government of indiahpaldc.org/nrpc_test/12/12_minutes.pdf~ ij{cfli{ government of india...

56
ij{CflI{ Government of India Ministry of Power Northern Regional Power Committee 1<:1'1 11 08/04/201811 6' No . NRPCI OPR/1 08104/20181 23 \l1'1C1{l, 2018 Dated: 23 rd January, 2018 Sir, Members of TeST Sub-Committee (As per List) m: 'ff'+ft 1'tf11B 1( ) Subject: 12th meeting of TeST Sub-Committee - Minutes. cfiT m cfiT 12 eft 22 RBkI(, 2017 <:1€1'13'l it 61141D1a cfiT 11{ m I Cfll41a cfiT 1ZCfi q Cfl14C11 W l:p.'f 1ih TeST Sub-Committee meeting of NRPC was held on 22 nd December, 2017 at UP-SLOC, Lucknow. A copy of the minutes of the meeting is enclosed herewith for favour of information and necessary action. . Yours faithfully, , '7 rl I 01 )u (Hemant Kumar Pandey) . Superintending Engineer

Upload: lekhanh

Post on 18-Mar-2018

215 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

~ ij{CflI{

Government of India

~4"'1~4 Ministry of Power ~~~ij~fil

Northern Regional Power Committee

~. ~~I SI~ 1<:1'1 11 08/04/201811 13~ ~ 6' ~ No. NRPCI OPR/1 08104/20181

~: 23 \l1'1C1{l, 2018 Dated: 23rd January, 2018

Sir,

Members of TeST Sub-Committee (As per List) m: ~ ~ ~ 'ff'+ft ~ (~ 1'tf11B 1 ( )

~:m~-~~12cff~CfiTCflI41*11 Subject: 12th meeting of TeST Sub-Committee - Minutes.

~ ~ ~ ~ cfiT m ~-~ cfiT 12 eft ~ ~ 22 RBkI(, 2017 ~ ~ ~~T-~.l01.tr.m., <:1€1'13'l it 61141D1a cfiT 11{ m I ~ ~ ~ Cfll41a cfiT 1ZCfi ~ ~ ~ q 3lfGf~(fCfi Cfl14C11 ~ ~ W l:p.'f ~ m~ ~ ~I

1ih TeST Sub-Committee meeting of NRPC was held on 22nd December, 2017 at UP-SLOC, Lucknow. A copy of the minutes of the meeting is enclosed herewith for favour of information and necessary action.

~ . Yours faithfully, , '7 ~ ~ . ~\

~~ rl LI\~l ~~j I (~¥fR~) 01 )u

(Hemant Kumar Pandey) . 3f~~~

Superintending Engineer

Page 2: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

List of Members of TeST sub-committee:

1. Chief Engineer(SLDC), PTCUL, Dehradun-248001 , (Fax-0135-2530336) 2. Dy Chief Engineer (SO) BBMB, Chandigarh-160019, (Fax-0172-2549548) 3. Chief Engineer (GM), CEA, R. K. Puram, New Delhi-110066, (Fax-011-26109750) 4. Chief Engineer, UT of Chandigarh, Chandigarh-160009, (Fax-0172-2740276) 5. General Manager (SLOC), DTL, New Delhi-110002, (Fax-011-23221012) 6. Chief Engineer (SO),HPGCL, Panchkula-134109, (Fax-0172-2560622 & 2565042) 7. Chief Engineer, HPPTC Ltd., Shimla-171004, (Fax-0177-2626284) 8. Superintending Engineer, SLDC, HP Load Dispatch Society, Totu, Shimla, (Fax-

0177-2837543) 9. Chief Engineer (SO&P)HPSEB Ltd, Shimla-171004, (Fax-0177-26163554) 10. Chief Engineer (SLDC) PSTCL, Patiala, (Fax-0175-2304017) 11 . Chief Engineer (Distribution) , PSPCL, The Mall , Patiala, (Fax- 0175-2212069) 12.Dy. Chief Engineer(PLCC), RVPNL, Heerapura, Jaipur-302005, (Fax-0141-

2250967) 13. Chief Engineer (TO), UPRVUNL, Lucknow-226001, (Fax-0522-2287861) 14. General Manager (RMU), UJVNL, Dehradun-248006, (Fax-0135-2530708) 15. Chief Engineer (O&M), NHPC, Faridabad-121003, (Fax-0129-2255706) 16. General Manager (OS)(NCR) , NCR-HO, NTPC, Noida-201301, (Fax-0120-

2410052) 17.General Manager(ULDC) & General Manager (LD&C) PGCIL, New Delhi-110016,

(Fax-011-26564849) 18.General Manager (C&SO), SJVNL, Sharma Niwas, Below BCS, New Shimla-

171009, (Fax-0177-2673283) 19. General Manager (Electrical Design),THDC, Rishikesh-249201, (Fax-0135-

2438682) 20.Addl. Chief Engineer Jaiprakash PVL, Noida, (Fax-0120-4516101/4516201) 21 . General Manager (Technical), IPGCL, New Delhi-11 0002, (Fax-011-23270590) 22.GM(0&M) DTL, New Delhi-110002, (Fax-011-23232721) 23. General Manager, NRLDC, New Delhi-110016, (Fax-011-26853082) 24. Chief Engineer (SO&C), SLDC, HVPNL, Sewah, Panipat , (Fax-0172-2560622) 25.Dy. General manager, Rosa PSCL , (Fax-05842-300003) 26. Chief Engineer(SLDC) , UPPTCL, Lucknow.(Fax 0522-2287880) 27. Chief Engineer(Transmission), NPCIL, Mumbai-400094, (Fax-022-

25993570/25991258) 28.DGM, Electrical, Jhajjar Power Ltd., Haryana, (Fax-01251-270155 29. Director, Lanco Anpara Power Ltd., (Fax-124-2341627 30. GM (Comml.), Aravali Power Company Pvt. Ltd ., NOIDA, (Fax-0120-2425944) 31 . Development Commissioner (P), POD, Srinagar, J&K, (Fax-0194-2452173) 32. Managing Director, J&K State Power Dev. Corp. , Srinagar, J&K, (Fax-0194-

2500145) 33. HOG power system control, TATA Power Delhi Distibution Limited, New Delhi,

(Fax-011-66050601), CENNET building, Opp to PP Jewellers Netaji Subhash Place" New Delhi ( Kind Attn Sh.P Devanand)

34. Sr. Vice President, JSW Energy Ltd ., New Delhi-110066 (Fax: 46032343 1 26183546)

35. Managing Director, UPCL, Dehradun-248006, (Fax-0135-2768867)

Page 3: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

1

NORTHERN REGIONAL POWER COMMITTEE

Minutes of 12th meeting of

Telecommunication, SCADA & Telemetry (TeST) Sub- Committee

12th meeting of Telecommunication, SCADA & Telemetry (TeST) Sub- Committee held on 22.12.2012 at Lucknow. The list of participants is enclosed at Annexure-I. Sh. A. K. Singh, Chief Engineer, UPPTCL welcomed the participants. While highlighting the importance of Telecommunication, SCADA and telemetry, the subject matter of the TeST sub-committee, he urged all the members to build and maintain a robust and reliable SCADA, telemetry & communication system. Citing the recent SCADA outage at UP, SLDC , he requested the sub-committee to discuss the problems which may be caused due to various reasons including IP conflict, firewall issues, hardware issues , human error etc. and search for solutions to the these issues in present SCADA system to avoid recurrence of such incidences. He emphasised that co-operation of the all the concerned including, NRPC, NRLDC,POWERGRID, service providers etc. in this regard, is of vital importance. He expressed hope that the deliberations in the meeting regarding improvement in present SCADA system functioning and reliability would help not only UP but all the States of Northern Region. Director, SLDC, UP welcomed the delegates. He urged to find root cause of the recent SCADA outage in UP SLDC and to take necessary action immediately to resolve the issues, whether it is hardware / software deficiency of the system or human error. He mentioned that SCADA & telemetry are eye & ear of power system. He emphasised that the reliability and security of SCADA and telemetry must be ensured for proper function of grid operation. A presentation was made by UP, SLDC on various aspects of CSDA and Telemetry system at LSDC. In presentation it was emphasised that since the establishment of SLDC, the SCADA & telemetry had played vital role in grid operation. It was informed that UP system is very large with 263 nos. of sub-stations and 208 RTUS reporting to SLDC. It was also informed that UP has 4 sub-SLDCs with back-up SLDC at sub-SLDC Modipuram. The presentation covered the challenges related to telemetry in form of planned integration of more than 400 nos. 132 kV sub-stations in SCADA and integration of PMU functionalities, with SCADA & EMS system for optimum utilistaion of PMUs installed at 16 no. of sub-stations in UP under URTDSM project. The presentation also highlighted the challenges of optimum utilistaion of EMS facilities, minimisation of difference in SCADA & SEM values, back-up SLDC operationalisation and integration of UFR & df/dt relays etc. Copy of the presentation is enclosed at Annexure-II. Members Secretary, NRPC welcomed the participants. He expressed his gratitude towards UPPTCL for hosting the meeting and making adorable arrangements. He highlighted the importance of a secure and reliable SCADA & telemetry system. Citing an example of security compromise due to non-updation of anti-virus he emphasised

Page 4: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

2

that cyber security of the system must be ensured .He urged all the states to minimise difference between SCADA and SEM values, so that deviation from schedule / mismatch between SCADA and SEM data may be reduced. He also stressed that the back-up SLDCs should always be kept in operational and tested periodically, so that in case of any eventuality in main SLDC all the load despatch functions are carried out from the back-up SLDC. He informed that EMS training by M/s Siemens was to be organised by NRPC at all SLDCs in Northern Region, except Uttarakhand. He requested all the states to take maximum benefit from this training so as to enable the SLDC personnel in running of the State Estimators.He mentioned that for proper functioning of State Estimator the network data must be updated by each SLDCs. He requested all the members to complete this exercise before start of EMS training. A presentation was made by NRPC secretariat on regulatory provisions regarding telemetry and communication in power system, in CERC and CEA Regulations/Standards. The directions by CERC in their orders ,for ensuring reliable telemetry and data as well as voice communication was also highlighted. It was emphasised that the NRPC forum had been given a lot of responsibilities and sub-committee has to play a vital role in ensuring reliable SCADA, telemetry and communication system for safe , efficient and economic grid operation. The presentation also covered various provisions in the new regulation by CERC on communication system for power sector. Copy of the presentation is enclosed at Annexure-III.

1. C O N F I R M A T I O N O F M I N U T E S

1. Confirmation of Minutes: The minutes of 11th meeting of TeST sub-Committee held on 10.17.2017 were issued on 08.08.2017. Comments from DTL were received. After discussion, it was decided that in para 2.5.4 of MoM, the date of Start of AMC would be read as 01.04.2016 in place of 01.04.2017.

With this correction the minutes were approved by the TeST sub-Committee.

