GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
8
9
10
11
13
14
15
16
12
GREEN ROOF
ROOFTOP SOLAR + GREEN ROOF
RAINWATER HARVESTING CISTERNS
BEER GARDEN / PATIO GREENING
1
2
3
4
FOREST EDGE
MEADOW SLOPE
HARDSCAPE WALKWAYS
NATURE TRAIL
EDUCATIONAL + WAYFINDING SIGNAGE
THE FALLS
THE GRASS BOWLS
TRAIL CONNECTIONS + UNDERPASS HABITAT
ARTWORK + SCULPTURE
GREEN INFRASTRUCTURE MASTER PLANUnion Collective
5
6
7
POCKET LANDSCAPES
RIVERSIDE HABITAT WETLAND
HILLSIDE OBSERVATION WETLAND
GREEN ROOF
DESCRIPTION:• Install 4” thick extensive green roof over the front
entrance awnings of Collective building• Green roof will be visible from the entrance
driveway and 41st Street • Green roof plantings include sedums, grasses, and
other heat/drought tolerant perennials and benefit pollinators
EXISTING SITE
Feature Green Roof
Environmental Impact
Green Roof Area: up to 2,300 ft2ESD Volume Treated (ESDv): 180 cfImpervious Area Treated: up to 2,300 ft2Annual Volume Treated: 366 cfPollutant Removal (lbs/yr): 0.11 TN, 0.01 TP, 47 TSS
Implementation Timeline
2-3 yearsYear 2: Design & PermittingYear 3: Construction
Design + Construction Costs
Medium Estimated $40,000 (~$16/sf for design + construction)
Permitting Considerations
● Eplans building permit required● DPW review required for SWM fee reduction
eligibility
Annual Maintenance Costs1
Medium Estimated $1,500 (0.75 per SF, estimate from EPA). Year 1-2 typically covered by installer
Funding Opportunities
All Design + Construction costs eligible for funding through grants: MDDNR, NFWF, CBT, BGE Green Grants
Additional Considerations
● Roof structural analysis required● Roof access needed for maintenance● Project eligible for a SWM fee reduction up to
$66 per year2
1
1Based on EPA estimate of $0.75 per SF2Site is eligible for a SWM fee credit of 55% x ERUPROPOSED PLAN
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
ROOFTOP SOLAR + GREEN ROOF
DESCRIPTION:• Install solar panels over the
larger Collective rooftop area• Option to install in combination
with additional green roof area• Project can result in significant
energy cost savings
Feature Rooftop Solar + Green RoofEnvironmental Impact
Up to 3 acres of rooftop available for improvementsGreen Roof Area: 60,000 sf (planning level estimate, option to +/-)Impervious Area Treated: 60,000 sfESD Volume Treated: 4,620 cfAnnual Volume Treated: 9,450 cfPollutant Removal (lbs/yr): 2.78 TN, 0.33 TP, 1,217 TSS
Implementation Timeline
4-5 yearsYear 2-3: Design & PermittingYear 4-5: Construction
Design Costs Low1
Construction Costs Low to High1
Est. $2.75M for 60,000 sf green + solar roof
Permitting Considerations
● Eplans building permit required for solar and green roof project● DPW review required for green roof project/SWM fee reduction
eligibility
Annual Maintenance Costs1
Low1
Funding Opportunities1
● Solar Design + Construction costs eligible for funding through incentive programs:
● Maryland Solar Rebate Program● Solar Renewable Energy Certificates (SREC)● Federal Investment Tax Credit (ITC)
Additional Considerations
● Roof structural analysis required● Roof access needed for maintenance● Solar projects are eligible for 26% federal tax credit in 2020● Addition of green roof would make project eligible for a SWM fee
reduction of $315/yr savings per 10,000 sf green roof area installed2
2
1There are numerous incentives for installing solar at no to low up front costs. Alternatively, owners can invest up front in solar to generate annual energy bill savings. Union should consult with a solar energy representative to evaluate site specific cost options.2Site is eligible for a SWM fee credit of 55% x ERU
EXISTING SITE
PROPOSED PLAN
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
ROOFTOP SOLAR + GREEN ROOF2
PRECEDENT IMAGES
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
Feature Rainwater Harvesting CisternsEnvironmental Impact
Cistern Size: 16,000+ galESD Volume Treated (ESDv): 5,300 cfImpervious Area Treated: 0.6 acres (26,000 sf)Annual Rainfall Captured: 48,000 gal/mo; 576,000 gal/yearPollutant Removal (lbs/yr): 1.39 TN, 0.16 TP, 611 TSS
Implementation Timeline
2-3 yearsYear 1-2: Design & PermittingYear 3: Construction
