 2019.3. Bing Maps Road - © 2018 Microsoft Corporation © 2018 HERE.
LegendWatson Spring Boat Launch
L4000O43 Centreline AlignmentE
!(
!(
!(
!(
!(
_̂
VancouverKamloops
ChetwyndFort St John
PrinceGeorge
ProjectLocation
This drawing was originally produced in colour.
CLIENT:
S:\Internal\KX052805-GIS\4CacheCreek\CCEW-AlignGeotechInvest-DetDes-Fig1-SiteLocationPlan.mxd
SCALE:
PROJECTION:
DATUM:
CHK'D BY:
DWN BY: TITLE:
PROJECT:REV NO.:
PROJECT NO.:
DATE:
HIGHWAY NO. 29BEAR FLAT CACHE CREEKUTM Zone 10
NAD 83
KS
BB SITE LOCATION PLANGEOTECHNICAL INVESTIGATION
A
FIGURE 1
KX05280503
FEBRUARY 2020
$
1:200,000
0 4 8 12 162km
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
WoodEnvironment & Infrastructure Solutions
a Division of Wood Canada Limited (Wood)
BC HYDRO c/o R.F. BINNIE &ASSOCIATES LTD.
402+500
403+000
403+500
404+000
404+500
405+000
LIMIT OF CONSTRUCTION
404+260.000
42+100
42+200
LIMIT OF CONSTRUCTION42+230.000
LIMIT OF CONSTRUCTION
42+000.000
")
")
") ")
")
")
")
")
")
")")
")
")
!A
")
")
!A !A
")
!A
!A
!A!A
!A
!A
")
")
")
")
")
")
")
Watson
Road
Watson Road
Highway 29
Watson SpringBoat Launch
(See Note 1)
TH16-A-032 TH16-A-033
TP16-A-030TP16-A-031
TP16-A-025
BH18-WS-002 BH18-WS-003
BH18-WS-004
BH18-WS-005
TP18-A-029TP18-A-030
TP18-A-031
TP18-A-032
TP18-WS-002
PV16-010
PV16-015
PV16-011 PV16-013PV16-014
PV16-009
PV16-017
PV16-018
PV16-012
PV16-016
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
a Division of Wood Canada Limited (Wood)Wood Environment & Infrastructure Solutions
PROJECTION:
DATUM:
CHK'D BY:
DWN BY:
This drawing was originally produced in colour.
CLIENT: DATE:
KX05280503
FEBRUARY 2020
A
SITE PLAN WITH ORTHOPHOTOGEOTECHNICAL INVESTIGATION
HIGHWAY NO. 29BEAR FLAT CACHE CREEK
TITLE:
PROJECT:
UTM Zone 10
NAD 83
KS
BBPROJECT NO.:
REV NO.:
1:6,000S:\Internal\KX052805-GIS\4CacheCreek\CCEW-AlignGeotechInvest-DetDes-Fig2-SitePlan-Ortho.mxd
SCALE:
0 100 200 300 40050m
Notes:1. Hole location provided by handheld GPS.2. L4000O43 centreline alignment and slope stake lines provided by R.F. Binnie & Associates Ltd. CAD file 'ACAD-20200108 - Plan.dwg', received 27 January 2020.3. L42-LINE centreline alignment and slope stake lines provided by R.F. Binnie & Associates Ltd. CAD file 'ACAD-SECT-L42A10-BFCC-15-0674- Model.dwg', received 13 September 2019.4. Maximum Normal Reservoir Level (461.8 m) downloaded from BC Hydro SharePoint 11 April 2018.5. Orthophoto imagery (foreground) provided by BC Hydro 9 January 2018.6. Orthophoto imagery (background; 2009) provided by R.F. Binnie & Associates Ltd., received 1 June 2011.
