guidelines for bidding documents for hydropower projects
TRANSCRIPT
Royal Government of Bhutan
GUIDELINES FOR BIDDING DOCUMENTS FOR
HYDROPOWER PROJECTS - 2020
Department of Hydropower and Power Systems
Ministry of Economic Affairs
Royal Government of Bhutan
April 2020
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
ii
DISCLAIMER:
This Guideline provides practical suggestions and best practices for the preparation of the
bidding document for hydropower projects in the country. The Guideline provides a general
framework which projects could use to make contracting decisions that are in the best interest
of projects and the provisions of the Guideline should be used in a flexible manner. It
supplements but does not replace any existing statutory requirements in vogue. Therefore,
each project should seek legal advice concerning the contracts.
While it is recommended to use this Guideline in a uniform manner, the projects must exercise
their judgement and wisdom on the implementability of various provisions of the Guideline.
As such, the Department shall not be held accountable for any implications in future that might
arise.
ACKNOWLEDGEMENT
The guideline has been formulated with the technical assistance of World Bank. We also would
like to extend appreciation and acknowledge the valuable contributions made by the
stakeholders from Bhutan Electricity Authority, Druk Green Power Corporation,
Punatsangchhu I & II, Tangsibji and Kholongchhu Project. Finally, the Department would like
to express heartfelt gratitude to the fraternity of DHPS for their collaboration in formulation of
this guideline.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
iii
Table of Contents
Abbreviations .......................................................................................................... vi
Preface ...................................................................................................................... 1
1.0 Mitigating Issues Arising at Hydropower Projects ................................... 2
1.1 The Main Parties .......................................................................................... 2
1.1.1 Hydropower Project Developer and Owner ............................................... 2
1.1.2 Contractors ............................................................................................... 3
1.1.3 Designers and other Experts ..................................................................... 3
1.1.4 Owner’s Engineer ..................................................................................... 4
1.2 Issues Arising at Previous Hydropower Projects .......................................... 4
1.3 Risk Management During the Project ........................................................... 7
1.3.1 Project Risk Register ................................................................................ 9
1.3.2 Project Risk Management ......................................................................... 9
2.0 The Preparation Phase .............................................................................. 10
2.1.1 Investigation ........................................................................................... 10
2.1.2 Geotechnical Risk ................................................................................... 12
2.1.3 Design Risk ............................................................................................ 14
2.1.4 Transfer of Information Through the Course of the Project ..................... 15
3.0 Tendering and Awarding Construction Contracts .................................. 17
3.1 Tender Documents for Bidders ................................................................... 17
3.1.1 Preparing a Bill of Quantities ................................................................... 18
3.1.2 Dayworks ................................................................................................ 23
3.2 Pre-qualification of Bidders ......................................................................... 25
3.3 Design Documents to be Provided to Bidders ............................................ 26
3.4 Introduction to FIDIC .................................................................................. 26
3.4.1 Structure of Contract ............................................................................... 30
3.4.2 Role of Engineer ..................................................................................... 31
3.4.3 Risk Management using the Contract ..................................................... 32
4.0 Management During Construction ........................................................... 35
4.1 Roles .......................................................................................................... 35
4.2 Risk Management ...................................................................................... 37
References .............................................................................................................. 38
Annex A: Recommended Particular Conditions of Contract ........................... 39
1.0 Particular Conditions of Contract: ........................................................... 39
1.1 Clause 2: The Employer ............................................................................. 39
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
iv
1.2 Clause 3: The Engineer .............................................................................. 39
1.3 Clause 4: The Contractor ........................................................................... 39
1.4 Clause 5: Sub-contracting .......................................................................... 40
1.5 Clause 6: Staff and Labour ......................................................................... 40
1.6 Clause 7: Plant, Materials and Workmanship ............................................. 42
1.7 Clause 8: Commencement, Delays and Suspension .................................. 42
1.8 Clause 9: Testing on Completion ................................................................ 44
1.9 Clause 10: Employer’s Taking Over ........................................................... 44
1.10 Clause 11: Defects after Taking Over ......................................................... 44
1.11 Clause 12: Measure and Evaluation ........................................................... 45
1.12 Clause 14: Contract Price and Payment ..................................................... 45
1.13 Clause 15: Termination by Employer .......................................................... 49
1.14 Clause 16: Suspension and Termination by Contractor .............................. 49
1.15 Clause 17: Care of the Works and Indemnities ........................................... 49
1.16 Clause 18: Exceptional Events ................................................................... 49
1.17 Clause 19: Insurance ................................................................................. 49
1.18 Clause 20: Employers and Contractors Claims .......................................... 49
1.19 Clause 21: Disputes and Arbitration ........................................................... 50
1.20 Particular Conditions - Part A: Contract Data .............................................. 51
1.21 Schedules relating to Particular Conditions to be used in Tender Documents
53
Annex B: DOCUMENTS TO BE SUBMITTED BY B IDDERS ................................... 56
Letter of Tender ................................................................................................... 57
Schedule of Cost Indexation .............................................................................. 60
Table of Adjustment Data ................................................................................... 61
Bill of Quantities .................................................................................................. 65
Daywork Schedule .............................................................................................. 68
Summary of Specified Provisional Sums .......................................................... 75
Grand Summary .................................................................................................. 76
Technical Proposal ............................................................................................. 77
Site Organization ................................................................................................. 78
Method Statement ............................................................................................... 79
Mobilization Schedule ......................................................................................... 80
Construction Schedule ....................................................................................... 81
ES Management Strategies and Implementation Plans .................................... 82
H&S Management Strategies and Implementation Plans ................................. 83
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
v
Code of Conduct for Contractor’s Personnel (ES) Form .................................. 84
Equipment ............................................................................................................ 87
Contractor’s Representative and Key Personnel .............................................. 89
Bidder’s Qualification following Prequalification ............................................. 95
Bidder Information Form .................................................................................... 96
Bidder's JV Information Form ............................................................................ 97
Historical Contract Non-Performance, and Pending Litigation ........................ 98
Environmental and Social Performance Declaration ...................................... 100
Financial Situation and Performance ............................................................... 102
Average Annual Construction Turnover .......................................................... 104
Current Contract Commitments / Works in Progress ..................................... 105
Form of Bid Security – Demand Guarantee ..................................................... 106
Form of Bid-Securing Declaration .................................................................... 107
Annex C – Documents to be used for Contract Award ..................................... 108
Notification of Intention to Award .................................................................... 109
Letter of Acceptance ......................................................................................... 114
Contract Agreement .......................................................................................... 116
Performance Security ....................................................................................... 119
Environmental and Social (ES) Performance Security ................................... 123
ES Demand Guarantee ...................................................................................... 123
Advance Payment Security............................................................................... 125
Retention Money Security ................................................................................ 127
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
vi
Abbreviations
BEA Bhutan Electricity Authority
BOQ Bills of Quantities
DGPC Druk Green Power Corporation Limited
DHPS Department of Hydropower and Power Systems
DPR Detailed Project Report
FIDIC International Federation of Consulting Engineers
FY Financial Year
GOI Government of the Republic of India
ICB Internationally Competitive Bidding
MDB Multilateral Development Bank
MHPA Mangdechhu Hydroelectric Project Authority
PHPA-I Punatsangchhu-I Hydroelectric Project Authority
PHPA-II Punatsangchhu-II Hydroelectric Project Authority
RAA Royal Audit Authority
RGOB Royal Government of Bhutan
SPV Special Purpose Vehicle
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
1
Preface
Bhutan is endowed with hydropower resources. In Bhutan, 100% of electricity is generated
from hydropower. To date 2,335MW has been harnessed and over 2,930MW is under
development, with more than 10,000MW in various stages of planning. The Government of
Bhutan has identified that hydro-electric power development has two important roles to play
in the socio-economic development of Bhutan:
i) to provide safe, reliable, affordable and abundant electricity to improve the lives of
all Bhutanese and drive industrial growth, and
ii) for exporting surplus power to enhance Government revenue and achieve positive
balance of payments.