Design Costs MediumEst. $10-25k
Construction Costs
Medium Est. $40k - $100k for 16,000 gal systemMaterials $16k (plastic to $50k+ (customized) for tanksLabor to install Tanks: $10-20kPlumbing Allowance: $15kStructural Allowance: $20k
Permitting Considerations
● Eplans building/grading permit required● Project is located within the 100-year floodplain● DPW review required for SWM fee reduction eligibility
Annual Maintenance Costs
LowEst. $500/yr for inspection + cleanout
Funding Opportunities
● All Design + Construction costs eligible for funding through grants: MDDNR, NFWF, CBT
● Consider Artist collaboration on design/build● Long-term cost savings on City water bill due to reduced water usage
Additional Considerations
● Roof re-plumbing will be required, MEP team to be consulted● Cistern placement must consider existing budiling signage● Structural platform or base will be needed to accomodate floodplainconcerns● Water can also be treated for more re-use options such as toilet flushing, beer
brewing● Project eligible for a SWM fee reduction up to $815/yr2
EXISTING SITE
2Site is eligible for a SWM fee credit of 55% x ERUPROPOSED PLAN
RAINWATER HARVESTING CISTERNS3
DESCRIPTION:• Install cisterns external to building to
capture rooftop runoff for reuse• Captured water can be reused for
equipment washing, site irrigation, or ther non-potable uses
• Option to expand to capture entire rooftop
• Water reuse requirement:• Passive irrigation of wetland• Reuse within brewery (non-potable
or potable)
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
RAINWATER HARVESTING CISTERNS3
PRECEDENT IMAGES
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
DESCRIPTION:• Improve patio through pavement
removal, tree planting & natural landscaping
• Option to include visible rainwater conveyance feature to emphasize water pathway to the Jones Falls
• Covered arbor or other roof can provide shading/cooling and direct water to tree strip/native landscaping
Feature Beer Garden/Patio GreeningEnvironmental Impact Impervious Removal Area: ~790 sf
# Trees Planted: 6ESD Volume Treated (ESDv): 80 cfPollutant Removal (lbs/yr): 0.14 TN, 0.03 TP, 42 TSS
Implementation Timeline
1 year
Design Costs Low Est. $5-10k
Construction Costs Low$5-20k Additional costs for custom water rills and arbor features
Permitting Considerations
Eplans grading permit will be needed if project involves significant demo/excavation work
Annual Maintenance Costs
Minimal – weeding, watering, and remulching by staffCleaning of patio rills as needed
Funding Opportunities
● CBT mini-grant (up to $5k) may cover a portion of the construction
● Depave and larger improvements could be covered by small CBT/NFWF implementation grant
● Design + full construction may require additional investment from Union or other funder
Additional Considerations
● Design to accommodate multiple uses and flexibility within the patio space
● Tree choice must provide screening or include shrubs● Option to include an arbor feature to provide rain and
sun protection. This would result in additional project design + construction costs
EXISTING SITE PROPOSED PLAN
BEER GARDEN/PATIO GREENING4
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
BEER GARDEN/PATIO GREENING4
PRECEDENT IMAGES
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
DESCRIPTION:• Plant individual trees in select locations around
parking lot, grass bowls, and hillslope. Some locations may require impervious removal
• Install small pockets of native landscape plantings for habitat and aesthetic improvements
Feature Pocket LandscapesEnvironmental Impact Impervious Removal Area: 4,100 sf
# Trees Planted: 56Native Planting Area = 5900 sf =12,112 landscape plugs at 9 inch OCESD Volume Treated (ESDv): 652 cfAnnual Rainfall Captured: 17,808 cfPollutant Removal (lbs/yr): 0.1 TN, 0.01 TP, 12 TSS
Implementation Timeline
6-12 months
Design Costs LowEst. $5k
Construction Costs Low - MediumEst. $15-25kAdditional costs for curbing/edging
Permitting Considerations
● Small-scale plantings may not require permits. ● For larger scale efforts or pavement removal project
an Eplan grading permit may be required.
