government of andhra pradesh irrigation & …apwsipnsp.gov.in/apwsip/downloads/other...
TRANSCRIPT
GOVERNMENT OF ANDHRA PRADESH
IRRIGATION & CAD (PW) DEPARTMENT
ANDHRA PRADESH WATER SECTOR IMPROVEMENT PROJECT
NAGARJUNA SAGAR DAM
4
th REPORT
OF
DAM SAFETY REVIEW PANEL
Nagarjuna Sagar 2nd
to 6th
November, 2009
2
CONTENTS
SECTION PARTICULARS PAGE NO.
I Introduction. 3
II Hydrology 5
III Construction 8
IV Power House 11
12
V Gates
13
VI Earth Dam
VII Masonry Dam 17
VIII Acknowledgement 21
ANNEXURE
I List of Officers 22
3
Section – I
INTRODUCTION
1. Members of Dam Safety Review Panel (DSRP) assembled in Hyderabad
on November-02, 2009 (FN) and proceeded to Nagarjunasagar Dam,
where on arrival, the DSRP members were presented with the following
documents for study and discussions during the fourth meeting.
(i) Comprehensive and detailed technical history of Nagarjunasagar
Project (Head works only) volume-I and Volume-II, July 1998.
(ii) Inspection Reports of Technical Expert Committees and Special Dam
Safety Inspection Committees.
(iii) Estimation of PMF: Progress report by IIT Kharagpur.
(iv) Dam break analysis and EAP: Proposals submitted by NIH and
Engineering staff College of India.
(v) Paper on PVC Geomembrane for water proofing the upstream face of
Kadamparai Dam.
(vi) Action Taken on 1st and 2
nd Reports of DSRP.
(vii) Action Taken on 3rd
Report of DSRP
(viii) TM on seepage through porous hole No.3 in Block No.24 in Gallery
at El.420.00 Feet
4
(ix) TM on Damages to Glacis of spillway and Bucket Portion.
(x) TM on seepage at CH.15.00 of left Earth Dam
(xi) Month wise record of observations of seepage in porous drain 3 of
Block 24 and deflections in Blocks 14 and 54 for the years 2007,2008
and 2009.
2. On November 03,2009 (FN) DSRP discussed the Action Taken on
its 3rd
report with project officers. Later in the after noon, the
galleries were inspected with reference to the reported high seepage
from porous drains.
3. The Right and Left earth dams, the left bank saddle dam, Spillway
Glacis, Bucket and down stream area were inspected and the left bank
power house visited on November 04, 2009.The DSRP had further
discussions with project authorities on November 05,2009 before
preparing its report.
4. The DSRP met with Dr.G.Malsur on Nov.05,2009 and discussed the
progress of rehabilitation measures.
5. The sections that follow give detailed review of Hydrology,
Construction, Power House, Gates, Earth Dam and Masonry Dam
including recommendations.
6. DSRP proposes to schedule its next meeting when the Reservoir
Water level is at the lowest.
7. The list of Officers who participated in discussion and site visits
and assisted in preparation of this report is appended.
8. DSRP presented its report to Chief Engineer, Nagarjunasagar
Project before dispersing on November 06,2009.
5
Section - II
HYDROLOGY
1.0 Probable Maximum Flood :
1.1 The information available shows that the dam has been designed for an
inflow design flood of 42,476 cumecs (15 lakhs cusecs). Subsequently
after the construction of the dam, 1000 year return flood was estimated as
58,340 cumecs (20.60 lakhs cusecs). The latest information indicates that
the PMF at Srisailam Dam is of the order of about 73,853 cumecs
( 26 lakhs cusecs). The catchment area of the Kirhsna basin at Srisaliam is
2.06 lakhs sq.km where as at the Nagarjunasagar Dam site it is 2.15 lakhs
Sq. Km. The PMF at the latter, therefore, is expected to be more than 26
lakhs cusecs.
1.2 At the time of second review, DSRP was informed that an interim report on
PMF would be available by February28, 2009. At the time of the 3rd
review, it was informed that IIT, Kharagpur will furnish a interim report by
12.09.2009.
