governance 1 complete

Upload: akas84

Post on 24-Feb-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/25/2019 Governance 1 Complete

    1/34

    CVEN90045 Engineering Project Implementation

    Organisation & Governance Requirements

    for a Civil Infrastructure Project

    Lecture 1 - 2013

    Organisation & Governance

    Prepared by Peter Bishop C.P.Eng.

  • 7/25/2019 Governance 1 Complete

    2/34

    CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    Definitions:Governance is the process of managing & controlling aproject with proper checks & balances at all stages.

    Who will

    approve this

    pipe

    connection ?

  • 7/25/2019 Governance 1 Complete

    3/34

    CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    Definitions:The governance process must take into account therequirements of all key stakeholders to ensure thatthe project delivers optimum outcomes includingthose of the project owner.

    We will incorporate

    your requirements

    into the approval

    process

  • 7/25/2019 Governance 1 Complete

    4/34

    CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    Definitions:The primary stakeholder is the project owner & one ofits objectives is to ensure that the project is acceptedby key stakeholders. (accepted by, notnecessarily acceptable to)

    They havent

    used our good

    idea !!

  • 7/25/2019 Governance 1 Complete

    5/34

    CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    Establishing Good Governance: The Owner (Project Manager) can initiate the

    governance process by setting up an appropriateorganisation structure involving relevant

    stakeholders.

    How would you then use the organisation

    structure to control decisions (checks &balances) during the implementation ofthe project?

  • 7/25/2019 Governance 1 Complete

    6/34

    CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    Establishing Good Governance:

    The governance (managing & controlling process) issuperimposed by defining the relationship between

    participants (stakeholders) in the proposedorganisation for project implementation;

    This relationship can be a defined and applied bylaw, by contract or by mutual agreement;

  • 7/25/2019 Governance 1 Complete

    7/34CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    Typical Contract Organisation for a Project

    Owner/Principal

    Construction

    Superintendent

    Specialist

    TechnicalAdvisors

    Principal

    Designer

    Suppliers &

    Sub-contractors

    Construction

    Contractor

    Banker

    Design

    Reviewer

    Accountant Lawyer

    Insurer

    External

    Stakeholders A

    External

    Stakeholders B

    Informal

    Obligation

    Statutory

    obligation

    Individual

    contracts

  • 7/25/2019 Governance 1 Complete

    8/34CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    Conventional Project Management Organisation:

    Stakeholders

    Owner/Principal &

    Project Manager

    Suppliers &

    Sub-contractors

    Specialist

    Technical

    Advisors

    Principal

    Designers

    Manager

    Contract

    Superintendent

    Construction

    Contractors

    Manager

    Owners Advisors

  • 7/25/2019 Governance 1 Complete

    9/34CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    Alliance Project Management Organisation

    Suppliers &

    Sub-contractors

    Specialist

    Technical

    Advisors

    Owner/Principal

    Lawyer

    Insurer

    Accountant

    Banker

    Independent

    Auditor

    Alliance

    Agreement

    Sub-Alliance

    Partners

    Project Manager

    Principal

    Designer

    Owner/Principal Construction

    Contractor

    Stakeholders

  • 7/25/2019 Governance 1 Complete

    10/34CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    Governance Control Measures:The governance process can be used to apply mandatory

    requirements or discretionary requirements. For example:

    A contractual obligation is a mandatory form ofgovernance;

    A statutory obligation is a mandatory form of governance

    such as environmental legislation, or OH&S legislation;

    A Steering Committee or Community Reference Group can

    provide opinions that are used to provide confidence that the

    Project direction is generally satisfactory.

  • 7/25/2019 Governance 1 Complete

    11/34CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    Governance Controls :The governance process is provided byparticipants having powers or authorisationswithin the organisation to:

    IncreasingPowerofAction

    DirectApprove

    Certify

    Endorse

    Recommend

    Check

    Review

    Advise

  • 7/25/2019 Governance 1 Complete

    12/34CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    Governance Controls (contd) :A direction is a binding and high level control measure

    reserved for the most impactive issues during

    implementation. (Board of Directors).

    Approval is the most powerful process in the

    governance arrangement & is reserved for major

    financial & technical gateways during implementation.

    Certificationis a powerful control involving a

    professional signing off (personal or corporate

    liability) that a process or outcome complies with

    contractual or statutory obligations.

  • 7/25/2019 Governance 1 Complete

    13/34CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    Governance :It is important to include governance gateways along the

    delivery path of the Project.

    Why ?