1A. Follow -up

1A .Follow-up of Decisions of 11th TeST meeting held on 10.07.2017 Brief of important decisions taken in the 11thTeST meeting and status as available in NRPC Sectt. was enclosed at Annexure-1.1 of the agenda and members were

Page 5: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

3

requested to provide latest status. It was noted that only few utilities had provided updated status before the meeting. The status of various works as per discussions in this meeting is updated in paragraphs under relevent agenda items. Sub-committee again advised all the members , to send, the status of the actions on remaining items. It was also advised that if the action could not be taken, then, the reasons, constraints and action plan for completion of the task may be submitted to NRPC Secretariat by 15th January,2018.

( Action: All the members; Time Line: 15th January,2018)

2. Telecommunication Related Issues

2.1 OPGW installation under central and state sectors:

2.1.1.1 Latest status of OPGW installation progress under central sector:

POWERGRID informed that out of 5203 Kms. of OPGW under Central sector, OPGW of 5162 Kms. had been completed. The details of balance OPGW, which was on under - construction lines were as under: i) Abdullapur – Dehradun : 64.6 Kms. out of 89 Kms completed. Balance

is 24.4 Kms. Expected to be completed by Feb.,2018 . Construction of transmission line is held up due to severe RoW issues.

ii) Kishenpur – Dulhasti : 113 Kms. out of 119 Kms completed. Balance

is 6 Kms.. Expected to be completed by Jan’2018. Delay was due to severe RoW issues.

iii) Uri-II to Uri-I line : 10Kms. It was deleted from the scope due to sever RoW problem However, as per discussion in 40th NRPC meeting, POWERGRID will deploy their team one more time, NHPC will provide necessary support during the work. Commissioner of Power, J&K PDD had also assured for District Administration’s help for clearance of RoW issues. POWERGRID informed that team will be deployed after completion of Kishenpur-Dulhasti link as same team may be utilised for completion of this link and this would be final attempt for this link.

2.1.2 Reliable Communication Scheme under Central Sector for NR.

2.1.2.1 SE, NRPC informed that in the 37th TCC & 40th NRPC meetings held on 27th & 28th October,2017 at Sri Nagar, implementation of following Communication Schemes were approved:

Page 6: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

4

a) Reliable Communication Scheme under Central Sector for Northern Region consisting of 5428 Km of OPGW along with communication equipments and associated items at a cost of Rs. 177 Cr.

b) Replacement of OPGW along with communication equipment and associated items installed under ULDC project Phase-I consisting of 1820 Km of OPGW along with communication equipments and associated items at a cost of Rs. 60 Crs. The same is taken up as a part of Reliable Communication Scheme under Central Sector for Northern Region.

2.1.2.2 In this meeting, Representative of POWERGRID informed that DPR had been

approved but due to revision in Qualifying Requirement (QR) with the provision of “Make-in-India” , tendering process was rescheduled. He added that NIT was expected by Jan’18.

2.1.3 Latest status of OPGW installation progress under state sector: 2.1.3.1 The progress as updated in the 11th TeST meeting, by POWERGRID, are as

under:

Sl No Name of Package Award Date

Completion schedule

Status

1 OPGW for State sector (Package-V) M/s ZTT/ECI/Steel Product

July, 2015 Feb, 2018 Out of total 1669 Kms., 1650 Kms. Completed. Balance – 19 Kms. (DTL-10, UPPTCL-9)

2 OPGW for State sector additional requirement (Package-I a) (supply Pkg) M/s SDGI-Offshore contract

Oct, 2015 Feb,2018 Initial Scope: 2800 Kms. Revised Scope: 3374 Kms. Supply completed: 2569 Kms. 403 Kms at Indian Port and balance 402 kms. to be supplied in Feb’2018.

3 OPGW for Additional requirement for CS and SS (Package-III a) M/s Prem Power

Sept,2015 March,2018

Revised scope: 706 Kms. Total supply completed. 350 Kms installation completed.

2.1.3.2 Regarding balance portion of 10 Km. under Package-V, on DTL lines i.e.

Bamnauli-Ballabhgarh ( 8 Km.) , and Bamnauli-Jhatikara (2 Km. ) ,

Page 7: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

5

representative of POWERGRID informed that under Package-V, DTL was not allowing for OPGW laying in “Live Line” condition and shut down was not provided by them till Oct’2017. POWERGRID want to do the work in “Live Line” condition as done in other links. He added that OPGW on these links would be completed at one go, as balance work is very less and vendor would not be able to deploy their team citing losses in work.

2.1.3.3 Representative of DTL agreed to arrange shutdown for completion of balance works. SE, NRPC informed that if POWERGRID is ready to do the work in “Live Line” condition then shutdown is not required and DTL should permit to complete the work. After detailed discussions, DTL agreed to issue work permit in “Live Line” condition, subject to deployment of one engineer from POWERGRID to oversee the work. POWERGRID agreed to the same.

(Action : DTL, POWERGRID; Time line:31st Jan,2018)

2.1.3.4 Representative of POWERGRID further informed that under Package-V on

UPPTCL’s 400kV Greater Noida - 220 kV Noida Sector 20 link, 2.7 Km. OPGW work was pending due to non-issuance of shutdown for both the circuits on Mono pole towers. Alternate option for fixing of clamp on mono pole tower for laying OPGW was explored and decision from UPPTCL was awaited ( subsequently, POWERGRID informed that decision from UPPTCL was received on 10.12.2017) . POWERGRID would procure these special clamps for laying of OPGW on this link. Completion is expected in Jan,2018.

2.1.3.5 POWERGRID representative further informed that under Package-V on UPPTCL’s Muradnagar-Loni link , 6.2 Km. OPGW work was pending due to severe ROW issues. He added that that balance materials would be handed over to UPPTCL as nobody from UPPTCL was involved for resolution of these issues. Representative of UPPTCL requested for one more attempt by POWERGRID in the presence of UPPTCL representative on the line during team deployment. POWERGRID representative agreed on the same and informed that this would be their final attempt. He suggested that UPPTCL may take necessary support from District Administration for resolving the RoW issues.

(Action : UPPTCL, POWERGRID; Time line:31st Jan,2018)

2.1.3.6 Regarding installation of OPGW supplied under State sector additional requirement (Package-I a) - 3374 Kms POWERGRID representative added that :

Installation for these OPGW links were bifurcated in two region i.e. NR-I (810Kms -all central sector links) and NR-II (2564 Kms Central sector & State sector). Out of 810 kms, 192 Kms had been completed, Completion target is Mar’2018. For

Page 8: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

6

NR-II, out of 2564 Kms, 730 Kms had been completed which includes HPSEBL & PSTCL links. Completion target is March,2018.

(Action : POWERGRID; Time line:March,2018)

2.1.4 State Sector Schemes through PSDF Funding: 2.1.4.1 SE, NRPC informed that for State portion UP, Rajasthan, Punjab, HP and

Uttarakhand had submitted proposal for Communication schemes for PSDF funding. Latest status of PSDF funding, of these schemes, as received from NPC division, CEA, was enclosed in the Agenda. Haryana representative had earlier informed that the scheme for their State would be submitted for PSDF funding shortly. He added that PSDF funding limit had been increased from 30% to 50%. In the last TCC & NRPC meeting held on 27th & 28th October, 2017, it was also deliberated that other States would also submit their proposal for PSDF funding and implement the schemes in a time bound manner.

2.1.4.2 In the meeting some of the members expressed that the funding limit from PSDF should further be increased to 90%, to enable states to implement the telemetry & communication schemes in a comprehensive manner.

2.1.4.3 Sub-committee advised all other states to take action as per decisions in TCC and NRPC meetings for submitting the proposal for PSDF funding and implementing the schemes in a time bound manner.

(Action : Haryana, Delhi, J&K; Timeline:March,2018) 2.1.5 Status of OPGW Connection at NHPC Power Stations:

2.1.5.1 Representative of POWERGRID informed that OPGW connectivity to NHPC’s Dulhasti, Bairasul, Sewa and Parvati-III, only, were pending. He also informed commissioning of the OPGW connectivity of different power stations as under:

Dulhasti, Bairasul and Sewa-II : by Feb,2018

Dulhasti link would be completed after completion of Kishenpur-Dulhasti line, Equipment for the same had already been installed. OPGW fibre for Bairasul and Sewa had also been laid and communication equipment would be supplied by Jan’2018 and commissioning shall be done by Feb’2018.

(Action : POWERGRID; Time line:Feb,2018)

Page 9: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

7

Parbati III: by June 2018

Salal : Completed in October 2017

POWERGRID informed that OPGW connectivity for Salal was established in April’2017, which was down due to fibre cut issues and same was rectified in Oct’2017, now data is reporting through both channels.

2.1.5.2 Uri-II connectivity covered at para 2.1.1.1.

2.1.5.3 Representative of POWERGRID informed that OPGW link for Chamera-III was working and data was reporting at NRLDC. However, reporting of data on both the channels were not working due to non-availability of dual port. He suggested that NHPC may explore the feasibility for commissioning of 2nd port at Chamera-III. NHPC informed that they had already taken up the issue with concerned SAS/Gateway firm and they were exploring the option for commissioning of 2nd port.

(Action : NHPC,POWERGRID; Time line: Feb,2018)

2.1.6 Issuance of code by NLDC/RLDC/SLDCs for changing relay setting from Auto to Non-auto mode for laying of OPGW cable in live line conditions :

2.1.6.1 POWERGRID representative informed that laying of OPGW cable in live line condition required code issued by NLDC/RLDC/SLDCs for changing relay setting from Auto to Non-auto mode. However, in spite of approval by NRPC, issuance of code by NLDC/NRLDC/SLDCs were delayed, causing delay in laying of OPGW in some links. He suggested that concerned officials may be informed for timely issuance of code for laying of OPGW.

2.1.6.2 Sub-committee advised all the concerned agencies to take necessary steps to avoid delay in work.

2.2 Communication Issues 2.2.1 Communication Plan for Channel Redundancy and to Back-up NRLDC

2.2.1.1 Representative from NRLDC informed that testing of redundant channels

was carried out along with PGCIL and it was found that out of 119 RTUs, only 76 had redundant channels and 43 RTUs were working on single channel. He emphasised that redundant channels must be provided at the earliest for ensuring reliability.

POWERGRID Representative informed that they were in the process of providing redundant channel for 27 RTUs. He stated that redundant channel for 4 RTU

Page 10: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

8

which has old S900 RTU would be provided along with replacement of RTUs. It was also informed that there were 6 IPP locations for which IPPs had to provide communication till Data collection point. He added that there were some NTPC and NHPC stations where redundant ports were not available in RTU/Gateway and requested them to provide redundant port at the earliest. Representative from NTPC and NHPC stated that they would provide redundant port within a months time.

2.2.1.2 List of RTUs without redundant communication channel, along with status of

communication channel, ownership etc. is enclosed at Annexure-IV.

