grid integration study results & recommendations · day 1, 12:00, 60 mins . introduction delhi...
TRANSCRIPT
![Page 1: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/1.jpg)
Project: Analysis of Indian distribution systems for the integration of high shares of rooftop PV
INTEGRATION OF RENEWABLE ENERGIES IN THE INDIAN ELECTRICITY SYSTEM (I-RE)
Final Workshop, 29 August 2017
Dr. Thomas Ackermann
Dr.-Ing. Eckehard Tröster
Grid Integration Study Results & Recommendations
Day 1, 12:00, 60 mins
![Page 2: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/2.jpg)
Introduction
Delhi Simulation Results
• Urban Feeder
• Rural Feeder
Bhopal Simulation Results
• Urban Feeder
• Rural Feeder
Summary
Recommendations
CONTENT
2
![Page 3: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/3.jpg)
Delhi urban Delhi rural 1 Delhi rural 2 Bhopal urban
Bhopal rural
Supplied from 33 kV 66 kV 66 kV 132/33 kV 33 kV
Dominant cable/line type
300XLPE cable, 5.7 MVA
Dog ACSR OHL, 5.7 MVA
Dog ACSR OHL, 5.7 MVA
Rabbit ACSR OHL, 2.9 MVA
Raccoon ACSR OHL, 3.8 MVA
Length OHL - 19.8 km 16.7 km 2.7 km 11.0 km
Length UG cables 3.1 km 10.9 km 2.6 km - -
Total length 3.1 km 30.7 km 19.3 km 2.7 km 11.0 km
Installed DT capacity
5.4 MVA 5.2 MVA 4.6 MVA 2.2 MVA 3.7 MVA
Peak load 2.5 MW 3.4 MW 3.0 MW 1.1 MW 1.6 MW
Expected main issues
Protection, reversed power flow
Voltage control, asset overloading (PV power plant)
Protection, reversed power flow
Voltage control
REMINDER: INVESTIGATED GRIDS COMPARISON OF RELEVANT 11 KV GRIDS
3
![Page 4: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/4.jpg)
INCREASING PV GENERATION
4
Delhi urban Delhi rural Bhopal urban Bhopal rural
% of DT MW % of DT MW % of DT MW % of DT MW
20% 1.1 15% 1.5 30% 3.9 30% 10.9
50% 2.7 40% 3.9 50% 6.5 50% 18.2
75% 4.1 75% 7.4 75% 9.8 75% 27.2
100% 5.4 100% 9.8 100% 13.0 100% 36.3
150% 8.1 150% 14.7 150% 19.5 150% 54.5
Stepwise increase of installed PV generation
Bhopal: Including upstream PV and parallel feeders
Both rural feeders combined
![Page 5: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/5.jpg)
RESULTS ON INCREASING PV PENETRATION
5
Loading Voltage
PV Penetration: 20 % of DTs
3.502.802.101.400.70-0.00 [km]
011k
V_V
a..
S02_
VVR
0..
2950
5055
..
2950
5059
..
2950
5059
..
S03_
VVR
0..
2950
1304
..
2950
1304
..
2950
1032
..
2950
1305
..
2950
1238
..
2950
1239
..
2950
1238
..
2950
1238
..
2950
1238
..
2950
1238
..
2950
1238
..
2950
1238
..
1.14
1.08
1.03
0.97
0.92
0.86
[p.u.]
Voltage, Magnitude
1.1 pu
0.9 pu
![Page 6: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/6.jpg)
RESULTS ON INCREASING PV PENETRATION
6
Loading Voltage
PV Penetration: 50 % of DTs
3.502.802.101.400.70-0.00 [km]
011k
V_V
a..
2950
5059
..
2950
5055
..
2950
5059
..
2950
5059
..
2950
1304
..
2950
1304
..
2950
1304
..
2950
1032
..
2950
1305
..
2950
1238
..
2950
1239
..
2950
1238
..
2950
1238
..
