Government Office Center Mid-Atlantic U.S. Penn State AE Senior Thesis Project Alexander Ward | Construction Management James Faust | CM Advisor. Government Office Center Mid-Atlantic U.S. Presentation Outline: Project Background Analysis #3: Integrated Processes Engaged Owner - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Government Office Center Mid-Atlantic U.S](https://reader030.vdocuments.net/reader030/viewer/2022032709/56813167550346895d97dd1a/html5/thumbnails/1.jpg)
Government Office Center
Mid-Atlantic U.S.
Penn State AE Senior Thesis ProjectAlexander Ward | Construction Management
James Faust | CM Advisor
![Page 2: Government Office Center Mid-Atlantic U.S](https://reader030.vdocuments.net/reader030/viewer/2022032709/56813167550346895d97dd1a/html5/thumbnails/2.jpg)
Government Office Center
Mid-Atlantic U.S.
Penn State AE Senior Thesis ProjectAlexander Ward | Construction Management
James Faust | CM Advisor
Presentation Outline:
I.Project BackgroundII.Analysis #3: Integrated Processes
A. Engaged OwnerIII.Analysis #2: SIPS Study for Curtain Wall Activities
A. Renewable Energy/Electrical BreadthIV.Analysis #1: Implementation of Building Information Modeling
A. Facilities ManagementV.Analysis #4: Progressive Collapse
A. Structural BreadthVI.Summary of Conclusions & Acknowledgements
![Page 3: Government Office Center Mid-Atlantic U.S](https://reader030.vdocuments.net/reader030/viewer/2022032709/56813167550346895d97dd1a/html5/thumbnails/3.jpg)
Project Background
Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
$42 Million Renovation 14 Story Federal Office &
Courthouse 316,000 SF August 1, 2011 – January 31, 2014 Major upgrades to Envelope and
HVAC systems LEED Gold (LEED 2009 EBO&M) Occupied throughout construction
Slide 3
![Page 4: Government Office Center Mid-Atlantic U.S](https://reader030.vdocuments.net/reader030/viewer/2022032709/56813167550346895d97dd1a/html5/thumbnails/4.jpg)
Integrated Processes
Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Problem Identification:Industry trending toward integrated solutionsEngaged owners extremely important in processNeed to educate owners on importance of role
Research Goal:Evaluate key benefits of engaged owner
Slide 4
![Page 5: Government Office Center Mid-Atlantic U.S](https://reader030.vdocuments.net/reader030/viewer/2022032709/56813167550346895d97dd1a/html5/thumbnails/5.jpg)
Integrated Processes
Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
An Engaged Owner is:Actively involved in the design and design review processAware of the unique challenges of the projectWilling to use uncommon project delivery and construction strategies when feasible
…improved delivery through schedule acceleration…
Slide 5
![Page 6: Government Office Center Mid-Atlantic U.S](https://reader030.vdocuments.net/reader030/viewer/2022032709/56813167550346895d97dd1a/html5/thumbnails/6.jpg)
Integrated Processes
Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
An Engaged Owner is:More informed of design options being considered by the project teamMore educated on the consequences of these design optionsActively involved in design reviewsSupportive and responsive during construction phase
…improved delivery through schedule acceleration…
…faster and more refined decision making…
Slide 6
![Page 7: Government Office Center Mid-Atlantic U.S](https://reader030.vdocuments.net/reader030/viewer/2022032709/56813167550346895d97dd1a/html5/thumbnails/7.jpg)
Integrated Processes
Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
An Engaged Owner is:Helpful in defining project needs early in the development processEducated and understands how design teams meet the previously defined program requirementsClear in explaining why a design change is needed and what it will accomplish
…improved delivery through schedule acceleration…
…faster and more refined decision making…
…reduced frequency and degree of changes…
Slide 7
![Page 8: Government Office Center Mid-Atlantic U.S](https://reader030.vdocuments.net/reader030/viewer/2022032709/56813167550346895d97dd1a/html5/thumbnails/8.jpg)
SIPS Study for Curtain Wall Activities
Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Problem Identification:Highly repetitive curtain wall replacement activitiesOpportunity to implement BIPV system
Research Goal:Evaluate the benefits of SIPS and BIPV
Slide 8
![Page 9: Government Office Center Mid-Atlantic U.S](https://reader030.vdocuments.net/reader030/viewer/2022032709/56813167550346895d97dd1a/html5/thumbnails/9.jpg)
SIPS Study for Curtain Wall Activities
Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Activities:Installation of weather wallDemolition of existing curtain wallInstallation of new structural steelInstallation of new curtain wallDemolition of weather wallFrame and rough-inRestoration of finishes
Slide 9
North Area in Red – South Area in Blue
![Page 10: Government Office Center Mid-Atlantic U.S](https://reader030.vdocuments.net/reader030/viewer/2022032709/56813167550346895d97dd1a/html5/thumbnails/10.jpg)
SIPS Study for Curtain Wall Activities
Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Existing Schedule:Oct. 11, 2011 – Sept. 16, 2013 (101 weeks)8 week schedule gap between North and SouthLongest activity requires 100 days (North finishes)
Slide 10
![Page 11: Government Office Center Mid-Atlantic U.S](https://reader030.vdocuments.net/reader030/viewer/2022032709/56813167550346895d97dd1a/html5/thumbnails/11.jpg)
SIPS Study for Curtain Wall Activities
Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
$1.65M Total Value
25 Weeks Saved
$425K
$1.225M
Slide 11
![Page 12: Government Office Center Mid-Atlantic U.S](https://reader030.vdocuments.net/reader030/viewer/2022032709/56813167550346895d97dd1a/html5/thumbnails/12.jpg)
BIPV Curtain Wall
Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Slide 12
![Page 13: Government Office Center Mid-Atlantic U.S](https://reader030.vdocuments.net/reader030/viewer/2022032709/56813167550346895d97dd1a/html5/thumbnails/13.jpg)
BIPV Curtain Wall
Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Slide 13
Feasibility:+$404,200 for PV marginal cost–$382,500 for sunshades deduction=$21,700 net marginal cost
~$13,000 per year in energy savings
Payback < 2 years
Need to consider heat gain, constructability, etc.