2.2.1.3 The sub-committee expressed concern about delay in process of providing redundant channels for RTUs. It was decided that POWERGRID would ensure that redundant communication channel for all the generating stations & sub-stations except owned by IPPs is provided by Feb, 2018. It was also decided that owner of respective generating stations would facilitate POWERGRID in ensuring reliable communication.

(Action: Concerned Agencies as per Annexure -V; Time line : Feb,2018)

2.2.1.4 POWERGRID informed that OPGW connectivity for Nathpa-Jhakri had been

completed.

2.2.2 Requirement of Additional Ethernet Ports at NRLDC

2.2.2.1 Representative of NRLDC informed that M/s GE had installed Hardware at

NRLDC Under NR-URTDSM. There is additional requirement of 10 numbers of Ethernet port for communication between NRLDC-NLDC/NRLDC-SLDCs/NRLDC-Sub-stations. Further NLDC, URTDSM is also being installed in NRLDC premises. There is further requirement of Ethernet ports for communication between NLDC URTDSM PDC- RLDC PDC/NLDC- Backup SCADA/NLDC-NTAMC.

2.2.2.2 NRLDC representative stated that POWERGRID may provide additional

SDH equipment/Ethernet ports at NRLDC/SLDC of Northern Region to cater the requirement of URTDSM Project.

2.2.2.3 After detailed deliberations, it was decided that POWERGRID would arrange

and provide additional SDH equipment/Ethernet ports as per Constituent’s requirement (Tejas make) and the expenditure on this work may be booked under Add-CAP of the Project.

Page 11: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

9

2.2.2.4 Representative of POWERGRID requested all Constituent’s to give details of

additional requirement to place order for combined requirement of SDH equipment/Ethernet ports.

2.2.2.5 Sub-committee advised constituents to inform the requirement to POWERGRID by 31.12.2017. POWERGRID was advised to procure SDH equipment/Ethernet ports at the earliest keeping in view requirement by different agencies and future requirements.

(Action: All the members; Time line: 31.12.2017) 2.2.3 AMR Data Through Fibre Optic Network

2.2.3.1 Representative of NRLDC informed that it was decided in 34th commercial

sub-committee meeting held on 30th November, 2017 that all AMR data should be routed through fibre optic network for better reliability. Representative from NRLDC also informed that AMR data from many locations was not coming at NRLDC due to SIM/GPRS issues and suggested to explore the possibility of data through fibre optic network wherever available.

2.2.3.2 After discussion, it was decided that POWERGRID would first do a pilot at

Maharanibagh sub-station for sending data through fiber-optic link. Subsequently, the project can be taken up for all locations. Further it was decided by the sub-committee that the expenditure on this work may be booked under Add-CAP in any relevant Project.

(Action : POWERGRID; Time line: 31st Jan,2018)

2.2.4. UPPTCL Communication issues:

2.2.4.1. UP representative stated that in 8th TeST meeting, representative of POWERGRID had informed about phasing out of PDH equipments by M/s Nokia w.e.f. 31-12-2013 and these equipment would complete their planned service life on 31-7-2017. He suggested to take comprehensive view on replacement of these equipment. Representative of POWERGRID informed that it had already been intimated to all constituents that Nokia would phase out their PDH equipment. Requirement for the same was also collected from all constituents and procurement was also done as per the requirement. He further, informed that the equipment had been phased out by OEM. He added that these equipment were installed in ULDC Phase-I scheme, which had completed their life span of 15 years in July’ 2017.

Page 12: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

10

He apprised that replacement of these equipment was also approved by NRPC for which tendering would be done by POWERGRID shortly. POWERGRID representative further, informed that for running of these equipment, constituent may explore the options to divert the cards (DN2/IUZ) from those sites including other states where new equipment have been installed.

2.2.4.2. Regarding underground fibre connectivity of SLDC Gomti Nagar with 220kV S/S Gomti Nagar representative of POWERGRID informed that the works initially delayed due to non-availability of NOC from Lucknow Nagar Nigam/Development Authority, now NOC had been obtained but vendor was not doing the work. POWERGRID was going to terminate the contract and the works would be awarded to another vendor, which may take another 5-6 months. UPPTCL representative stated that this link is very critical for redundancy. The sub-committee advised POWERGRID for expediting the award process and complete the connectivity at the earliest.

( Action: POWERGRID; Time Line :May,2018)

2.2.4.3. UP representative informed that symbol for monitoring healthiness of UFR, df/dt

relays was not provided by Siemens. Representative of NRLDC informed that system was implemented by Siemens as per philosophy agreed in the earlier meetings. He stated that if there are any minor problems, Siemens would again check for resolving the issues.

2.2.4.4. UP representative informed that in Tejas communication system there were no spare ports available at SLDC Lucknow and Backup SLDC, Modipuram. Moreover, one port is defective at Panki since long time but same had not been attended. Decision and action plan in this regard is covered at item 2.2.2.

2.2.4.5. UP representative stated that data Communication routes to provide real time data of all 132 KV Sub-stations (around 400 Nos.) is proposed to be connected with existing SCADA system at Main & Backup SLDC of UP. He added that POWERGRID / Siemens may give their consent / opinion in respect of following issues: i) Connectivity issues & modification in SCADA system architecture. ii) Requirement of additional equipment for successful implementation of

scheme. POWERGRID informed that as per specification, technically there may not be any limitation and these additional stations can be integrated in existing SCADA

Page 13: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

11

system. Siemens representative assured to extend their help to the possible extent. The sub-committee advised UP to take up the issue with M/S Siemens.

2.2.5. DTL communication issues :

2.2.5.1. Replacement of diverted Communication Equipments /Additional BOQ.

DTL representative informed that a number of SDH/PDH communication equipment had been diverted / utilized by PGCIL for the project works, from earlier allocated DTL sites, such as 220KV Patparganj / Preet Vihar etc. He mentioned that plan for replacement / installation at those sites along with the additional approved BOQ for other sites, may be provided.

Representative of POWERGRID informed that procurement was under process

and same shall be replaced/replenished by Mar’ 2018.

( Action: POWERGRID; Time Line: March,2018) 2.2.5.2. Training / Drawings/documents of newly installed Communication / DCPS

DTL representative stated that no drawings / details / literature / specifications of the new Communication and DCPS equipment being installed by PGCIL at various Grid locations had been provided. He added that training on handling / utilisation of the equipment should be provided.

Representative of POWERGRID informed that all documents have been shared

with DTL. For training on OPGW and communication equipment, schedule shall be sent by 2nd week of Jan’ 2018.

( Action: POWERGRID; Time Line: 15th Jan,2018) 2.2.5.3. Regarding false alarms in DCPS Supplied at DIAL and Gopalpur Sub-stations

representative of POWERGRID informed that sites were not handed over and work was still going on. He informed that during SAT, 3 DCPSs namely Ghazipur, DIAL & Gopalpur were showing false alarms. All issues had been rectified.

2.2.5.4. Plan for completion of remaining work of 400KV Bamnauli – Ballabhgarh and Bamnauli – Jhatikara OPGW. Covered under Item 2.1.3.

2.2.5.5. Regarding plan for final commissioning of SDH & PDH supplied by M/s ECI, representative of POWERGRID informed that M/s ECI had commissioned all equipment at DTL locations, however shifting of telemetry data was yet to be migrated by DTL. On a query by DTL POWERGRID representative confirmed that as per the provision in the contract, this activity is to be carried by DTL only,

Page 14: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

12

not by M/s ECI. He informed that all data under Central sector has been shifted by POWERGRID/NRLDC, and POWERGRID can’t take risk on live data. DTL agreed on the same.

2.2.6. HP Communication Issues:

2.2.6.1. Implementation of OPGW under Package-I (a). Regarding the apprehension expressed by HP representative regarding slow pace of work under package-I (a) in HP, representative of POWERGRID accepted that installation work was very slow at present and expected to complete by May’ 2018. The sub-committee advised POWERGRID to take all necessary steps to complete the work at the earliest.

2.2.6.2. Installation of OLTE under Package- V & Package IV (a). HP representative informed that under package-V, Terminal equipment (SDH & PDH) were to be installed on 14 Nos. HPSEBL locations and DCPS system were to be installed on 08 nos. locations. As per LoA work was to be completed by 31.03.2017. He added that as information available with HP, M/s ZTT/ECI had committed to complete installation and commissioning of HPSEBL links by February’2018, subject to availability of 45A DCPS which was in the scope of Package-IV(a). Representative of POWERGRID informed that work will be completed by Feb 2018.

It was also mentioned that 45A DCPS with associated cables for HPSEBL which was in the scope of M/S Fibcom Package-IV(a) was to be supplied at site by December’2017. Representative of POWERGRID confirmed that work would be completed by the end of Feb’2018.

2.2.7. Communication Issues of BBMB

2.2.7.1. Implementation of Multisite Configuration between BBMB SLDC and PSTCL SLDC.

Representative of BBMB informed that the implementation of Multisite Configuration between BBMB SLDC and PSTCL SLDC was pending due to non-availability of communication links. The RTUs reporting through Ganguwal Sub-LDC were connected as per multisite configuration, but all the RTUs of PSTCL become down. He informed that as advised by POWERGRID the

Page 15: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

13

possibility of IP conflict was also checked, but the problem of non-reporting of PSTCL, RTUs by connecting the multisite link at PSTCL end remained the same. Representative from POWERGRID informed that the SIEMENS engineer would visit BBMB in first week of Jan,2018 to resolve the issue.

( Action: POWERGRID/SIEMENS; Time line: 15th Jan,2018)

2.2.7.2. Additional Requirement of Cards in the TEJAS make SDH:

This issue is covered in item 2.2.2.

2.2.8. Communication Issues of PSTCL:

2.2.8.1. PSTCL Multisite link issue:

Representative of PSTCL informed that data is being transferred through ICCP due to non functioning of multisite functionality and requested POWERGRID to take up the matter with M/s Siemens Ltd. for its early solution. Representative of POWERGRID informed that the Siemens engineer would visit BBMB in first week of Jan, 2018 to resolve the issue.

( Action: POWERGRID/SIEMENS; Time line: 25 th Jan,2018)

2.2.8.2. Earthing issue at 220 kV Moga station (PSTCL)

POWERGRID representative informed that Cards of Communication equipment got faulty/burnt at 220kV Moga sub-station of PSTCL due to earthing issues in the sub-station. He added that cards burnt at least Eight (08) times in last 2 years. However, no action was taken up by PSTCL. He further informed that PSTCL had only replaced earthing instead of third party audit (by SAMEER - Govt. of India) as discussed during the 11th TeST meeting. After the discussion in last meeting, cards were burnt 2 more times at Moga 220kV (PSTCL) and caused non-receipt of at least 5-6 sub-station data routed through that direction. Replacement of cards (5-6 cards) at each time was done , which had huge financial implication.

The Sub-committee expressed its concern on non-availability of telemetry from

a number of stations due to this issue. The sub-committee advised representative of PSTCL get the earthig audited by third party at the earliest.