BC HYDRO c/o R.F. BINNIE & ASSOCIATES LTD.Legend!A 2018 Borehole Location
") 2018 Test Pit Location
!A 2016/2017 Borehole Location") 2016/2017 Test Pit Location
") 2016 Pavement Core Location
L4000O43 Centreline AlignmentL4000O43 Slope Stake LineL42-LINE Centreline AlignmentL42-LINE Slope Stake LineMaximum Normal Reservoir Level (461.8 m)
$12
1:70,000
FIGURE 21 of 2SHEET NO.
405+000
405+500 406+000 406+500
407+000
407+500
408+000
LIMIT
OF CO
NSTR
UCTIO
N
406+
744.0
10
")
")
")
")
")
")
")
")
")
")
")
!A
!A
!A
!A
!A!A
!A
!A!A!A
!A!A
!A
!A
!A
")
")
")
")
")
")
")
")
")")
")")
")
")
")
Highway 29
Ca c h e
Cr e
ek
(See Note 1)
BH16-A-013 BH16-A-015
TP18-A-033
TP18-A-034
TP18-A-035TP18-A-036
TP18-A-037TP18-A-038
TP18-A-039 TP18-A-040
TP18-A-041
TP18-A-042
TP18-A-043
BH18-A-054
BH18-A-055BH18-A-056
BH18-A-057
BH18-A-058
BH18-A-059
BH18-A-060BH18-A-061
BH18-A-062BH18-A-063
TH18-A-043
TH18-A-044
PV16-024PV16-022
PV16-025
PV16-028
PV16-026
PV16-023
PV16-021PV16-020
PV16-019
PV16-027
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
a Division of Wood Canada Limited (Wood)Wood Environment & Infrastructure Solutions
PROJECTION:
DATUM:
CHK'D BY:
DWN BY:
This drawing was originally produced in colour.
CLIENT: DATE:
KX05280503
FEBRUARY 2020
A
SITE PLAN WITH ORTHOPHOTOGEOTECHNICAL INVESTIGATION
HIGHWAY NO. 29BEAR FLAT CACHE CREEK
TITLE:
PROJECT:
UTM Zone 10
NAD 83
KS
BBPROJECT NO.:
REV NO.:
1:6,000S:\Internal\KX052805-GIS\4CacheCreek\CCEW-AlignGeotechInvest-DetDes-Fig2-SitePlan-Ortho.mxd
SCALE:
0 100 200 300 40050m
Notes:1. Hole location provided by handheld GPS.2. L4000O43 centreline alignment and slope stake lines provided by R.F. Binnie & Associates Ltd. CAD file 'ACAD-20200108 - Plan.dwg', received 27 January 2020.3. L42-LINE centreline alignment and slope stake lines provided by R.F. Binnie & Associates Ltd. CAD file 'ACAD-SECT-L42A10-BFCC-15-0674- Model.dwg', received 13 September 2019.4. Maximum Normal Reservoir Level (461.8 m) downloaded from BC Hydro SharePoint 11 April 2018.5. Orthophoto imagery (foreground) provided by BC Hydro 9 January 2018.6. Orthophoto imagery (background; 2009) provided by R.F. Binnie & Associates Ltd., received 1 June 2011.
BC HYDRO c/o R.F. BINNIE & ASSOCIATES LTD.Legend!A 2018 Borehole Location
") 2018 Test Pit Location
!A 2016/2017 Borehole Location") 2016/2017 Test Pit Location
") 2016 Pavement Core Location
L4000O43 Centreline AlignmentL4000O43 Slope Stake LineL42-LINE Centreline AlignmentL42-LINE Slope Stake LineMaximum Normal Reservoir Level (461.8 m)
$12
1:70,000
FIGURE 22 of 2SHEET NO.