Annual Maintenance Costs
MinimalWeeding, watering, and remulching by staff
Funding Opportunities
All Design + Construction costs eligible for funding through grants: CBT, MDDNR, NFWF, CBT Mini-Grants, BGE Greening Grants
Additional Considerations
● Parking lot can be reconfigured to improve parking and pedestrian flow and expand landscape islands.
● An optional addition of a rideshare pick-up/drop-off zone is shown.
EXISTING SITE
PROPOSED PLAN
POCKET LANDSCAPES5
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
EXISTING SITE
DESCRIPTION:• Convert grassed area behind north lot to
constructed wetland feature• Add trees along back of feature to screen
highway • Option to add observation deck to feature• Wetland will provide significant habitat and
water quality enhancement adjacent the Jones Falls waterway
Feature Riverside Habitat WetlandEnvironmental Impact Wetland Area: 6,500+ sf
ESD Volume Treated (ESDv): 5,300 cfImpervious Area Treated: 1.5 acresAnnual Rainfall Captured: 199,880 cfPollutant Removal (lbs/yr): 4.34 TN, 0.29 TP, 617 TSS
Implementation Timeline
2-3 yearsYear 1-2: Design & PermittingYear 2: Construction
Design Costs High$40-50k including structural decking design
Construction Costs High$200-300k
Permitting Considerations
● Project is located within the 100-year floodplain● DPW SWM/ESC Review required● MDE JPA Permit required● Eplans grading permit required
Annual Maintenance Costs
Medium$1,000-$3,000. Most years will be on the lower end, but occasional forebay sediment removal required.
Funding Opportunities
All Design + Construction costs eligible for funding through grants: MDDNR, NFWF, CBT
Additional Considerations
● Consider including viewing deck at edge of feature. ● Project eligible for an annual SWM fee reduction up
to $2,046 per year2
2Site is eligible for a SWM fee credit of 55% x ERUPROPOSED PLAN
RIVERSIDE HABITAT WETLAND6
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
RIVERSIDE HABITAT WETLAND6
PRECEDENT IMAGES
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
DESCRIPTION:• Convert concrete-lined ditch at east
parking lot to a constructed wetland feature
• Construct boardwalk trail with observation decks and areas for ADA viewing
• Wetland can be enhanced with educational signage and custom stepping stones (#12 and 16)
Feature Hillside Observation WetlandEnvironmental Impact
Wetland Area: ~8,500 sfESD Volume Reated (ESDv): 8,000 cfImpervious Area Treated: 2.1 acresAnnual Rainfall Captured: 302,478 cfPollutant Removal (lbs/yr): 11.30 TN, 0.51 TP, 1,023 TSS
Implementation Timeline
5-7 yearsYear 2-4: Grants and Fundraising Year 3-4: Design & PermittingYear 5-6: Construction
Design Costs Very HighEst. $70-100k
Construction Costs
Very High$400k+
Permitting Considerations
● Project is located within the 100-year floodplain● DPW SWM/ESC Review required● MDE JPA Permit required● Eplans grading permit required● Project eligible for SWM fee reduction
Annual Maintenance Costs
Medium/High$2,000-$5,000. Most years will be on the lower end, but occasional forebay sediment removal required.
Funding Opportunities
● Wetland Design + Construction costs eligible for funding through grants:
● MDDNR, NFWF, CBT● Mitigation Credits: Maryland Port Authority, GreenVest● Pedestrian/Structural/Artistic improvements may require additional
investment from Union, Private Foundations, Arts grants
Additional Considerations
● Project should be designed concurrent with meadow trail to accommodate entry points and observation areas
● Project eligible for an annual SWM fee reduction up to $2,871 per year2
EXISTING SITE
2Site is eligible for a SWM fee credit of 55% x ERUPROPOSED PLAN
HILLSIDE OBSERVATION WETLAND7
See full site plan for full wetland and boardwalk plan.