To date hydropower projects in Bhutan have been developed by the Special Purpose Vehicles
(SPV) or Project Authority engaging international contractors through a range of bidding
processes and using a range of contract forms. Common issues have arisen during
hydropower projects in Bhutan which have impacted on project quality, delivery time and cost.
Many of these issues could be mitigated at various stages of the project, including the project
preparation phase and the construction phase. Some can be mitigated in the Contractor
selection (bid) process and others through prudent use of contract conditions.
FIDIC (Fédération Internationale Des Ingénieurs-Conseils or the International Federation of
Consulting Engineers) provides an appropriate form of standard conditions of contract (the
“Red Book”) for engaging a contractor for a hydropower project designed by a consultant for
the project Developer. The General Conditions of Contract in the Red Book are supported by
Particular Conditions that apply for the specific project.
This “Guideline for Bidding Documents for Hydropower Projects” describes the steps
necessary to mitigate issues arising at hydropower projects. The Guidelines describe how
time, cost and quality issues that impact hydropower development can be addressed at each
stage of project development, namely project preparation, bidding and management of
construction. The Guidelines then have three Annexes
1 Annex A: Recommended Particular Conditions of Contract: Provides
recommended particular conditions that should be included in a contract using the
FIDIC 2017 Red Book Contract. This part also includes Schedules within FIDIC
Red Book that need to be issued with the Bidding Documents.
2 Annex B: Forms to be included in Bidding Documents for the Bidder to submit.
3 Annex C: Contract forms to be used during the award of the contract.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
2
1.0 Mitigating Issues Arising at Hydropower Projects
This Guidance document for Bidding Documents identifies the main issues that impact
effective delivery of hydropower projects in Bhutan. When issues outlined in this document
arise, there can be major impact on the delivery time for the project and the final out-turn cost.
However, the impact of the main issues can be mitigated to reduce the likelihood of delays
and cost overruns at several stages of the project, namely:
i. during the project preparation phase (i.e. Detailed Project Report (DPR)),
ii. in preparation of bidding documents when designing contractual mechanisms, and
iii. undertaking effective risk management during construction.
Responsibility for achieving mitigation of the identified issues changes through the project as
accountability for the project moves from project preparation to construction phase.
1.1 The Main Parties
Hydropower projects require several parties (in particular the Developer, the Designer, the
Owner’s Engineer, and the Contractor) to work together to successfully deliver the completed
hydropower project.
Identification of risk and apportionment to the project parties are key factors in successful
projects. Correct application of contract models is central to the management of risk during
construction.
1.1.1 Hydropower Project Developer and Owner
In Bhutan the following key entities are involved in the development of hydropower projects:
• Department of Hydropower and Power Systems (of the Ministry of Economic Affairs): DHPS is the policy advisor for development of new hydropower projects. DHPS is the nodal agency for according approval of the Detailed Project Report (DPR) on behalf of the Royal Government of Bhutan.
• Special Purpose Vehicle (SPV)/Project Authority is typically the Developer of the project responsible for design, construction and first reservoir filling of the project. It is sometimes a joint venture between a developer/financier and the Royal Government of Bhutan. The SPV/Project Authority will appoint a Contractor and Designer for the development phase of the project. The SPV/Project Authority becomes the “Employer” in the terminology of FIDIC contracts.
• Druk Green Power Corporation (DGPC): DGPC is the Government owned power utility. Ownership of the newly developed power project usually transfers to DGPC within 2 years following completion of first reservoir filling. DGPC has internal engineering resource for operations and maintenance or uses consultants as technical advisors.
• Bhutan Electricity Authority (BEA) is the Electricity Regulator approving licences, setting domestic tariffs, setting standards and requirements for dam safety etc.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
3
1.1.2 Contractors
Contractors need to have experience in construction works including experience and expertise
in hydropower projects.
Contractors also need to have the financial strength to manage risk allocated to it for the
project. The Contractor needs to provide evidence and assurance that they have the financial
strength to complete the project without going out of business. If the Contractor goes out of
business then the project site will be frozen until debts are paid, resulting in significant time
delays for the project.
The Contractor’s project team should include engineers who have constructed the same type
of hydropower projects and wherever possible, in similar geological conditions.
1.1.3 Designers and other Experts
For hydropower projects in Bhutan, the preparation phase will include preparation of DPR.
The SPV/Project Authority will typically then employ the design consultant separately from the
Contractor.
Designers need to have experience on the hydropower project. The level of experience and
expertise of those involved should relate to the hazard of the completed projects and
complexity and geotechnical risk relating to the specific project. For high hazard dams, dams
on complex foundations or with high seismic hazard, the lead Designer should have more than
20 years’ experience in hydropower engineering, including the type of dam being developed.
Hydropower construction is a specialised activity that involves knowledge of many different
disciplines from geology, hydrology, geotechnical engineering, structural engineering, and
other professions. Having a multi-disciplinary team with a wide variety of experience and
knowledge will be essential for the successful outcome for the project.
To ensure design advice is not compromised by commercial links, the Designer must not have
a commercial link to the Contractor.
Independent experts are recommended for some activities, such as review of design.
Independence ensures that external perspective is applied to the safety of the dam.
Independent experts should also have 15 to 20 years’ experience in their field of expertise or
should have served as an independent Expert for atleast three hydropower projects.
An independent Panel of Experts (PoE) is strongly recommended for design and construction
of high hazard dams on complex foundations or high seismic zones. A PoE should include
experts with more than 20 years’ experience in design or construction of the project, especially
complex dam projects. Each PoE member would be expected to contribute a different
speciality of expertise relating to the risks involved with the project.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
4
1.1.4 Owner’s Engineer
The Employer is required to have an Engineer to the Contract. This role is required to assess
matters identified in the Technical Specification for approval.
The Owner’s Engineer may be within the SPV/Project Authority staff, or a consultant with
experience in managing hydropower construction.
1.2 Issues Arising at Previous Hydropower Projects
With several hydropower projects developed, or under development, several issues have
been identified which have impacted project financial outcomes in Bhutan. The Royal Audit
Authority has confirmed a number of these in audits of some hydropower projects.
Issues relating to deficiencies in the site investigation, design, contract management, and
construction management components of the projects could be avoided or improved with a
strengthening of the approach to project preparation and contracting as set out in the bidding
documents.
Identified issues are summarised below. This list provides a reference from which
improvements can be made to subsequent projects and associated contractual mechanisms.
Table 1.1: Main Issues Occurring in Hydropower Projects
Issue
Impact on Project
1
Inadequate site investigation prior to
construction failing to identify geological
conditions accurately, and unsatisfactory
design not accurately considering site
conditions.