403+900 404+000 404+100 404+200 404+300 404+400
470
480
490
470
480
490
403+950 404+050 404+150 404+250 404+350 404+450
Elevation (m
)
Station (m)
Elevation (m
)
403+850403+800
40
4+
26
0.0
00
LIM
IT
O
F
CO
NS
TR
UC
TIO
N
0.31
3.7
TSCL
GP
19152222
21 46
m
TP16-A-031WW PL LL
END
N/A
PROJECTION:
N/A
DATUM:
PROFILE
STATION 403+800 TO 404+450
GEOTECHNICAL INVESTIGATION
PROJECT:
TITLE:
REV. NO.:
PROJECT NO.:
KX05280503
A
CLIENT:
DWN BY:
CHK'D BY:
FEBRUARY 2020
DATE:
SCALE:
KS
AS NOTED
BB
HIGHWAY NO. 29
BEAR FLAT CACHE CREEK
This drawing was originally produced in colour.
FIGURE 3
SHEET NO. 1 of 6
Notes:
1. SPT N values and associated laboratory testing data provided with the Sticklogs may not be presented
at representative elevations. Please refer to Appendix B – Investigation Logs for additional details.
2. L4000O43P6 centreline alignment profile and existing ground profile provided by R.F. Binnie &
Associates Ltd. CAD file 'ACAD-20200108 - Profile.dwg', received 8 January 2020.
Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited (Wood)
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
BC HYDRO c/o R.F. BINNIE & ASSOCIATES LTD.
0m 25 50 75 100
H 1 : 2000
V 1 : 400
0m 5 10 15 20
Legend
L4000O43P6 Centreline Alignment Profile
Existing Ground Profile at Centreline
Maximum Normal Reservoir Level (461.8 m)
404+600 404+700 404+800 404+900 405+000 405+100
460
470
480
460
470
480
404+550 404+650 404+750 404+850 404+950 405+050
Elevation (m
)
Station (m)
Elevation (m
)
404+500404+450
TSCH
GP
END
0.31.2
4.9
232122
3
26 54
m
TP18-A-029WW PL LL
TSCL
GW
END
0.31
4.2
19122
4
m
TP18-A-030WW
TSCL GM1
SM1 BREND
0.20.31.71.82.8
181911
m
TP18-A-031WW TS
MLCH GC2
BREND
0.20.40.61.72.4
139
139
m
TP18-A-032WW
0.31.7
3.4
TSCH
GP
81351
79
191713151422
30 57
m
TH16-A-032N WW PL LL
0.3
3
TS
GP28
R
R
2031
3
m
TH16-A-033
N WW
END
END
(See Note 1)
N/A
PROJECTION:
N/A
DATUM:
PROFILE
STATION 404+450 TO 405+100
GEOTECHNICAL INVESTIGATION
PROJECT:
TITLE:
REV. NO.:
PROJECT NO.:
KX05280503
A
CLIENT:
DWN BY:
CHK'D BY:
FEBRUARY 2020
DATE:
SCALE:
KS
AS NOTED
BB
HIGHWAY NO. 29
BEAR FLAT CACHE CREEK
This drawing was originally produced in colour.
FIGURE 3
SHEET NO. 2 of 6
Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited (Wood)
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
BC HYDRO c/o R.F. BINNIE & ASSOCIATES LTD.
0m 25 50 75 100
H 1 : 2000
V 1 : 400
0m 5 10 15 20
Notes:
1. Hole location provided by handheld GPS.
2. SPT N values and associated laboratory testing data provided with the Sticklogs may not be presented
at representative elevations. Please refer to Appendix B – Investigation Logs for additional details.
3. L4000O43P6 centreline alignment profile and existing ground profile provided by R.F. Binnie &
Associates Ltd. CAD file 'ACAD-20200108 - Profile.dwg', received 8 January 2020.
