Public Service of Colorado Ponnequin Wind Farm Geothermal Technologies Program 2010 Peer Review HUMAN HEALTH SCIENCE BLDG GEO HEAT PUMP SYSTEMS Principal Investigator Source Heat Pumps Demo Projects May 20, 2010 This presentation does not contain any proprietary confidential, or otherwise restricted information. Jim Leidel Oakland University

Upload: others

Post on 24-Jan-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

1 | US DOE Geothermal Program eere.energy.gov

Public Service of Colorado Ponnequin Wind Farm

Geothermal Technologies Program 2010 Peer Review

HUMAN HEALTH SCIENCE BLDGGEO HEAT PUMP SYSTEMS

Principal Investigator

Source Heat Pumps Demo ProjectsMay 20, 2010This presentation does not contain any proprietary confidential, or otherwise restricted information.

Jim LeidelOakland University

Page 2: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

2 | US DOE Geothermal Program eere.energy.gov

• Timeline – Geothermal ground array bid package: April 2010– Geothermal ground array construction: Summer 2010– Main building construction begins: June 2010– Substantial completion: Summer 2012– Performance monitoring & reporting: 2012 through 2014

• Budget – Total project: $9,778,930– DOE share $2,738,100– Awardee share $7,040,830

• Barriers (No funds received yet)– Lack of experience with: Geothermal projects of this size, VRF

heat pumps, large solar thermal systems, & desiccant cooling• Architect / Engineer: Smithgroup• Construction Manager: Christman Company• Geothermal Specialist: Strategic Energy Solutions

Project Overview

Page 3: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

3 | US DOE Geothermal Program eere.energy.gov

Relevance/Impact of Demonstration

Geothermal Heat Pump DemonstrationUtilize a ground sourced heat pump HVAC system.

Variable Refrigerant Flow TechnologyUtilize variable refrigerant flow (VRF) heat pumps, allows for less compressors and enhanced internal heat recovery.

Solar Thermal Desiccant DehumidificationDedicated outdoor air supply units will utilize a thermally regenerated desiccant dehumidification section. A large solar thermal system along with a natural gas backup boiler will provide the thermal regeneration energy.

Page 4: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

4 | US DOE Geothermal Program eere.energy.gov

Technical Approach

Original Concept

Page 5: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

5 | US DOE Geothermal Program eere.energy.gov

Technical Approach

Water Only, No Antifreeze

Page 6: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

6 | US DOE Geothermal Program eere.energy.gov

Variable Refrigerant Flow

Page 7: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

7 | US DOE Geothermal Program eere.energy.gov

Solar Thermal Desiccant Cooling

Page 8: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

8 | US DOE Geothermal Program eere.energy.gov

Choice of Thermally Activated Technology – Desiccant Cooling

Geothermal Heat Pump Demonstration

Page 9: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

9 | US DOE Geothermal Program eere.energy.gov

Technical Approach

Page 10: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

10 | US DOE Geothermal Program eere.energy.gov

Outdoor AirIntake

Exhaust from Space

Conditioned Air to Space

Exhaust Air

Technical Approach

Page 11: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

11 | US DOE Geothermal Program eere.energy.gov

Technical Approach

Page 12: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

12 | US DOE Geothermal Program eere.energy.gov

Technical Approach

Page 13: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

13 | US DOE Geothermal Program eere.energy.gov

Page 14: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

14 | US DOE Geothermal Program eere.energy.gov

Technical Approach

Geothermal Heat Pump Demonstration

90 deg FMaximum HP Unit Inlet Fluid Temp

40 deg FMinimum HP Unit Inlet Fluid Temp

Water onlyFluid

1,225 GPMTotal Flow

FLUID INFORMATION

42 feet of headGHX Pressure Drop

53.0 deg FUndisturbed Ground Temperature *

0.83 foot2 / daySoil Diffusivity

1.23 BTU / (hr-ft-deg F) Thermal Conductivity *

20Number of Circuits

25 feetBorehole Separation

320 feetBorehole Depth

256Borehole Quantity

Vertical Closed LoopConfiguration

HEAT EXCHANGER INFORMATION

* From formation thermal conductivity test data taken July 30, 2009

Page 15: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

15 | US DOE Geothermal Program eere.energy.gov

Technical Approach

Geothermal Heat Pump Demonstration

929 hoursCooling EFLH

1,455 hoursHeating EFLH

4,920,000 BTU / hour (410 tons)Peak Cooling

2,000,000 BTU / hour (166 tons)Peak Heating

GHX CAPACITY INFORMATION

47 feet of headPurge Pressure Drop (per circuit)

75 GPMMinimum Purge Flow (per circuit)

2 feet / secondMinimum Fluid Velocity

FLUSH & PURGE INFORMATION

0.88 BTU / (hr-ft-deg F)Minimum Thermal Conductivity

Thermally Enhanced BentoniteGrout Type

GROUT INFORMATION

Page 16: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

16 | US DOE Geothermal Program eere.energy.gov

Page 17: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

17 | US DOE Geothermal Program eere.energy.gov

Page 18: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

18 | US DOE Geothermal Program eere.energy.gov

Page 19: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

19 | US DOE Geothermal Program eere.energy.gov

Accomplishments, Expected Outcomes and Progress

• Three Test Bores – Geothermal Conductivity Tests Completed• Geothermal System Design is Complete• Geothermal Bid Package Issued• Full Project Design 90% Complete• Formal Ground Breaking in April 2010

Page 20: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

20 | US DOE Geothermal Program eere.energy.gov

Project Management/Coordination

• Geothermal Well Field to be Constructed & Completed by September 2010• Site Work & Foundation Bid Package Due to be Issued in May 2010• Full Construction Bid Package Due to be Issued in Summer 2010• Substantial Completion by Summer 2012•Three Full Years of System Monitoring & Reporting

Page 21: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

21 | US DOE Geothermal Program eere.energy.gov

Project Summary

• Innovative Project with Proven Technologies, but New the United States

– Variable Refrigerant Flow Heat Pumps– Desiccant Dehumidification of Outdoor Air

Ventilation with Solar Thermal Regeneration

• Large 400 Ton System• USGBC LEED Building Gold or Platinum Rating

Page 22: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

22 | US DOE Geothermal Program eere.energy.gov

Construction Photos – Summer 2010

Page 23: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

23 | US DOE Geothermal Program eere.energy.gov

Construction Photos – Summer 2010

Page 24: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

24 | US DOE Geothermal Program eere.energy.gov

Construction Photos – Fall 2011

Page 25: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

25 | US DOE Geothermal Program eere.energy.gov

Construction Photos – Fall 2011

Page 26: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

26 | US DOE Geothermal Program eere.energy.gov

Construction Photos – Fall 2011

Page 27: Geothermal Technologies Program 2010 Peer Review...Thermal Conductivity * 1.23 BTU / (hr-ft-degF) Number of Circuits 20 Borehole Separation 25 feet Borehole Depth 320 feet Borehole

27 | US DOE Geothermal Program eere.energy.gov

Geothermal Technologies Program 2010 Peer Review

May 20, 2010

Jim LeidelOakland [email protected]

Thank youwww.oakland.edu/energy