Page 16: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

14

PSTCL representative assured that the matter has already been taken up at the higher management level and the audit of earthing would definitely be completed by first week of Jan, 2018. He requested POWERGRID to provide the cards. The Sub-committee advised PSTCL to complete the earthing audit by third party by 10th Jan, 18 and inform POWERGRID, NRPC Sectt. and NRLDC.

(Action: PSTCL; Time Line: 10th Jan,2018) The Sub-committee advised POWERGRID to replace the cards at the earliest, so that telemetry can be established.

(Action: POWERGRID; Time Line: At the earliest)

2.2.8.3. Speech Connectivity: Representative from PSTCL informed that most of the Renewable Energy Sources/Plants telemetry data is reporting at SLDC Ablowal through MPLS/Lease Line/ GPRS etc. However, speech connectivity has not been made available. As a lot of renewable energy generators (of capacity from 1MW to 50 MW) are coming up & being integrated with the SCADA at the level of 132 KV, 66KV, 33KV & 11KV, matter needs to be deliberated amongst the members for deciding the required measures/alternatives to be taken by Renewable Energy Sources/Plants for making available the speech, along with the telemetry data from Renewable Energy Sources/Plants to SLDC, Ablowal and complying with “CEA Regulations for Grid Connectivity of Renewable Energy Sources”. A presentation on the different provisions in Central Electricity Regulatory Commission (Communication System for inter-State transmission of electricity) Regulations, 2017 was given by NRPC Secretariat in the meeting, wherein the role of various agencies is clearly defined. It was clarified that as per provisions in these regulations, the STU is responsible for planning, coordination and development of reliable communication system for data communication within a State including appropriate protection path among State Load Despatch Centre, Area LDC, Sub-LDC and DISCOM LDC including Main and backup as applicable along with STU Sub-Stations, intra-State Generating Stations. Further, the “Users” including renewable energy generators are responsible for provision of compatible equipment along with appropriate interface for uninterrupted communication with the concerned control centres and shall be responsible for successful integration with the communication system provided by CTU or STU for data communication as per guidelines issued by NLDC. It was also clarified that the word “Data” includes voice also. Thus, the responsibilities for voice communication are clearly defined in the Regulations.

Page 17: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

15

The sub-committee advised all the concerned agencies to abide by the regulations and if there is any specific issue in implementing the system, it can be brought to the sub-committee for resolution.

2.2.9. Communication issues of RVPNL

2.2.9.1 Requirement of E&M card for fiber home PDH/SDH system

RVPNL representative informed that E&M cards for fiber home PDH/SDH system was required for VF data channel. But M/S COMMTEL had conveyed that the E&M cards were obsolete and no more available with the OEM (i.e. Fiber home). She suggested that M/S COMMTEL may be directed to provide the E&M cards on priority basis . It may also be ensured that at least after up to ten years (after functioning), the firm should be able to provide spare parts such as E&M cards etc. Representative of POWERGRID stated that vendor could not run away from their responsibility and agreed to take up the issue with M/s Fibrehome & M/s Commtel in line with the contractual terms & conditions. He stated that POWERGRID will convey the actions taken in this regard by 15th Jan.2018 to RVPNL and NRPC Sectt.

(Action: POWERGRID; Time Line: 15th Jan., 2018)

2.2.9.2 Repairing of HBL Make DCPS Installed by M/S COMMTEL:

RVPNL representative informed that repairing of HBL make DCPS installed by M/S COMMTEL at various site in the RVPN at various sites was pending since long. Representative of POWERGRID informed that there was issue in 48V DCPS at PSTCL and RRVPNL sites, which had already taken up M/s Commtel & M/s HBL, they would rectify the 48V DCPS and batteries. He added that HBL team had started the work from Punjab and after completion of work in Punjab; the teams would be deployed at RRVPNL sites.

(Action: POWERGRID; Time line: 31st Jan, 2018)

Page 18: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

16

2.2.9.3 Issuing of Letter Regarding Transfer of Assets to the RVPN Under ULDC :

RVPN representative raised the matter of issuing of letter for transfer of assets, under ULDC phase-I, to the RVPN by the POWER GRID so that the unused material / spares may be deposited in our store for further auction. Representative of POWERGRID informed that mater had been taken up with concerned department and it was informed by them that payment against FERV part was yet to be settled with Constituents. POWERGRID had raised the invoices for FERV up to Mar’ 2017 and payment for the same was yet to be received from Constituents. He added that balance invoice up to July’ 2017 would be raised shortly and requested all the constituents to release the payment at the earliest, so that POWERGRID can issue the letter for payment settlement. The sub-committee advised POWERGRID and all the members to take necessary action to settle the long pending issue by March, 2018.

(Action: POWERGRID & All the States; Time line: 31st March, 2018)

2.3 RTU Related issues

2.3.1 Replacement of S900 RTUs

SE, NRPC informed that in 11th TeST Meeting, it was decided that POWERGRID would replace S900 RTUs at their sub-stations and procure the same for other constituents who had consented for their RTU replacement through POWERGRID. He added that in the 37th TCC and 40th NRPC meetings held on 27th & 28th October,17, the matter was discussed . Concern was expressed over delay in replacement of RTUs and POWERGRID was advised to procure RTUs as per request of other utilities at the earliest, so that replacement may be done timely. POWERGRID representative assured that if there is delay in replacement, then AMC would be extended to ensure proper maintenance of the RTUs. POWERGRID had informed that procurement would be done on deposit basis, after advance payment. Keeping in view, small amount of expenditure and complications in procurement of RTUs, separately by different utilities, TCC had advised all the concerned utilities to consider POWERGRID proposal to avoid further delay in the process.

In this meeting, Representative from POWERGRID informed that after approvals from management for procurement of new RTUs. MOU/Agreement for the same would be sent to Constituents within 15 days for signing, after signing of MOU, POWERGRID will float the NIT. On enquiry for extension of AMC of these RTUs, POWERGRID informed that presently AMC for these RTUs is up to July’2018 and same may be extended by one more year.

Page 19: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

17

The sub-committee advised other members, who are procuring themselves, to take necessary action for timely replacement of S900 RTUs in their system. All the members were advised to submit action plan by 15th Jan,2018, for replacing S 900 RTUs in their system, to NRLDC and NRPC Sectt.

( Action: All the members; Time Line: 15th Jan,2018)

2.3.2 Charges for bay extension in Siemens RTU’s.

Representatives of DTL and HPSEB requested POWERGRID to provide Unit charges for extension of 220 / 66 / 33 KV bays in RTU’s installed by Siemens under ULDC#2 to the Utilities to enable the proposed bay extension work at various sites. Representative from POWERGRID informed that they would provide bay extension charges for SIEMENS RTU by 15.01.2018

( Action: POWERGRID; Time Line: 15th Jan,2018)

2.3.3 Flip Flop of HVPNL RTU data : HVPNL representative informed that the RTUS reporting to SCADA Control center over 60870-5-101 protocol were getting flip flop i.e. get suspected frequently. Representative of POWERGRID informed that the Siemens engineer would visit HVPNL on 26.12.2017 to resolve the issue and requested HVPNL to ensure availability of Schneider engineer at their end.

( Action: POWERGRID, HVPNL; Time Line: 26.12.2017)

3. Issues in Unified Load Dispatch & Communication scheme of NR (Phase-II)

3.1.1 Rollover to IPv6:

NRLDC representative stated that as per notification from Ministry of Power all external world connectivity has to be migrated to IPv6. He added that they were in the process of shifting the external world connectivity to IPv6 and internal SCADA LAN would be on IPv4 only. NRLDC suggested all the utilities to migrate their external world connectivity to IPv6. The sub-committee advised all the members to take timely action for migration to IPv6 in compliance to Govt. directions. It was also clarified that the concerned utilities had to carry out this activity themselves, in coordination with their internet service provider.

( Action: All the SLDCs / STUs: Time line: At the earliest)

Page 20: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

18

3.1.2 Weather data

Representative from NRLDC informed that weather data from new locations installed under SCADA upgrade was not updating correctly at NRLDC and requested Siemens to rectify at the earliest. Representative from M/s Siemens informed that they will take up the matter and rectify all the data within one month time.

( Action: Siemens; Time line: 31st Jan,2018)

3.2 SCADA Issues raised by State SLDCs 3.2.1 SCADA Issues of HPSEB

3.2.1.1 Latency Issue

HPSEB representative informed that latency was observed in SIEMENS RTU’s in HP. Due to latency in data reporting, difference in SEM vs SCADA values has been observed. He added that during the AMC visit of M/s SIEMENS’s RTU Engineer, baud rate was increased to 600 baud at Baddi & Giri Stations but the latency issue could not be resolved Representative from M/s Siemens informed that they would resolve the issue in next visit for preventive maintenance.

( Action: M/s Siemens; Time line: 15th Jan,2018)

3.2.2 PSTCL SCADA Issues:

3.2.2.1 Interruption in publishing of SCADA data on SCADA Web Server:

PSTCL representative informed that data publishing on web server was getting interrupted many times, which resulted into inconvenience to remote user/ Dispatcher.

Representative from M/s Siemens informed that they had raised the issue to the developer and issue would be resolved shortly.

( Action: POWERGRID, M/s Siemens; Time line: 31st Jan,2018)

3.2.2.2 PSTCL representative informed that during the last TeST meeting held on 10.07.2017, POWERGRID agreed for shifting of telemetry data route of 400 KV Mukatsar, 400 KV Talwandi Sabo & 400 KV Mukatsar to SLDC, Ablowal via 400 KV PGCIL Moga instead of existing PDH system installed at 220KV Moga but no affirmative action had been taken .

Page 21: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

19

Representative from POWERGRID informed alternative route through 400KV Moga is not possible and requested PSTCL to arrange Third part inspection of earthing at the earliest. PSTCL informed that they would arrange third party audit and requested POWERGRID to arrange the cards.

(Action: POWERGRID, PSTCL; Time line: 15th Jan,2018)

3.2.3 SCADA issues of UPPTCL:

3.2.3.1 EMS Issues: UPPTCL representative informed following issues to be resolved:

(i) For some buses in database, name of buses were appearing as LUCK1-up, ALHAe1-UP instead BB1, BB2.

(ii) For transformers, estimated values for both HV & LV sides were showing

load flow either towards the T/F or away from T/F (towards HV & LV buses). Moreover, if direction of any side data was corrected manually then big difference between HV & LV values were been observed in estimated values.

(iii) After sometime (1,2 months), data of some of the RTU stations get erased.

This phenomenon was observed after data synch also.

iv) Per unit voltage profile for various voltage level was still unresolved.

(v) EMS database loading into OTS was still not taking place even after attending measurement consistency problems.

(vi) Following EMS applications were still not running

(a) Security Analysis (b) Voltage scheduler (c) Security Despatch (d) Transmission corridor Monitoring

(vii) Even after changes in database, UPPTCL load in State Estimator was not

increasing beyond 6000- 8000MW.