Legend
L4000O43P6 Centreline Alignment Profile
Existing Ground Profile at Centreline
Maximum Normal Reservoir Level (461.8 m)
405+200 405+300 405+400 405+500 405+600 405+700
470 470
405+250 405+350 405+450 405+550 405+650 405+750
Elevation (m
)
Station (m)
Elevation (m
)
405+100 405+150
480 480
460 460
450 450
440 440
430 430
TSGP-GM
BR
END
0.11.1
4.4
1632
62RRR
71817151095
m
BH18-A-054N WW SP
GP
BREND
Water Level6/7/2018
3.5
7.89
24364029424341
27
27
R
2333443
3
886
m
BH18-A-055N WW
TS
GP
END
0.1
3.23.4
5
43
10
m
TP18-A-033WW
TS
GP
END
0.2
5
56
4
4
4
m
TP18-A-034WW TS
SM2
GP-GM
0.10.2
5
444
44
m
TP18-A-035WW
TS
GP
END
0.1
4.9
34
544
m
TP18-A-036WW
BREND
TS
GP
BR
0.2
5.2
41.5
12
50
34
R
R
R
0.06 / 0.19
0.15 / 0.27
0.08 / 0.23
0.10 / 0.31
0.06 / 0.32
0.18 / 0.59
0.07 / 0.62
0.14 / 0.38
0.03 / 0.48
0.13 / 0.76
0.09 / 0.73
0.18 / 0.56
1.30 / 1.78
0.15 / 1.24
0.25 / 0.70
0.17 / 0.49
0.49 / 0.89
0.16 / 0.36
0.13 / 0.97
0.13 / 0.97
0.65 / 0.83
m
BH16-A-013N WW Is50Is50
Dia/Axial
END
(MPa)
0.06 / 0.19
N/A
PROJECTION:
N/A
DATUM:
PROFILE
STATION 405+100 TO 405+750
GEOTECHNICAL INVESTIGATION
PROJECT:
TITLE:
REV. NO.:
PROJECT NO.:
KX05280503
A
CLIENT:
DWN BY:
CHK'D BY:
FEBRUARY 2020
DATE:
SCALE:
KS
AS NOTED
BB
HIGHWAY NO. 29
BEAR FLAT CACHE CREEK
This drawing was originally produced in colour.
FIGURE 3
SHEET NO. 3 of 6
Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited (Wood)
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
BC HYDRO c/o R.F. BINNIE & ASSOCIATES LTD.
0m 25 50 75 100
H 1 : 2000
V 1 : 400
0m 5 10 15 20
Notes:
1. SPT N values and associated laboratory testing data provided with the Sticklogs may not be presented
at representative elevations. Please refer to Appendix B – Investigation Logs for additional details.
2. L4000O43P6 centreline alignment profile and existing ground profile provided by R.F. Binnie &
Associates Ltd. CAD file 'ACAD-20200108 - Profile.dwg', received 8 January 2020.
Legend
L4000O43P6 Centreline Alignment Profile
Existing Ground Profile at Centreline
Maximum Normal Reservoir Level (461.8 m)
405+900 406+000 406+100 406+200 406+300 406+400
470
480
470
480
405+850 405+950 406+050 406+150 406+250 406+350
Elevation (m
)
Station (m)
Elevation (m
)
405+800405+750
490 490
TS
GP
END
0.4
3.7
33
44
m
TP18-A-041WW
TS
GP-GM
GP
BREND
0.2
4.4
7.4
9.1
69R78
125R534767
R
R
R
832232
2
910
8
m
BH18-A-056N WW
TS
GP
GP-GM
GM1
BREND
Water Level5/19/2018
0.21.4
7.3
11.9
13.5
526945575249
64
R
92R
46
R
R
233423
2
6
9
8
9
12
m
BH18-A-057N WW
TSSM4
GP
END
0.10.2
4.6
71
2
2
m
TP18-A-037WW TS
GW
END
0.1
4.4
2
2
34
m
TP18-A-038WW
TSSM1
GP
END
0.10.1
4.4
2
24
3
m
TP18-A-039WW TS
GP
END
0.1
5.5
228343
4
m
TP18-A-040WW
N/A
PROJECTION:
N/A
DATUM:
PROFILE
STATION 405+750 TO 406+400
GEOTECHNICAL INVESTIGATION
PROJECT:
TITLE:
REV. NO.:
PROJECT NO.:
KX05280503
A
CLIENT:
DWN BY:
CHK'D BY:
FEBRUARY 2020
DATE:
SCALE:
KS
AS NOTED
BB
HIGHWAY NO. 29
BEAR FLAT CACHE CREEK
This drawing was originally produced in colour.