Re-design during construction and extra
works resulting in time delays and cost
increase, which is falling on Employer since
risk not contractually shared with Contractor
2
Insufficient understanding of hydrology and
lack of clarity on responsibility for design of
temporary works affected by construction
floods (e.g. cofferdam).
Temporary works overwhelmed because
design based on poor hydrology
understanding resulting in dispute over
responsibility for damage costs
3
Poor planning of disposal areas resulting in
insufficient or inadequate disposal areas
during construction
Increased cost to make new disposal areas
and possible environmental impacts (e.g.
sediment in rivers)
4
Provisional works underestimated during
project preparation compared to reality found
during implementation
Cost increases during construction when
actual need and cost is realised
5 Inadequate evaluation of contractors and
subcontractors
Contractors not able to conduct quality works
resulting in re-work delaying the project (and
cost overruns if Employer fails to claim
Contractor’s responsibility)
6
Contractors methods or equipment accepted
during bid evaluation but later found
unsuitable for site conditions
Cost and time delay implications if unsuitable
methods require design change, extra ground
support etc.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
5
Issue
Impact on Project
7 Inadequate supervision of contractors and
subcontractors
Unsatisfactory quality of works, and cost
overruns as claims are not sufficiently
challenged
8
Delays in the delivery of design drawings
and failure of the Designer to make timely
decisions regarding needed design
variations
Delays in works with consequent claims by
Contractor for extra costs
9
Contractors progress slowed or put at risk by
contractors running into liquidity problems
during the project
Employer must pay subcontractors and labour
to maintain progress of the project
10
Frequent occurrence of introducing
processes/ works which were not included in
the Contract documents
Cost overruns due to claims for extra costs
not in BoQ.
11
Items during construction exceeding 130%
of the BoQ-estimated quantities, leading to
large cost increases for parts of the works.
Employer has insufficient information to
adequately negotiate revised rates
Cost overruns
Mitigation to reduce the likelihood or severity of issues impacting hydropower projects could
be at the DPR preparation phase, in preparation of the bidding documents, or management
actions during construction. Table 1.2 gives an indication of the project stages when mitigation
should be possible. From this it is apparent that the first steps to mitigate or avoid the effects
of an issue in a number of cases can often start during the DPR preparation phase. Also, not
every issue mentioned can be mitigated effectively within the bidding documents to select the
Contractor.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
6
Table 1.2: Mitigations that can be applied to Reduce Impact of Issues on Hydropower
Projects
Issue
Stage of Project to Apply Mitigation
Preparation/DPR Bidding docs Management
1
Inadequate site investigation prior to construction failing to identify geological conditions accurately, and unsatisfactory design not accurately considering site conditions.
• More thorough site investigation
• Panel of Engineers
• Include GBR in bidding docs
• Record all site conditions
• Design change before design issue delays Works.
2
Insufficient understanding of hydrology and lack of clarity on responsibility for design of temporary works affected by construction floods (e.g. cofferdam).
• Clarity of construction floods in DPR.
• Clear risk allocation in bidding docs.
• Data records during Works.
• Flood management during Works.
3
Poor planning of disposal areas resulting in insufficient or inadequate disposal areas during construction
• Proper site surveys
• Clearly include in specification and drawings
-
4
Provisional works underestimated during project preparation compared to reality found during implementation
• Reduce number of unknowns in design phase
• Define provisional items with detailed rates in BoQ
• Pricing review of Provisional Sums
• Rate data to support valuation of Provisional Works
5 Inadequate evaluation of contractors and subcontractors.
-
• Appropriate Pre-qualification and Tender evaluation criteria
• Owner’s Engineer’s QA/QC approvals in specification
• Capacity of SPV/Project Authority and Owner’s Engineer for supervision
6
Contractors methods or equipment accepted during bid evaluation but later found unsuitable for site conditions
-
• Exclude methods in Technical Specification
• Tender evaluation
• Owner’s engineer assessment of methods
7 Inadequate supervision of contractors and subcontractors
-
• State Quality Assurance requirements and approvals in Specification
• Appointment of experienced Owner’s Engineer to supervise Contractor
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
7
Issue
Stage of Project to Apply Mitigation
Preparation/DPR Bidding docs Management
8
Delays in the delivery of design drawings and failure of the Designer to make timely decisions regarding needed design variations
• Consider designer track record and capacity during DPR consultant selection.
• Review and strengthen contract with DPR consultant
-
• Designer capacity and resources during construction
9
Contractors progress slowed or put at risk by contractors running into liquidity problems during the project
-
• Appropriate Pre-qualification and Tender evaluation criteria
• Securities in contract
-
10
Frequent occurrence of introducing processes/ works which were not included in the Contract documents
• Ensure complete DPRs
• Valuation process in Particular conditions
• Require submission of detailed rates
• Scope control to minimize non-project-related works.
• Rate data to support variation negotiation
11
Items during construction exceeding 130% of the BoQ-estimated quantities, leading to large cost increases for parts of the works. Employer has insufficient information to adequately negotiate revised rates
• Accurate calculation of quantities
• Valuation process in Particular conditions
• Require submission of detailed rates
• Use rate data to support variation negotiation
1.3 Risk Management During the Project
Large hydropower projects encounter many risks during implementation. Risks are those
events that could lead to adverse consequences (including time delays and cost increases).
In a hydropower project this could be any of the issues listed in Table 1.1.
The overall objective of good project risk management is to minimise the consequence of
adverse events while at the same time maximising the potential to secure opportunities. Risks
impact on projects in many ways however the consequence of these impacts is almost always
reflected in terms of time delays and/or increased costs.
Risks need to be allocated between the Owner/Developer and the Contractor in accordance
with the party best able to manage the risk. This needs to be set out clearly in the contract.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
8
Risk management for projects involves several interrelated aspects. All these aspects are
likely to require periodic re-assessment and refinement as the project advances through its
many development stages. As indicated in Table 1.2, some risks may be able to be fully
addressed in the investigation and design (preparation) phases of the project and therefore
largely removed from further consideration. Many risks however will remain with the project
throughout its evolution and hence the focus is on understanding, controlling and mitigating
these risks. Furthermore, additional risks will almost certainly be identified as the project
progresses.
The main aspects of project risk management are shown in Table 1.3:
Table 1.3: Aspects of Risk Management
Identification.
•Potential and actual risks for the project need to be identified. This process should be initiatedearly in project development staging as it helps guide subsequent project stages plus ensuresissues are not overlooked as development progresses.
Analysis
•Assess the nature of the risk. How likely it is to impact on the project and the consequence ofthat impact. This assessment is frequently revised at various stages of the development as newinformation becomes available.
Uncertainty
•Determine what level of certainty exists around this risk. Particularly at early stages in a projectquantifying risks is dominated by uncertainty. This does not make a particular risk more severe,rather it highlights where future investigations can refine certainty.
Response
•What options might exist to manage and mitigate each risk. These are likely to be very genericat early stages but become more refined and specific as risks are more accurately quantified.
Ownership
•Who is best to placed to control or “own” each risk? This should be based on who is best placedto respond to risks if and when they occur. Ultimately this is usually a balance betweencontractor and employer (owner) and is reflected in contractual mechanisms.
