THE OFFICE OF THE STATE LONG-TERM CARE OMBUDSMAN’S CERTIFICATION FOR OMBUDSMAN SPECIALISTS
Green Belt Six Sigma Project Report Out Karla Warren Ohio Department of Aging Tuesday, Dec. 2, 2014
1
![Page 2: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/2.jpg)
LEANING THE OMBUDSMAN CERTIFICATION PROCESS
2
Ohio Department of Aging Beverley Laubert Sponsor
Erin Pettegrew Subject Matter Expert
LaTosha Slappy Subject Matter Expert
Karla Warren Facilitator
Randall Wright External Voice to Process
![Page 3: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/3.jpg)
BACKGROUND
3
![Page 4: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/4.jpg)
WHAT IS AN OMBUDSMAN?
Advocate for home care, assisted living and nursing home consumers
Resolve complaints and offer selection assistance
Independent State Ombudsman at ODA 12 regional programs
State ombudsman certifies new staff
4
![Page 5: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/5.jpg)
5
![Page 6: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/6.jpg)
DEFINE
6
![Page 7: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/7.jpg)
PROBLEM/OPPORTUNITY STATEMENT
• No standardization, reinvention
• Multiple calendars
• Uncertainty of content • Education coor. runs in circles because of
others
7
![Page 8: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/8.jpg)
PROJECT
Scope: Project is intended to standardize the certification process of new long-term care ombudsman. Objective: Reduce the number of steps and streamline the process of certifying ombudsman specialists.
8
![Page 9: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/9.jpg)
DEFINING OUR SCOPE
9
![Page 10: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/10.jpg)
To improve the details, you have to start BIG.
10
![Page 11: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/11.jpg)
HIGH LEVEL PROCESS - SIPOC
Suppliers Inputs Process Outputs Customers Training Coor. Forms Certified Spec. Program Dir. Presenters Agendas Knowledge State staff State staff Presentations Letters/forms Presenters Consumer voice Equip/set-up ID cards Consumers
11
Collect conflict of interest screen
Determine PD
schedule
Welcome letter
Complete training,
take exam
Send cert. letter
![Page 12: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/12.jpg)
CURRENT STATE: DETAILED PROCESS MAP
12
![Page 13: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/13.jpg)
MEASURE
13
![Page 14: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/14.jpg)
CHECK SHEET
14
Number of modifications to training calendar l l l l
![Page 15: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/15.jpg)
ANALYZE
15
![Page 16: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/16.jpg)
TIMWOOD
16
Waiting
Waiting Transportation Waiting
Motion
![Page 17: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/17.jpg)
CURRENT PROCESS
17
Min of 84 steps
Multiple, changing calendars
No back ups
Where’s the content?
No established exam dates
![Page 18: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/18.jpg)
ROOT CAUSE OF WHY IT’S NOT WORKING
18
× It’s not the person – it’s the process.
![Page 19: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/19.jpg)
WHY THE VARIATION
19
![Page 20: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/20.jpg)
IMPROVE
20
![Page 21: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/21.jpg)
PROJECT GOALS
1. Develop a standardized process so there’s no guess work of what is the next step
2. End the “it depends” 3. Make it “automatic” 4. Stick to the established calendar of dates 5. Hold people accountable
21
![Page 22: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/22.jpg)
BRAINSTORM – FREE FLOW METHOD
The team brainstormed and evaluated more than 10 improvement ideas.
22
![Page 23: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/23.jpg)
IMPROVEMENT SUMMARY
No back-up for trainers
Modified and different versions of calendar
Presentations are created with speaker notes saved in content folder on shared drive, which allows other team members can step in.
23
Variation in process Formulized process and informing stakeholders
One master calendar
![Page 24: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/24.jpg)
COST SAVINGS
Old process: 84 steps. Often more. New process: 60 steps.
24
![Page 25: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/25.jpg)
25
![Page 26: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/26.jpg)
WHERE IS THE MEDICAID FOLDER?
26
![Page 27: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/27.jpg)
REMOVING THE GUESSWORK
27
![Page 28: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/28.jpg)
IMPLEMENTATION PLAN
28
Task Who When Status
Master calendar Ed. coordinator End of current
training session Completed
Content-labeled folders Ed. coordinator Sept. 2014 Completed
Handouts Ed. coordinator End of current
training session In progress
Presentations State
ombudsman staff
End of current training session
In progress
![Page 29: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/29.jpg)
CONTROL
× Visual Management × Pocket guides of the new
process × Handout: “What does a
program director need to do when they hire an ombudsman?”
29
![Page 30: Green Belt Six Sigma Project Report Out Karla Warren Ohio Department …lean.ohio.gov/Portals/0/docs/beltprojects/KarlaWarren... · 2014. 12. 2. · THE OFFICE OF THE STATE LONG -TERM](https://reader035.vdocuments.net/reader035/viewer/2022062605/5fdd4c0ac9d24661f44c6c21/html5/thumbnails/30.jpg)
SPECIAL THANKS TO…