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
HILLSIDE OBSERVATION WETLAND7
PRECEDENT IMAGES
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
DESCRIPTION:• Establish a forest of native species adjacent
to 41st Street through invasive removal and extensive new tree plantings
• Forest edge planting emphasizes native edge conditions as it transitions to the adjacent meadow
Feature Forest EdgeEnvironmental Impact Reforestation Area: 0.07 ac
ESD Volume Treated (ESDv): 145 cfAnnual Rainfall Captured: 6,360 cfPollutant Removal (lbs/yr): 0.04 TN, 0 TP, 0.5 TSS
Implementation Timeline
1-3 yearsYear 1: Develop planting & invasive removal planYear 1-2: Invasive removalYear 2-3: New tree planting
Design Costs Low - MediumEst. $10-20k
Construction Costs MediumEst. $50k
Permitting Considerations
Forest Conservation Plan Review
Annual Maintenance Costs
Minimal – occasional watering, weeding, and pruning by staff/volunteers during establishment period
Funding Opportunities ● Design + Construction costs eligible for funding through grants: CBT, MDDNR, NFWF
● Crowd Funding: Adopt a Tree / Rent a Goat● Maintenance: Volunteer work days, Weed Warriors,
Treekeepers
Additional Considerations
● Existing tree line along 41st street has large quantity of invasive species. An invasive removal plan should be developed concurrent with new tree planting plan
● A proposed nature trail (#11) travels through the forest, forest edge, meadow and ends at wetland deck. It provides shorter route to Union Collective and should be designed and constructed in conjunction with forest planting
EXISTING SITE PROPOSED PLAN
FOREST EDGE8
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
DESCRIPTION:• Establish meadow plantings along the
hillslope• Establish a defined nature trail down
hillslope along Forest Edge, through Meadow Plantings to wetland deck,providing a shorter route to Union Collective
Feature Meadow Slope + Nature TrailEnvironmental Impact
Meadow Area: 0.86 acESD Volume Treated (ESDv): 936 cfAnnual Rainfall Captured: 41,181 cfPollutant Removal (lbs/yr): 0.13 TN, 0.02 TP, 36 TSS
Implementation Timeline
4-5 yearsYear 1-2: Develop planting plan, establish test no-mow areaYear 2-3: Establish small meadow sample area, crowd-source fundraisingYear 4-5: Establish larger area of meadowYear 5-7: Intensive period of meadow establishment & maintenance
Design Costs Medium Est. $10-25k
Construction Costs MediumEst. $50-75k
Permitting Considerations
● Limit of disturbance to be under 5,000 sf area at any given time● Eplans grading permit may be required● Project is located within the 100-year floodplain
Annual Maintenance Costs
High to LowMeadow Maintenance Year 5-7: $5k+Meadow Maintenance Year 8+: $1k or lessPlus $500 - 1k annually for trail repair
Funding Opportunities
● Design + Construction costs eligible for funding through grants: CBT, MDDNR, NFWF
● Crowd Funding: Adopt a Meadow Plant● Private Foundations
Additional Considerations
● Due to steep slope, turf cannot be stripped and seeded. Consider adding plugs in hillslope to establish meadow with minimal slope disturbance
● The proposed nature trail travels through the forest and forest edge (#8) and should be designed and constructed in conjunction with this feature
EXISTING SITE
PROPOSED PLAN
MEADOW SLOPE + NATURE TRAIL9
11
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
MEADOW SLOPE + NATURE TRAIL9
11PRECEDENT IMAGES
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
DESCRIPTION:• Construct ADA sidewalk along entrance
drive and continuing down to Union patio area
• Install painted pedestrian routes through parking lot for improved safety and wayfinding
• Construct new stairs between wetland loop and patio area
Feature Hardscape WalkwaysEnvironmental Impact
N/A
Implementation Timeline
2-7 YearsYear 2-7: Painted pedestrian pathways, added in phases with new featuresYear 1-2: ADA Path DesignYear 3-4: ADA Path Construction
Design Costs Medium$10-25k for ADA path and new stairs design
Construction Costs
Medium$25-100k for ADA construction
Permitting Considerations
● ADA Path:○ Site Plan Review○ Eplan grading permit○ DPW SWM/ESC Review required for disturbance over 5000 sf
● Painted Walks:○ None, no earthwork disturbance proposed
Annual Maintenance Costs
Minimal to LowADA Path: nonePedestrian Paths: periodic repainting and touch-up
Funding Opportunities
Design + full construction will require investment from Union or other Private Foundations
Additional Considerations
● Portion of the ADA sidewalk will need to be cantilevered over the hillside slope, or extend into driveway parking lane.
