GLAST LAT Project I&T PDR Presentation (IFCT Dept.) – January 9, 2002
Larry Wai
Integration and Test Organization ChartIntegration and Test Organization Chart
I&T ManagerElliott Bloom
WBS 4.1.9
I&T EngineerB. Grist
WBS 4.1.9.1
Reliability & QAD. Marsh
WBS 4.1.9.2
Environmental Test Manager
M. Lovellette
Online ManagerR. Claus
Science Verification, Analysis, and Calibration
E. do Couto e Silva
Particle Test ManagerG. Godfrey
Integration, Facilities, Configuration, and Test
L. Wai
Instrument Operations CoordinatorS. Williams
Mechanical Ground Support Equipment
TBD
I&T Preparation 4.1.9.3
EM1 Model I&T
Calibration Unit I&T 4.1.9.4
Flight LAT I&T 4.1.9.6
Mission I&T Support 4.1.9.7
I&T Preparation 4.1.9.3
EM1 Model I&T
Calibration Unit I&T 4.1.9.4
Flight LAT I&T 4.1.9.6
Mission I&T Support 4.1.9.7
I&T Preparation 4.1.9.3
Flight LAT I&T 4.1.9.6
Mission I&T Support 4.1.9.7
I&T Preparation 4.1.9.3
EM1 Model I&T
Calibration Unit I&T 4.1.9.4
Flight LAT I&T 4.1.9.6
Mission I&T Support 4.1.9.7
GLAST LAT Project I&T PDR Presentation (IFCT Dept.) – January 9, 2002
Larry Wai
Outline of TalkOutline of Talk
1. Responsibilities2. Requirements3. Operational flow4. Contamination Control5. Mechanical GSE6. Traveler implementation7. “To do” list
GLAST LAT Project I&T PDR Presentation (IFCT Dept.) – January 9, 2002
Larry Wai
ResponsibilitiesResponsibilities
1. Manufacturing support functionsa) Technician coordination, training, and support
b) Flight hardware receiving inspection
c) Hardware non-conformance reporting
d) Review of LAT handling and transportation procedures
2. Mechanical test flow implementationa) Traveler / work instruction control system for flight
hardware
b) Review of I&T mechanical GSE
c) Coordination of mechanical integration
d) Review of test plans and procedures
e) Support and oversight of LAT tests
3. Contamination control implementation
GLAST LAT Project I&T PDR Presentation (IFCT Dept.) – January 9, 2002
Larry Wai
RequirementsRequirements
1. LAT Performance Assurance Implementation Plan (LAT-MD-00039)
2. LAT Quality Manual (LAT-MD-00091)
3. LAT Contamination Control Plan (LAT-MD-00404)
4. LAT Installation Performance Verification Plan (LAT-MD-00408)
GLAST LAT Project I&T PDR Presentation (IFCT Dept.) – January 9, 2002
Larry Wai
Operational flowOperational flow
I&T ManagementElliott BloomBrian Grist
Contamination Control
TransportTestsIntegration
CAL
TRK
ACD
Technician ControlGrid
Manufacturing ManagementLarry Wai
Ossie Millican
ReceiveValidate
Store
QA ManagementDarren Marsh
NASA Flight Hardware TrainingSystem safety
Non Conformance RequirementsAudits and surveillance
GLAST LAT Project I&T PDR Presentation (IFCT Dept.) – January 9, 2002
Larry Wai
Contamination ControlContamination Control
1. Implement LAT CCP
2. Supervise technician training and conformance
3. Controlled flight hardware storage
4. Mechanical GSE control
5. Clean room procedures enforcement
6. Clean room environmental monitoring: particulate count, temperature, humidity
7. Wireless alarm system for disaster prevention: automated real time analysis of environmental data, manager (me) lives within 10 min of Integration Area
8. Tape lift, witness plate processing
GLAST LAT Project I&T PDR Presentation (IFCT Dept.) – January 9, 2002
Larry Wai
Component Contamination Specifications MatrixComponent Contamination Specifications Matrix
LAT Component:
Control Category:
ACD
(plastic scintillator tiles)
TRK
(silicon strips)
CAL
(Cesium Iodide crystals)
Molecular sources •Helium •Salt •Water
Particulate •<=class 100,000 •<=class 100,000•Misc. fallout
•<=class 100,000•Misc. fallout
Other environmental •>30% humidity
(prevent ESD)
•30-50% humidity
(prevent ESD,
prevent water contamination)
GLAST LAT Project I&T PDR Presentation (IFCT Dept.) – January 9, 2002
Larry Wai
Mechanical GSEMechanical GSE
1. Frame: connecting to Grid bosses and Frame Support Fixture
2. Worm Gear Reducers: connect to Frame and Frame Support Fixture. 360 degree rotation.
3. Frame Support Fixture: connects to floor and Frame via Worm Gear Reducers
4. TKR Unit Lift Fixture: maintains stability for Unit as it is connected to Grid.
5. CAL Unit Lift Fixture: maintains stability for Unit as it is connected to Grid.
6. CAL Container: connects to Frame and contains nitrogen flow to CAL.
7. Overhead Crane: 5 ton overhead crane for lowering subsystems and lifting integrated LAT
8. ACD Lift Fixture: connects to ACD and crane rigging.
9. Metrology Fixtures: strategic location of laser tracker balls for measurement of fiducial points
10.Fixtures for integrated LAT testing: SLAC test beam, shipping, thermal vacuum, vibration table
GLAST LAT Project I&T PDR Presentation (IFCT Dept.) – January 9, 2002
Larry Wai
GLAST Integration Area – Building 33 SLACGLAST Integration Area – Building 33 SLAC
GLAST LAT Project I&T PDR Presentation (IFCT Dept.) – January 9, 2002
Larry Wai
LAT Integration High Bay Clean Room (1)LAT Integration High Bay Clean Room (1)
GLAST LAT Project I&T PDR Presentation (IFCT Dept.) – January 9, 2002
Larry Wai
Hook Height
Maximum
Hook Height
Minimum
ACD
LAT Integration High Bay Clean Room (2)LAT Integration High Bay Clean Room (2)
GLAST LAT Project I&T PDR Presentation (IFCT Dept.) – January 9, 2002
Larry Wai
LAT Integration Fixture Conceptual Drawing (1)LAT Integration Fixture Conceptual Drawing (1)
GLAST LAT Project I&T PDR Presentation (IFCT Dept.) – January 9, 2002
Larry Wai
LAT Integration Fixture Conceptual Drawing (2)LAT Integration Fixture Conceptual Drawing (2)
GLAST LAT Project I&T PDR Presentation (IFCT Dept.) – January 9, 2002
Larry Wai
Traveler implementationTraveler implementation
1. Management uses SureTrack 3.0a from Primavera Systems
2. Wireless palm PC interface to flight hardware traveler / work instruction system
3. Flight hardware validation check-list
4. Controlled generation of Non Conformance Reports
5. Associated records from test flow implementation
6. Associated calibration records for metrology tools
7. Associated flight hardware environmental history records from contamination monitors (temperature, humidity, particulate count, tape lift/witness plate results)
GLAST LAT Project I&T PDR Presentation (IFCT Dept.) – January 9, 2002
Larry Wai
““To do” listTo do” list
1. Contamination control implementation plan
2. Technician coordination and training plan
3. Hardware test flow implementation plan
4. Validation of test flow implementation plan
5. Setup/test of (wireless) electronic traveler system
6. Work instruction development