(viii) Large difference in company load was appearing as seen through following commands.

SE > RT Summaries > Company Summary

SE > Input > System Operating Parameters > Company Summary

Page 22: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

20

(ix) Mechanism / Procedure for checking accuracy of estimated loads of individual feeders/ Sub-Stations/ Gen-Stations/ Zones / Company was required.

(x) In database, for weekdays hourly data provision for 24 Hrs. has been

provided, where as for Saturday and Sunday provision for hourly data has been provided for only 2 Hrs.

(xi) Write up/ user Manual from operation point of view describing procedure for

using various EMS applications in study as well as in real time mode was not provided.

Representative of SIEMENS informed that there were some database modelling issues which needs to be corrected. He further informed that their representative would visit UPPTCL by 23rd Jan 2018 for resolving above issues. The sub-committee advised M/s Siemens and POWERGRID to take necessary action for resolving the issues by 31st Jan,2018.

( Action: POWERGRID, M/s Siemens; Time line: 31st Jan,2018)

3.2.3.2 OTS issues: UPPTCL representative informed that data Population /

Synchronisation problem was still persisting. Various SCADA & EMS applications were not running.

Representative of SIEMENS informed that they had raised the issue to the developer and would try to resolve the issue as soon as some inputs are received. POWERGRID was advised by the sub-committee to take up the matter with concerned agencies.

( Action: POWERGRID, M/s Siemens; Time line: 31st Jan,2018) 3.2.3.3 PDS issues: UPPTCL representative informed that running of PDS was

not smooth. Problems in PDS were occurring frequently which remained unattended for long period.

Representative of SIEMENS informed that this issue is because of mismatch between real time database and PDS database. He suggested to first update the model in PDS then migrate to real time for smooth functioning of PDS.

3.2.3.4 Representative of UPPTCL informed that following points with reference to recent outage of SCAD at SLDC, UP needs clarification:

Page 23: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

21

i. Standby servers (Hot standby servers for some applications and backup servers for some other applications) also failed. Is there any change required in system architecture to avoid simultaneous failure of Main & standby servers?

ii. Failure of SCADA Switch-1 resulted in non- reporting of data on consoles through SCADA switch-2 indicates special efforts are required to avoid the repeatability of the event in future.

iii. The time taken for normalization of various systems & application took more than 7 days. Lessons from this incidence is to be taken so as to avoid such happenings.

iv. In Web-servers, some displays do update while some displays do not. Proper action plan is required to avoid such events. Representative of M/s SIEMENS stated that all these issues would be seen during SIEMENS representative during the proposed visit of UP, SLDC in third week of Jan,2018.

( Action: POWERGRID, M/s Siemens; Time line: 25th Jan,2018) The sub-committee expressed concern over the outage of SCADA system at UP SLDC. UP, SLDC was advised to submit a detailed report on the incident including reason for outage, remedial action taken, issues still to be resolved, learning and actions required to be taken by other utilities to avoid such incidences, by 31st Jan,2018 to NRPC Sectt.. It was also decided that UP, SLDC would make a presentation in the next TeST meeting on this report. POWERGRID and M/s Siemens were advised to take all the remedial measures required to be taken to avoid such incidences.

( Action: UP, SLDC; Time Line: 31st Jan,2018) 3.2.3.5 Maintenance of UPS system:

UPPTCL representative informed that 2 Number cells were defective since more

than 2 months and had not been replaced. POWERGRID and M/s Siemens representative assured to get it rectified.

( Action: POWERGRID, M/s Siemens; Time line: 25th Jan,2018)

3.2.3.6 Monitoring of UPS Status & Alarms through SCADA:

Page 24: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

22

UPPTCL representative informed that provision of FRTU was agreed by the constituents.

Representative of POWERGRID informed that as per discussion during last TeST sub-committee meeting, procurement of FRTUs will be done along with procurement of RTUs.

( Action: POWERGRID; Time line: along with RTUs)

3.2.4 SCADA Issues of HVPNL 3.2.4.1 Website:-HVPNL representative informed that Haryana SLDC website name is

www.haryanasldc.org, but it opens up with the domain name www.haryanasldc.org/CorporateUI . He added that ‘CorporateUI’ should not be required with the domain name, so that website could be accessed with its domain name www.haryanasldc.org.

Representative of SIEMENS informed that the solution to the issue had been found and it would be implemented within few days. NRLDC representative assured to coordinate in the matter.

( Action: NRLDC, M/s Siemens; Time line: 31st Dec,2017) 3.2.4.2 Database Synchronization: - HVPNL representative informed that the

incremental ICCP data base should be provided along with domain data while database synchronization on monthly basis, so that changes with respect to the other constituents could become available with every database modifications.

Representative of NRLDC informed that as decided in 11th TeST meeting,

database synchronization activity was being done on monthly basis. This only includes synchronization of domain data. However, ICCP and TNA database is to be maintained individually by each control centre. NRLDC would share the ICCP database before database synchronization to facilitate ICCP configuration by Constituents. HVPNL representative insisted that NRLDC should provide updated data, periodically. The sub-committee advised NRLDC to explore the feasibility of sharing updated ICCP data base in first week of every month with States.

(Action: NRLDC; Time line: Monthly) 3.2.4.3 EMS tuning: HVPNL representative raised the issue of suitable manpower

deployment by M/s SIEMENS, who can help in EMS tuning activity by SLDC. M/s Siemens representative assured to look into the issue. It was also

Page 25: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

23

deliberated that the training on EMS would be organised shortly, which may provide hands on training to SLDC personnel on EMS.

3.2.5 Other Deliberations:

3.2.5.1 Many of the members suggested arranging regular periodic meeting with concerned vendors of ULDC Ph-II to resolve issues. POWERGRID representative agreed to call bimonthly meeting with all concerned .

( Action: POWERGRID; Time line: Bimonthly)

3.2.5.2 The issue of testing of back-up SLDCs was also raised by some members. It was informed that BBMB and UP were in process of testing their back-up SLDCs, wherein they were facing some issues. M/s Siemens representative assured to resolve the issues by Jan., 2018.

3.2.5.3 To verify healthy functioning of back-up SLDC, as it is very important for system reliability, It was decided that all the SLDCs would test back-up SLDC at least once in every six month. The sub-committee advised all the members to complete this exercise by 31st March, 2018 and then repeat this exercise in every six month. It was also decided that M/s Siemens would extend necessary help in this endeavour to resolve issues expeditiously.

(Action: All SLDCs, M/s Siemens; Time line: 31st March,2018)

4.1 Present Status of Telemetry: 4.1.1 Non-Availability / Reliability of Telemetry:

NRLDC representative gave a detailed presentation on telemetry status. He informed that the new stations at 400 kV were being integrated in the system. In some of the stations , the telemetry was implemented before charging of the new element, but subsequently, the reliability of telemetry was not at all assured. He informed that the reliability of telemetry of the following stations was very poor :

400 kV Hapur 400 kV Chitorgarh

400 kV Chhabra

400 kV Banauli

400 kV 400 kV Talwandi 400 KV Orai 400 kV

4. Telemetry Related Issues

Page 26: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

24

Muradnagar(N) Saboo

Srinagar 400 kV Nehtaur 400 kV Muktshar 400 kV Kashipur 400 kV Uri

400 kV Mathura 400 kV Nakodar 400 kV Rishikesh 400 kV Fatehabad

400 kV Karcham Wangto 400 kV Parvati – II 400 kV Parvati - III 400 kV Chamba 400 kV Nathpa Jhakri 400 KV Banala 400 KV Deedwana 400 KV Aligarh 400 KV Greater Noida 400 KV Dhanoda 400 KV Agra UP 400 KV Bhadla 765 KV Unao 400 KV Muradnagar 400 KV Makhu

He further informed that reliability of telemetry for some of the stations were poor since its integration. Representative from NRLDC informed that the data from above stations was highly intermittent and requested for restoration of reliable Telemetry at the earliest. MS NRPC also requested to look into the matter seriously, as data availability is very critical for smooth grid operation. He further requested all constituents to rectify the issue within one month’s time.

The issues behind non-reliable telemetry, in each station, were discussed in detail. All the concerned utilities had assured to resolve the issues by 31st Jan,2018 .The sub-committee advised all the concerned utilities to resolve the issues within the agreed time line and send report to NRLDC and NRPC Sectt.

(Action: Concerned Utilities Owning the sub-station; Time line: 31st Jan,2018)

4.1.2 Telemetry of digital status

Representative from NRLDC in his presentation highlighted that digital telemetry was very poor. MS, NRPC requested all the members to take up the issues with concerned agencies to ensure 100% digital data telemetry , as without telemetry the grid operation may be detrimental to safety and security of the grid.

(Action: Concerned Utilities Owning the sub-station; Time line: 31st Jan,2018) The sub-committee advised all the utilities to ensure availability of digital telemetry. It was also decided that NRLDC and SLDCs would rigorously monitor the status of telemetry in the Gen. Stations & Grid sub-stations in their control area and send periodic reports to all concerned for taking remedial action. A copy of the report should also be sent to NRPC Sectt. for further follow up with higher management of respective utilities.

(Action: NRLDC and SLDCs; Time line: Monthly Periodic) 4.1.3 ICCP Communication Between PTCUL and NRLDC:

Page 27: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

25

ICCP communication link between PTCUL and NRLDC is highly non-reliable and there is outage of days together. Till time Fibre optic connectivity is established alternate channel may be arranged at the earliest. Representative from NRLDC informed that ICCP communication between PTCUL and NRLDC had been established through OPGW in Dec 2017.

4.1.4 RGMO Telemetry at NRLDC:

Representative from NRLDC informed that RGMO status from NHPC and THDC stations were available at NRLDC and requested other generating stations to provide RGMO telemetry to NRLDC at the earliest. The sub-committee appreciated the successful efforts by NHPC and advised other generating companies to take immediate necessary action to provide RGMO telemetry. Representative from NTPC informed that they were in process of integration and would provide the status by 31.01.2018. Representatives of other Generators also agreed to submit their action plan to achieve this task.

(Action: All Generating Stations Except NHPC’s& THDC’s; Time line:

31st Jan,2018)

4.2 HVPNL Telemetry issues:

4.2.1 Calculation of Actual Drawl in SCADA: Representative of HVPNL informed The SEM and SCADA data for each points are being compared and the points for which % age errors are more than 5 % are reported for correction. The inaccuracy/mismatch (in SCADA Vs SEM) for the points mentioned below was reported in past months but the problem was yet to be resolved.