● Geotechnical and structural evaluation needed to determine slope stability.
● Coordinate with DOT about ADA sidewalks and crossings along 41st Street right-of-way.
EXISTING SITE
PROPOSED PLAN
HARDSCAPE WALKWAYS10
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
DESCRIPTION:• Install educational and wayfinding signage
throughout the site• Installation can be done at time of feature
installation or can be done when all features are completed
Feature Educational & Wayfinding SignageEnvironmental Impact
N/A. Education & Outreach
Implementation Timeline
Ongoing
Design Costs Low $10k-or less
Construction Costs
Low $25k or less
Permitting Considerations
Can be designed and permitted as an element of other projects
Annual Maintenance Costs
Minimal
Funding Opportunities
Design + Construction costs eligible for funding as part of implementation grants: CBT, NFWF
Additional Considerations
● Signage to be consistent throughout site.● Ensure that Union Collective signage, site
feature signage, and path signage are complementary and appropriately hierarchical.
EXISTING SITE
PROPOSED PLAN
EDUCATIONAL & WAYFINDING SIGNAGE12
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
Signage locations are throughout the site.
EDUCATIONAL & WAYFINDING SIGNAGE12
PRECEDENT IMAGES
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
DESCRIPTION:• A custom site feature that diverts
stormwater runoff down the steepest section of hillslope and also provides low steps for climbing
• The Falls will be a visual focal point from the patio area
• Steps should be no more than 18” high for easy climbing
Feature The FallsEnvironmental Impact Native Planting Area: TBD
ESD Volume Treated (ESDv): TBDImpervious Area Treated: TBDAnnual Rainfall Treated: 61,300 cfPollutant Removal (lbs/yr): 1.00 TN, 0.09 TP, 351 TSS
Implementation Timeline
4-5 YearsYear 1-2: FundraisingYear 3-4: Design + PermittingYear 5: Construction
Design Costs Medium - HighEst. $20-50k
Construction Costs Medium - HighEst. $80k +
Permitting Considerations
● Eplans grading permit required● DPW SWM/ESC Review required for disturbance over 5000 sf● Portion of project may be located within the 100-year floodplain
Annual Maintenance Costs
Medium Est. $1-2k
Funding Opportunities ● Portion of Design + Construction costs eligible for funding through grants: CBT, NFWF
● Structural/Artistic improvements will require additional investment from Union, Private Foundations, Arts Grants
Additional Considerations
● Project should include landscape and seating improvements to the area immediately north of the falls. Coordinate with design of “The Grass Bowls.” May be a good candidate for an Art Design-Build Project
● Consider use of recycled/sustainable materials in feature● Feature could incorporate water flowing through and down falls, with
possible option to pump water for continuous flow● Geotechnical and structural evaluation needed to determine slope
stability
EXISTING SITE
PROPOSED PLAN
THE FALLS13
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
DESCRIPTION:• Re-grade the landscape island area to create
a shallow, gently sloping grass bowl for event seating and native plantings. This will allow for better connection from beer garden to hillslope area.
