gross reservoir expansion project...
TRANSCRIPT
2017
2018
2019 Secured U.S. Army Corps of Engineers Record of Decision and 404 Permit
Begin final dam design and secure FERC hydropower license amendment
Final design engineering and test quarry
2020
2021-23
Site development, road improvements, continued test quarrying. Recreation access at Osprey Point and access on both sides of dam will be closed.
Build dam foundation, application of Roller Compacted Concrete
2024
2025
Tree clearing, hydropower modification andspillway work
Reservoir fills
GROSS RESERVOIR EXPANSION PROJECT TIMELINE