Monitor
•The risk needs to be measures and monitored particularly during construction andcommissioning. This is both for reasons of verifying project performance but also for contractualpurposes.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
9
1.3.1 Project Risk Register
A Project Risk Register (PRR) is a simple but highly effective tool for facilitating the
identification and management of project risks. These need to be made transparent to all
project parties (e.g. Employer, Contractor, Financer). Depending on the nature and complexity
of the project, the exact nature of the PRR will vary. Table 1.4 is an example of a simple PRR.
Table 1.4: Example of Simple Project Risk Register
Risk (ID &
Name) Details
Risk Owner
Likelihood (L) of occurrence
Consequence (C) (physical, time,
cost)
Severity (L*C)
Controls &
Mitigation (C&M)
Post C&M risk
1 Cofferdam flood
Flood breaches cofferdam
C Medium 20% each year
High Time & Cost
High Demobilisation. Flood warning
Medium
2 Grout
Increased grouting needed
C < 30% E > 30%
High
Medium Time delays
High Allowance made in project plan
Low
3 4 Key C, Contractor
E, Employer
The PRR can be extended to include opportunities (PORR). This is where each risk might be
partially mitigated through including an allowance for the risk to occur to some level during
project delivery. If the risk does not occur, then there should be a saving in time and/or costs.
However, if the risk occurs to a greater amount than allowed for, then it is accepted that it will
induce additional time and or cost.
If this approach is adopted, the project parties will seek ways (or opportunities) for reducing
risks and benefits will be achieved by the parties. For example using new methods of
technology, adding additional resource to manage time on high risk areas, or refining project
sequencing to move sensitive components of work outside high risk periods (e.g. flood
seasons) will reduce the risk of time delays which impact the Owner, meanwhile the Contractor
may be able to save costs.
1.3.2 Project Risk Management
The documents and systems discussed above all contribute to good project risk management
(PRM). This is primarily about informed decision making and includes selecting appropriate
project technologies, construction methodologies and procurement strategies. This in turn
needs to inform contract document preparation including the clear allocations of risk, risk
control and mitigation mechanisms and provision of contingency funds.
Aspects such as health and safety, environmental controls and management and community
and cultural safety should also be included within PRM.
A transparent and unambiguous mechanism for managing design variations and associate
claims is also a fundamental component of PRM.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
10
2.0 The Preparation Phase
Important stages of the preparation phase are described in this Section.
i. DPR will be vetted and approved by DHPS.
ii. The SPV/Project Authority takes over the project to prepare bidding documents.
2.1.1 Investigation
When investigation prior to construction is inadequate, there is an increased risk that design
will not adequately account for site conditions. Areas potentially impacted include geometric
layout design, geotechnical, design, hydraulic design and structural design.
1. Lack of accurate topographic survey impacts the layout of the structure. Inaccurate
topographic data could result in increased quantities of dam material being assumed
before construction starts.
2. Geological conditions may not be identified accurately, resulting in design not
accounting for geologic hazards, for example unsuitable foundations, unstable
abutments or active faults. This can result in significant cost overruns on projects.
3. Insufficient understanding of hydrology poses a risk that discharge facilities are not
designed to pass inflow design floods. Furthermore, poor understanding of hydrology
has the potential to impact sizing of temporary river diversion works during construction
(e.g. cofferdams). Therefore, responsibility for design of temporary works will not be
clear. If the diversion facilities are overwhelmed during construction, responsibility for
damage will be disputed unless the risks are allocated based on agreed data.
Investigations cover a wide range of disciplines and methods. They all have one primary
purpose which is to reduce uncertainty. Investigations provide the framework within which;
design can be refined, construction programmes and costs developed, and project economics
determined.
Table 2.1: Scope of Investigations
Investigation Scope Relevance to Construction and Contract Management
Topographic Survey & Mapping.
Provides core baseline data relevant to site layout, construction logistics (access etc.) and schedule of quantities.
Geological and Geotechnical
Key to identifying and understanding risks associated with dam foundations & abutments, site and slope stability and material suitability.
Hydrology Provides details of risk from floods during construction as well as weather related impacts and constraints on construction programmes.
Seismic Hazards Provides details of risk to construction activities from seismic events at the site but also associated infrastructure such as access roads.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
11
For more details on the scope and purpose of investigations, refer to Independent Dam Safety
Guidelines for Dam Safety in Bhutan [1] and Guidelines for Development of Hydropower
Projects Part II [2]
Undertaking investigations does not necessarily mean investigations always reduce risk. In
fact, many risks are identified from investigations when uncertainty is translated to
understanding. Rather the investigations allow risks to be more accurately defined and
quantified. During early project stages, particularly up to project feasibility, investigations seek
to identify risks and broadly quantify them. At later stages (final design and preparation of
bidding documents) specific investigations may be necessary to target individual risks to better
understand their likely impact on the project (particularly time, cost and quality impacts) and
how they can be managed through construction and beyond.
Investigations need to be sufficient to provide the most complete bidding documents possible
and thereby reduce the likelihood of time delays and cost increases after construction
commences. It can be tempting to not invest in investigations in the preparation phase to save
cost, but experience shows this is short-sighted and the end result is invariably a greater
number of unexpected conditions arising during construction, resulting in time delays and
significant cost increases. Nevertheless, investigations may still be required once construction
is underway if unexpected ground conditions arise or materials are found to be unsuitable or
insufficient to complete the project. The objective is to minimise the need for investigations
during construction when the financial impacts will be greatest.
These targeted investigations may still be undertaken directly by the design team (for the
Employer), or by contractors seeking to develop well informed bids. Targeted investigations
can be shared by all entities involved in the project where all parties benefit from the increased
certainty provided.
When designing investigation programmes, some key considerations should include;
i. Achieving adequate definition of baseline information such as the geological
setting, underground conditions and hydrological data.
ii. How the investment, and associated cost, made in investigations leads to
increased understanding of project risks and hence improved control of costs and
project delivery time.
iii. Data on natural hazards, (e.g. river flows, intensity of rains, monsoon period,
frequency and magnitude of earthquakes) should be collated and made available
with the bidding documents to contractors to allow them to assess project risks.
This is particularly important for periods of increased risk exposure during
construction such as flood risk.
iv. Proper provision and use of this data is also essential for the definition of thresholds
for causes of force majeure events and consequently in the risk management of
the Contract.
v. Clear identification of material sources (e.g. quarries) and associated data on
material properties and variability. This is to ensure availability of suitable
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
12
construction material in adequate quantities including allowance for material that
may be required to address identified risks.
vi. Locations for, and suitability of, disposal areas, and satisfactory capacity of the
disposal areas.
vii. Identification of environmental effects that require mitigation so that controls
associated with environmental requirements can be identified within which
construction must occur, and
viii. The preparation of accurate and realistic documentation of investigation findings is
important to manage major geological surprises during construction including the
most effective construction methodology.
2.1.2 Geotechnical Risk
Geotechnical risks deserve specific mention in the context of hydropower projects. That is
because they dominate many aspects of design, construction and performance including;
• selection of dam type,
• material suitability and availability,
• dam, abutment and reservoir performance and safety, and
• leakage losses and yield efficiency of the reservoir
All of these have significant impacts on project costs including; construction, operational and
future enhancement and rehabilitation related costs. The challenge with geotechnical aspects
is that they are largely hidden, being below the ground surface and vegetation cover.
Investigations by their very nature can only sample very small percentages of the area relevant
to the design, construction and operation. From these samples geologists and geotechnical
specialists form a model of the foundation and abutment conditions on site.
Geotechnical uncertainties and risks are almost always amongst the dominant project risks.