FIGURE 3
SHEET NO. 4 of 6
Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited (Wood)
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
BC HYDRO c/o R.F. BINNIE & ASSOCIATES LTD.
0m 25 50 75 100
H 1 : 2000
V 1 : 400
0m 5 10 15 20
Notes:
1. SPT N values and associated laboratory testing data provided with the Sticklogs may not be presented
at representative elevations. Please refer to Appendix B – Investigation Logs for additional details.
2. L4000O43P6 centreline alignment profile and existing ground profile provided by R.F. Binnie &
Associates Ltd. CAD file 'ACAD-20200108 - Profile.dwg', received 8 January 2020.
Legend
L4000O43P6 Centreline Alignment Profile
Existing Ground Profile at Centreline
Maximum Normal Reservoir Level (461.8 m)
406+500 406+600 406+700 406+800 406+900 407+000
430
440
450
460
470
430
440
450
460
470
420 420
406+550 406+650 406+750 406+850 406+950 407+050
Elevation (m
)
Station (m)
Elevation (m
)
406+400 406+450
480 480
406+744.010
LIMIT OF
CONSTRUCTION
C a c h e C r e e k
Cross Section
Station 406+744.010
See Figure 4 Sheet 1
MNRL
TS
GPBR
END
0.21.4
3.13.8
73R3329
82RR
196
1269
12
mN WW
TS
SPCLSPBR
0.3
2.12.33.74.7
45R432572R
45
118
125
m
BH18-A-061
N WW
TS
GP
END
0.2
3.7
23
43
m
TP18-A-042WW
TS
GPCLGP
BREND
0.2
2.12.3
4.85.9
287561162064
R
32
2172689
12
m
BH18-A-058N WW
TS
GP
BREND
Water Level5/20/2018
0.2
7.4
8.9
70R5450564330
57
R
R
312222
10
71011
m
BH18-A-059N WW
TS
GP
BR
END
0.2
5.3
55
4465R85282115
62R
R
645534
13
11N/A / N/A0.36 / 0.77
N/A / N/A
N/A / N/A
N/A / N/A
N/A / N/A
N/A / N/A
N/A / N/A
0.29 / 0.22
0.27 / 0.00
0.29 / 0.42
0.28 / 0.33
0.34 / 0.39
0.31 / 0.35
0.34 / 0.42
1.08 / 1.43
0.95 / 1.28
0.56 / 1.09
0.43 / 0.65
0.18 / 0.55
0.38 / 0.38
0.44 / 0.63
0.42 / 0.45
0.37 / 0.37
0.36 / 0.51
0.30 / 0.61
0.42 / 0.46
0.57 / 0.76
0.52 / 0.82
0.78 / 0.67
0.48 / 0.39
0.22 / 0.64
m
BH18-A-062NWWIs50
Dia/AxialGP
SPBR
Water Level9/23/20183.4
3.74.6
34297
12R
4332811
m
TH18-A-043NWW TS
SP-SMSP
GM1
BR
END
0.21.22.3
3.8
21.4
16131949RR
268957
159
0.06 / 0.310.40 / 0.51
0.27 / 0.41
0.12 / 0.36
0.33 / 0.56
0.37 / 0.25
0.16 / 0.36
0.33 / 0.36
0.06 / 0.58
0.41 / 0.40
0.50 / 0.47
m
TH18-A-044NWWIs50
Dia/Axial
(MPa) (MPa)
Water Level5/21/2018
SM2
BH18-A-060
END
TS
GP -GC
BR
0.2
5.9
51.1
14
R
67
41
R
1913
2
0
5
0.01 / 0.24
0.05 / 0.24
0.06 / 0.18
0.28 / 0.34
0.14 / 0.45
0.07 / 0.25
2.21 / 1.84
0.24 / 0.64
0.11 / 0.41
0.13 / 0.52
2.24 / 1.87
0.17 / 0.41
0.60 / 1.39