![Page 14: Government Office Center Mid-Atlantic U.S](https://reader030.vdocuments.net/reader030/viewer/2022032709/56813167550346895d97dd1a/html5/thumbnails/14.jpg)
Implementation of BIM
Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Problem Identification:Minimal push of information downstream for future needs
Research Goal:Evaluate the benefits of implementing BIM for facilities management uses
Slide 14
![Page 15: Government Office Center Mid-Atlantic U.S](https://reader030.vdocuments.net/reader030/viewer/2022032709/56813167550346895d97dd1a/html5/thumbnails/15.jpg)
Implementation of BIM
Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Slide 15
![Page 16: Government Office Center Mid-Atlantic U.S](https://reader030.vdocuments.net/reader030/viewer/2022032709/56813167550346895d97dd1a/html5/thumbnails/16.jpg)
Implementation of BIM
Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Slide 16
![Page 17: Government Office Center Mid-Atlantic U.S](https://reader030.vdocuments.net/reader030/viewer/2022032709/56813167550346895d97dd1a/html5/thumbnails/17.jpg)
Progressive Collapse
Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Problem Identification:Original construction decades prior to recent federal requirements
Research Goal:Compare the cost and schedule impacts of adding this scope of work in three scenarios
Slide 17
![Page 18: Government Office Center Mid-Atlantic U.S](https://reader030.vdocuments.net/reader030/viewer/2022032709/56813167550346895d97dd1a/html5/thumbnails/18.jpg)
Progressive Collapse
Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Freyrom Anchor Section Slide 18
![Page 19: Government Office Center Mid-Atlantic U.S](https://reader030.vdocuments.net/reader030/viewer/2022032709/56813167550346895d97dd1a/html5/thumbnails/19.jpg)
Summary of Conclusions
Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
The Balfour Beatty Construction Team
Industry Professionals
Penn State AE Department
My Family and Friends
Slide 19
Acknowledgements
Questions or Comments?
![Page 20: Government Office Center Mid-Atlantic U.S](https://reader030.vdocuments.net/reader030/viewer/2022032709/56813167550346895d97dd1a/html5/thumbnails/20.jpg)
Appendix Slides
Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of ConclusionsVII.Acknowledgements
Government Office Center | Mid-Atlantic U.S.
![Page 21: Government Office Center Mid-Atlantic U.S](https://reader030.vdocuments.net/reader030/viewer/2022032709/56813167550346895d97dd1a/html5/thumbnails/21.jpg)
Project Background
Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Owner | U.S. General Services Administration
CM | Balfour Beatty Construction Architect | TranSystems Corporation Structural Engineer | Thornton
Tomasetti MEP Engineer | Greenman-Pedersen,
Inc. Sustainability / Design Consultant |
William McDonough + Partners
![Page 22: Government Office Center Mid-Atlantic U.S](https://reader030.vdocuments.net/reader030/viewer/2022032709/56813167550346895d97dd1a/html5/thumbnails/22.jpg)
SIPS Study for Curtain Wall Activities
Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.
Traditional SIPS:
Non-Traditional SIPS:
![Page 23: Government Office Center Mid-Atlantic U.S](https://reader030.vdocuments.net/reader030/viewer/2022032709/56813167550346895d97dd1a/html5/thumbnails/23.jpg)
Implementation of BIM
Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements
Government Office Center | Mid-Atlantic U.S.