  • 7/25/2019 Governance 1 Complete

    14/34CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    0

    1

    2

    3

    4

    5

    6

    DegreeofImpa

    ct

    Impacts of Change During Project Development & Project Delivery

    Strategy or

    Pre-feasibility

    Business CaseFeasibility Procurement Construction Commissioning

    Ability to make a

    change to the

    project scope

  • 7/25/2019 Governance 1 Complete

    15/34CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    0

    1

    2

    3

    4

    5

    6

    DegreeofImp

    act

    Impacts of Change During Project Development & Project Delivery

    Strategy or

    Pre-feasibility

    BusinessCaseFeasibility Procurement Construction Commissioning

    Ability to make a

    change to the

    project scope

    Cost to make a

    change to the

    project scope

  • 7/25/2019 Governance 1 Complete

    16/34CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    The time needed to exercise the governance controls

    can be time consuming and may slow down the

    implementation by having too many gateways ;

    Approval Bottle-neck

    Recommendation

    Request

    For

    Approval

    ReviewComments

  • 7/25/2019 Governance 1 Complete

    17/34CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    How can you reduce the potential

    bottle neck caused by thegovernance process?

  • 7/25/2019 Governance 1 Complete

    18/34

    CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    Delegation:This can be improved by delegating the powers

    (authorisations) to lower levels in the organisation.

    The delegated powers may be to certify or approve

    matters up to a certain value, risk level, or complexity.

    The delegation may also be to empower less

    experienced personnel to review, check and recommendcertification or approval.

  • 7/25/2019 Governance 1 Complete

    19/34

    CVEN90045 Engineering Project Implementation

    Governance & Organisation 1Governance Action Examples Authorisation Above $1M or

    High Risk Level

    Authorisation below $1M or Low

    Risk Level Delegated to:

    Direct: Owner's Board of Directors Owner's General Manager

    Approve: Example 1, Change of Project

    Scope

    Owner's General Manager Project Manager

    Approve: Example 2, An increase in the

    depth of foundations

    Construction Manager Senior Engineer for Foundation Area

    Approve: Example 3, An extension of time

    to a critical program activity

    Contract Superintendent Superintendents Representative

    Certify: Example 1, Contractors monthly

    payment from the Owner

    Contract Superintendent Superintendents Representative

  • 7/25/2019 Governance 1 Complete

    20/34

    CVEN90045 Engineering Project Implementation

    Governance & Organisation 1Governance Action Examples (contd) Authorisation Above $1M or

    High Risk Level

    Authorisation below $1M or Low

    Risk Level Delegated to:

    Endorse or Recommend: Example 1, The

    design of a crane foundation.

    Contractors temporary works

    designer.

    Sub-contractor responsible for crane

    supply and erection.

    Endorse or Recommend: Example 2, A

    change to the project cash-flow.

    Project Construction Finance

    Manager

    Site Cost Engineer

    Check: Example 1, A claim from a

    Contractor for extra costs from the Owner

    Superintendents

    Representative

    Site Engineer

    Check: Example 2, A change to the quality

    standard of material.

    Chief Design Engineer Senior Engineer for each discipline.

    Review, comment & advise High Credibility Specialist Recognised Specialist

  • 7/25/2019 Governance 1 Complete

    21/34

    CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    Governance for External Stakeholders: The lecture about stakeholders describes how to

    determine the importance of particular stakeholdersin the organisation. based on a simple riskassessment (mapping) process.

    Using the stakeholder map and the implementationwork breakdown structure, the organisation can bedeveloped to engage the stakeholders to the degreewarranted by their importance to the achievement

    of the Owners project objectives.

    The governance for internal stakeholders is usuallymore definitive than for some external stakeholders.

  • 7/25/2019 Governance 1 Complete

    22/34

    CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    External Stakeholders:The Project Owner may wish particular external

    stakeholders to review and comment on some proposed

    decisions.

    Governance can be applied to this involvement by

    forming the stakeholders into a "Steering Committee

    that may represent several interest groups.

    The Steering Committees decisions may have

    sufficient weight to influence project decisions or even

    the direction of the project.

  • 7/25/2019 Governance 1 Complete

    23/34

    CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    External Stakeholders (contd):

    Does the Project Manager have to adopt

    all the proposed recommendations or

    resolutions put forward by

    external Stakeholders?

  • 7/25/2019 Governance 1 Complete

    24/34

    CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    External Stakeholders (contd):The comments from an external stakeholder may be

    taken by the Project Owner as an opinion to be

    considered on its merits and adopted or not based on a

    judgement of associated risks and benefits.

    However, the external stakeholders must be advised of

    the decision to adopt or not and be given reasons for

    this.

  • 7/25/2019 Governance 1 Complete

    25/34

    CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    Conflict of Interest:Individuals may adversely affect project implementation

    because of personal or corporate interests that are different

    from those of the project organisation or different from those

    of others in the organisation.