2950
1238
..
2950
1238
..
2950
1238
..
2950
1238
..
1.14
1.08
1.03
0.97
0.92
0.86
[p.u.]
Voltage, Magnitude
1.1 pu
0.9 pu
![Page 7: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/7.jpg)
RESULTS ON INCREASING PV PENETRATION
7
Loading Voltage
PV Penetration: 75 % of DTs
3.502.802.101.400.70-0.00 [km]
011k
V_V
a..
2950
5059
..
2950
5055
..
2950
5059
..
2950
5059
..
2950
1304
..
2950
1304
..
2950
1304
..
2950
1032
..
2950
1305
..
2950
1238
..
2950
1239
..
2950
1238
..
2950
1238
..
2950
1238
..
2950
1238
..
2950
1238
..
2950
1238
..
1.14
1.08
1.03
0.97
0.92
0.86
[p.u.]
Voltage, Magnitude
1.1 pu
0.9 pu
![Page 8: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/8.jpg)
RESULTS ON INCREASING PV PENETRATION
8
Loading Voltage
PV Penetration: 100 % of DTs
3.502.802.101.400.70-0.00 [km]
011k
V_V
a..
2950
5059
..
2950
5055
..
2950
5059
..
2950
5059
..
2950
1304
..
2950
1304
..
2950
1304
..
2950
1032
..
2950
1305
..
2950
1238
..
2950
1239
..
2950
1238
..
2950
1238
..
2950
1238
..
2950
1238
..
2950
1238
..
2950
1238
..
1.14
1.08
1.03
0.97
0.92
0.86
[p.u.]
Voltage, Magnitude
1.1 pu
0.9 pu
![Page 9: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/9.jpg)
RESULTS ON INCREASING PV PENETRATION
9
Loading Voltage
PV Penetration: 150 % of DTs
3.502.802.101.400.70-0.00 [km]
011k
V_V
a..
2950
5059
..
2950
5055
..
2950
5059
..
2950
5059
..
2950
1304
..
2950
1304
..
2950
1304
..
2950
1032
..
2950
1305
..
2950
1238
..
2950
1239
..
2950
1238
..
2950
1238
..
2950
1238
..
2950
1238
..
2950
1238
..
2950
1238
..
1.14
1.08
1.03
0.97
0.92
0.86
[p.u.]
Voltage, Magnitude
1.1 pu
0.9 pu
![Page 10: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/10.jpg)
VOLTAGE RECORDING EXAMPLE
10
Voltage over feeder length
09:00:00
Voltage over feeder length
12:00:00
Voltage over feeder length
15:00:00
Max. voltage over time
Condense the information by using max. voltage without length information
![Page 11: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/11.jpg)
From the simulations, two
specific result parameters
are taken for evaluation:
• Maximum Loading
• Maximum Voltage
The result includes the
11kV and for the Urban
Feeder also the 400 V
networks
RESULT EVALUATION
11
![Page 12: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/12.jpg)
Simulation of a full day with
Maximum PV infeed profile
Minimum load
Evaluation of
Highest voltage
Highest loading
at every time step regardless of position in the grid
Peak loading and peak voltage get stored for each variation of installed PV
RESULT EVALUATION CRITERIA
12
Voltage
Loading Peak values
Peak values
![Page 13: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/13.jpg)
VOLTAGE LIMIT DEFINITION
13
Rural Feeder: Relevant Voltage limit for PT+MV+DT = 1.06 pu
Voltage increase or drop allowed:
•1 % Tolerance 11 kV busbar of OLTC Transformer (66/33 kV – 11 kV)
•4 % at the 11 kV level
•1 % at the Distribution Transformer
•4 % at the 0.4 kV level
Total Drop = 1 + 4 + 1 + 4 = 10 %
Load PV
Load PV
Load PV
Load PV Urban Feeder Relevant Voltage limit for PT+MV+DT+LV = 1.1 pu
![Page 14: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/14.jpg)
14
DELHI SIMULATION RESULTS
URBAN FEEDER
![Page 15: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/15.jpg)
DELHI URBAN FEEDER MEASURE IMPLEMENTATION
15
Voltage
Loading Thermal limit of 100%
Voltage limit for LV ±10%
Voltage recommendation
for MV (±6%)
Scenario 1: PV equal distribution
![Page 16: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/16.jpg)
DELHI RESULTS - URBAN FEEDER SCENARIO 1: PV EQUALLY DISTRIBUTED ALONG THE FEEDER WITH NORMAL LOAD
