➢ Grinnell College HSSC Project
Leadership Team:
➢ Anne Harris
➢ Jim Swartz
➢ Erik Simpson
➢ Keith Brouhle
➢ Rick Whitney
➢ Dave Robinson
➢ Larry Gleason
➢ Keith Archer
➢ Nancy Combs
➢ Christi Baker
➢ Jane Taylor
➢ EYP Architects
➢ Jennifer Amster
➢ Eric Kern
➢ Eric Petersen
➢ Alison Ledwith
➢ OPN Architects
➢ Bill Catrenich
➢ Pylar Eaton
McGough Project Team
➢ Dustin Schwake – Project Executive
➢ Ryan Drew– Senior Project Manager
➢ Jennifer Radniecki – Project Manager
➢ Alex Maass – Assistant Project Manager
➢ Amy Robinson – Lead Project Coordinator
➢ Chuck R. Carpenter – Senior Superintendent
➢ Greg Evans – Superintendent
➢ Jon Hansen – Laborer Foreman
Subcontractors
➢ 1st Interiors
➢ Advance Equipment Co.
➢ All-American Scaffold
➢ American Fence Co.
➢ American Structural Metals
➢ Architectural Wall Systems
➢ Baker Electric
➢ Baker Group
➢ Bartley Sales
➢ Blue Sky Cleaning
➢ Bolander
➢ C&C Demolition
➢ CGA
➢ D&N Fence
➢ DA Bunch
➢ Danny’s Construction
➢ Des Moines Marble
➢ Energy Control of Iowa
➢ Floors by Beckers
➢ Forman Ford
➢ Heartland Finishes
➢ J&M Roofing
➢ Johnson Specialty Sales
➢ KONE Elevator
➢ Larry’s Window Services
➢ Midwest Caulking
➢ Navetta
➢ PAC-VAN
➢ Pella Tree Service
➢ Peterson Contractors, Inc.
➢ Premier Edge
➢ Pro-Bel
➢ S&F Underground
➢ Seedorff Masonry
➢ Skold Companies
➢ Soil-Tek
➢ Summit Fire Protection
➢ Superior Painting
➢ Swanson & Youngdale
➢ Waldinger Mechanical
➢ Walsh Door & Security
➢ Western Specialty
➢ Wilkie Sanderson
➢ Wynn O. Jones
➢ Landscaping:
➢ Threshold pier lanterns are being set
and powered.
➢ Light poles outside of ARH and
Carnegie are installed and are in
process of being powered up.
➢ Black dirt is being spread and
backfilled against new sidewalk.
➢ Plantings to start week of 5/18/20,
dependent upon weather.
Current Highlights
➢ Carnegie:
➢ Punchlist corrections
➢ Furniture delivery and installation
➢ Behind Firewall:
➢ Punchlist corrections
➢ ARH:
➢MEP trim-out continues
➢ Installation of wood paneling and fins
in auditorium
➢ Terrazzo installation at corridors
➢ Paint touch-ups ongoing
Grinnell College main sign at Hwy 6 and Park Street
Threshold piers at Bucksbaum
Threshold piers and steppers between Goodnow and Steiner Hall
Threshold piers between Carnegie and Herrick Chapel
Backfill of black dirt and final grading nearing completion pending weather compliance, looking south towards Herrick Chapel
Backfill of black dirt and final grading nearing completion pending weather compliance, looking north towards Younker Hall
ARH 1st floor - Metal panels and doors set at atrium connection
ARH 1st floor - Wood ceiling installation
ARH 1st floor - Coffee Bar tile installed
ARH 2nd floor - Bridge connection, finishes installed
ARH 2nd floor looking south
ARH - Plumbing fixtures installed
ARH - Vanity set, fixtures installed
ARH - Carpet installed in individual rooms
ARH - Auditorium ceiling
ARH - Reading Room ceiling
ARH - Wood fin backup system
Carnegie basement furniture installation
Carnegie 1st floor office space
Carnegie 2nd floor hallway
Carnegie 2nd floor - Wall covering at ST401
Upcoming Highlights
➢ Carnegie:
➢ Furniture installation
➢ Punchlist corrections
➢ Behind Firewall:
➢ Punchlist corrections
➢ ARH:
➢MEP trim-out
➢Wood fin installation
➢ Terrazzo completion
➢ Paint touch-ups
➢ Landscaping:
➢Completing plantings Tile D west
➢Saw cutting and demolition of
intersection 8th Ave. and Park Street
➢Saw cutting and demolition of widened
crosswalks on 8th Ave. towards JRC