1.3 The current status of studies, as reported, is that Agriculture and Food
Engineering Department, IIT Kharagpur has started PMF studies in
September’2009. They have collected some data and have approached
various organizations and departments such as CWC, IMD, Indian Institute
of Tropical Meteorology ( IITM) for some more vital data as input in
studies. The IIT Kharagpur has informed the Project authorities that they
will produce an interim report in two months time after they obtain all the
data from different organizations and departments
6
1.4 It is advised that the IIT Kharagpur may be pursued to provide the interim
report with out further delay and the final report based on the detailed
studies for estimation of the PMF at the earliest.
2.0 Dam Break Analysis and EAP
2.1 The project authorities reported that two agencies, namely National
Institute of Hydrology, Roorkee and Engineering Staff College of India,
Hyderabad have submitted their proposals. The DSRP has following
observations to make on these proposals.
2.2 The NIH Proposal is restricted to dam break analysis only. Details of
technical personnel to be involved in the studies have not been included in
the proposal. The proposal is very sketchy.
The proposal submitted by the Engineering Staff College of India,
Hyderabad includes both the dam break analysis and the preparation of
emergency action plan (EAP). The time schedule proposed by them
includes two years for preparation and submission of the EAP from the
date of signing the agreement and for finalization of the plan at various
levels one more year . The above points may be kept in view while
finalizing the agency.
2.3 The agency should also keep the following points in view while giving their
proposals.
i) “Guidelines for Development and Implementation of Emergency
Action Plan (EAP) for Dams” , 2006 may be followed strictly
while preparing the report .The guidelines are approved by the
National Committee of Dam Safety in their meeting convened in
2006.
7
ii) The EAP is supposed to be covered from the Nagarjuna Sagar dam
to the Pulichintala dam site located on the river Krishna.
iii) The credentials of the experts involved in the studies may be
verified.
iv) The time for completing the studies could be shortened.
v) The EAP may be subject to review after it is reviewed to
the DSRP.
3.0 In view of the huge unprecedented flood occurred in September –
October 2009, in the Krishna basin and actual discharge measured at
Srisailam dam, the hydrological and meteorological data of this period
must be taken into account while carrying out the PMF and Dam Break
Studies and preparation of the EAP.
4.0 It was suggested by the panel that pending the estimation of the
PMF, the dam break analysis and preparation of emergency action plan
could be initiated assuming an average value of PMFs computed for the
Srisaliam and the Pulichintala Project as the Nagarjunasagar Dam is
located in between Srisailam and Pulichintala dams.
5.0 Keeping in view the importance of PMF for Dam Safety evaluation,
the Project is advised to get the studies done on priority basis. Dam
break analysis and EAP should also be expedited.
8
Section-III
CONSTRUCTION
1.0 Spillway
It is reported that during October 2009, the spillway was operated for a short
period of 11 days to allow a maximum outflow of 10.22 lac cusecs against the
previous maximum of 8.58 lac cusecs in 1998. The max. water level attained
was R.L.589.40 Feet .The DSRP inspected the Spillway glacis on 03.11.09 and
04.11.09 to note the extent of damages.
1.1 Glacis
Spillway became fully operational after erection of Radial Gates in the year
1974 and since then damages due to scouring/erosion were a recurring feature
whenever the spillway was put into operation. Remedial measures have been
carried out from time to time to restore the damaged surface by back filling with
concrete using epoxy mortar as bond between old and new concrete. DSRP has
opined earlier that the damage to glacis concrete is a typical cavitation induced
erosion which can be remedied only through aeration .The extent and method of
aeration can be decided only through physical model studies.
1.2 Stop Logs
Piers have to be extended for accommodating stoplog gates and this will also
require a physical hydraulic model study for evaluation of Cd. These model
studies have , therefore, to be expedited . Meanwhile, details of proposed civil
structure arrangement for stoplog gates may be furnished to DSRP for review .
9
1.0 Foundation Drainage holes
The progress of reaming of drainage holes in foundation gallery and the results
there, of may be presented to DSRP for review .
