glast large area telescope: i&t integration kickoff meeting mgse march 9th, 2004 eric m....
DESCRIPTION
Gamma-ray Large Area Space Telescope. GLAST Large Area Telescope: I&T Integration Kickoff Meeting MGSE March 9th, 2004 Eric M. Gawehn SU-SLAC MGSE Department Manager [email protected] 650 – 926 – 3622 Office 650 – 796 – 2576 Cell. AGENDA. - PowerPoint PPT PresentationTRANSCRIPT
GLAST LAT Project I&T Integration Kickoff Meeting 03/09/04
LAT I&T MGSE Page 1 of 11
GLAST Large Area Telescope: GLAST Large Area Telescope:
I&T Integration Kickoff Meeting MGSE
March 9th, 2004
Eric M. GawehnSU-SLAC
MGSE Department Manager
[email protected] – 926 – 3622 Office650 – 796 – 2576 Cell
Gamma-ray Large Gamma-ray Large Area Space Area Space TelescopeTelescope
GLAST LAT Project I&T Integration Kickoff Meeting 03/09/04
LAT I&T MGSE Page 2 of 11
AGENDAAGENDA
• MGSE Required for Assembly / Disassembly of the LAT ( SLAC Ops )– Hardware List
• Long Lead Items
– Status– Readiness Verification
• Procedures– List– Training
• Schedule
GLAST LAT Project I&T Integration Kickoff Meeting 03/09/04
LAT I&T MGSE Page 3 of 11
LAT MGSE Hdwr List, Cont.LAT MGSE Hdwr List, Cont.• Long Lead Items• LAT 4 x 4 Rotation / Support Stand (including drive system and flex coupling)• Personnel Access Platform { Interfaces to Rotation Stand Weldment }• GPR and GPR to Grid attach bracketry• Support Shaft-Flange Assemblies, GPR to Rotation / Support Stand• LAT Z Axis Vertical Lift Fixture• LAT Z Axis Horizontal Lift Fixture• Proof test weights for LAT Lift Fixture, GPR, GPR to Grid brackets, Support
Shaft Flange Assemblies and Rotation Stand• 1x4 Lift Fixture
• Short Lead Items• CAL –Z Up Lift Fixture, Complete and Ready for Use• CAL +Z Up Lift Fixture• TKR Lift Fixture – Provided by TKR• TKR Alignment System• Crane Scale; Being Modified; Will Require Re-Calibration• CAL Alignment Tool• EM-2 Single Bay Mod ( Updated TKR Interface Plate )
- Items Needed at Integration Start - Provided by Other Group, or Needed Later
GLAST LAT Project I&T Integration Kickoff Meeting 03/09/04
LAT I&T MGSE Page 4 of 11
LAT MGSE Hdwr List, Cont.LAT MGSE Hdwr List, Cont.
• Short Lead Items, Continued• CAL Alignment Rods
• TKR to TKR No Touch During Ascent Verification Tool
• CAL Inversion Stand
• Metrology Bay for Shimming E-Box Height with respect to CAL Grid Interface
• TWR ( TKR, CAL, TEM, TEM PS ) Mass Simulators
• Lift Fixture relocation dollies; Use Lead Stack dollies from EM Series
• LAT Z Axis Horizontal Support Braces / Counterweight Moment Arms
• Menning Plate Installation Equipment
• Interim Integration E-Box support brackets TBD
• ACD Low Profile Integration Stand
• Brackets to hold Lift Fixture Spreaders on top of Bonded Stores Containers
• Ambient Test Thermal Control System
• 1 x 4 EM-Calibration Unit Rotation Stand
- Items Needed at Integration Start - Provided by Other Group, or Needed Later
GLAST LAT Project I&T Integration Kickoff Meeting 03/09/04
LAT I&T MGSE Page 5 of 11
LAT MGSE ImagesLAT MGSE Images
GLAST LAT Project I&T Integration Kickoff Meeting 03/09/04
LAT I&T MGSE Page 6 of 11
LAT MGSE ImagesLAT MGSE Images
GLAST LAT Project I&T Integration Kickoff Meeting 03/09/04
LAT I&T MGSE Page 7 of 11
LAT MGSE ImagesLAT MGSE Images
ACD Low Profile
Integration Stand ACD on
8’ by 8’ Dolly
Integration Stand is Placed to Allow Range
of Motion for PAPs
GLAST LAT Project I&T Integration Kickoff Meeting 03/09/04
LAT I&T MGSE Page 8 of 11
MGSE Status Tracking MatrixMGSE Status Tracking Matrix
GLAST LAT Project I&T Integration Kickoff Meeting 03/09/04
LAT I&T MGSE Page 9 of 11
MGSE Status Tracking MatrixMGSE Status Tracking Matrix
GLAST LAT Project I&T Integration Kickoff Meeting 03/09/04
LAT I&T MGSE Page 10 of 11
LAT MGSE ProceduresLAT MGSE Procedures
• Assemble MGSE Per Design Drawings– Procedures will point to drawings – Procedures will capture trace ability for installation of Certified
Fasteners
• Special Procedures and Travelers for Qualification Steps
• Training Procedures to ensure team is ready– 4x4 Integration Stand
• For Range of Motion Checks Prior to PAP Relocation Events
– Lift Fixtures– Stand Relocations in Rm 104– Shipment Preps
GLAST LAT Project I&T Integration Kickoff Meeting 03/09/04
LAT I&T MGSE Page 11 of 11
LAT MGSE Subsystem ScheduleLAT MGSE Subsystem Schedule