Page 1: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

NAVFAC HAWAII

Guam Unique Challenges &

ePermitting System

Scot UradaNAVFAC Pacific

December 1, 2010

Page 2: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

2

PRESENTATION OUTLINE

* Guam & CNMI Military Relocation

* Finegayan & Unique Challenges

* Laws & Regulations

* Compliance Approach

*ePermitting System

*SWDA Submittal Requirements

12/1/2010

Page 3: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

3

Guam & CNMI Military Relocation

12/1/2010

Page 4: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

4

Guam & CNMI Military Relocation

• USMC: Okinawa to Guam• Apra Harbor wharf construction to support aircraft carrier• Relocating US Army Air & Missile Defense Task Force to Guam• $6B construction funds from Japan

• Approx. 8,600 Marines & 9,000 dependents• “transient” Navy personnel • Approx. 600 Army personnel & 900 dependents• Nearly 2,600 acres total land area• Develop over 1,100 acres• Construct: admin building, housing, training facilities, support

facilities, new or relocated utilities, and new or relocated roadways

• ….LOTS OF PROJECTS!

12/1/2010

Page 5: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

512/1/2010

Finegayan development area

Page 6: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

612/1/2010

Land Uses in Finegayan

Page 7: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

7

Finegayan & unique challenges

12/1/2010

Page 8: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

8

Finegayan & Unique Challenges

Existing conditions• Sole Source Aquifer• Karst geology & sinkholes

Protecting the drinking water• Federal Laws & Regulations• Local Laws & Regulations• Compliance to laws & regulations

12/1/2010

Page 9: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

912/1/2010

Limestone – Karst Conditions

Page 10: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

1012/1/2010

Karst geology with lots of sinkholes

Page 11: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

1112/1/2010

Aquifer

*Sole source aquifer

Page 12: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

1212/1/2010

Groundwater Management Protection Zone

Groundwater Protection Zone

Finegayan (Navy) Base Property Zone

Andersen (AF) Base Property

Page 13: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

1312/1/2010

Wellhead Protection Areas (1,000’ circles)

We need to protect Guam’s drinking water source by complying with regulations designed for this purpose.

Page 14: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

14

Laws and RegulationsCompliance Approach

12/1/2010

Page 15: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

15

Laws, Regulations, andCompliance Documents

Laws and Regulations• Guam Administrative Rules, Title 22, Chapter 7• Guam Administrative Rules, Title 22, Chapter 6-Section 53106 of the Guam Safe Drinking Water Act-Section 6141.5 of Guam Primary & Secondary SDW Regs.• Section 438 of the Energy Independence and Security Act

DoD Compliance Documents• Unified Facilities Criteria (UFC) 3-210-10 & 3-210-10N• Dept. of Navy LID Policy for Storm Water Management

Other Standards and Guidance• CNMI and Guam Stormwater Management Manual

12/1/2010

Page 16: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

16

Laws and Regulations

Guam Administrative Rules, Title 22, Chapter 7, Section 7130“…no person shall construct, utilize, operate, occupy or cause, allow or let, permit or suffer or to be constructed, utilized, operated or occupied any land use served or to be served by septic tank and leached field, sanitary sewer, storm water disposal method, or liquid waste storage, disposal or treatment method, and which is within the GWMPZ and within any 1,000 feet radius of any public utility potable water supply well, until the person has obtained prior written approval of the Administrator…”

Section 438 of the EISA“The sponsor of any development or redevelopment project involving a Federal facility with a footprint that exceeds 5,000 square feet shall use site planning, design, construction, and maintenance strategies for the property to maintain or restore, to the maximum extent technically feasible, the predevelopment hydrology of the property with regard to the temperature, rate, volume, and duration of flow.”

12/1/2010

Page 17: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

17

DoD Compliance Documents

UFC 3-210-10, Low Impact Development• This UFC provides guidelines for LID planning, design, construction, and O&M• “…reduce the hydrologic impact of the development and to incorporate techniques

that maintain or restore the site’s hydrologic and hydraulic functions…”

UFC 3-210-10N, Low Impact Development• Provides technical criteria, requirements and references for the planning & design

to comply with stormwater requirements under EISA

• Maintain or restore predevelopment hydrology to the maximum extent technically feasible

• State and local standards for LID Integrated Management Practices (IMP) design shall be used if available.