16
No issues with PV
No voltages issues up to ca. 120% PV
Base case violates loading of network elements (in this case a cable)
Suitable solutions:
• 07 cap pv
• 09 grid reinforcement
![Page 17: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/17.jpg)
DELHI RESULTS - URBAN FEEDER SCENARIO 2: PV EQUALLY DISTRIBUTED ALONG THE FEEDER WITH ADAPTED LOAD
17
No issues with PV
![Page 18: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/18.jpg)
DELHI RESULTS - URBAN FEEDER SCENARIO 3: PV WITH HIGHER PV PENETRATION AT THE END OF FEEDER WITH NORMAL LOAD
18
No issues with PV
![Page 19: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/19.jpg)
DELHI RESULTS - URBAN FEEDER SCENARIO 4: PV WITH HIGHER PV PENETRATION AT THE END OF FEEDER WITH ADAPTED LOAD
19
No issues with PV
![Page 20: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/20.jpg)
DELHI RESULTS - URBAN FEEDER SCENARIO 5: PV WITH CABLES CONVERTED TO CABLES WITH LOWER CROSS-SECTION
20
No issues with PV
![Page 21: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/21.jpg)
21
DELHI SIMULATION RESULTS
RURAL FEEDER
![Page 22: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/22.jpg)
DELHI RESULTS - RURAL FEEDER SCENARIO 1: PV EQUALLY DISTRIBUTED ALONG THE FEEDER WITH NORMAL LOAD
22
No issues with PV
No issues with PV and storage peakShaving
Example: Choosing a solution
![Page 23: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/23.jpg)
DELHI RESULTS - RURAL FEEDER SCENARIO 2: PV EQUALLY DISTRIBUTED ALONG THE FEEDER WITH ADAPTED LOAD
23
No issues with PV
![Page 24: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/24.jpg)
DELHI RESULTS - RURAL FEEDER SCENARIO 3: PV ON ALL FEEDERS WITH A PV POWER PLANT CONNECTED
24
No issues with PV
![Page 25: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/25.jpg)
DELHI RESULTS - RURAL FEEDER SCENARIO 4: PV WITH OHL CONVERTED TO CABLES WITH SIMILAR CROSS-SECTION
25
No issues with PV
![Page 26: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/26.jpg)
26
BHOPAL SIMULATION RESULTS
URBAN FEEDER
![Page 27: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/27.jpg)
BHOPAL RESULTS – URBAN FEEDER SCENARIO 1: ROOFTOP PV EQUALLY DISTRIBUTED ALONG THE FEEDER WITH NORMAL LOAD
27
Voltage
Loading
No issues with PV
![Page 28: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/28.jpg)
BHOPAL RESULTS - URBAN FEEDER SCENARIO 2: ROOFTOP PV EQUALLY DISTRIBUTED ALONG THE FEEDER WITH ADAPTED LOAD
28
Voltage
Loading
No issues with PV
![Page 29: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/29.jpg)
29
Voltage
Loading
No issues with PV
BHOPAL RESULTS - URBAN FEEDER SCENARIO 3: ROOFTOP PV WITH HIGHER PV AT THE END OF FEEDER WITH NORMAL LOAD
![Page 30: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/30.jpg)
BHOPAL RESULTS - URBAN FEEDER SCENARIO 4: ROOFTOP PV WITH HIGHER PV AT THE END OF FEEDER WITH ADAPTED LOAD
30
Voltage
Loading
No issues with PV
![Page 31: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/31.jpg)
31
Voltage
Loading
No issues with PV
BHOPAL RESULTS - URBAN FEEDER SCENARIO 5: ROOFTOP PV WITH OVER-HEAD-LINES CONVERTED TO CABLES WITH LOWER CROSS-SECTION
![Page 32: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/32.jpg)
32
BHOPAL SIMULATION RESULTS
RURAL FEEDER
![Page 33: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/33.jpg)
BHOPAL RESULTS – RURAL FEEDER SCENARIO 1: ROOFTOP PV EQUALLY DISTRIBUTED ALONG THE FEEDER WITH NORMAL LOAD
33
Voltage
Loading
No issues with PV
![Page 34: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/34.jpg)