These in turn will need to be managed through project planning, management and contractual
mechanisms.
In the context of successful project contracts, geotechnical investigations and risk assessment
seek to;
I. Facilitate contractual understanding of the site conditions, referred to as the
geotechnical / geological baseline.
II. Inform the parties about risks arising from geotechnical conditions and provide
the basis for how these risks are assigned between Contractor and
Employer. For example, the contract should clearly state when the Contractor
bears risk (e.g. at or below baseline) and when the Employer accepts risk (e.g.
above baseline). The boundaries need to be clear to minimise contractual
disputes.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
13
III. Establish the baseline setting in order to determine risk allocation and therefore
influence risk acceptance, bid prices, quantity of change orders and the final
cost of the project.
To facilitate the clear transfer of geotechnical and geological information to allow contractors
to make risk informed decisions the following documents are recommended:
Table 2.1: Key Geotechnical Information Documents
For more details on geological and geotechnical documentation;
Dam Safety Guidelines. [1]
ASCE 2007, Geotechnical Baseline Report for Construction – Suggested Guidelines” [3]
ICOLD Bulletin 129. Dam Foundations Geologic considerations, Investigation methods,
Treatment, Monitoring [4]
Geotechnical Data Reports (GDR)
•A factual report prepared by geologists to contain all the raw data from investigation, such asborehole logs and laboratory results. Also, geotechnical hazards if known. The GDR documentstransfer factual information to the Contractor assisting them to make informed decisions.
Geotechnical Baseline Reports (GBR):
•Prepared by geologists to provide a summary of anticipated ground and groundwater conditionsfor the purpose of understanding the risks directly applicable to the project. Assists in theproposal and bid preparation process for projects and during contract pricing. These reports seekto provide common understanding to manage risks, potentially reduce construction costs andminimize disputes over unforeseen ground conditions. The GBR should clearly staterespective risks for the Employer and the Contractor.
A Geotechnical Interpretative Report (GIR):
•Prepared by qualified engineers and geologists to translate the factual report information forgeotechnical analysis, e.g. carrying out rock mechanics analysis to estimate foundation strengthproperties. Expert judgement is necessary in developing conclusions in these reports
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
14
2.1.3 Design Risk
Inadequate design or a lack of time to complete the design will become evident during
construction, resulting in delays while re-design takes place and cost implications to pay for
the changes compared to the bid price.
Inadequate design may be due to lack of investment in investigation (discussed above under
geotechnical risk) when design has not accounted for ground conditions that are then
encountered.
Other reasons for inadequate design may be a consequence of inexperience within the design
consultant or lack of capacity to carry out design tasks in the time required. Appointment of a
design consultant with experience in the hydropower projects and has qualified staff available
is a key step in reducing the risk of design delays or errors and omissions in the design.
A Panel of Experts (PoE) acting as peer reviewers can also reduce the risk of inadequate
design.
Otherwise these problems can cause significant time delays and increases in the project’s
cost through delaying the Contractor and introducing unscheduled construction works.
Appointing the Design Consultant
An experienced designer should be selected to carry out the design from pre-feasibility stage
(i.e. DPR consultant) onwards. The process to select the Designer should be based on the
following essential attributes:
i. track record of the design consultancy company,
ii. leadership of the design team by designer experienced in the hydropower projects,
iii. experience of the key design team members in the hydropower projects, and
iv. the methodology and design standards that the Designer proposes to use to carry out
design.
Panel of Experts
A Panel of Experts (PoE) independent of the Designer should be engaged for high value and
technically complex projects. The PoE brings independent expert advice to the Employer and
Owner during both the preparation phase and throughout construction and first filling,
Members of the PoE should cover the key expertise areas relating to the likely risks that may
be encountered, for example; engineering geology and rock mechanics, hydrology, dam
design (in this type of dam) and gate engineering.
Avoid Under-estimation of Quantities
One of the most significant impacts on project cost occurs when items in the Bill of Quantities
exceed estimated quantities by 30% or more. The risk of cost overruns due to underestimation
of quantities will be reduced if:
i. accurate topographical data is available,
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
15
ii. adequate investigations are carried out in the preparation phase to identify excavation
quantities, and
iii. if the design is sufficiently detailed to accurately estimate quantities.
Therefore, where possible the investigation and design phase in preparing the DPR needs to
be detailed enough to provide a reasonable assessment to remove the need for provisional
sums in the bidding documents.
Provisional Items
If the cost of Provisional Items is not estimated with some level of accuracy, then the contract
is highly likely to experience cost overruns when the true cost is known (during construction).
Therefore, where possible the investigation and design phase in preparing the DPR needs to
be detailed enough to provide a reasonable assessment of remove the need for provisional
sums in the bidding documents.
2.1.4 Transfer of Information Through the Course of the Project
Geological Baseline Report
The GDR and GBR are essential documents to be included in the bidding documents.
Design Information
The DPR should be supplied with the tender documents to inform the Contractor during the
formulation of their bid documents. In particular the following design information should be
included in the bidding documents:
• Hydrological information and responsibility for temporary works such as cofferdam
design.
• Construction drawings
• Technical specification to support the construction drawings.
• Quantities for the Bill of Quantities
Potential Failure Modes Workshop
Potential Failure Modes describe the way that the dam could fail and also capture operational
failures that could lead to large and unplanned releases from the reservoir that could harm
people and property downstream.
During the design process, the design consultant needs to be identifying potential failure
modes and then reducing their likelihood or mitigating their effect. Mitigation of the Potential
Failure Mode will occur through:
i. engineering measures to reduce likelihood,
ii. instrumentation and surveillance measures to identify if they are occurring, and
iii. emergency action plans to reduce the consequences if a failure occurs.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
16
An important step in the project is to transfer knowledge of Potential Failure Modes from the
preparation phase all the way through construction to the final phase of long-term operation.
Hence a workshop shall be held before the DPR is completed and handed over to the
SPV/Project Authority. The workshop should be attended by the design consultant, DHPS, the
SPV/Project Authority and Owner’s Engineer. The eventual operator (e.g. DGPC) should also
be invited to attend. The workshop findings should be summarised in the DPR.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
17
3.0 Tendering and Awarding Construction Contracts
The Department of Hydropower and Power Systems (DHPS) has published Hydropower
Guidelines for “Tendering and Awarding Construction Contracts” as Part III Section C of its
2018 Guidelines for Development of Hydropower Projects [5].
This Guidance document recommends the use of FIDIC Conditions of Contract for Bhutan’s
hydropower development projects because it is an internationally recognised form of contract
that has been used successfully on many projects world-wide. A standardised contract form
provides the Government of Bhutan with confidence that the risks affecting the national
interest are being supported by a well tried and recognised contract, regardless of the
nationality of the Contractor. Furthermore, international contractors have most likely been
involved with a project that uses FIDIC. The DHPS Hydropower Guidelines discuss contract
options. FIDIC forms of contract meet the requirements in the Hydropower Guidelines.
3.1 Tender Documents for Bidders
The Hydropower Guidelines require the tender documents to include:
• Instructions to bidders.
• Proposed General and Particular (Special) Conditions of Contract. Annex A has
advice on Particular Conditions that are recommended for hydropower projects in
Bhutan.
• Owner’s requirements (including Construction Schedule and Technical
Specifications).