12/1/2010

Page 18: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

18

CNMI and Guam Stormwater Management Manual

• Provides minimum criteria for BMPs that are acceptable for meeting construction & post-construction stormwater criteria and water quality treatment goals

• Specifies that infiltration of stormwater runoff from “hotspots” is not allowed without prior water quality treatment, and that a Stormwater Pollution Prevention Plan (SWPPP) must be prepared and implemented for “hotspots” to reduce the generation of pollutants and prevent contact of rainfall with the pollutants.

• The Navy has made a commitment with GEPA to comply with this document in anticipation of the adoption of Guam’s updated Erosion Control and Stormwater Management Regulations into Guam’s new regulations.

12/1/2010

Page 19: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

19

What does all this mean?

• Need to protect Guam’s water resources• Need Guam EPA’s approval for water systems (siting approvals

and design approvals)• Need Guam EPA’s approval for sewer system (design approvals)• Need Guam EPA’s approval for wellhead protection• Need to pay special attention to projects inside the 1,000’ circles*especially for “high risk” land uses/activities

• Follow standards and guidelines in the 2006 CNMI & Guam SWMM

• Follow DoD Low Impact Development policies

12/1/2010

Page 20: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

20

Overall Stormwater Management & Compliance Strategy

12/1/2010

Planning

Design

Operations/ Maintenance

Page 21: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

21

Planning Phase

Mitigation Strategies

• Relocate certain types of activities (entire or pollutant-generating part) outside of WHPA

• Convey and infiltrate runoff outside WHPA

• Consider relocating certain wellhead(s) (possible example: low producing well with high chlorides) or consider shutdown of certain wellheads or designating them for non-potable use

12/1/2010

Page 22: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

22

Planning: Categories of proposed“High Risk” Activities that encroach into WHPAs

12/1/2010

A. Vehicle fueling stations

B. Vehicle service and maintenance facilities

C. Vehicle and equipment cleaning facilities

D. Outdoor loading/unloading facilities

E. Facilities that generate or store hazardous materials and/or liquid or solid waste

F. Stormwater disposal facilities

G. Dining facilities / food preparation

H. Engineering Training Pit

*Also we need to pay special attention to parking lots

Page 23: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

23

Design Phase – LID Site Design

LID Site Design strategies reduce the hydrologic impact of development and incorporate techniques that maintain or restore the site’s hydrologic and hydraulic functions to pre-project conditions. Strategies include:

• Reduce amount of impervious areas

• Disconnect impervious areas

• Direct runoff into or across vegetated areas

• Preserve, or design into the infrastructure, naturally vegetated areas that are in close proximity to parking areas, buildings, and other impervious expanses in order to slow runoff, filter out pollutants, and facilitate infiltration

**Taking care of water “at the source” instead of the traditional “end of pipe” approach using small scale approaches or Integrated Management Practices (IMPs)**

12/1/2010

Page 24: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

24

Design Phase – BMP/IMP &Treatment Trains

12/1/2010

Pollutants of concern:• TSS• Nutrients (TN and TP)• Metals• Bacteria• Hydrocarbons

BMP/IMP Treatment Trains are multiple treatment devices operatingin series designed to remove specific pollutants of concern.

* Finegayan Main Cantonment Area Comprehensive Drainage and Low ImpactDevelopment Implementation Study Final Report (April 2010)

Applicable BMPs/IMPs*:• Proprietary oil/grit separator; Filter Strip, Dry Swale, Bioretention

Basin, TSS filter Chamber, Inlet Protector, Rain Barrel / Cistern

Treatment Trains developed for*:• Roof Runoff• Impervious paved areas w/insignificant oil or suspended metals• Impervious paved areas w/significant oil or suspended metals• Impervious paved roadways with insignificant oil or suspended

metals• Landscaping, grass and recreational areas• Site-Optional porous pavement (non-vehicle)

Page 25: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

25

Design Phase – Source Control BMPs

Source Control BMPs are low-technology practices designed to prevent pollutants from contacting runoff or to prevent discharge of contaminated runoff to the storm drainage system, such as:

• Include an overhanging roof structure or canopy over fuel dispensing areas, vehicle wash areas, and outdoor work areas

• Pave fuel dispensing areas, repair/maintenance floor areas, hazardous material or waste storage areas, and loading/unloading areas with Portland cement concrete instead of asphalt concrete

• Slope/grade/berm fuel dispensing areas, vehicle wash areas, outdoor repair bays, and material storage areas to prevent ponding and run-on

• Prevent spilled materials and wash-down waters from repair bays from entering the storm drain system.