BHOPAL RESULTS - RURAL FEEDER SCENARIO 2: ROOFTOP PV EQUALLY DISTRIBUTED ALONG THE FEEDER WITH ADAPTED LOAD
34
Voltage
Loading
No issues with PV
![Page 35: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/35.jpg)
BHOPAL RESULTS - RURAL FEEDER SCENARIO 3A: ROOFTOP PV WITH A PV POWER PLANT AT THE BEGINNING OF THE FEEDER
35
Voltage
Loading
No issues with PV
![Page 36: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/36.jpg)
BHOPAL RESULTS - RURAL FEEDER SCENARIO 3B: ROOFTOP PV WITH A PV POWER PLANT AT THE MIDDLE OF THE FEEDER
36
Voltage
Loading
No issues with PV
![Page 37: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/37.jpg)
BHOPAL RESULTS - RURAL FEEDER SCENARIO 3C: ROOFTOP PV WITH A PV POWER PLANT AT THE END OF THE FEEDER
37
Voltage
Loading
No issues with PV
![Page 38: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/38.jpg)
BHOPAL RESULTS - RURAL FEEDER SCENARIO 4: ROOFTOP PV WITH OVER-HEAD-LINES CONVERTED TO CABLES WITH SIMILAR CROSS-SECTION
38
Voltage
Loading
No issues with PV
![Page 39: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/39.jpg)
39
RESULT SUMMARY
![Page 40: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/40.jpg)
Impact Symbol
Measure increases hosting capacity from base case, above 100 %
Measure increases hosting capacity from base case but stays below 100 %
Measure has no effect O
Measure reduces hosting capacity from base case
RESULT ASSESSMENT
40
![Page 41: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/41.jpg)
Measure
Scenario 1: PV equally distributed with normal load
Scenario 2: PV equally distributed with adapted load
Scenario 3: PV at the end of the feeder with normal load
Scenario 4: PV at the end of the feeder with adapted load
Scenario 5: PV at the end of the feeder with lower cable cross-section
base 90% 100% 75% 80% 55%
oltc 90% o 100% o 75% o 80% o 55% o
wide area control
90% o 100% o 75% o 80% o 50%
fixed PF 80% 85% 65% 70% 50%
qvchar 90% o 95% 70% 75% 55% o
cap pv 150% 150% 140% 150% 105%
storage own consumption
90% o 100% o 75% o 80% o 55% o
storage peakShaving
120% 130% 100% 115% 80%
dsm 90% o 100% o 75% o 80% o 55% o
grid reinforcement
150% 150% 150% 150% 150%
DELHI URBAN FEEDER RESULT OVERVIEW
41
![Page 42: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/42.jpg)
Measure Scenario 2: PV equally distributed with normal load
Scenario 3: PV equally distributed with adapted load
Scenario 4: PV equally distributed with 3.5 MW PV power plant
Scenario 5: PV equally distributed with network fully cabled
Base 90% 110% 50% 70%
wide area control
105% 110% o 75% 100%
fixed PF 95% 105% 65% 95%
qvchar 105% 110% o 70% 90%
cap pv 150% 150% 70% 145%
storage own consumption
90% o 110% o 50% o 70% o
storage peak shaving
125% 150% 70% 100%
dsm 90% o 110% o 50% o 70% o
grid reinforcement
150% 150% 150% 150%
DELHI RURAL FEEDER RESULT OVERVIEW
42
![Page 43: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/43.jpg)
BHOPAL URBAN FEEDER RESULT OVERVIEW
43
Measure
Scenario 1: PV equally distributed normal load
Scenario 2: PV equally distributed adapted load
Scenario 3: PV at the end of the feeder normal load
Scenario 4: PV at the end of the feeder adapted load
Scenario 5: PV equally distr., cabled network
base 110 % 115 % 110 % 110 % 110 %
mvoltc 110% o 115% o 110% o 110% o 110% o
shunt V control
110% o 115% o 110% o 110% o 110% o
wide area control
110% o 115% o 105% 110% o 110% o
fixed PF 100% 105% 90% 95% 100%
qvchar 110% o 110% 105% 110% o 110% o
cap pv 145% 150% 140% 145% 145%
storage own consumption
110% o 115% o 110% o 110% o 110% o
storage peakSh.