• Tender drawings
• Bill of Quantities and price schedule (for equipment supply contracts)
• Equipment data sheet for equipment-supply contracts, including performance data
requirements.
• Tender and Contract Forms. Annex A includes tender data forms and Annex B
provides proforma documents that Bidders will need to submit.
The quality of tender documents will influence the contract outcome. Poor quality documents,
ambiguity, errors and omissions are likely to be identified in claims by the Contractor for extra
time or cost impacts. The drawings and technical specification need to support each other.
Copying technical specification clauses from previous projects should be avoided. This can
lead to incorrect or inappropriate technical standards being used.
The Project Board or equivalent governance group shall review the Tender Documents and
provide final approval before the documents are distributed to bidders.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
18
3.1.1 Preparing a Bill of Quantities
These Notes for Preparing a Bill of Quantities are intended only as information for the
Employer or the person drafting the bidding documents. They should not be included in the
final documents. Annex B contains the proforma for a Bill of Quantities.
Objectives
The objectives of the Bill of Quantities are:
(a) to provide sufficient information on the quantities of Works to be performed to enable
bids to be prepared efficiently and accurately; and
(b) when a contract has been entered into, to provide a priced Bill of Quantities for use in
the periodic valuation of Works executed.
In order to attain these objectives, Works should be itemized in the Bill of Quantities in
sufficient detail to distinguish between the different classes of Works, or between Works of the
same nature carried out in different locations or in other circumstances which may give rise to
different considerations of cost. Consistent with these requirements, the layout and content of
the Bill of Quantities should be as simple and brief as possible.
Content
The Bill of Quantities should be divided generally into the following sections:
(a) Preamble;
(b) Work Items (grouped into parts);
(c) Daywork Schedule; and
(d) Summary.
Preamble
The Preamble should indicate the inclusiveness of the unit prices, and should state the
methods of measurement that have been adopted in the preparation of the Bill of Quantities
and that are to be used for the measurement of any part of the Works.
Rock
Where excavation, boring, or driving is included in the Works, a comprehensive definition of
rock (always a contentious topic in contract administration), should be provided in the
Technical Specification and this definition should be used for the purposes of measurement
and payment.
Work Items
The items in the Bill of Quantities should be grouped into sections to distinguish between those
parts of the Works that by nature, location, access, timing, or any other special characteristics
may give rise to different methods of construction, phasing of the Works, or considerations of
cost. General items common to all parts of the Works may be grouped as a separate section
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
19
in the Bill of Quantities. When a family of Price Adjustment Formulae is used, they should
relate to appropriate sections in the Bill of Quantities.
Quantities
Quantities should be computed net from the Drawings, unless directed otherwise in the
Contract, and no allowance should be made for bulking, shrinkage, or waste. Quantities
should be rounded up or down where appropriate and spurious accuracy should be avoided.
The Bill of Quantities must provide as accurate as possible estimate of quantities for each
schedule item. The “130% rule” (refer Section 1.2 above and Annex A, Section 1.2) means
that the Contractor is entitled to renegotiate the rate when quantities are more than 130% of
the Bill of Quantities item. This has been an issue on several hydropower projects in Bhutan.
Improved quantity estimation will reduce this risk.
Units of Measurement
Table 3.1 lists units of measurement and abbreviations recommended for use.
Table 3.1: Units to be used in Bill of Quantities
Unit Abbreviation Unit Abbreviation
cubic meter
hectare
hour
kilogram
lump sum
meter
metric ton
(1,000 kg)
m3 or cu m
ha
h
kg
sum
m
t
millimeter
month
number
square meter
square millimeter
week
mm
mon
nr
m2 or sq m
mm2 or sq mm
wk
Ground and Excavation Levels
The commencing surface should be identified in the description of each item for work involving
excavation, boring, or driving, for which the commencing surface is not also the original
surface. The excavated surface should be identified in the description of each item for work
involving excavation for which the excavated surface is not also the final surface. The depths
of work should be measured from the commencing surface to the excavated surface, as
defined.
Daywork Schedule
A Daywork Schedule should be included if the probability of unforeseen work, outside the
items included in the Bill of Quantities, is relatively high. To facilitate checking by the Employer
of the realism of rates quoted by the bidders, the Daywork Schedule should normally comprise:
(a) a list of the various classes of labour, materials, and Contractor’s Equipment for which
basic Daywork rates or prices are to be inserted by the bidder, together with a
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
20
statement of the conditions under which the Contractor will be paid for work executed
on a Daywork basis; and
(b) a percentage to be entered by the bidder against each basic Daywork Subtotal amount
for labour, materials, and Plant representing the Contractor’s profit, overheads,
supervision, and other charges.
Provisional Quantities and Sums
Provision for quantity contingencies in any particular item or class of work with a high
expectation of quantity overrun should be made by entering specific “Provisional Quantities”
or “Provisional Items” in the Bill of Quantities, and not by increasing the quantities for that item
or class of work beyond those of the work normally expected to be required. To the extent not
covered above, a general provision for physical contingencies (quantity overruns) should be
made by including a “Provisional Sum” in the Summary of the Bill of Quantities. Similarly, a
contingency allowance for possible price increases should be provided as a “Provisional Sum”
in the Summary of the Bill of Quantities. The inclusion of such Provisional Sums often
facilitates budgetary approval by avoiding the need to request periodic supplementary
approvals as the future need arises.
The estimated cost of specialized work to be carried out, or of special goods to be supplied,
by a Nominated Subcontractor should be specified in the relevant part of the Bill of Quantities
as a particular Provisional Sum with an appropriate brief description. A separate bidding
procedure may be undertaken by the Employer to select the specialists, who are then
nominated as subcontractors to the main or prime Contractor. To provide an element of
competition among the main bidders (prime Contractors) in respect of any facilities, amenities,
attendance, etc., to be provided by the successful bidder as prime Contractor for the use and
convenience of the specialist or nominated subcontractor, each related Provisional Sum
should be following by an item in the Bill of Quantities inviting a percentage (to be quoted by
the main bidder) payable on the actual expenditure from the Provisional Sum.
The provisional sums shall also include an estimated amount to cover the Employer’s portion
of DAAB’s fees and expenses.
As for the estimation of quantities for the Bill of Quantities, it is important to be as realistic as
possible about the value of a provisional sum. Contractual claims have been made during
construction when a provisional sum is significantly different from the actual cost.
Summary
The Summary should contain a tabulation of the separate parts of the Bill of Quantities carried
forward, with provisional sums for Daywork, for physical (quantity) contingencies, and for price
contingencies (upward price adjustment) where applicable, including DAAB fees and
expenses.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
21
Sample Bill of Quantities
A. Preamble
1. The Bill of Quantities shall be read in conjunction with the Instructions to Bidders, General and Particular Conditions of Contract, Technical Specifications, and Drawings.
2. The quantities given in the Bill of Quantities are estimated and provisional and are given to provide a common basis for bidding. The basis of payment will be the actual quantities of work ordered and carried out, as measured by the Contractor and verified by the Engineer and valued at the rates and prices bid in the priced Bill of Quantities, where applicable, and otherwise at such rates and prices as the Engineer may fix within the terms of the Contract.
3. The rates and prices bid in the priced Bill of Quantities shall, except insofar as it is otherwise provided under the Contract, include all Constructional Plant, labour, supervision, materials, erection, maintenance, insurance, profit, taxes, and duties, together with all general risks, liabilities, and obligations set out or implied in the Contract.
