Global Positioning Systems Directorate
23 June 2011
MGUE Briefing to Southern CA ION Chapter
Colonel Jon Anderson
Chief, GPS User Equipment Division
2
Recent Accomplishments
Modernized User Equipment (MUE):
• All GB-GRAM Cards completed FQT and delivered to the government
• Began independent government testing at SPAWAR (in progress)
• Began anti-tamper testing at Sandia and Aerospace (in progress)
Military GPS User Equipment (MGUE):
• Technology Development Strategy (TDS) approved by SAF – in coordination with OSD (AT&L)
• Completed Service Cost Position (SCP) and Independent Cost Estimate (ICE): 2366a certification imminent
• Technical Requirements Document (TRD) baselined at 31 Mar 11 CCB
3
Modernized GPS Capabilities
Anti-TamperDesigned for Foreign use
More effective coalition ops
M-Code Access
New, more secure signal
Anti-Spoof Detect and reject false
signals
31
16
23
32
16
20
4Red: False SV Signals
Acquisition in Jamming
Fast secure time-to-first-fix
M-Code PowerOperate closer to
jammer, under trees
Blue Force Electronic
AttackOperate near
friendly jamming
External Augmentation
SystemsEnhance GPS accuracy and
availability
4
MGUE Architecture
GPS Space Segment
GPS Control Segment
Master Control Station
Ground Antenna Monitor Station
MGUE Products
(GB-GRAM-M )
GRAM SEM-E-M(GRAM S/M)
(GRAM-M-PMC)
(CGM)
Maritime- Arleigh Burke Class Destroyer (DDG)USN: PMW/A 170
Aviation – F-15EUSAF: 912 AESG
Lead Platforms & Host Applications
Handheld and other applications
Ground--RQ-11B, RavenUSA : PM-UAS-SUAV
External Augmentation Systems
L1 SIS
SIS
L2 SIS
SIS
Data
Data
Data
Data
Ground Embedded
Aviation
Maritime
Common GPS Module
5
New Business Approach for GPS User Equipment Division
Migrate from end user products
To Common GPS Module (CGM) and Support Tools
6
What is the MGUE Overarching Strategy?
• May 2010 ADM by USD(AT&L) directed us to deliver capability ASAP
• Deliver a usable capability as close as possible to FY13
• We’re completing a successful Technology Demonstration Program
• Achieved M-Code Crypto, SAASM, C/A-code, AT and AS capability
• Implemented several new policies, programs, and requirements
• GPS User Equipment Information Assurance Program
• USD(AT&L) Anti-Tamper program
• Trusted Foundry program
• ICDs 703, 722, 723, etc….
• 3 prototype contracts 2 development contracts maintains industrial base
• Implement DoD policies on efficiencies and affordability
Leverage technology developed under MUE Finish Discovery
Mature the technology and move into EMD
7
Contract Strategy Overview
Technology Development Engineering & ManufacturingDevelopment
Production &Deployment
Material SolutionAnalysis
MUE Program
MS B MS C
Ground & CGMTech Development
Ground & CGMEMD
Ground & CGMLRIP
Aviation / MaritimeTech Development
Aviation / MaritimeEMD
Aviation / MaritimeLRIP
SourceSelection
Tech Samples PDR CDR Functional Qualification
Report
EMD Options ExercisedAfter MS B approval
LRIP Options ExercisedAfter MS-C approval
MS A
Contract A
Contract B
MGUE will Leverage
Technology • L-3 Communication• Rockwell Collins• Raytheon
FRP will be subject of separate Acquisition
Strategy
Supports TRA
MGUE TDS Development Contracts
Ground & CGMTech Development
Ground & CGMEMD
Ground & CGMLRIP
8
Program Acquisition Schedule
As of 21 Apr 11
Decision PointsMS B MS C
Technology Development
Engr & Mfg DevelopmentProduction & Deployment
Source Selection
MS A
Material Solution Analysis
MS FRP
9
Increment 1: Industry Defined Increment 2: Government Standard
CGM Business Model
(CGM)
(GB-GRAM-M )
Ground Embedded
GRAM SEM-E-M(GRAM S/M)
Aviation
(GRAM-M-PMC)
Maritime
Common GPS Module
Handheld Demo Munitions Demo
Specific Instantiation TBD
32 nm ASIC, or S/W Defined Radio, or Network-based device, or …
(SDK)
S/W Developer Kit
+
+
Third Party Developers
SDK
Many Applications
10
CGM
C/A, P(Y), M-Code
COTSL5
COTSGalileo
“On the Board”
How to incorporate additional civil signals
Increment 1C/A, P(Y), M-Code Current CGM
Potential to Add – L5, L1C, Galileo Use “On the Board” approach
Increment 2C/A, L1Y, L2Y, L1M, L2M, L1C, L2C, L5, E1,
E2, E5Can design into future CGMs with enough lead time
Opportunity On Ramp
CGM Signal Support
CGM & MGUE receiver cards will include C/A, P(Y), and M-Code
Upgraded receivers may add L5, Galileo, and other signals by integrating COTS chips on the receivers cards
11
Key Challenges
• Trusted Foundry
• Information Assurance/Security Certification
• Performance Certification
• Transitioning to Fixed-Price Development
• Increment 2
12
• GPS Directorate Technology Priorities
• Reduced SWAP & C
• NetCentricity / Comm/Nav Integration
• Software Defined Radio – Structured IP, IA/AT Solutions, CGM Alternative
• PNT Robustness – Focused on Sensor Integration and Disadvantaged User
• MGUE Delta/Objective CDD Requirements
• Advanced BFEA Compatibility, Anti-Spoof, Integrity, M-Code External Augmentation System, Reprogrammability, Multiple Signals
• Support the GPS Enterprise Modernization and PNT Assurance AoA
Advanced Technology MGUE Increment 2 Technology Maturation
Mature Critical Technology Element (CTEs) to support Increment 2 Technology Readiness Assessment
13
Questions?