140% 150% 130% 135% 140%
grid reinf. 150% 150% 150% 150% 150%
![Page 44: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/44.jpg)
Measure Scenario 1: PV equally distributed normal load
Scenario 2: PV equally distributed adapted load
Scenario 3C: PV equ. dist. with PV plant at end of feeder
Scenario 4: PV equally distributed, fully cabled network
base 100 % 105 % 65 % 105 %
mvoltc 105% 110% 65% o 105% o
shunt V control
90% 105% o 60% 100%
wide area control
100% o 110% 65% o 100%
fixed PF 90% 85% 60% 95%
qvchar 100% o 110% 65% o 100%
cap pv 125% 130% 85% 130%
storage own consumption
100% o 115% 65% o 105% o
storage peakShaving
125% 140% 80% 130%
grid reinforcement
150% 150% 150% 150%
BHOPAL RURAL FEEDER RESULT OVERVIEW
44
![Page 45: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/45.jpg)
• Grids in India are not very different from other grids in the world.
• PV systems with an aggregated capacity of up to 75% of the transformer rating can usually be connected without any further measures. In most cases 100% are actually possible.
• Above 75% the rural networks suffers predominately from over-voltage issues.
• Voltage issues can be solved with wide area control of the 66/11kV transformer and reactive power provision by the PV systems
• Above 75% in the urban network, mostly loading problems occur.
• As the lines are short there is less voltage drop across them.
• Above 75% line loading issues and above 100% distribution transformer overloading have to be considered critical
• Besides conventional network reinforcement, implementing peak-shaving battery systems is a possible solutions
GENERAL CONCLUSIONS
45
![Page 46: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/46.jpg)
Peak shaving batteries • Needs to be procured and installed by the customer
• Would roughly double the price of the installation
• No grid parity for such a system
• Indian homes are already equipped with batteries that could be used for PV storage
• Additional incentive for batteries to operate in peak shaving mode
Capping of inverters • Cheaper solution, almost the same grid impact during extreme situations
• Possible to cap PV feed-in at 70 – 75 % of the maximum without losing more than 3 % of energy annually
• Solution is currently used for small rooftop PV units in Germany
PERFORMANCE OF TECHNICAL SOLUTIONS ACTIVE POWER MANAGEMENT
46
Additional incentive scheme required
![Page 47: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/47.jpg)
Wide area control • Voltage rises induced by PV and drops caused by high load are detected and
alleviated
• The general quality of supply will be improved by improving the voltage profile
• Continuous measurements have to be made at multiple points resulting in a constant stream of operational data
• Estimated cost at 50,000 € per 110/20 kV transformer
Voltage control from PV inverters • Utilizes reactive power and increases loading
• In highly loaded grids, using a Q-V characteristic provides better results
• In grids with no loading issues, a fixed power factor of 0.95 lagging performed better
• If a large amount of PV power is located at one node in the grid, a Q-V characteristic performs better
PERFORMANCE OF TECHNICAL SOLUTIONS VOLTAGE CONTROL MEASURES
47
![Page 48: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/48.jpg)
Overcurrent protection Short circuit current contribution of the units feeding in between the protection relay and the location of the fault have to be considered
Short circuit current of PV system is no larger than the rated current of the inverter
Simple solution:
Require the inverters to not feed in current at detection of a voltage drop (Zero-Current-Mode)