4. A rate or price shall be entered against each item in the priced Bill of Quantities, whether quantities are stated or not. The cost of Items against which the Contractor has failed to enter a rate or price shall be deemed to be covered by other rates and prices entered in the Bill of Quantities.
5. The whole cost of complying with the provisions of the Contract shall be included in the Items provided in the priced Bill of Quantities, and where no Items are provided, the cost shall be deemed to be distributed among the rates and prices entered for the related Items of Work.
6. General directions and descriptions of work and materials are not necessarily repeated nor summarized in the Bill of Quantities. References to the relevant sections of the Contract documentation shall be made before entering prices against each item in the priced Bill of Quantities.
7. Provisional Sums included and so designated in the Bill of Quantities shall be expended in whole or in part at the direction and discretion of the Engineer in accordance with Sub-Clauses 13.4 and 13.5 of the General Conditions (refer: 2017 FIDIC Red Book) except with respect to DAAB Fees and Expenses for which no instruction will be required from the Engineer.
8. Provisional Sums included and so designated in the Bill of Quantities shall be expended in whole or in part at the direction and discretion of the Engineer in accordance with Sub-Clause 13.4 and Clause 13.5 of the General Conditions (refer: 2017 FIDIC Red Book).
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
22
9. The method of measurement of completed work for payment shall be in accordance with [insert the name of a standard reference guide, or full details of the methods to be used].1
B. Work Items
1. The Bill of Quantities usually contains the following part Bills, which have been grouped
according to the nature or timing of the work:
Bill No. 1—General Items;
Bill No. 2—Earthworks;
Bill No. 3—Culverts and Bridges;
Bill No. 4—etc., as required;
Daywork Schedule; and
Summary Bill of Quantities.
2. If the ITB requires currency of Bid and payment to be the same (a) applies, Bidders shall
price the Bill of Quantities in local currency only and shall indicate in the Appendix to Bid
the percentage expected for payment in foreign currency or currencies. Otherwise ITB
foreign currency requirements apply, Bidders shall price the Bill of Quantities in the
applicable currency or currencies.
Note that the tables in the Bill of Quantities must be prepared in accordance with the
currency alternative nominated in the Information to Tenderers.
1 The method of measurement should be spelled out precisely in the Preamble to the Bill of Quantities, describing for example the allowances (if any) for timbering in excavation, etc. Many national standard reference guides have been prepared on the subject, and one such guide is the Standard Method of Measurement of the U.K. Institution of Civil Engineers.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
23
3.1.2 Dayworks
A “Daywork Schedule” is commonly found in contracts where the likely incidence of
unforeseen work cannot be covered by definitive descriptions and approximate quantities in
the Bill of Quantities. The preferred alternative is to value the additional work in accordance
with the Conditions of Contract. A Daywork Schedule normally has the disadvantage of not
being competitive among bidders, who may therefore load the rates assigned to some or all
the items. If a Daywork Schedule is to be included at all in the bidding documents, it is
preferable to include nominal quantities against the items most likely to be used, and to carry
the sum of the extended amounts forward into the Bid Summary in order to make the basic
Schedule of Daywork Rates competitive.
The total amount assigned to such competitive daywork is normally 3–5 percent of the
estimated base Contract Price and is regarded as a Provisional Sum for contingencies to be
expended under the direction and at the discretion of the Engineer.
General
Work should not be executed on a daywork basis except by written order of the Engineer.
Bidders will therefore be required to enter basic rates for daywork items in the Schedules,
which rates shall apply to any quantity of daywork ordered by the Engineer. Nominal quantities
will be entered in the Bill of Quantities against each item of daywork and the extended total
for Daywork shall be carried forward as a Provisional Sum to the Summary Total Bid Price.
Unless otherwise adjusted, payments for daywork will be subject to price adjustment in
accordance with the provisions in the Conditions of Contract.
Daywork Labour
In calculating payments due to the Contractor for the execution of daywork, assume the hours
for labour will be reckoned from the time of arrival of the labour at the job site to execute the
particular item of daywork to the time of return to the original place of departure, but excluding
meal breaks and rest periods. Only the time of classes of labour directly doing work ordered
by the Engineer and for which they are competent to perform will be measured. The time of
gangers (charge hands) actually doing work with the gangs will also be measured but not the
time of foremen or other supervisory personnel.
The Contractor will be entitled to payment in respect of the total time that labour is employed
on daywork, calculated at the basic rates entered by the Contractor in the Schedule of
Daywork Rates, together with an additional percentage payment on basic rates representing
the Contractor’s profit, overheads, etc., as described below:
(a) The basic rates for labour shall cover all direct costs to the Contractor, including
(but not limited to) the amount of wages paid to such labour, transportation time,
overtime, subsistence allowances, and any sums paid to or on behalf of such
labour for social benefits in accordance with [country of Borrower] law. The basic
rates will be payable in local currency only.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
24
(b) The additional percentage payment to be quoted by the bidder and applied to costs
incurred under (a) above shall be deemed to cover the Contractor’s profit,
overheads, superintendence, liabilities, and insurances and allowances to labour,
timekeeping, and clerical and office work, the use of consumable stores, water,
lighting, and power; the use and repair of stagings, scaffolding, workshops, and
stores, portable power tools, manual plant, and tools; supervision by the
Contractor’s staff, foremen, and other supervisory personnel; and charges
incidental to the foregoing. Payments under this item shall be made in the following
currency proportions:
(i) foreign: percent (to be stated by bidder).2
(ii) local: percent (to be stated by bidder).
This method of indicating profit and overheads separately facilitates the addition of further
items of daywork, if needed, the basic costs of which can then be checked more easily. An
alternative is to make Daywork rates all-inclusive of the Contractor’s overhead and profit, etc.,
in which case this paragraph and the relevant Daywork Schedule should be modified
accordingly.
Daywork Materials
The Contractor will be entitled to payment in respect of materials used for daywork (except for
materials for which the cost is included in the percentage addition to labour costs), at the basic
rates entered by the Contractor in the Schedule of Daywork Rates, together with an additional
percentage payment on the basic rates to cover overhead charges and profit, as follows:
(a) the basic rates for materials shall be calculated on the basis of the invoiced price,
freight, insurance, handling expenses, damage, losses, etc., and shall provide for
delivery to store for stockpiling at the Site. The basic rates shall be stated in local
currency, but payment will be made in the currency or currencies expended upon
presentation of supporting documentation.
(b) the additional percentage payment shall be quoted by the bidder and applied to
the equivalent local currency payments made under (a) above. Payments under
this item will be made in the following currency proportions:
(i) foreign: percent (to be stated by the bidder);3
(ii) local: percent (to be stated by the bidder);
(c) the cost of hauling materials for use on work ordered to be carried out as daywork
from the store or stockpile on the Site to the place where it is to be used will be
paid in accordance with the terms for Labour and Construction in this schedule.
2 The bidder shall state the percentage in a common foreign currency equivalent required for payment and the exchange rates and official sources used. 3 The bidder shall state the percentage in a single foreign currency equivalent and the exchange rates and official sources used.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
25
Daywork Contractor’s Equipment
The Contractor shall be entitled to payments in respect of Contractor’s Equipment already on
Site and employed on daywork at the basic rental rates entered by the Contractor in the
Schedule of Daywork Rates. These rates shall be deemed to include allowance for
depreciation, interest, indemnity, and insurance, repairs, maintenance, supplies, fuel,
lubricants, and other consumables, and all overhead, profit, and administrative costs related
to the use of such equipment. The cost of drivers, operators, and assistants will be paid for
separately as described under the section on Daywork Labour. An alternative, sometimes
adopted for administrative convenience, is to include the cost of drivers, operators, and
assistants in the basic rates for Contractor’s Equipment.
