Guam Society of Professional Engineers Presentation
John M. Benavente, P.E.
Martin L. Roush, P.E.
January 25, 2011
Guam Waterworks Authority
December 6, 2010
Presentation Agenda
1. Introduction
2. Military Buildup
3. GWA Overview
4. Capital Improvement Program
5. Ongoing and upcoming initiatives
6. Conclusion
2
Mission Statement:
GWA will Provide the community of Guam with outstanding customer service in delivering excellent water and wastewater services in a safe , reliable,
responsible, and cost effective manner.
GWA recognizes that employees are its greatest asset!!
3
1. Introduction
4
Consolidated Commission on Utilities (CCU)
The CCU was created by Public Law in 2002
Five members elected at large with staggered four year terms to oversee the Guam Waterworks Authority and the Guam Power Authority
Functions like a Board of Directors with fiduciary, strategic and oversight responsibilities
– Includes setting of rates subject to the regulatory review and approval of the Public Utilities Commission
– The CCU hires GWA’s General Manager, Chief Financial Officer and Attorney and retains contracting authority for GWA
The CCU has acted independently to improve GWA performance, obtain federal compliance, and plan for the future
The CCU is an independent governing board
From Left to Right:Eloy P. Hara, Vice-Chair for GWA, CCU Chairman for the Committee on Customer RelationsJoseph T. Duenas, TreasurerGloria B. Nelson, Secretary, Chair for the CCU Committee for Employee Development and Relations Benigno M. Palomo, Vice Chair for GPA, CCU Chairman for the Committee on Social WelfareSimon A. Sanchez, II, Chairman
Current CCU Board Members
Simon A. Sanchez, II - Elected and Chairman Since 2003– Former Vice Chairman of the PUC, Senator and Businessman
Benigno M. Palomo - Elected Since 2003– Former Senator and 30 year Government of Guam Employee
Eloy P. Hara - Elected Since 2007– Former Assistant GM of GPA and PUC Member
Gloria B. Nelson - Elected Since 2005– Teacher and Former Chair of Guam Board of Education
Joseph T. Duenas - Elected Since 2008– Former PUC Chairman and Rev & Tax/DOA Director, Local Businessman
5
GWA Overview
GWA has faced some challenges over the past few years and has taken significant steps to address those challenges
Multi-year rate increases have been put in place to replenish necessary reserves, improve debt service coverage, fund capital needs and provide future liquidity
GWA is making prudent capital investments to meet EPA requirements while improving the system in a cost-effective manner
GWA is well-positioned to accommodate and benefit from the anticipated military buildup while committing its core resources to the system's generic growth and capital needs
GWA possesses the credit fundamentals of an essential island utility with experienced management and strong regulatory support firmly in place
GWA’s continues to improve its engineering capacity and the utility is well-positioned for remarkable growth
6
2. Military Buildup and Guam Waterworks Authority
7
Military Buildup and GWA: Collaboration
GWA and the Department of the Navy signed an MOU in July 2010 detailing broad agreement to upgrade water and wastewater systems to support the buildup while protecting the environment
GWA and USEPA worked together to identify $1.14 Billion in projects to insure the buildup and Guam’s resulting growth can be supported for the long term
The Record of Decision contained the Department of Defense’s commitment to pursue this funding from Japan and Federal sources
The Department of Defense is negotiating with Japan to determine how it will invest its $740 million for water, wastewater and power improvements
GWA continues regular meetings with the Department of Defense and USEPA to plan the final scope and timing for upgrades
GWA and GPA will be engaging Performance Management Contractors to assist in Buildup and Other infrastructure upgrade needs
GWA has been actively involved in all military buildup discussions
8
Military Buildup and GWA: Details
The Department of Defense to provide loans from the Government of Japan at no cost to GWA rate payers
Allocation of $580 Million:
– $340 million to upgrade Guam’s two largest wastewater plants, increasing their capacity and changing processing to secondary treatment
This upgrade will provide sufficient treatment capacity to absorb Guam’s growth beyond the buildup
– $160 million for a new Northern water system to be connected to existing GWA and Navy water systems, providing greater reliability and enough capacity for all northern customers beyond the buildup
– $80 million for upgrades of Guam’s central wastewater collection system