Collides with low voltage ride through capabilities
Short circuit current of all units on a feeder should be limited to
𝑰𝒔𝒄,𝒖𝒏𝒊𝒕 ≤ 𝑰𝒔𝒄,𝒎𝒊𝒏 − 𝑰𝒔𝒄,𝒕𝒓𝒊𝒈𝒈𝒆𝒓
PROTECTION
48
![Page 49: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/49.jpg)
49
RECOMMENDATIONS
![Page 50: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/50.jpg)
Studies • Great variety of results observed in this study
• High hosting capacity observed for both distribution grid areas
• Each grid area in India should be analysed independently
• Simple estimation approaches might be sufficient
• Simulation studies of example feeder is recommended to evaluate impact on grid operation
General technical requirements for PV systems • Compliance with international standards that limit emissions (Harmonics, Flicker,
DC currents)
• Generator protection to avoid damage and unintentional islanding
• Compatibility of fault behaviour and protection settings
RECOMMENDATIONS 1/4
50
![Page 51: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/51.jpg)
Technology options • Automatic voltage control at 132/33, 220/66 or 220/33 kV should be
implemented
• Automatic voltage control at 66/11 or 33/11 kV is very beneficial, but not strictly required
• Under- and overvoltage can be efficiently eliminated using wide area control
• Voltage control by rooftop PV inverters through reactive power
• Can easily be required by the grid code and is highly recommended
• PV power plants connected to the 11 or 33 kV level should be equipped with active voltage control by Q-V characteristic
• Active power controllability should be required from all PV units
• Large centralized PV power plants should be remotely controllable
• Rooftop PV units should either be capped at 70 to 75 % of their maximum expected output, or be remotely controllable, or be equipped with a peak shaving storage (requires incentive)
RECOMMENDATIONS 2/4
51
![Page 52: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/52.jpg)
Legal and regulatory framework • Remote control of PV units
• Requires legal framework of operation (When, who and how to use)
• Require voltage control capability from PV inverters, controlled by grid operator
• Active power curtailment requires agreed remuneration of lost energy
• Recommended to align the voltage control requirements with the German low voltage grid code, most PV systems already comply
• Capping of PV at 70 or 75 % would have to be specified in grid code and net metering scheme, and checked for legal complications
• PV batteries require incentives for installation and running them in peak shaving mode
• Grid code requirements should be developed in coordination transmission system operators
• Example: frequency response of PV units
RECOMMENDATIONS 3/4
52
![Page 53: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/53.jpg)
Specific recommendations Delhi
Once the 66/11 and 33/11 kV transformers are upgraded to automatic voltage control, there are no specific recommendations that deviate from the previously stated.
Bhopal
Enable more control over the voltage control regimes
• Retrofit 132/33 kV transformers with automatic tap changing
• Equip 33/11 kV transformers with on-load tap changers
• Automatic voltage control should be used in new projects or when replacing old or damaged units
RECOMMENDATIONS 4/4
53
![Page 54: Grid Integration Study Results & Recommendations · Day 1, 12:00, 60 mins . Introduction Delhi Simulation Results ... fixed PF 100% 105% 90% 95% 100%](https://reader033.vdocuments.net/reader033/viewer/2022052019/60332b07093cf76f1047e2ae/html5/thumbnails/54.jpg)
54
THANK YOU FOR YOUR ATTENTION!