1. Hisar_PG - 220 KV Fatehabad-1 2. Bhiwadi_PG – 220KV Mau 3. Kurukshetra HVDC_PG – 400/220KV T/F T-1 & T-2 4. Fatehabad_PG – 400KV RGTPS 5. Bhiwadi_PG – 220KV Rewari -1 6. Fatehabad_PG – 220KV T/F T-1 7. Hisar_BB – 132KV Rajgarh 8. Hisar_BB – 132KV Amarpurthedi 9. Jagadhari_Bb – 220KV T/F T-3 10. Ballabgarh_BB – 220KV T/F T-1 11. Dhulkote_BB – 66KV Chandigarh -2

Page 28: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

26

12. Delhi_BB – 66KV Gurgaon-1 13. Hisar_BB – 220KV Jindal

HVPNL requested POWERGRID/ NRLDC to resolve the problem of SCADA data mismatch with SEM to ensure accuracy of telemetry data. NRLDC representative informed that Bhiwadi_PG – 220KV Mau and Kurukshetra HVDC_PG – 400/220KV T/F T-1 & T-2 were at no load. For other grid points POWERGRID and BBMB agreed to resolve the issues by 15th Jan,2018. Member Secretary, NRPC requested HVPNL, BBMB, NRLDC and POWERGRID to resolve the issue and rectify the mismatch problem at the earliest, this mismatch has financial implications . Representatives of POWERGRID , BBMB and HVPNL agreed to take action to resolve the issue. The sub-committee advised all concerned utilities to take immediate action and send report to NRPC Sectt. by 15th Jan,2018.

( Action: POWERGRID, BBMB, HVPNL; Time Line 15th Jan,2018)

4.3 Discrepancy between data from interface meters and SCADA

4.3.1 Procedure approved by NRPC in 36th NRPC meeting

SE, NRPC informed that in 32nd TCC and 36th NRPC meeting held on 23rd and 24th Dec, 2015, report of the group , constituted by NRPC secretariat to analyze reasons for mismatch between drawl of Uttar Pradesh calculated from SCADA and Interface Meters and to suggest suitable measures for minimizing this difference, was approved. Details of the procedure given in that report and agreed for verifying the drawal data on weekly basis & to find out reasons for discrepancy, if any, were given in the Agenda.

He urged all the members to follow this procedure and submit the details to NRPC Sectt. and NRLDC before putting it in TeST meeting, so that the matter may be examined and fruitful discussions may be held in the TeST meeting. The sub-committee advised all the constituents to follow the agreed procedure, carry out exercise at their end and report the mismatch to NRLDC/NRPC Sectt.

( Action: All the STUs/SLDCs; Time Line: Periodic)

5.1.1 Space at NTPC- Dadri for installation of PMUs under URTDSM Project :

5. Unified Real Time Dynamic State Measurement (URTDSM) Scheme.

Page 29: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

27

Representative of POWERGRID informed that POWERGRID was installing PMUs at various sub-stations of central and state sector utilities under URTDSM Project. There was space problem in NTPC- Dadri for installation of PMUs at control centre. Matter was pending since long back as supply of PMUs was made in Jan’2016 and installation was pending due to space issue, earlier NTPC informed that works for extension of existing control centre will be taken up and then PMUs can be installed, however space is yet to be provided by NTPC for installation of PMUs. Representative of NTPC informed that extension work of building at Dadri was going on and work would be completed by end of Feb’ 2018, then POWERGRID can install PMUs in Dadri NTPC control centre.

( Action: NTPC, POWERGRID; Time line: Feb,2018)

5.1.2. URTDSM Status: Representative of POWERGRID informed that materials for PDC had been supplied in all control centres. Installation has been completed except NLDC, Jammu & Dehradun SLDCs which would be completed by end of Dec, 2017. SAT at some of the constituents was going on. Latest status is enclosed at Annexure-V. All constituents were requested to nominate and post at least 2 nos. of officials for WAMS system who had taken training on the PDC system. The sub-committee expressed concern over inordinate delay in implementation of the URTDSM project and advised POWERGRID as well as other concerned utilities to take necessary action for completion of the project in all respect by March,2018.

( Action: POWERGRID; Time Line: 31st March,2018)

5.1.3. Installation of PMU at HVPNL:

Representative of HVPNL informed that 3 No. PMU had been installed at 220 kV Generating station in Stage 1 to 4 , 5 to 6 and 7 to 8 PTPS, HPGCL Panipat. But now Unit 1 to 4 has been approved for dismantlement & the PMU is not useful. Moreover Unit 5 to 6 and Unit 7 to 8 are have common bus. He added that HVPNL was not associated in the installation work of these RTUs. He suggested that PMUs may be relocated to useful sites.

POWERGRID representative informed that PMU installed was done in 2015, at that time no information about alternate location was provided by HVPNL. HVPNL requested that since the generation unit was closed so there is no use of PMUs at

Page 30: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

28

that location, so shifting of PMUs may be explored to other locations which are included in Phase-II scheme. The sub-committee advised that in consultation with NRLDC, alternate location may be finalised for installation of these PMUs. POWERGRID requested that a cut-off date may be fixed for shifting of PMUs as after some time other plants may be closed which will impact the closing of contracts. After detailed deliberations, it was decided that information regarding change in location of installed PMUs may be sent to POWERGRID, NRLDC and NRPC Sectt. latest by 15th Feb,2018, after which no request for any relocation would be accepted.

( Action: All Gen. & Transmission Utilities; Time line: 15th Feb,2018)

5.1.4. Installation of URTDSM Equipment in BBMB: Representative of BBMB informed that URTDSM equipment cannot be installed at BBMB, SLDC until the commissioning of new UPS to be supplied at BBMB, SLDC is installed. Due to implementation of GST etc. the tender for the civil works required to be executed in the proposed UPS Room could not been completed. He suggested that POWERGRID may explore the possibility of carrying out the civil work by the UPS vendor and booking of the cost for this work URTDSM Project. POWERGRID informed that it was not possible as no civil work item was mentioned under this contract. He mentioned that BBMB should carry out the installation as it was a long pending issue. POWERGRID informed that New UPS would be supplied in Feb, 2018, before that BBMB should ensure readiness of UPS room for installation. Commissioning of URTDSM system would be done through existing UPS System and after commissioning of new UPS load would be shifted on new UPS.

( Action: BBMB; Time Line: Feb,2018)

.

6.1 Disposal of Old and Obsolete SCADA Equipment of ULDC-I Scheme

6. Other Misc. Issues

Page 31: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12th meeting of TeST Sub-committee (22.12.2017)-Minutes

29

SE, NRPC stated that in the 11thTeST Meeting, representative of POWERGRID had informed that the matter was taken up internally with the commercial department regarding processing of the residual value of the equipment installed under ULDC Ph.-I, after depreciation and the disposal would be confirmed through letter by 31st July, 2017. But as per information received from many utilities, no confirmation in this regard had been sent by POWERGRID.

Representative of POWERGRID informed that they were yet to receive the final payment from the constituents. Once the payment is received they would issue the letter. Details covered at para 2.2.9.3.

( Action: POWERGRID; Time line: March,2018)

6.2 Dismantling of Microwave Tower in NRLDC

This agenda was deferred.

6.3. Additional Agenda

UPPTCL URTDSM Issues:

Representative of UPPTCL informed that out of 16 PMU Stations ( 5 no. Gen. Stations & 11 no. Grid Sub-Station), data of only 6 Six nos. was available at PDC. Issues and the updated status given by POPWERGRID are as under:

6.3.1 Data Communication:

a) Harduaganj TPS – OFC laying by first week of Jan’ 2018 b) Moradabad-1 – data already reported c) Obra- A TPS - OFC cable laying done, data integration by 15th Jan’ 2018 d) Obra-B TPS - OFC cable laying done, data integration by 15th Jan’ 2018

6.3.2 Backup data communication link for PMU data reporting from Sub-Station to

control centre would be provided after procurement of Tejas make Equipment/cards (additional requirement)

6.3.3 Problem in data reporting: Anpara , Azamgarh , Khara , Sarnath are reporting at control centre. Would be integrated by 10th Jan’ 2018.

Page 32: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

Annexure-I

List of participants in the 12th meeting of Telecommunication, SCADA and Telemetry sub-committee held on 22.12.2017 in Lucknow

Organization

Name of Officer DISIGNATION Email ID

NRPC Sh. MAKP Singh Sh. Upendra Kumar Sh. Hemant Kumar Pandey Sh. K.N.M Rao Sh. Vikrant Dhillon Sh.PR Koushik

Member Secretary SE(O) SE(C ) Asst. GM AEE AE

[email protected] [email protected] [email protected] [email protected]

POWER GRID

Sh. Y.K. Dixit Sh. N K Meena Sh. M P Singh

GM(ULDC & Engg.) Dy. Manager NR-I Dy. Mgr, NR-II, Jammu

[email protected] [email protected] [email protected]

POSOCO Sh. Ankur Gulati Dy. Manager

[email protected]

PSTCL Sh.Ankit Bedi

AE SLDC

[email protected]

PDD J&K Er Asgar Ali Majaz Dev.commr,power PDD(J&K)

[email protected]

UPPTCL Sh. Ram Swaruth Sh. A K Singh Sh. C K Shukala Md. Irfan. Alam Md.Sanshad Hussen Sh.Ashtosh Dixit Sh. Piyush Shukla Shazad Alam Khan Zahir Ahmad Sh. A K Verma Sh.M.N Shukla Sh. Raj Ashok Sh. Amit Narayan Sh.Sanjeev Bhasker Nishant Hamidi

Director(SLDC) CE(C&S) CE(PSO) SE(SCADA&IT) SE(Microwave) SE SE SE SE SLDC AE(SCADA&IT) EE EE(ETD1) EE EE EE SLDC EE

[email protected] [email protected] [email protected], [email protected] system.upptcl;@gmail.com [email protected], [email protected] [email protected] [email protected] [email protected] [email protected] [email protected] [email protected] [email protected]

Page 33: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

Sh.Vivek Mortolia

DTL Sh. Pradeep Katiyar Parvez Khan

DGM(SLDC) Manager(T)

[email protected] [email protected]

HVPNL Sh. R K Koushik

SE(SLDC) [email protected]

RVPNL Sh.Arvind Agarwal Smt. Sheela Mishra

SE(comml.) SE( SSDA-SLDC)

[email protected] [email protected]

BBMB Sh. H.S Manocha Sh. S Dilbagi Sh. Rajneesh Sarwal

Addnl SE Addnl. SE AEE

harpreetsmanocha@gmaii [email protected] [email protected]

HPSEBL Deepak Uppal Dy. CE(ALDC) [email protected] HPPTCL

Sanjay Koushal Sh. Vivek Sharma

Sr. Mgr Dy. Mgr

[email protected] [email protected]

PTCUL Sh.Anupam Singh Sh. Ashu Sagar

SE (SCADA) EE(SCADA)

[email protected] [email protected]

NTPC Sh.Rakesh Chopra Sh. B. L.Yadav Sh.Abhishek Jain

GM(Comml) AGM Mgr(EM) Jajjar

[email protected] [email protected] [email protected]

NHPC Sh. Rahul Ranjan

DM(E&C)

[email protected] [email protected]

THDCIL Sh. S D Basiyal Manager [email protected]

SJVN Sh.Rajeev Agarwal

Manager

[email protected]

IPGCL-PPCL

Sh. Satyendra Praksh Addnl. GM(T) [email protected]

Page 34: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

1

ROLE OF SCADAIN PROSPECTIVE WITH

UPSLDC22-December-2017

Presented By

UPSLDC Vibhuti Khand Gomtinagar, Lucknow

UTTAR PARADESH

UPSLDC

State Load Despatch Centre, (UPSLDC ), established in 2011 is under administrative control of Uttar Pradesh Power Transmission Corporation Limited (UPPTCL).