2.0 Porous drains
These are also being cleaned but in the slant portion only. It is well known that
it is difficult to maintain these drains in original condition. It is understood that
Maharastra had initiated development of a machine named RF-03 and modified
as ZR –04 to clean the porous drains. This machine is said to be working
successfully at Bhatsa Dam near Mumbai. Project authorities may obtain
details and literature along with performance reports of the said machine from
Bhatsa Dam project. If found suitable, the same can be tried at NS Dam to make
Porous Drains functional.
4.0 Up stream face of Dam
Panel had earlier opined that the following measures may be undertaken to
minimize seepage of water in to the dam body .
(a) Block joints on upstream face to be treated with epoxy.
(b) Upstream face of Dam to be shotcreted, from top of Dam to minimum
possible MDDL ( 510 feet).Block No.24 may be taken up on priority
basis.
The DSRP does not consider installation of a Geo-membrane on the
upstream face as a solution as the same cannot be taken down below MDDL
and anchored to foundation rock. Shotcreting / Guniting is considered as the
best available option. A detailed proposal may be presented for review by
DSRP.
5.0 Area down stream of Right NOF Blocks
Regular leakage is being observed from Right bank canal Power House area
with water flowing into the depression downstream of NOF Blocks 50 to 60.
10
This needs to be regulated and the area developed as a park. An infrastructure in
the form of tanks etc appears to be in place but in deplorable condition. The
area may be restored and maintained for safety as well as aesthetic reasons.
This area can also be utilised for housing machinery required for immediate
repairs and regular maintenance of spillway and EDA.
The alignment of proposed road to connect area down stream of spillway
may be further examined in light of unprecedented floods in October 2009.
11
Section –IV
POWER HOUSE
No specific problem relating to the power houses, especially having any
bearing on dam safety, were brought to the notice of DSRP. Fine clearances of
the mechanical equipment of power plant, normally closely monitored during
maintenance, form good indicators for development of any distress to the dam.
12
Section - V
GATES
From the Action taken report, it is seen that action is initiated by
Project Authorities for taking up repairs/replacement of equipments as
suggested by DSRP during the previous visits. Further progress may be reported
for review by DSRP.
13
Section - VI
EARTH DAM
1.0 Left Earth Dam
1.1. A Technical Memo on seepage at Ch. 15.00 was presented by the project
authorities. The problem of seepage through left earth dam is continuing
since 1978. TIMS Book mentions that there was not much seepage after
remedial measures were taken. The book, however, does not mention any
details about the measures and the year of their implementation. The
subject matter was also not refered to any committee since 1978. The
seepage is reported to start when reservoir water level reaches El 545 ft.
During last 5 years, the maximum seepage observed was 1285 GPM in
2005 when water level reached El. 589.90 ft. On 13.10.09, with water level
at El. 588.60 ft, the seepage observed was 1035 GPM. As reported by
Project authorities, some bubbling was also noticed at the toe at Ch.
15.00.It is necessary to keep a continuous record of the leakage
measurements through out the year, both for rising and receding reservoirs
water levels.
1.2. DSRP, during its visit in November 2008 (2nd meeting) (Reservoir Water
level 577.10 Feet) had discussed this issue and suggested certain measures.
On 04 -November’2009 i.e., one year later the site inspection again under
similar conditions, did not reveal much change in the scenario which was
observed during November’08 visit. The bubbling phenomenon, as was
reported during discussion is not considered a major problem. The seepage
water was clear. It is not practical to prevent the seepage entirely. The
only way is to allow this water to pass safely without causing any damage
to the dam toe. Keeping this in view, remedial measures were suggested in
the 2nd
report of DSRP (6th to 10th
Nov.2008).
14
1.3. The suggested measures are reiterated below.
• On the left bank, in most of the length, two parallel longitudinal
drains carry the seepage discharge. The drains are separated by a
high ground. Cross drains joining the above drains are provided at
twenty two locations.