0.66 / 1.21
0.27 / 0.56
0.1 / 0.25
0.24 / 0.29
0.15 / 0.25
0.17 / 0.36
0.19 / 0.36
0.21 / 0.7
0.02 / 0.52
0.06 / 0.43
0.11 / 0.85
0.10 / 0.38
0.25 / 0.44
m
BH16-A-015N WW Is50Is50
Dia/Axial
END
(MPa)
N/A
PROJECTION:
N/A
DATUM:
PROFILE
STATION 406+400 TO 407+050
GEOTECHNICAL INVESTIGATION
PROJECT:
TITLE:
REV. NO.:
PROJECT NO.:
KX05280503
A
CLIENT:
DWN BY:
CHK'D BY:
FEBRUARY 2020
DATE:
SCALE:
KS
AS NOTED
BB
HIGHWAY NO. 29
BEAR FLAT CACHE CREEK
This drawing was originally produced in colour.
FIGURE 3
SHEET NO. 5 of 6
Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited (Wood)
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
BC HYDRO c/o R.F. BINNIE & ASSOCIATES LTD.
0m 25 50 75 100
H 1 : 2000
V 1 : 400
0m 5 10 15 20
Notes:
1. SPT N values and associated laboratory testing data provided with the Sticklogs may not be presented
at representative elevations. Please refer to Appendix B – Investigation Logs for additional details.
2. L4000O43P6 centreline alignment profile and existing ground profile provided by R.F. Binnie &
Associates Ltd. CAD file 'ACAD-20200108 - Profile.dwg', received 8 January 2020.
Legend
L4000O43P6 Centreline Alignment Profile
Existing Ground Profile at Centreline
Maximum Normal Reservoir Level (461.8 m)
480
Elevation (m
)
42+125
Station (m)
475
42+10042+07542+05042+02542+000
470
42+22542+20042+17542+150
480
Elevation (m
)
475
470
465 465
460 460
Cross Section
Station 42+140
See Figure 4 Sheet 2
42+
230.000
LIM
IT
O
F
CO
NS
TR
UC
TIO
N
42+
000.000
LIM
IT
O
F
CO
NS
TR
UC
TIO
N
GP-GM
CL
GP
BR
8.4
9.6
11.1
12.5 END
Water Level10/2/2018
51
24
24
36
33
37
25
31
26
52
R
2
6
3
7
4
6
7
4
287
9
11
23 46
m
BH18-WS-004N WW PL LL
GP-GM
CL
GP-GM
BR
7.9
8.7
10.5
15.2 END
Water Level10/2/2018
44
43
31
10
27
21
29
28
58
82
2
2
2
2
2
2
3
2
4
712
N/A / N/A
N/A / N/A
N/A / N/A
0.22 / 1.06
m
BH18-WS-005N WW Is50Is50
Dia/Axial
(MPa)
GP
BR
0.5
2.9
3
17
23
m
TP18-WS-002WW
END
TS
GP
0.3
5
3
2
m
TP16-A-025WW
END
N/A
PROJECTION:
N/A
DATUM:
PROFILE
STATION 42+000 TO 42+230.2
GEOTECHNICAL INVESTIGATION
PROJECT:
TITLE:
REV. NO.:
PROJECT NO.:
KX05280503
A
CLIENT:
DWN BY:
CHK'D BY:
FEBRUARY 2020
DATE:
SCALE:
KS
AS NOTED
BB
HIGHWAY NO. 29
BEAR FLAT CACHE CREEK
This drawing was originally produced in colour.
FIGURE 3
SHEET NO. 6 of 6
Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited (Wood)
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
BC HYDRO c/o R.F. BINNIE & ASSOCIATES LTD.