• Install sumps to collect wash water from cleaning facilities or loading/unloading areas

12/1/2010

Page 26: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

26

Operations and Maintenance Phase

Industrial SWPPP

• Be in compliance with NPDES regulations

• Identify potential stormwater pollution sources

• Implement & maintain stormwater control measures

• Procedures to follow to comply with MSGP or state general industrial stormwater permit

Components of Industrial SWPPP

• Stormwater pollution prevention team

• Site description

• Summary of potential pollutant sources

• Description of control measures

• Schedules and procedures

• Documentation to support eligibility considerations under other federal laws

• Certification of the SWPPP

12/1/2010

Page 27: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

27

Operations and Maintenance Phase (cont.)

General Guidelines for O&M• Prevent pollution

• Minimize exposure

• Combine controls

• Examine site pollutant sources

• Maximize infiltration

• Use existing vegetated areas

• Buffer on-site or adjacent waterbodies or drainage systems

• Use structural practices (as applicable)

• Implement good procedures and practices

• Worker awareness & education12/1/2010

Page 28: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

28

Overall Stormwater Management Strategy

12/1/2010

Planning

Design

Operations/ Maintenance

Page 29: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

29

ePermitting System

12/1/2010

Page 30: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

30

ePermitting

Challenges• Lots of projects coming• Limited number of Guam EPA Staff• Unable to hire or fund additional bodies• Increased workload is not permanent• Guam EPA approval required by local regulations• Timely reviews & approvals needed to meet 2014 goal

ePermitting system solution• A means to make the design reviews and approval more efficient• A more transparent process to track reviews & approvals• Web access 24/7

12/1/2010

Page 31: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

31

ePermitting (cont’d)

12/1/2010

Launched late summer 2010 and continually being enhanced!

Page 32: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

32

ePermitting (cont’d)

How to use ePermits:• You must be a registered user to:

– Enter or upload data into the system, – modify data and – receive notifications from the system

• To request access, click on the “New User? Register here” link on the ePermitting System home page

– Be sure to notify your Navy contracting officer (design or construction)

– ePermits administrator will seek the Navy’s contracting officer’s approval of your access request

ePermits URL:http://jrm-epermit.dzsp21.com/Structure/Home.aspx

12/1/2010

Page 33: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

33

ePermitting (cont’d)

12/1/2010

Page 34: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

34

ePermitting (cont’d)

12/1/2010

Page 35: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

35

ePermitting (cont’d)

12/1/2010

Page 36: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

36

ePermitting (cont’d)

12/1/2010

Page 37: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

37

ePermitting (cont’d)

ePermits training:• Training currently being held on Guam at DZSP21 corporate

office, Bank of Hawaii Building, 3rd floor- Dec. 8th & 15th (8:30 AM)

• Or webcasts offered- Dec. 10th (9:00 AM)

• To sign up, email: [email protected] or call 671-479-3999In the email subject line, put “e-Permitting Training Reservation”

12/1/2010

Page 38: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

38

SDWA Submittal Requirements

12/1/2010

Page 39: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

39

Submittal Requirements

• Permits or design reviews that require Guam EPA’s action will be processed on ePermits

• SDWA Design approval submittals:- Water Systems- Sewer Systems- Wellhead Protection

• Other typical permits (construction or operating) processed during construction:

- Test Boring permit- Well Drilling Permit- Air Emissions Permit: Standby Generator- Underground Injection Control (UIC) Well Permit (note – Navy’s preference is to

avoid UICs)- Well Operating Permit

12/1/2010

Page 40: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

40

Required Submittals – Water Systems

All projects with:•more than 200 LF of new waterlines, or•waterlines more than 6 inches in diameter, or•Serving more than 10 residential units, or•new materials or new processes•New water source, booster pump, storage tank or transmission line requires a SITING approval as well as DESIGN approval.

12/1/2010

When submittals are required:•30% design (basis of design or 1391

and may include SITING information)

•90% design (pre-final package)•Final design (final package)

Submittal Components:•SITING approval- Project purpose, description, population

served, Location map, NEPA documentation

•30% design- basis of design, calculations, one-line

diagram with key nodes, project description, pre-final RFP/1391

•90% design•Final design

Page 41: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

41

Required Submittals – Water Systems

12/1/2010

Submittal Components:•SITING approval- Project purpose, description, population served, location map, NEPA documentation•30% design- basis of design, calculations, one-line diagram with key nodes, project description- optional meeting with Guam EPA recommended- For D-B projects, pre-final RFP. For D-B-B projects, 1391 documents•90% design- Full sized hard copy of plans showing water system & details ONLY, detail showing all

hydrants protected by bollards, specifications, boring logs, one-line diagram showing hydraulic analysis (for large projects – hydraulic analysis from source to project showing key pressure points. For small projects like a single facility – hydraulic analysis from point of connection), summary of how Guam EPA’s 30% comments were addressed