    The organisation and governance arrangements must avoid

    conflicts of interest and they must include methods to manage

    conflicts of interest if they arise.

  • 7/25/2019 Governance 1 Complete

    26/34

    CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    Conflict of Interest (contd):Conflicts of interest are dealt with at the time of entering

    into a contract arrangement (contractual obligations);

    Less rigorous agreements with committees or advisors

    ( voluntary members particularly) are less explicit in theconflict of interest obligations.

    Typically committee members will be asked to sign a

    confidentiality agreement and a conflict of interest statement.

    Actions by organisation members may not show a blatant

    conflict of interest but behaviour may adversely influence

    others in the organisation.

  • 7/25/2019 Governance 1 Complete

    27/34

    CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    Matrix Management Definition:Matrix management is a style of management where an individual has two

    reporting superiors (bosses) - one functional and one operational.

    This is commonly seen in project management where an engineer, for example,

    reports to the chief engineer functionally, but reports to the project manager onoperational project issues.

    Matrix management also is common in branch offices. The accountant in the

    Melbourne office reports functionally to the Vice President of Accounting in

    headquarters in Sydney, but reports operationally to the Regional Manager in

    charge of the Melbourne office.

    Generally the functional reporting relationship is stronger, because the

    functional manager controls the individual's compensation and evaluations.

  • 7/25/2019 Governance 1 Complete

    28/34

    CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    Matrix Management Definition:Matrix management is a style of management where an

    individual has two reporting superiors (bosses) - one

    functional and one operational.

    Functional

    Manager

    Functional

    Manager

    Functional

    Manager

    Functional

    Manager

    Project

    Manager

    Engineer 1 Engineer 2 Engineer 3 Engineer 4

    Project

    Manager

    Engineer 5 Engineer 6 Engineer 7 Engineer 8

    Project

    Manager

    Engineer 9 Engineer 10 Engineer 11 Engineer 12

  • 7/25/2019 Governance 1 Complete

    29/34

    CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    Matrix Management Example:Matrix management is a style of management where an

    individual has two reporting superiors (bosses) - one

    functional and one operational.

    Managing

    Director

    Manager

    Engineering

    Regional OH&S

    Manager

    Contracts

    Manager

    Purchasing

    Manager

    Project

    Manager 1

    Site Engineer 1 Site Engineer 1 Site Engineer 1 Site Engineer 1

    Project

    Manager 2

    Site Engineer 2 Site Engineer 2 Site Engineer 2 Site Engineer 2

    Project

    Manager 3

    Site Engineer 3 Site Engineer 3 Site Engineer 3 Site Engineer 3

  • 7/25/2019 Governance 1 Complete

    30/34

    CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    Documentation of Governance Arrangements:To implement effective governance, the roles and responsibilities

    of all members of the organisation must be clearly documented,

    including the relationship between each.

    The project management plan must include:

    roles and responsibilities;

    Authority levels;

    Dispute resolution method;

    Reporting obligations.

    Reference documents (contracts, agreements, statutes)

  • 7/25/2019 Governance 1 Complete

    31/34

    CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    Governance Role of the Professional Engineer:As a professional Engineer, you may be operating in a project

    organisation as an employee of the Owner, or as an employee of

    one of the entities participating as a service provider or as an

    external stakeholder.

    How will you know what your obligations are in

    the project Governance arrangements?

  • 7/25/2019 Governance 1 Complete

    32/34

    CVEN90045 Engineering Project Implementation

    Governance & Organisation 1

    Governance Role of the Professional Engineer:Your employment conditions will include obligations to your

    employer including respect for confidentiality and notification of

    any conflict of interest risks.

    Project- specific responsibilities may be added to your employee

    obligations.

    Your Employer will have signed a contract or agreement thatspecifies governance obligations and you must be made aware of

    these obligations to meet you personal obligations.

  • 7/25/2019 Governance 1 Complete

    33/34

    CVEN90045 Engineering Project Implementation

    Governance & Organisation 1Governance Role of the Professional Engineer:

    Owner/Principal &

    Project Manager

    **

    Suppliers &

    Sub-

    contractors

    **

    Specialist

    Technical

    Advisors

    **

    Principal

    Designers

    Manager

    **

    Contract

    Superintendent

    **

    Construction

    Contractors

    Manager

    **

    Owners Advisors

    **

    **Professional

    Engineer

    Stakeholders **

  • 7/25/2019 Governance 1 Complete

    34/34

    CVEN90045 E i i P j t I l t ti

    Governance & Organisation 1

    Governance Role of the Professional Engineer:

    In all roles in the organisation you will be expected to behave

    ethically as an individual professional engineer.

    End of L ecture Part 1

    I am not

    a

    Professional

    Engineer