Notes:
1. SPT N values and associated laboratory testing data provided with the Sticklogs may not be presented
at representative elevations. Please refer to Appendix B – Investigation Logs for additional details.
2. L42-LINE centreline alignment profile and existing ground profile at centreline provided by R.F. Binnie
& Associates Ltd. CAD file 'ACAD-SECT-L42A10-BFCC-15-0674-Model.dwg', received 13 January
2020.
Legend
L42-LINE Centreline Alignment Profile
Existing Ground Profile at Centreline
5 1510 20 25 300m
H 1 : 750
V 1 : 150
1 32 4 5 60m
-30 -25 -20 -15 -10 -5 0 5 10 15 20 25 30
470
35
470
Elevation (m
)
Elevation (m
)
Offset (m)
460 460
450 450
440 440
430 430
420 420
℄L4000O43
406+744.010
40
TSSP
CLSPBR
0.32.12.33.74.7
45R432572R
45118125
m
BH18-A-061N WW Is50Is50
Dia/Axial TS
GP
BR
0.3
5.96.6
Water Level9/21/2018
332216129R3438
87545
912
m
BH18-A-063N WW Is50Is50
Dia/AxialTS
GP
BR
0.2
5.3
55 END
4465R85282115
62R
R
645534
13
11 N/A / N/A0.36 / 0.77
N/A / N/A
N/A / N/A
N/A / N/A
N/A / N/A
N/A / N/A
N/A / N/A
0.29 / 0.22
0.27 / 0.00
0.29 / 0.42
0.28 / 0.33
0.34 / 0.39
0.31 / 0.35
0.34 / 0.42
1.08 / 1.43
0.95 / 1.28
0.56 / 1.09
0.43 / 0.65
0.18 / 0.55
0.38 / 0.38
0.44 / 0.63
0.42 / 0.45
0.37 / 0.37
0.36 / 0.51
0.30 / 0.61
0.42 / 0.46
0.57 / 0.76
0.52 / 0.82
0.78 / 0.67
0.48 / 0.39
0.22 / 0.64
m
BH18-A-062N WW Is50Is50
Dia/Axial
END
(MPa) (MPa) (MPa)
N/A
PROJECTION:
N/A
DATUM:
CROSS SECTION
STATION 406+744.010
GEOTECHNICAL INVESTIGATION
PROJECT:
TITLE:
REV. NO.:
PROJECT NO.:
KX05280503
A
CLIENT:
DWN BY:
CHK'D BY:
FEBRUARY 2020
DATE:
SCALE:
KS
AS NOTED
BB
HIGHWAY NO. 29
BEAR FLAT CACHE CREEK
This drawing was originally produced in colour.
Legend
Typical Cross Section Based on L4000O43 Centerline Alignment
Existing Ground Profile at Centreline
FIGURE 4
SHEET NO. 1 of 2
Notes:
1. SPT N values and associated laboratory testing data provided with the Sticklogs may not be presented
at representative elevations. Please refer to Appendix B – Investigation Logs for additional details.
2. Typical cross section based on L4000O43 centerline alignment and existing ground profile at
centreline provided by R.F. Binnie & Associates Ltd. CAD file 'ACAD-20200108 - Cross Sections-
Model.dwg', received 16 January 2020.
Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited (Wood)
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
BC HYDRO c/o R.F. BINNIE & ASSOCIATES LTD.