• The southern end of the hillslope is already bowl-shaped and can remain grassed to accommodate seating and events
Feature The Grass BowlsEnvironmental Impact
N/A
Implementation Timeline
2-3 Years
Design Costs MediumEst. $10-25k
Construction Costs
MediumEst. $25-100k
Permitting Considerations
● Eplans grading permit required● DPW ESC review required if project disturbance exceeds
100 cy● Portion of project may be located within the 100-year
floodplain
Annual Maintenance Costs
Minimal Weeding, mowing, watering (during establishment and drought), and remulching of non-grass areas by staff
Funding Opportunities
● Native Planting Design + Construction costs eligible for funding through grants: CBT, NFWF
● If being built in conjunction with The Falls, seating/grading improvements will require additional investment from Union, Private Foundations, Arts Grants
Additional Considerations
● Area can serve as a seating area during events● Seating can be tied into adjacent Falls area● Geothermal well location to be carefully considered during
grading design● If built in conjunction with The Falls, structural engineering
may be required depending on complexity of seating
EXISTING SITE
PROPOSED PLAN
THE GRASS BOWLS14
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
DESCRIPTION:• Connect pedestrian/bike trail from
Woodberry light rail to Union Collective. Incorporate environmental art along trail related to the Jones Falls Waterway
• Improve trail connection up to Medfield Neighborhood
Feature Trail Connections & Underpass HabitatEnvironmental Impact
Environmental Education
Implementation Timeline
7-10 years Year 1-2: Work with City/FOJF to secure property agreements for Light Rail trail connection. Discuss Medfield trail with neighborhood and Seawall. Year 3-4: Develop trail hardscape connection. Provide temporary wayfinding, aesthetic improvements, and install lighting. Seek art & restoration grants for more permanent improvements Year 5-6: Install permanent signage. Install native plantings & develop design for additional habitat restoration improvements. Year 7-10: Continue to incorporate art elements along trail
Design Costs Medium -HighEst. $25-50k
Construction Costs
Medium -HighEst. $25-100k+
Permitting Considerations
● Eplans grading permit required● Possible SWM/ESC review required if disturbance exceeds 5000 sf● MDE JPA Permit may be required for wetland/waterway impacts● Light Rail connection trail is located within the 100-year floodplain
Annual Maintenance Costs
MediumEst. ($2-5k) for cleanup, weeding, watering, trail maintenance. Some of this could be managed by volunteer groups
Funding Opportunities
● BOPA Community Arts Grant ● CBT/NFWF/MDDNR for habitat components● Various Greenway and Art Trails grants
Additional Considerations
● Project will require coordination with FTJF, City, DOT, and adjacent property owners
● Any planned 41st St capital improvements should be confirmed with DOT. ● Safety and lighting considerations● Consider SWM treatment opportunities from cascading runoff of overhead
41st St
EXISTING SITE
PROPOSED PLAN
TRAIL CONNECTIONS & UNDERPASS HABITAT
15
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
LIGHT RAIL TRAIL CONNECTION & UNDERPASS HABITAT PRECEDENT IMAGES
15
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
DESCRIPTION:• There are strong opportunities for
visual and environmental art installations throughout site
• Seek input from resident and local artists on artistic enhancements to site plan
Feature Artwork & SculptureEnvironmental Impact
Opportunities for environmental education
Implementation Timeline
On-going
Design Costs Varies
Construction Costs
Varies
Permitting Considerations
Larger installations may require Eplan grading permit
Annual Maintenance Costs
Varies
Funding Opportunities
● BOPA Community Arts Grant ● Private Foundations
Additional Considerations
● Seek input and collaboration with LukeWorks or other resident/local artists
● Recycled materials● The Falls and Grass Bowl site features
may be well suited for artistic design + build projects
ARTWORK & SCULPTURE16
PROPOSED PLAN
EXISTING SITE
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
ARTWORK & SCULPTURE16
PRECEDENT IMAGES
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
5
6
7
8
9
10
11
13
14
15
16
12
GREEN ROOF
ROOFTOP SOLAR + GREEN ROOF
RAINWATER HARVESTING CISTERNS
BEER GARDEN / PATIO GREENING
1
2
3
4
POCKET LANDSCAPES
RIVERSIDE HABITAT WETLAND
HILLSIDE OBSERVATION WETLAND
FOREST EDGE
MEADOW SLOPE
HARDSCAPE WALKWAYS
NATURE TRAIL
EDUCATIONAL + WAYFINDING SIGNAGE
THE FALLS
THE GRASS BOWLS
TRAIL CONNECTIONS + UNDERPASS HABITAT
ARTWORK + SCULPTURE
PROJECT TIMELINEYear 1 (through Summer 2021)
● Beer Garden/Patio Greening● Install select Pocket Landscape Areas● Develop Invasive Removal Plan for Forest
Edge● Secure Property Agreements for Light Rail
Trail Connection● Parking Lot Reconfiguration & Rideshare
(optional)● No-Mow Test Areas + Temporary Nature Trail
Delineation ● Organize Volunteer Events for Stream