• The longitudinal toe drain adjacent to the rock toe may be filled up
by pervious materials comprising of graded filter laid under the
rock - fill. The filling is required to be done to the same level as
the high ground between the two longitudinal drains. Wherever the
drain is silted up, the same shall be removed before being back
filled to the required level with pervious material. The
arrangement will provide a loading berm on the existing toe of the
dam. The material being permeable, the seepage discharge is not
obstructed. The loading will provide safety to the toe against any
bubbling or excessive pressure. The provision of filter will take
care of any possibility of particle migration from dam body.
• The cross drains shall be filled with rock-fill laid over the
appropriate filter upto the raised ground level. This provides a
continuous path way near the dam toe. The cross drains filled with
pervious material will release the seepage discharge into the outer
longitudinal drain. Thus the entire seepage discharge will get
released away from the dam toe.
The sketches showing the arrangement were appended with report
of 2nd
DSRP meeting.
1.4. The instrumentation proposed in the 2nd
Report was meant to know the
phreatic surface in the dam body. The same may be augmented as given
below .
15
• Instruments may be provided in sections at Ch. 15.00 and
Ch. 35.00 at the following locations
- At the dam axis
-Downstream edge of top road
-Inner edge of the berm on Downstream slope at
El.575.0 ft.
There is no objection for vibrating wire type instruments as suggested
by CWPRS so long as phreatic surface can be delineated.
1.5 In order to review the seepage problem further, the following shall be
prepared.
i. Contour map of upstream area along with cross sections at
representative locations.
ii. Detailed Geological map of the area upstream of dam.
iii. Data on Drilling and Grouting done earlier.
2.0 Right Earth Dam
2.1. The seepage in the dam body was of the order of 130 GPM when the
water level reached El. 588.60 in October 2009.On 04.11.2009, during
DSRP’s inspection, the water level and discharge reported were El. 573.0
ft. and 40 GPM respectively. Out of total length of dam from Ch. 133 to
Ch. 158.5, only the reach from Ch. 150 to Ch. 155 is contributing to this
seepage, which is being carried to the natural drain. To prevent water
logging of the Downstream Zone, measures were suggested during 2nd
DSRP meeting of November’08.
2.2. Similar instruments, as proposed for left earth dam, are recommended for
right earth dam also at Ch. 152.0 at following three locations to establish
the phreatic surface.
• Axis of Dam
• D/s edge of top road
• At El. 590. D/s slope.
16
3.0 Saddle dam.
3.1 The data regarding rock fill dam in the saddle dam could not be traced by
the project authorities. DSRP, could therefore, only review the safety of the
saddle dam by visual inspection.
3.2. Settlement was noticed on the top of dam at the junction with head
regulator structure. Bulging in upstream and downstream slopes at higher
elevations in this reach was also noticed .Survey may be carried out to
establish the dam profile and sections in all reaches of the dam.
The section at the junction with head regulator may be made up to match
with the profile in the in the rest of the dam by filling or removing the
bulges.
3.3. As reported the dam behaved satisfactorily during the monsoon and no
distress was noticed. However, the seepage discharge needs to be
channelised properly. The existing water pools may be filled up to bring
low-lying areas to an uniform level. The vegetation has to be removed
and the large quantity of quarry spoil available around can be used for
back filling.
17
Section – VII
MASONARY DAM
1.0 Third Report of DSRP
1.1. The fourth review is in continuation of the earlier review. This section
shall, therefore, be read along with section-VII of the 3rd
Report.
2.0 Review of Documents
The Project authorities made a power- point presentation of the following
documents.
- Action taken on 3rd
Report
- Technical Memorandum on seepage through porous hole No. 3 in
Block No. 24, in top gallery.
- Technical Memorandum on damages to Glacis of spillway and Bucket
Portion.
3.0. Stability Analysis
It was reported that Stability Analyses have been completed by
CDO through a consultant. The results have to be presented through a
proper Technical Memo for further review by DSRP.
