Groningen, 1-2 February 2001
FPU Preliminary Design Review 1
First Stage Cryogenic IF First Stage Cryogenic IF AmplifierAmplifier
Centro Astronómico de YebesCentro Astronómico de Yebes
Observatorio Astronómico NacionalObservatorio Astronómico Nacional
SPAINSPAIN
![Page 2: Groningen, 1-2 February 2001 FPU Preliminary Design Review1 First Stage Cryogenic IF Amplifier Centro Astronómico de Yebes Observatorio Astronómico Nacional](https://reader035.vdocuments.net/reader035/viewer/2022062519/5697bfaf1a28abf838c9ce1e/html5/thumbnails/2.jpg)
Groningen, 1-2 February 2001
FPU Preliminary Design Review 2
Centro Astronómico de YebesObservatorio Astronómico Nacional
SPAIN
• DM Program– New Devices
– New Design
– Results
• QM & FM Programs: Fabrication by the Industry– Transfer to Industry
– Processes
– Components
• Summary of critical items
• Planning
CONTENTSCONTENTS
![Page 3: Groningen, 1-2 February 2001 FPU Preliminary Design Review1 First Stage Cryogenic IF Amplifier Centro Astronómico de Yebes Observatorio Astronómico Nacional](https://reader035.vdocuments.net/reader035/viewer/2022062519/5697bfaf1a28abf838c9ce1e/html5/thumbnails/3.jpg)
Groningen, 1-2 February 2001
FPU Preliminary Design Review 3
Centro Astronómico de YebesObservatorio Astronómico Nacional
SPAIN
DM PROGRAMDM PROGRAM
![Page 4: Groningen, 1-2 February 2001 FPU Preliminary Design Review1 First Stage Cryogenic IF Amplifier Centro Astronómico de Yebes Observatorio Astronómico Nacional](https://reader035.vdocuments.net/reader035/viewer/2022062519/5697bfaf1a28abf838c9ce1e/html5/thumbnails/4.jpg)
Groningen, 1-2 February 2001
FPU Preliminary Design Review 4
Centro Astronómico de YebesObservatorio Astronómico Nacional
SPAIN
DM PROGRAMDM PROGRAM
![Page 5: Groningen, 1-2 February 2001 FPU Preliminary Design Review1 First Stage Cryogenic IF Amplifier Centro Astronómico de Yebes Observatorio Astronómico Nacional](https://reader035.vdocuments.net/reader035/viewer/2022062519/5697bfaf1a28abf838c9ce1e/html5/thumbnails/5.jpg)
Groningen, 1-2 February 2001
FPU Preliminary Design Review 5
Centro Astronómico de YebesObservatorio Astronómico Nacional
SPAIN
DM PROGRAMDM PROGRAM
![Page 6: Groningen, 1-2 February 2001 FPU Preliminary Design Review1 First Stage Cryogenic IF Amplifier Centro Astronómico de Yebes Observatorio Astronómico Nacional](https://reader035.vdocuments.net/reader035/viewer/2022062519/5697bfaf1a28abf838c9ce1e/html5/thumbnails/6.jpg)
Groningen, 1-2 February 2001
FPU Preliminary Design Review 6
Centro Astronómico de YebesObservatorio Astronómico Nacional
SPAIN
DM PROGRAMDM PROGRAM
![Page 7: Groningen, 1-2 February 2001 FPU Preliminary Design Review1 First Stage Cryogenic IF Amplifier Centro Astronómico de Yebes Observatorio Astronómico Nacional](https://reader035.vdocuments.net/reader035/viewer/2022062519/5697bfaf1a28abf838c9ce1e/html5/thumbnails/7.jpg)
Groningen, 1-2 February 2001
FPU Preliminary Design Review 7
Centro Astronómico de YebesObservatorio Astronómico Nacional
SPAIN
DM PROGRAMDM PROGRAM
![Page 8: Groningen, 1-2 February 2001 FPU Preliminary Design Review1 First Stage Cryogenic IF Amplifier Centro Astronómico de Yebes Observatorio Astronómico Nacional](https://reader035.vdocuments.net/reader035/viewer/2022062519/5697bfaf1a28abf838c9ce1e/html5/thumbnails/8.jpg)
Groningen, 1-2 February 2001
FPU Preliminary Design Review 8
Centro Astronómico de YebesObservatorio Astronómico Nacional
SPAIN
DM PROGRAMDM PROGRAM
3 4 5 6 7 8 90
5
10
15
20
25
30
YCF 2010Low Power (1.1 mW < P
stage < 1.5 mW)
ETH 200 ETH 150 TRW 200 B TRW 200 S
Gai
n (d
B)
Freq. (GHz)
0,0
2,5
5,0
7,5
10,0
12,5
15,0
Tn (
K)
ETH 200 ETH 150 TRW 200 B TRW 200 S
![Page 9: Groningen, 1-2 February 2001 FPU Preliminary Design Review1 First Stage Cryogenic IF Amplifier Centro Astronómico de Yebes Observatorio Astronómico Nacional](https://reader035.vdocuments.net/reader035/viewer/2022062519/5697bfaf1a28abf838c9ce1e/html5/thumbnails/9.jpg)
Groningen, 1-2 February 2001
FPU Preliminary Design Review 9
Centro Astronómico de YebesObservatorio Astronómico Nacional
SPAIN
DM PROGRAMDM PROGRAM
• New Design– First prototype using InP TRW 200 devices in both stages – Oscillations?– Substrate glued to the box using epoxy instead solder– MDM connector for the bias circuit– Gate voltage divider included in the bias circuit– Smaller size (582910.5mm)– Mechanical interface with mixer sub-assembly– SMA connectors with “O ribbon” connection (Pending due to delivery of connectors)– Final decision for ESD protection: LEDs or big capacitors (Pending)– EMC filtering (Pending)– Bias circuit in the QM and FM different from that in the DM