0m 2 4 6 8 10
H 1 : 250
V 1 : 500
0m 4 8 12 16 20
-20 -10 0 10 20 30
Elevation (m
)
Offset (m)
480
40 50 60
475
470
465
70 80 90 100-30
Elevation (m
)
480
475
470
465
GP-GM
CL
GP-GM
BR
7.9
8.7
10.5
15.2 END
Water Level10/2/2018
44
43
31
10
27
21
29
28
58
82
2
2
2
2
2
2
3
2
4
712
N/A / N/A
N/A / N/A
N/A / N/A
0.22 / 1.06
m
BH18-WS-005N WW Is50Is50
Dia/Axial
GP
BR
0.5
2.9
3
17
23
m
TP18-WS-002WW
(MPa)
℄L42-LINE
N/A
PROJECTION:
N/A
DATUM:
CROSS SECTION
STATION 42+140
GEOTECHNICAL INVESTIGATION
PROJECT:
TITLE:
REV. NO.:
PROJECT NO.:
KX05280503
A
CLIENT:
DWN BY:
CHK'D BY:
FEBRUARY 2020
DATE:
SCALE:
KS
AS NOTED
BB
HIGHWAY NO. 29
BEAR FLAT CACHE CREEK
This drawing was originally produced in colour.
FIGURE 4
SHEET NO. 2 of 2
Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited (Wood)
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
BC HYDRO c/o R.F. BINNIE & ASSOCIATES LTD.
Note:
1. SPT N values and associated laboratory testing data provided with the Sticklogs may not be presented
at representative elevations. Please refer to Appendix B – Investigation Logs for additional details.
2. Typical cross section based on L42-LINE centerline alignment and existing ground profile at centreline
provided by R.F. Binnie & Associates Ltd. CAD file 'ACAD-SECT-L42A10-BFCC-15-0674-Model.dwg',
received 12 September 2019.
3. Additional existing ground surface (approximate) processed from LIDAR received from BC Hydro 9
January 2018.
Legend
Typical Cross Section Based on L42-LINE Centerline Alignment
Existing Ground Profile at Centreline
0m 4 8 12 16
H 1 : 400
V 1 : 200
0m 2 4 6 8
Limitations
Geotechnical Assessment and Design
Bear Flat Cache Creek Segment (West)
Project # KX05280503| 2/19/2020
‘Wood’ is a trading name for John Wood Group PLC and its subsidiaries
Limitations
1. The work performed in the preparation of this report and the conclusions presented are subject
to the following:
a. The Standard Terms and Conditions which form a part of our Professional Services
Contract;
b. The Scope of Services;
c. Time and Budgetary limitations as described in our Contract; and
d. The Limitations stated herein.
2. No other warranties or representations, either expressed or implied, are made as to the
professional services provided under the terms of our Contract, or the conclusions presented.
3. The conclusions presented in this report were based, in part, on visual observations of the Site
and attendant structures. Our conclusions cannot and are not extended to include those portions
of the Site or structures, which are not reasonably available, in Wood’s opinion, for direct
observation.
4. Where testing was performed, it was carried out in accordance with the terms of our contract
providing for testing. Other substances, or different quantities of substances testing for, may be
present on-site and may be revealed by different or other testing not provided for in our contract.
5. The utilization of Wood’s services during the implementation of any remedial measures will allow
Wood to observe compliance with the conclusions and recommendations contained in the report.
Wood’s involvement will also allow for changes to be made as necessary to suit field conditions as
they are encountered.
6. This report is for the sole use of the party to whom it is addressed unless expressly stated
otherwise in the report or contract. Any use which any third party makes of the report, in whole or
the part, or any reliance thereon or decisions made based on any information or conclusions in
the report is the sole responsibility of such third party. Wood accepts no responsibility whatsoever
for damages or loss of any nature or kind suffered by any such third party as a result of actions
taken or not taken or decisions made in reliance on the report or anything set out therein.
7. This report is not to be given over to any third party for any purpose whatsoever without the
written permission of Wood.
8. Provided that the report is still reliable, and less than 12 months old, Wood will issue a third-party
reliance letter to parties that the client identifies in writing, upon payment of the then current fee
for such letters. All third parties relying on Wood’s report, by such reliance agree to be bound by
our proposal and Wood’s standard reliance letter. Wood’s standard reliance letter indicates that in
no event shall Wood be liable for any damages, howsoever arising, relating to third-party reliance
on Wood’s report. No reliance by any party is permitted without such agreement.