4.0. Spillway Glacis
It is abundantly clear that restoration of the damaged surface with
concrete backfill is not a lasting solution. Such concrete backfill cannot
resist cavitation induced damages. A proper aeration arrangement
together with the use of high strength concrete and epoxy mortar bonding
should be able to substantially reduce the degree of damage.
Introduction of aeration arrangement on the existing glacis will
necessarily take a long time, especially because of the length and the
number of bays. APERL should expedite their studies. Meanwhile
18
action should also be taken to finalise design mix for silica fume based
concrete with or without steel fibre reinforcement to be used for repair if
aeration arrangement cannot be executed before next reservoir filling.
Aeration may also have to consider for execution in phases.
The Technical Memo may also be upgraded to demarcate more
precisely the damaged areas and extent of damage in each block.
5.0. Porous Drains
5.1 Porous Drain No. 3 in Block 24
During October 2009 when the reservoir level reached EL.587.60
Feet, leakage of the order of 106 GPM was observed in the above drain
outlet into gallery at EL.420. It was apprehended that this drain is
connected to the reservoir through some channels formed in the dam body
as the colour of leakage water was the same as that of reservoir water.
Other five holes in the blocks were discharging insignificant quantity. The
graphs showing RWL Vs the leakage quantity presented in the current TM
are completely at variance with those presented in TM submitted during 3rd
DSRP meeting. The data needs to be checked. It is also necessary to
continue the plot as the RWL recedes to complete the cycle. Plots with
RWL on Y-axis and discharge along X-axis will help to have a better
visual appreciation. On 03.11.2009, the RWL was EL. 574 feet and the
seepage quantity was 79 GPM. Though a ‘V’ notch is fixed in block No.25,
the measurement of leakage quantity is done by collecting the water in a
drum and recording the time. It was emphasized by the panel that ‘V’
notches, wherever installed, should be got calibrated by APERL and future
measurements done by using the same . More ‘V’ notches be installed to
compartmentalize the gallery to precisely measure the reach wise
leakage/seepage.
19
5.2 Porous Drain No.4 in Block No.77
The leakage from the above drain into EL.420 gallery which is also the
foundation gallery, of the order of 6 GPM with reservoir water level at
EL.574 feet is not significant. However, the other five drains in the block
carry no water. The leakage, per se, through this hole may not be of
immediate concern.
5.3 Porous Drain No.5 in Block. No.44
The out let of the above drain into foundation gallery at EL.250 is
fitted with a 3” pipe and a valve, which is not functional. The leakage was
reported to be 5.30 GPM at the time of the visit. The TM for the 3rd
review
showed a decreasing trend in leakage. The plotting of RWL Vs leakage
should be continued. The valve may be replaced. The closure of the valve
temporarily may help in studying the behavior of other porous drains in the
block.
6.0 Drainage Holes
6.1 In block No.79 the drainage hole in the gallery is fitted with a pressure
guage and a valve. The guage is not functional. However, significant flow
of water can be noticed by opening the valve. Reaming of all other
drainage holes in the block in the vicinity of the above drainage hole may
mitigate the problem.
6.2. Drainage holes in the foundation gallery at EL. 250 were being reamed.
As reported, the cleaned holes are getting operative.
7.0 Down Stream face seepage
On the downstream slope of the NOF blocks on either side of
spillway, seepage is being observed since long. Seepage is also observed
on the down stream face at contraction joints between block No.67,68 as
well as block No.35.The likely reasons for these seepages have been
discussed in the 3rd
review report.
20
8.0 Remedial Measures
The reasons for dam body leakages and seepage have been discussed in
the earlier reports. Visual inspection of the upstream face of dam above EL 510
has not revealed any areas of direct access of water from the face. Various
measures of re-pointing and sealing of contraction joints in the upstream have
not proved successful. In view of this and considering the service of the dam for
more than 30 years, DSRP is of the view that the entire upstream face of dam,
which can be exposed by lowering the water level to the extent possible, may be
treated by shotcreting / Guniting. Project authorities should prepare a TM on
this subject for review by DSRP.