SLDC is responsible for optimum scheduling and despatch of electricity within a State, in accordance with the contracts entered into with the licensees or the generating companies operating in that State.

Bairwa
Typewritten Text
Annexure-II
Bairwa
Typewritten Text
Bairwa
Typewritten Text
Bairwa
Typewritten Text
Page 35: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

2

Load

UP LOAD :

Maximum: 18100MW (JUNE-2017)

Total NR LOAD:

Maximum: 58100MW(JUNE-2017)

UPSLDC

Supervisory Control and Data Acquisition system referred as SCADA is available at SLDC to get real time data of power system.

Total no. of substations covered under SCADA: 263 UPPTCL: 147 UPRVUNL+UPJVNL: 13 IPP: 7 COGEN Plants: 61 Solar Plants: 26 WUPPTCL: 7 SEUPPTCL: 2

Page 36: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

3

UPSLDC-no of Substations covered in SCADA

No of 765 KV Substation: 5 UPPTCL-2 WUPPTCL-02 SEUPPTCL-01

No of 400 KV Substation: 27 UPPTCL-21 WUPPTCL-05 SEUPPTCL-01

No of 220 KV Substation: 101

No of132 KV Substation: 24

UPSLDC

Generating Stations: 20 UPRVUNL-8 UPJVNL-3 IPP-9(Thermal-7+Hydro-2)

Total No. of RTUs: 208

No. of feeders covered under Remote Demand Management System(DMS): 9

No. of substation Covered under WAMS(URTDSM) project: 16(765/400KV)

Page 37: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

4

UPSLDC

Four Sub State Load Despatch Centres (SUB-SLDC)

are set up at:

Sarnath (Varanasi)

Panki (Kanpur)

Moradabad &

Modipuram (Meerut) It is also Backup SLDC of UP SLDC.

Challenges before SCADA Scheme

Integration of all 132KV s/s(More than 400) in existing SCADA System.

Operation of SCADA System in Main & Backup redundant mode.

Optimization, reliability, accuracy and availability of input analog & digital data in SCADA.

Page 38: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

5

Challenges before SCADA Scheme

Proper running of all EMS Applications and their utilization in Power System Operation & Control.

Complete Under Frequency Relay Mapping in SCADA.

Rectification of complete SCADA System down problem due to any suspected IP conflicts in the network or due to problem in Firewall.

Challenges before SCADA Scheme

In our opinion system should be safeguarded against these threats. And able to self diagnose probable cause.

WAMS(URTDSM) system adoption in UPSLDC.

Minimizing difference between SEM & SCADA data of interstate Tie lines. So that we can control effectively and economically, and minimize DSM charges.

Page 39: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

6

Running of State Estimator and Various EMS Applications

Proper co-ordination is required for maintaining TNA database accurately and all-round efforts should be made for running of state estimator so that it can be utilized for dispatcher training as well as system operation.

Strengthening of Communication Network

Redundant and reliable data communication network is required from each generating station and transmission sub-stations as well as between control centers by having two ring main communication networks.

Page 40: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

1

12TH TEST MEETING

22.12.2017

IEGC 4.6.2.

Reliable and efficient speech and datacommunication systems shall be provided tofacilitate necessary communication anddata exchange, and supervision/ control ofthe grid by the RLDC, under normal andabnormal conditions.All Users, STUs and CTU shall provideSystems to telemeter power systemparameter such as flow, voltage and statusof switches / transformer taps etc. in linewith interface requirements and otherguideline made available by RLDC.

Bairwa
Typewritten Text
Annexure-III
Bairwa
Typewritten Text
Page 41: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

2

IEGC 4.6.2.

The associated communication system tofacilitate data flow up to appropriate datacollection point on CTU's system shall alsobe established by the concerned User orSTU as specified by CTU in the ConnectionAgreement.

All Users/STUs in coordination with CTUshall provide the required facilities at theirrespective ends as specified in theConnection Agreement.

GENERAL CONNECTIVITY CONDITIONS The requester to furnish data to Utility to whom connection is sought Facilities for voice and data communication and transfer of on-line

operational data Requester and user to cooperate with the RPC & LDC on operational

aspects. Protection coordination Contingency operation participation Furnishing data for system studies,tripping analysis etc. Carry out modification Abide by coordinated outage planning Cooperation in PSS tuning

Interconnection study Connection agreement with CTU/STU/DISCOM (in case of connection

with transmission licensee, a tripartite agreement involving CTU/STUas well)

Page 42: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

3

CALIBRATION AND TESTING OF INTERFACE METERS Mandatory testing at the time of commissioning Testing at least once in five years or whenever

abnormal or inconsistent (with adjacent meters)recording

Whenever there is unreasonable difference betweenthe quantity recorded by Interface meter and thecorresponding value monitored at the billing center viacommunication network, the communication systemand terminal equipment shall be tested and rectified.

The meters may be tested using NABL accreditedmobile laboratory or at any accredited laboratory andrecalibrated if required at manufacturer’s works.

Testing and calibration of interface meters in thepresence of the representatives of the supplier andbuyer.

STANDARDS FOR INTERFACE METERS….CONTD

Data to be stored in meter for a period of at least tendays.

An optical port on its front for tapping all data stored in itsmemory using a hand held data collection device.

The meter shall be suitable for transmitting the data toremote location using appropriate communicationmedium.

Two reactive energy registers- one for the period whenaverage RMS voltage >103% and the other for < 97%.

Export to be taken as +ve and import as –ve. The meters shall also display (on demand), by turn, the

parameters in a specified sequence.

Page 43: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

4

6 (3) of the Central Electricity Authority (TechnicalStandard for Connectivity to the Grid) Regulations,2007 provides as under:

"6(3). The requestor and user shall providenecessary facilities for voice and datacommunication and transfer of operational data,such as voltage, frequency, line flows, and status ofbreaker and isolator position and other parametersas prescribed by Appropriate Load Despatch Centre."

IEGC 2 (1) gggg) “User” means

a person such as a Generating Companyincluding Captive Generating Plant orTransmission Licensee ( other than the CentralTransmission Utility and State Transmissionutility) or Distribution Licensee or Bulk Consumer,whose electrical plant is connected to the ISTS ata voltage level 33kV and above;

Page 44: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

5

IEGC 5.2 (q)

Each User, STU, RLDC, NLDC and CTU shallprovide and maintain adequate and reliablecommunication facility internally and with otherUsers/STUs /RLDC/SLDC to ensure exchange ofdata/information necessary to maintain reliabilityand security of the grid.

Wherever possible, redundancy and alternatepath shall be maintained for communication alongimportant routes, e.g., SLDC to RLDC to NLDC.

CERC Communication Reg. 7.2 Role of CTU(i) The CTU shall in due consideration of the planning criteriaand guidelines formulated by CEA, be responsible forplanning and coordination for evelopment of reliableNational communication backbone Communication Systemamong National Load despatch Centre, Regional LoadDespatch Centre(s) and State Load Despatch Centre(s) andREMCs along with Central Generating Stations, ISTS Sub –Stations, UMPPs, inter-State generating stations, IPPs,renewable energy sources connected to the ISTS, Intra-Stateentities, STU, State distribution companies, CentralisedCoordination or Control Centres for generation andtransmission.

While carrying out planning process from time to time, CTUshall in addition to the data collected from and inconsultation with the users consider operational feedbackfrom NLDC, RLDCs and SLDCs.

Page 45: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

6

(iv) The CTU shall integrate communication planning with transmission and generationproject planning in a comprehensive manner.(v) The CTU shall discharge the above function in consultation with the CEA,State Transmission Utilities, ISGS, Regional Power Committees, NLDC and RLDCsand SLDCs.(vi) The CTU shall provide access to its communication node to interface the widebandnetwork being implemented by State Transmission Utilities to have a singleinterconnected network and shall coordinate with State Utility for the interfacerequirement.(vii) CTU shall be the Nodal Agency for supervision of communication system in respectof inter-State communication system and will implement centralized supervision forquick fault detection and restoration. CTU shall prepare Procedure for same and submit to Commission for approval within 60 days of notification of these Regulations.(viii) The CTU in consultation with STUs shall carry out the integrated planning fordevelopment of backbone communication systems providing interfaces to widebandcommunication network of STUs at interface nodes.(ix) The CTU shall provide access to its wideband network for grid management andasset management by all users.(x) The CTU shall extend the required support to Control Centres for integration ofcommunication system at respective ends.

7.3 Role of National Power Committee (NPC) and Regional Power Committee(RPC):

(ii) The RPC Secretariat shall certify the availability ofcommunication equipment for CTU, ISGS, RLDCs,NLDC, SLDCs based on the data furnished by RLDC.

(iii) The RPC Secretariat shall monitor instances of non-compliance of these regulations as amended from time to time and make endeavour to sort out the issues in the respective region in such a way that cases of non-compliance are prevented in future. Unresolved issues and non-compliance of any of the provisions of these regulations shall be reported by the Member Secretary of respective RPC to the Commission.

Page 46: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

7

7.5 Role of RLDCs:(i) The Regional Load Despatch Centre shall be nodal agency for integration and supervision of Communication System of the ISTS, ISGS, SLDCs and IPPs at RLDC end for monitoring, supervision and control of Power System and adequate data availability inreal time.(ii) The Regional Load Despatch Centre (RLDC) shall collect and furnish data related to Communication System of various users, CTU, RLDC, STU and SLDC to RPCs.(iii) RLDCs shall provide operational feedback to CTU.

7.6 Role of SLDCs:(i) The State Load Despatch Centres shall be nodal agency for integration of Communication System in the intra-State network, distribution system and generating stations at SLDC end for monitoring, supervision and control of Power System andadequate data availability in real time.

(ii) SLDC shall provide operational feedback to CTU and STU.

Page 47: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

8

7.7 Role of STUs(i) The STU shall be responsible for planning, coordination and development ofreliable communication system for data communication within a State includingappropriate protection path among State Load Despatch Centre, Area LDC, Sub-LDCand DISCOM LDC including Main and backup as applicable along with STU Sub-Stations, intra-State Generating Stations.

(ii) The STU shall also plan redundant communication system up to the nearestInter-State Transmission System wideband communication node for integration withthe inter-State communication system at appropriate nodes.

(iii) The STU shall discharge all functions of planning related to the Statebackbone communication system in consultation with Central Transmission Utility,State Government, generating companies and distribution companies in the State.