•Final design- set final drinking water design plans (electronic), summary of how Guam EPA’s 90%

comments were addressed•Post Construction - As-built drawings within 60 days from project completion

***A Guam Environmental Protection Agency Approval Checklist – Safe Drinking Water Actis available from the Navy ***

Page 42: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

42

Required Submittals – Sewer Systems

All projects with:• more than 600 LF of new gravity sewerlines that are greater than

8 inches in diameter, or• more than 2 sewer manholes, or• New or modified pump station, or• Sewer force mains, or• new materials or new processes (example: treatment systems)

When submittals are required:• 30% design (Guam EPA will indicate if 90% submittal is needed)

• 90% design

12/1/2010

Page 43: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

43

Required Submittals – Sewer Systems

12/1/2010

Submittal Components:•30% design- project location map, basis of sewer design, calculations (if available), project description & purpose

- pre-final RFP for D-B projects or 1391 for D-B-B projects- Guam EPA will review and advise Navy if 90% design submittal is required•90% design- full sized hard copy of plans showing sewer system & details- electronic copy of plans- hydraulic analysis (showing modeling runs clearly showing adequate capacity

for proposed project. For large projects – show downstream analysis to receiving pump station or wastewater treatment plan. For small projects –hydraulic analysis to POC to existing system and showing adequate capacity in receiving gravity sewer or pump station)

***A Guam EPA Sewer Design Plan Plan Review Requirements checklist is available from the Navy ***

Page 44: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

44

Required Submittals – Wellhead protection

• Applicability and submittal requirements currently being discussed with Guam EPA

• Guam EPA contemplating on developing a flowchart (as of 10/2010)

12/1/2010

Stay Tuned !

Page 45: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

45

ePermitting : Process for D-B-B SDWA Design Submittals

12/1/2010

A-E prepares GEPA design approval submittal package

Navy’s Design Manager reviews submittal package

Navy’s Environmental Office reviews submittal package A-E finalizes

submittal package based on Navy’s comments

Navy’s Environmental Office uploads to ePermits

Guam EPA review & enters comments into ePermits

Design Mgr reviews draft responses, forwards to Environ. Office

A-E prepares draft responses, additional info or revised submittal material as required

Design Manager and Eviron. Office reviews Guam EPA’s comments

Environ. Office reviews draft responses & uploads finalized documents to ePermits

Design Submittal approved by Guam EPA

GEPA review within 30 days for 30% or 90% submittals; 15 days for SITING or FINAL submittals ----

Note: If submittal is deemed to be incomplete, review period starts over

Page 46: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

46

ePermitting : Process for D-B SDWA Design Submittals

12/1/2010

D-B prepares GEPA design approval submittal package

Navy’s Construction Manager (CM) forwards to design & environ. office review/support

Navy’s construction, design & environ. offices reviews submittal Navy CM transmits

comments to D-B

D-B revises submittal package, furnish addit. info as req’d & resubmits to Navy

Navy reviews & approves revised submittal package

D-B contractor reviews & prepares responses to Guam EPA’s comments.

Guam EPA reviews design submittal & enters comments into ePermits

Navy CM uploads submittal documents into ePermits

Navy CM reviews D-B’s responses and revised submittal documents and obtains design & environ. support as req’d Design Submittal

approved by Guam EPA

D-B revises documents as necessary and obtains Navy’s approval

Navy’s CM uploads responses and other revised documents to ePermits for Guam EPA’s review

GEPA review within 30 days for 30% or 90% submittals; 15 days for SITING or FINAL submittals

Note: If submittal is deemed to be incomplete, review period starts over

Page 47: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

47

Submittal Process for Construction or Operating Permits by Contractors

12/1/2010

Page 48: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

48

ePermitting - Construction or Operating Permit Process

12/1/2010

Contractor prepares construction or operating permit application

Navy’s CM and Environmental Office reviews permit application

Navy provides comments to Contractor Contractor finalizes

permit application

Contractor submits permit application via ePermits

Guam EPA review & enters comments into ePermits

Navy CM reviews revised permit application Contractor addresses

Guam EPA’s comments, drafts response

Contractor reviews Guam EPA’s comments

Contractor submits revised permit application or addit. info via ePermits

Permit approved by Guam EPA

Page 49: Guam Unique Challenges ePermitting System - c.ymcdn.com · CNMI and Guam Stormwater Management Manual ... • Need to protect Guam’s water resources ... of contaminated runoff to

NAVFAC HAWAII

THANK YOU