9.0 Toe Gallery
It was earlier expected that the cross wall in block 48/49 was a temporary
structure and could, therefore, be dismantled easily. The reasons for its
construction now need to be ascertained since the wall is reported
to have been constructed in RCC. TIMS report may throw some light. Now
that the gallery is dewatered, its layout and longitudinal profile may be prepared
and TIMS report studied to find out the objectives of the gallery as also the
extent of foundation grouting from and drainage holes in the gallery. The
gallery will have to be inspected from both ends before taking any further action
on the cross wall.
10.0 Other Actions
Progress on other actions being taken may be reported for review by
DSRP.
21
Section – VIII
ACKNOWLEDGEMENT
The DSRP acknowledges with thanks the participation of the officers (list
enclosed) in the field visit and in discussions and their help and co-operation in
preparation of the Report.
The DSRP would like to compliment the efforts in preparation of the
TMs and other documentation presented during the visit.
The DSRP appreciates very much the participation and assistance of Sri
I.S.N. Raju, Chief Engineer, CDO in the field visit and in review discussions.
The DSRP would like to specially thank Dr.G.Malsur, Project Director
and Sri M. Ramachandraiah, Chief Engineer, N.S. Project for their support.
Special thanks are due to Sri G.V. Appa Rao, Assistant Engineer for the logistic
and pre and post review assistance.
Dr M.S. Reddy
Chairman
Sri A.N. Singh Sri M.K.V. Sharma
Member Member
Sri G.S. Choudhary Sri B.M. Upadhyay
Member Member
Sri S.R. Toley Sri S.R. Pradhan
Member Member
22
ANNEXURE
List of Officers Present
1. Sri M. Ramachandraiah : Chief Engineer, N.S.Project, Hill Colony.
2. Sri I.S.N.Raju : Chief Engineer, Central Designs
Organisation, I & CAD Department ,
Hyderabad.
3. Dr. G.Malsur : Project Director, PPMU, APWSIP,
Hyderabad.
4. Sri B. Lakshman Reddy : Superintending Engineer, N.S.Dam Circle,
Hill Colony.
5. Sri M.A. Saleem, : Executive Engineer, Dam Maintenance
Division, Hill Colony.( A/c)
6. Sri A.Vijaya paul : Dy. Chief Engineer, N.S.Project, Guntur.
7. Sri.S.M. Subrahmaneswera
Rao
: Dy . Superintending Engineer,
NSLBC O& M Circle, Tekulapally.
8. Sri A. Solomon : Dy. Executive Engineer, Earth Dam
Sub- Division, Hill Colony.
9. Sri G.V.V. Madhusudhana
Rao
: Dy. Executive Engineer, O/o Chief
Engineer , N.S.Project, Hill Colony.
10 Sri .M.N.V. Chandrashekar : Dy. Executive Engineer, Central Designs
Organization, I & CAD Department ,
Hyderabad.
11 Sri K. Vijay Kumar Asst. Executive Engineer, N.S .Dam Circle
12 Smt B. Ananda kumari : Asst. Executive Engineer, Dam Mtc
Division
13 Sri B. Adiseshu : Asst. Executive Engineer, Spillway Section
14 Sri. K Krishnaiah : Asst. Executive Engineer, Gates Section
23
15 Sri BH. Subrahmanyam : Asst. Engineer, Gates Section
16 Sri T. J. Narasimhamurthy : Asst. Engineer, D & G Section
17 Sri K. Manohar : Asst. Executive Engineer, Earth Dam
Section
18 Sri A Kesava Rao : Asst. Executive Engineer, D & G Section
19 Sri .V.S. R. Prabhu Asst. Executive Engineer, Earth Dam
20 Sri B..Satyanarayana
Murthy.
: Asst Engineer , O/o Chief Engineer ,
N.S.Project,
21 Sri. B. Srinivasa Rao : Asst Engineer , B& R Section
20 Sri G. V. Appa Rao : Asst Engineer , O/o Chief Engineer ,
N.S.Project,
21 Sri M.Vinod Babu : Asst.Executive Engineer , O/o Chief
Engineer , N.S.Project, Camp office,
Hyderabad.