Repayment costs related to Japan’s $580 million will be paid by the Department of Defense
The recent GWA financing of $118M will be used to upgrade infrastructure that is not related to the buildup
The Department of Defense to provide $580M to upgrade GWA infrastructure for civilian and military growth
9
3. GWA Overview
10
Background
GWA is the sole supplier of civilian island water and wastewater needs
www.guamwaterworks.org
In 2002, GWA became a Guam public corporation under the control of the Consolidated Commission on Utilities (CCU)
GWA facts:– 311 full time employees– 39,000 customers– $495 million in total assets– $74M O&M Budget
11
GWA’s Water System
Three water systems
– Extensive facilities
– 108 operable wells, 2 springs
– 1 treatment plant
– 29 reservoirs
– 26 booster stations
– 800 miles of pipe
Population served
– 156,000 (civilian)
– Department of Defense maintains separate system
– GWA buys some of its water from the U.S. Navy for its needs
GWA provides all water service to the civilian population on Guam
12
Existing GWA and Navy Water Systems
13
GWA’s Wastewater System
7 service basins
Extensive facilities
– 145 miles of pipe
– 72 pumping stations
– 7 treatment plants
– 3 ocean outfalls
Population served
– 100,000 (civilian)
– Treats all Air Force and part of Navy wastewater
GWA will add the new Marine base to join Anderson Air Force base as two large military wastewater customers
GWA collects and treats wastewater throughout the island
14
Existing GWA and Navy Wastewater Systems
15
4. Capital Improvement Program
16
FY 2011 Budget Sources and Uses of Funds
17
FY 2011 Income Sources: Percentage
Base Rate Water/Wastewater 78%
Surcharge 8%
System Development Charge 4%
Grants 11%
Total: 100%
FY2011 Uses of Funds: Percentage
Labor 22.9%
Power 17.6%
Debt Service ( 2005 Bond, BOG ST) 16.2%
CIP ( Grants, Cash) 14.8%
Other 13.1%
Surcharge (GPA, Navy, Retiree) 8.2%
Purchased Water 7.2%
Total: 100.0%
GWA’s Capital Improvement Program
Only 65% of the CIP is being funded with revenue bonds
Future bond issue size may decrease substantially with additional sources from the military buildup anticipated
GWA’s CIP represents funding of necessary improvements unrelated to the buildup
GWA's Capital Improvement Program: Sources and Uses
($000s) Fiscal Year Ending September 30 2010 2011 2012 2013 2014 Total
Capital Improvement Program (1)
Water Production, Treatment and Distribution $9,212 $24,112 $34,032 $16,951 $25,146 $109,453
Wastewater Collection and Treatment 4,000 10,635 4,299 17,856 15,518 52,308
Electrical, Including Monitoring and Control 66 3,784 2,350 4,614 1,750 12,564
Miscellaneous 101 8,213 6,400 8,400 3,835 26,949
Total $13,379 $46,744 $47,081 $47,821 $46,249 $201,274
Sources of Funds
Current Revenues (2) $0 $500 $2,000 $2,500 $2,500 $7,500
Proceeds form the 2005 Bonds 4,730 4,797 0 0 0 9,527
Proceeds from the 2010 Bonds 0 27,798 36,432 19,872 0 84,102
Proceeds from Future Bonds (3) 0 0 0 16,800 20,500 37,300
Proceeds from Loans (4) 0 5,000 0 0 0 5,000
System Development Charges (5) 0 0 0 0 14,600 14,600
Grants 8,649 8,649 8,649 8,649 8,649 43,245
Total $13,379 $46,744 $47,081 $47,821 $46,249 $201,274
1. Escalated to future dollars using an assumed annual rate of escalation of 4%.
2. Revenues available for capital improvements after paying operating expenses and debt service.
3. Assumes bonds are issued in FY2013 to fund approximately $37.3 million of the remaining CIP through FY2014.
4. Amount in FY2011 represents a portion of the proceeds from the $30 million Bank of Guam loan obtained in June 2010.
5. Represents expenditure of amounts collected annually starting in 2010.
18
Potable Water CIP Summary ( x 1,000)CIP # Name 2011 2012 2013 2014 2015
PW 05-01 Ground Water Disinfection $727
PW 05-02 Water Reservoir Condition Assessment $439
PW 05-03 Booster Pump Rehabilitation, Phase II $303 $125
PW 05-04 Ugum Water Treatment Plant Refurbishment $200
PW 05-05 “A” Series Well Transmission Line $745 $600 $59
PW 05-06 Water Booster Pump Station $500 $3,766
PW 05-07 Meter Replacement Program $3,500 $6,000
PW 05-08 Barrigada Tank Repair/Replacement $2,000
PW 05-09 Leak Detection / Line Replacement $3,077 $364
PW 05-10 Potable Water System Planning $200 $500 $800
PW 05-11 Implement Ground Water Rule
PW 05-12 Brigade II (Ugum Lift) BPS Upgrade $1,200
PW 05-13 Deep Well Rehabilitation $548
PW 05-14 New Deep Wells at Down Hard Well Sites $3,773
PW 05-15 Rehabilitation of Asan Springs Ground Reservoir $900
PW 05-16 Master Meters $100 $1,500
PW 09-01 Ugum Water Treatment Plant Intake Modifications $1,470 $2,200
PW 09-02 Water Wells $2,356 $1,000 $9,500 $5,500
PW 09-03 Water Distribution System Pipe Replacement $1,848 $5,384 $3,500 $5,698 $5,520