(iv) The STU shall also provide access to its wideband Network for gridmanagement by all users.

(v) The STU shall extend the required support to Control Centres for integration ofcommunication system at respective ends.

7.8 Role of Users:(i) The Users including renewable energy generators shall be responsible for provision of compatible equipment along with appropriate interface for uninterrupted communication with the concerned control centres and shall be responsible for successful integration with the communication system provided by CTU or STU for data communication as per guidelines issued by NLDC.

(ii) Users may utilize the available transmission infrastructure for establishing communication up to nearest wideband node for meeting communication requirements from their stations to concerned control centres.

(iii) The Users shall also be responsible for expansion /up-gradation as well as operation and maintenance of communication equipment owned by them.

Page 48: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

9

10. Periodic Auditing of Communication System:The RPC Secretariat shall conduct performance audit of communication system annually as per the procedure finalised in the forum of the concerned RPC.

Based on the audit report RPC Secretariat shall issue necessary instructions to all stakeholders to comply with the audit requirements within the time stipulated by the RPC Secretariat.

An Annual Report on the audit carried out by respective RPCs shall be submitted to the Commission within one month of closing of the financial year.

11. FAULT REPORTING:(i) RLDC and SLDC in case of outage of telemeter data, or communication failure shall inform the respective user so that the user shall ensure healthiness of its communication system. In case outage pertains to fault in communication system ofother user, the user shall lodge complaints for failure of the communication to the communication system owner for quick restoration.(ii) The communication provider shall explore the possibility for route diversion on the existing facility in close co-ordination with concerned provider in case the fault restoration is prolonged. No separate charges shall be paid for such route diversion or channel re-allocation. However, such rerouting shall be discontinued once the original channel is restored.

Page 49: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

10

12. COMMUNICATION SYSTEM AVAILABILITY:All users of CTU, NLDC, RLDCs, SLDCs, STUs shall maintain the communication channel availability at 99.9% annually:Provided that with back up communication system, the availability of communicationsystem should be 100%.

13. Cyber Security:(i) Communication infrastructure shall be planned, designed and executed to address the network security needs as per standard specified by CEA and shall be in conformitywith the Cyber Security Policy of the Govt. of India, issued from time to time.(ii) NLDC, shall monitor case of cyber security incidences and discuss them at RPC level and take necessary action as deemed fit.(iii) RPC shall ensure that third party cyber security audits shall be conducted periodically (period to be decided at RPC) and appropriate measures shall be implemented to comply with the findings of the audits. The audits shall be conducted by CERT-In certified third party auditors.

Page 50: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

11

Para 13 of CERC Order dated 29.01.2016 in Petition No. 7/SM/2014

We are not satisfied with the improvement in theintermittency in telemetred of PGCIL`s system.

Despite our repeated instructions, PGCIL has notmade sincere efforts to improve the problem ofintermittency in its telemetry.We direct PGCIL to undertake effective monitoring oftelemeter data and to minimize the intermittency intelemetry in all regions within sixmonths from the issueof the order.NLDC is directed to submit status of PGCIL`stelemetry within one month thereafter.

Para 14.

Moreover, in view of the requirement ofcommunication system for a generating stationand sub-station, the planning should be done inadvance by the generating company andtransmission licensee to ensure that necessarysystem are in place before commissioning ofgenerating station or sub-station to take care ofthe communication requirements even at thetime of injection of power infirm by a generatingstation and sub-station during testing.

Page 51: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

12

17. We further direct all the utilities/generatingcompanies which have to still establish telemeterpower system parameters as per details given inpara11 above to provide data to RLDCs/SLDCs as perthe provisions of the Grid Code and CEA Grid StandardsRegulations by 31.7.2016.If the utilities/generating companies do not complywith our directions, it will be construed as non-compliance of the order of the Commission andappropriate proceedings under Section 142 of theElectricity Act, 2003 shall be initiated against suchutilities/generating companies.NLDC is directed to submit user- wise latest status oftelemetry, by 31.8.2016.

18. NLDC and respective RLDC are directedto up-date the status of telemetry everymonth at their web-site and persistent non-availability of data from the generatingstations/sub-stations be taken up in RPCmeetings for appropriate direction andaction.

Page 52: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

13

Package

Region

Scope After Amendment

Dispatch 

Installation & 

Commissioning

ON‐HOLD SITES

Integrated with CC

S/s PMUs S/S PMUs S/SPMUs

S/SPMUs

S/SPMUs

Package‐I

NR‐I 71 240 69 234 67 226 2 8 56 199

NR‐II 44 157 43 156 40 147 3 9 29 105

Total Package‐I 115 397 112 390 107 373 5 17 85 304

CERC Order dated 16.09.2016 in 206 MP 2014

22. It is noticed that URTDSM scheme was approved withthe purpose to improve the visibility and security and tomitigate the probability of grid failure. By considering thepresent progress of the Phase-I, the petitioner does notseem to have made adequate efforts to complete thephase-I of the scheme. The implementation period forphase-I was 2014-15. However, it is still underimplementation.We express our unhappiness with the progress of Phase Iof URTDSM scheme to be implemented by the petitioner.We direct the petitioner toexpedite the work of Phase-I ofthe scheme so that it may be completed by November2016 as submitted by the petitioner.

Page 53: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

14

STATUS OF AMR SYSTEM IN NORTHERN REGION as on 21stDecember, 2017•Total locations as per LOA/phase‐I: 1250SEM/220 Locations•Total locations as per LOA/phase‐II: 575 SEM/150 DCUs•Total locations for which data is received: 150 Locations•No of Energy meters for which AMR is commissioned presently: 1320 SEM /266DCU•No of Energy meters removed from Substations by PG and in AMR System:11•No of Energy meters for which data is received at NRLDC: 1072 SEM

•No of DCUs online: 232DCU•No of DCUs offline: 34 DCU•Total locations for which SAT(Site acceptance test) is completed till date: 205 locations (i.e. 1305 SEMs)•Percentage availability of data: 81%The balance energy meters are offline due to following issues (detailed sheet attached):•97 SEMs – GPRS Communication/SIM card•43SEMs – Feeder shutdown/Meter replacement•108 SEMs ‐ ICU/ORU related Issues SEM which are not having RS485 port, is beingintegrated with ICU(Interface converter unit) whereinORU(optical reading unit) is placed on SEM.Provision of data downloading is provided in ICU and

Page 54: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

Annexure- IV

Details of RTUs Without Redundant Channel Communication

( As on 10th January,2018)

Sr. No.

Sub-station/ Generating

Station Status/ Reason Owner of Sub-station 1 Kankroli GPRS not working PGCIL 2 Samba Standby PLCC not working PGCIL 3 Fatehabad PLCC not working PGCIL 4 Chamba GPRS not working PGCIL 5 Wagoora Port faulty PGCIL 6 Allahabad PLCC not working PGCIL 7 Lucknow 765 Port faulty PGCIL

8 Agra 400kV PLCC modem faulty. S 900

RTU PGCIL 9 Mainpuri PLCC not working PGCIL

10 Badarpur Main Channel not working PGCIL 11 Tehri PLCC not working PGCIL 12 Agra HVDC Single link of ZTE 104 PGCIL 13 Moga765 KV Port Fauty PGCIL 14 Wanpoh Single link Telecom PGCIL

15 Nathpa Jhakri Distsnce betwnne RTU to

MUX is large. PGCIL

16 Banala

Only GPRS link, PLCC route up to nearest wide

band may be through PGCIL

17 Nallagarh

Both link Healthy but intermitent if both are

connected PGCIL

18 Dhauliganga

Both Link Healthy but Standby Port is not

available NHPC 19 Chamera-3 Port not available NHPC

20 Salal

Lease Line & Fiber(Fiber problem between Kishanpur- Moga) PGCIL

21 Jhajjar

PLCC not working due to tower collapse of Mundka-

Bawana Line PGCIL

22 Uri-1 Standby Lease Line

Problem PGCIL

Page 55: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

23 Uri-2 Both PLCC and lease line

down PGCIL 24 Parbati-2 Lease Line PGCIL 25 Parbati-3 Lease Line PGCIL 26 Sewa2 Lease Line NHPC 27 Rihand-3 FIBER NTPC

28 Rihand NTPC Standby not working. S

900 RTU NTPC

29 Unchahar-

400KV FIBER NTPC 30 Anta FIBER NTPC

31 Budhil (IPP) Lease Line

Lanco Budhil Hydro Power Private Limited ( Lanco-Budhil)

32 Sri cement

(IPP) GPRS Shree Cement Limited (SCL)

33 Sorang (IPP) NOT REPORTING Himachal Sorang Power Ltd (HSPL)

34 Karcham

(IPP) PLCC JSW Energy

35 Malana (IPP) PLCC Everest Power Private Limited (EPPL)

36 Mundra

HVDC (IPP) Lease Line Adani Power

37 Lucknow 400kV Port not available PGCIL

38 Bahadurgarh Port not available PGCIL

39 Kurukshetra No Provision for automatic

shifting of Gateway PGCIL 40 Manesar Port faulty PGCIL 41 Koldam Port not available NTPC

42 RAPP-A Port not available. S 900

RTU NPCIL

43 RAPP-C Port not available. S 900

RTU NPCIL

Page 56: Government of Indiahpaldc.org/NRPC_TeST/12/12_Minutes.pdf~ ij{CflI{ Government of India ~4"'1~4 Ministry of Power ~~~ij~fil Northern Regional Power Committee ~. ~~I SI~ 1

Annexure-V

Status of URTDSM Project Phasor Measurement Unit (PMUs):

Package Region Scope After Amendment Dispatch Installation &

Commissioning ON-HOLD

SITES (Issues)

Integrated with Control

Centre S/s PMUs S/S PMUs S/S PMUs S/S PMUs S/S PMUs

Package-I NR-I 71 240 69 234 67 226 2 8 56 199 NR-II 44 157 43 156 40 147 3 9 29 105

Total Package-I 115 397 112 390 107 373 5 17 85 304 Hold Site: Dadri-NTPC, IP Power-DTL, Wanpoh, Dulhasti & Uri Control Centre Status:

Activities Dispatch Status

Integration Status

Commissioning Status

SAT Status

Total Tests

Closed Tests

Open Tests Remark, If Any

Main NLDC Yes No No 167

NRLDC Yes Yes Yes 172 10 SAT in progress

SLDC UP Yes Yes Yes Yes 35 34 1 Pending point, IIT Mumbai Applicaton Testing

SLDC Rajasthan Yes Yes Yes Yes 35 34 1

SLDC DTL Yes Yes Yes Yes 35 34 1

SLDC Haryana Yes Yes No 35 Commissioning

scheduled by 15-Jan-18 SLDC

Punjab Yes Yes No 35

SLDC BBMB Yes Yes No 35

SLDC HP Yes Yes No 35 Commissioning scheduled by 10-Jan-18 SLDC

Uttarakhand Yes No No 35

SLDC J&K Yes No No 35