Cleanups, Invasive Removal near Forest Edge
Year 2-3● Remove Invasives & Plant Forest Edge● Construct Riverside Habitat Wetland● Install Rainwater Harvesting Cisterns● Construct Grass Bowls● Improve Trail to Medfield Neighborhood● Install Green Roofs● Install Solar Roof
Year 4-5● Construct Nature Trail ● Plant Meadow Slope ● Construct The Falls ● Hardscape Walkway + ADA Path
Construction
Year 6-7● Period of Intensive Meadow Maintenance● Construct Hillside Observation Wetland
Year 7-10● Complete Light Rail Trail Connection &
Undepass Habitat
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
GRANT TIMELINE0-6 months
● August 2020 - CBT WAG Design Grant ○ Complete Design of Riverside Wetland○ Design for Rainwater Harvesting Cisterns
● August 2020 - CBT O&R Construction Grant○ Install Pocket Landscapes & Parking Lot De-Pave
● Rolling - CBT Mini-Grant○ Native Plantings and De-Pave around Patio
Year 1● February 2021 NFWF Grants
○ Invasive Removal and Tree Planting at Forest Edge○ Green Roof/Solar Roof○ Hillside Observation Wetland Design
● March 2021 - MD DNR○ Construct Riverside Wetland **○ Green/Solar Roof
● August 2021 - CBT O&R Construction Grant○ Construct Riverside Wetland **○ Install Rainwater Harvesting Cisterns
● August 2021 - CBT WAG Design Grant○ Meadow + Trail Design○ Hillside Observation Wetland Design
Year 2 Priorities● Secure design funding for Hillside Observation Wetland (NFWF)● Construct Meadow + Nature Trail (NFWF + Private Funding)
*** Timeline will depend on schedule for securing design funding
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
Total Project Cost: $4.8MGSI Costs*: $4.5M
*Projects eligible for full or partial funding through greening grants
Grant Funding Notes: 1. Funding is generally awarded
3-6 months following grant due date
2. Design timeline is typically 12-18 months
3. Construction timeline varies by project
4. Projects not eligible for full greening funds include Patio Improvements, the Grass Bowls, and Hardscape Walkways
PARTNERSHIPS Friends of the Jones Falls (FTJF)
• FTJF can assist with fundraising and outreach for most components of the GSI plan• Lead the coordination and implementation effort for Light Rail Trail • Coordinate with DPT and DPW about stream channel restoration adjacent Medfield Trail
Baltimore City DOT• Consult with DOT about expanding accessibility and traffic safety measures along 41st street• Discuss opportunities for restoration of eroded stream channel adjacent Medfield trail. This property
is City right-of-way managed by DOT
Baltimore City DPW• DPW should be closely engaged with design of wetlands, green roofs, and cisterns. Coordinate with
DPW about possible SWM fee reduction credits related to construction of these projects• Discuss opportunities for restoration of eroded stream channel adjacent Medfield trail. Restoration
may be eligible for funding through Stormwater Program
Baltimore City Forestry• Consult with Forestry about invasive removal and forest edge project• Consult with Forestry for canopy improvements along Light Rail and Medfield Trail connections
Medfield/Woodberry Neighborhood Associations • Neighborhood associations should be closely engaged with the Light Rail + Trail Connection
Projects, and any City improvements along 41st Street• Engage for Stream Cleanups and Volunteer Events
Area Schools• Consider environmental education partnerships with nearby schools, such as Poly/Western High
Schools and Medfield Heights Elementary School
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020
Certain features will require unique maintenance tasks, particularly during early establishment.
Meadow • Planting through year 5-7: Mowing of new plantings will be timed to reduce invasives. Seeding and
overseeding must occur during appropriate seasonal windows. Hand weeding of particular invasives may be required if the invasive is rampant or particularly noxious.
• Once established: Maintenance is reduced to a late winter mowing and possibly a late spring mowing if there is weed pressure. Monthly inspections during the growing season are recommended to ensure the health of the meadow.
Wetlands • Bi-annual inspections needed to ascertain specific maintenance needs, including repair of eroded
areas, removal of sediment, clearing of inflow/outflow areas, removal of dead or unwanted vegetation, vegetation thinning
The Nature Trail• Requires regular inspection to ensure that the path and retaining materials are not compromised• Any signs of wear or erosion should be addressed immediately
Wetland & Boardway Decking • Need regular inspection and maintenance per the manufacturer’s or contractor’s specifications
(depends on chosen decking material and finish)
Native Plantings and Forest • Year 1 and 2: weekly watering and twice monthly weeding • Once established: water during drought, seasonal weeding, cutting back in late winter
MAINTENANCE CONSIDERATIONS
GREEN INFRASTRUCTURE MASTER PLAN UNION COLLECTIVE | JULY 2020