PW 09-04 Pressure Zone Realignment/Development 2005 Impr. $1,150 $2,400 $1,400
PW 09-05 Northern System Water Distribution System 2005 Impr. $2,425 $300 $875 $500
PW 09-06 Central Water Distribution System 2005 Improvements $600 $300 $600
PW 09-07 Southern Water Distribution System 2005 Improvements $500 $650 $1,300
PW 09-08 Mechanical/Electrical Equipment Replacement $500 $430 $860
PW 09-09 Water Reservoir Internal/External Corrosion Asmt. $500
PW 09-10 Water Reservoir Internal/External Corrosion Rehb. $800 $800 $800 $400 $400
PW 09-11 Water System Reservoirs 2005 Improvements $3,697 $8,000 $5,000 $3,000 $12,503
PW 11-01 Distribution System Upgrades $1,500 $1,682 $618
PW 11-02 Ugum Water Treatment Plant Reservoir Replacement $1,322 $2,350
Total $26,112 $34,032 $16,951 $25,146 $31,823
19
Wastewater CIP Summary ( x $1,000)
CIP # Name 2011 2012 2013 2014 2015
WW 05-01 Old Agat Wastewater Collection (Phase II) $1,200
WW 05-02 Collection Line Upgrade/ Collection System Upgrades*
WW 05-03 NDWTP Diffuser Installation*
WW 05-04 Wastewater System Planning $1,500
WW 05-05 Wastewater Vehicles $235
WW 05-06 Wastewater Pump Station Upgrades*
WW 05-07 NDWWTP - Chlorine Tanks $250
WW 05-08 Umatac-Merizo STP Improvements*
WW 09-01 LS Priority 1 Upgrades*
WW 09-02 Moratorium $5,000
WW 09-03 Old Agat Collection Continuation (Phase III) $1,200
WW 09-04 Manhole Frame Seal Repair*
WW 09-05 Agat Manhole Rehabilitation
WW 09-06 Wastewater Collection System Repl./Rehabilitation*
WW 09-07 Sewer Upgrades $100
WW 09-08 Facilities Plan/Design for STP Repl. $2,575
WW 09-09 Facilities Plan/Design for the N. District STP Bio-solids*
WW 09-10 Facilities Plan/Design for Agat-Santa Rita STP Repl. $600 $1,624
WW 09-11 WWTP Priority 1 Upgrades $6,751
WW 11-01 Priority 1 Sewer Upgrades – Agat District $2,500
WW 11-02 Priority 1 Sewer Upgrades – Baza Garden District $650
WW 11-03 STP Replacement $3,567 $6,267 $12,078
WW 11-04 Facilities Plan/Design for the Umatac-Merizo STP Impr. $140
WW 11-05 Facilities Plan for Hagatna STP Impr. & Effluent WWPS*
WW 11-06 Hagatna STP Improvements and Effluent WWPS*
WW 11-07 Northern District STP Expansion – Biosolids Electrical*
WW 11-08 Agat/Santa Rita STP Replacement $14,289
Total $10,635 $4,299 $17,856 $15,518 $12,218
20
Electrical and General Plant CIP Summary ( x $1,000)
CIP # Name 2011 2012 2013 2014 2015
EE 05-01 Well Electrical Protection $134
EE 05-02 SCADA Pilot Project $300
EE 09-01 Wastewater Pumping Station Electrical Upgrade $614
EE 09-02 Electrical Upgrade - Water Wells $500 $500 $2,000 $500
EE 09-03 Electrical Upgrade - Water Booster Pump Stations $650
EE 09-04 Electrical Upgrade -Water Booster Pump Stations $350
EE 09-05 Electrical Upgrade - Other Water Booster Pump Stations $250
EE 09-06 SCADA Improvements – Phase 1 $250
EE 09-07 SCADA Improvements – Phase 2 $1,100
EE 09-08 SCADA Improvements – Phase 3 $1,500 $1,000
EE 09-09 SCADA Improvements – Phase 4 $850 $750 $1,250
Total $3,784 $2,350 $4,614 $1,750
CIP # Name 2011 2012 2013 2014 2015
MC 05-01 Laboratory Modernization $400 $400 $400
MC 05-02 Land Survey $743 $500 $500 $493
MC 09-01 General Plant Improvements / Water Distribution System $7,070 $5,500 $7,500 $3,342 $997
Total $8,213 $6,400 $8,400 $3,835 $997
21
5. Ongoing and upcoming initiatives
22
Current Major Initiatives
Compliance with the current Stipulated Order and negotiation of a consent decree or a second Stipulated Order
Implement the recommendations of the management audit
Implement the capital improvement programs to improve operation reliability, production capability and reduce overall operational cost
Continue the training and certification programs to insure having adequate personnel to effectively and efficiently run the systems
Continue our CTP compensation program to attract and retain qualified and experienced employees
Continue to work with DoD to upgrade infrastructure utilizing federal family funding
Continue to work towards compliance with the Safe Drinking Water Act and the Clean Water Act
23
6. Conclusion
24
Conclusion
Utility is poised for significant growth due to military buildup
Elected CCU governance structure is working
Positive actions taken by the PUC has led to a return to financial health and credit rating agencies confidence
Experienced management and engineering team
Stable and increasing revenue base
2010 $118M bonds to trigger major infrastructure upgrades
Working collaboratively with USEPA on new Consent Decree to reflect the impact of military buildup
Military buildup to fund $580 Million in improvements at no cost to GWA ratepayers
Substantial engineering help needed in the Horizon
GWA’s has improved dramatically and is poised for even stronger performance in the coming years
25