![Page 10: Groningen, 1-2 February 2001 FPU Preliminary Design Review1 First Stage Cryogenic IF Amplifier Centro Astronómico de Yebes Observatorio Astronómico Nacional](https://reader035.vdocuments.net/reader035/viewer/2022062519/5697bfaf1a28abf838c9ce1e/html5/thumbnails/10.jpg)
Groningen, 1-2 February 2001
FPU Preliminary Design Review 10
Centro Astronómico de YebesObservatorio Astronómico Nacional
SPAIN
DM PROGRAMDM PROGRAM
DM 2001
DM 5001
623512mm582910.5mm
![Page 11: Groningen, 1-2 February 2001 FPU Preliminary Design Review1 First Stage Cryogenic IF Amplifier Centro Astronómico de Yebes Observatorio Astronómico Nacional](https://reader035.vdocuments.net/reader035/viewer/2022062519/5697bfaf1a28abf838c9ce1e/html5/thumbnails/11.jpg)
Groningen, 1-2 February 2001
FPU Preliminary Design Review 11
Centro Astronómico de YebesObservatorio Astronómico Nacional
SPAIN
DM PROGRAMDM PROGRAM
![Page 12: Groningen, 1-2 February 2001 FPU Preliminary Design Review1 First Stage Cryogenic IF Amplifier Centro Astronómico de Yebes Observatorio Astronómico Nacional](https://reader035.vdocuments.net/reader035/viewer/2022062519/5697bfaf1a28abf838c9ce1e/html5/thumbnails/12.jpg)
Groningen, 1-2 February 2001
FPU Preliminary Design Review 12
Centro Astronómico de YebesObservatorio Astronómico Nacional
SPAIN
DM PROGRAMDM PROGRAM
• Results
Critical Issues: Output Reflection, Gain Stability and Oscillations.
DevicePower
Dissipation
AverageNoise Temp.
AverageGain and ripple
MinimumOutput Ref.
GainStability
PD [mW]/Stg. Tn [K] Gav (dB) G (dB) out [dB]
G Hz-1/2 (@1Hz)
Goal 2 5 22 1.5 15 1.410-4
YCF 5001 TRW 2 3.9 26.8 1.32 14 310-5-210-4
YCF 200x ETH 1.25 5.3-5.8 21.7-22.61.2-1.7 13.5-16.5 110-4
![Page 13: Groningen, 1-2 February 2001 FPU Preliminary Design Review1 First Stage Cryogenic IF Amplifier Centro Astronómico de Yebes Observatorio Astronómico Nacional](https://reader035.vdocuments.net/reader035/viewer/2022062519/5697bfaf1a28abf838c9ce1e/html5/thumbnails/13.jpg)
Groningen, 1-2 February 2001
FPU Preliminary Design Review 13
Centro Astronómico de YebesObservatorio Astronómico Nacional
SPAIN
QM & FM PROGRAMS: FABRICATION BY THE INDUSTRYQM & FM PROGRAMS: FABRICATION BY THE INDUSTRY
• Transfer to Industry
– Industry: Inexperience in space projects at cryogenic temperatures
– CAY: Distribution of QA responsibilities.
Difficulties of small groups in dealing with documentation.
• Processes
– Epoxies (EPOTEK H20E, ABLEFILM 5025)
– “O ribbon” connection for SMA connectors
– Bonding
![Page 14: Groningen, 1-2 February 2001 FPU Preliminary Design Review1 First Stage Cryogenic IF Amplifier Centro Astronómico de Yebes Observatorio Astronómico Nacional](https://reader035.vdocuments.net/reader035/viewer/2022062519/5697bfaf1a28abf838c9ce1e/html5/thumbnails/14.jpg)
Groningen, 1-2 February 2001
FPU Preliminary Design Review 14
Centro Astronómico de YebesObservatorio Astronómico Nacional
SPAIN
QM & FM PROGRAMS: FABRICATION BY THE INDUSTRYQM & FM PROGRAMS: FABRICATION BY THE INDUSTRY
• Components
– Passive Components
1.- Components are not qualified at cryogenic temperatures
2.- Chip resistors from SOTA, size 0302, only available as commercial part.
– LEDs or big capacitors for ESD protection
– InP Transistors: Supplying and qualification JPL
– Isolators: Supplying and qualification Pamtech delays
– SMA Connectors: Pin orientation
![Page 15: Groningen, 1-2 February 2001 FPU Preliminary Design Review1 First Stage Cryogenic IF Amplifier Centro Astronómico de Yebes Observatorio Astronómico Nacional](https://reader035.vdocuments.net/reader035/viewer/2022062519/5697bfaf1a28abf838c9ce1e/html5/thumbnails/15.jpg)
Groningen, 1-2 February 2001
FPU Preliminary Design Review 15
Centro Astronómico de YebesObservatorio Astronómico Nacional
SPAIN
SUMMARY OF CRITICAL ITEMSSUMMARY OF CRITICAL ITEMS
• Output reflection
• Gain stability
• Oscillations (change of device?)
• ESD Protection: LEDs or big capacitors
• EMC filtering
• Passive components at cryogenic temperature
• Chip resistors from SOTA, size 0302
• Qualification and procurement of Isolators from Pamtech
• SMA Connectors for “O ribbon” connection