In calculating the payment due to the Contractor for Contractor’s Equipment employed on
daywork, only the actual number of working hours will be eligible for payment, except that
where applicable and agreed with the Engineer, the travelling time from the part of the Site
where the Contractor’s Equipment was located when ordered by the Engineer to be employed
on daywork and the time for return journey thereto shall be included for payment.
The basic rental rates for Contractor’s Equipment employed on daywork shall be stated in
local currency, but payments to the Contractor will be made in currency proportions, as follows:
(a) foreign: percent (to be stated by the bidder).4
(b) local: percent (to be stated by the bidder).
3.2 Pre-qualification of Bidders
The Hydropower Guidelines discuss the merits of pre-qualification of tenderers versus post-
qualification of tenderers. This Guideline recommends use of pre-qualification processes. Pre-
qualification Criteria for final selection of the Contractor should be included in the tender
document.
The Developer needs to consider the recommendations in Section 1.1 of this Guideline when
selecting both the Designer and the Contractor. If the necessary expertise is not present, then
the Developer should re-consider the preferred selection or add suitably qualified and
experienced advisors to the project.
As noted in Section 1.1.2, the Developer needs to determine if the Contractor has sufficient
financial strength to complete the contract. The Government of Bhutan has found it necessary
to intervene in previous projects to support the Contractor (e.g. advance payments or taking
over the works). None of these are satisfactory, so trying to ascertain the financial strength of
the Contractor in the bid stage is important to prevent future occurences.The Pre-qualification
process is the time to determine if a Contractor is at risk of liquidity problems during the project.
This is difficult when the Contractor is part of a larger multi-layered conglomerate, and some
4 The bidder shall state the percentage in a single foreign currency equivalent and the exchange rates and official sources used.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
26
expert consulting advice may be needed to provide satisfaction that the Contractor is able to
complete the project. Penalties, performance bonds and other financial instruments that
provide some recourse for the Developer should be investigated during preparation of the
Tender Documents.
As noted in Section 1.1.3, to be assured that the Employer is receiving independent advice,
the Contractor must not have any commercial links to the Designer or to the Owner’s Engineer
(and certainly not to the Engineer to the Contract).
Several of the forms for Bidders to submit in Annex B can be used for the pre-qualification
stage.
3.3 Design Documents to be Provided to Bidders
The Hydropower Guidelines describe the information that should be prepared to provide the
Tender Design for the tendering Contractors. In accordance with the Hydropower Guidelines,
the Tender Design should aim to “fully define all technical characteristics of the project”. The
DPR (or a Design Report to similar level of detail) is to be provided in the Request for Bid
documents, which includes:
• a summary of field investigations,
• design criteria applied,
• results of geotechnical, stability and structural analyses,
• the full GBR,
• design criteria for hydro-mechanical and electro-mechanical equipment, and
• main characteristics of equipment.
The Panel of Experts shall review the design documents and provide final approval before the
documents are distributed to bidders.
3.4 Introduction to FIDIC
The FIDIC form of contract is internationally recognised and suitable for hydropower projects.
Some specific additions and adjustments need to be included with the FIDIC standardised
conditions of contract to align with local practises and requirements of Bhutan, and this
approach is typical throughout the world. The following guidance material is provided on the
basis that FIDIC contract forms are adopted.
FIDIC is a French language acronym for Fédération Internationale Des Ingénieurs-Conseils,
which means the international federation of consulting engineers. Over time concerted effort
has been placed on gaining broad consultation and acceptance of standard contract forms
resulting in them being ratified by many international contracting and financing institutions.
Because of the broad support for FIDIC contracts, they are the foremost contracts in
international construction, with representative associations in over 100 countries.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
27
A range of contracts forms are available within the FIDIC document library. The one most
typically relevant to hydropower construction in Bhutan is “The (new) Red Book” [6] which is
most suited to contracts where the majority of design rests with the Employer. This can be
compared to “The (new) Yellow Book” [7] where the Contractor holds most of the design
responsibility, and “The Silver Book” [8] which is used for turn-key projects.
A derivative of the Red Book is the Multilateral Development Bank (MDB) Pink Book that
represents a formalisation of the amendments to the Red Book that had been developed by
the MDBs for use in aid-funded projects. The purpose was to ‘simplify the use of the FIDIC
Conditions of Contract not only for the MDBs and their borrowers but also for others involved
with project procurement including engineers, contractors, and contract specialists. The “Pink
Book” was intended for use on MDB financed projects only.
Essentially, the Pink Book should be regarded as a version of the Red Book, though the
amendments should not be underestimated. Many of the amendments are additional
provisions aimed at achieving financial probity and transparency. The intention of many of the
Pink Book amendments to the Red Book is to avoid fraudulent and corrupt practices, and the
Employer is given additional explicit powers of termination on such grounds.
A brief introduction to each of these is provided in Table 3.2 below.
Table 3.2: Main FIDIC Contracts
FIDIC Contract
Relevant design and construction situation
Red Book
The design, prepared by the Employer’s staff or by consultants acting on its behalf, is provided to the Contractor in the form of Specifications and Drawings (and any Schedules). The payment mechanism is traditional measurement and valuation. However, it is open to the Parties to vary this position.
Yellow Book
The design is prepared by the Contractor in accordance with the Employer’s Requirements, which specify ‘the purpose, scope and/or design and/or other technical criteria for the Works. The Contractor accepts a fitness-for-purpose obligation for the Works, including the design. The payment mechanism for the Yellow Book is lump sum fixed price, with provision for progress payments on the basis of Engineer certification. Like the Red Book, the Yellow Book contract is administered by the Engineer (see above)
Silver Book
Is a lump sum EPC turnkey contract. As with the Yellow Book, the design is prepared by the Contractor in accordance with the Employer’s Requirements. The Contractor assumes full responsibility for the engineering, procurement and construction of the Works and undertakes a fitness for purpose obligation for the Works, including the design.
Pink Book A version of the Red Book with Conditions of Contract for Construction MDB (Multilateral Development Bank - Harmonised Edition) for Building and Engineering Works Designed by the Employer, Third Edition 2010.
The DHPS Hydropower Guidelines recommend the FIDIC Red Book for Civil Works Contracts
using a traditional Bill of Quantities approach. Note the DHPS Guidelines assume the 1999
(first) edition of the Red Book. These Guidelines recommend the up to date 2017 edition of
the Red Book as outlined below.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
28
The Hydropower Guidelines recommend the FIDIC Silver Book for EPC (Engineering,
Procurement and Construction) contracts and provide advice on some clause amendments to
the General and Particular Conditions.
The Hydropower Guidelines recommend the FIDIC Yellow Book for equipment supply
contracts.
Contract Version (FIDIC 2017)
With the exclusion of the Pink Book, all of the contract types discussed above were all revised
in 1999 so that they share a common format and sequence clauses. This assists users to
move between contracts as required. Various updates to individual contracts have occurred
since 1999; however, the full set (Red, Yellow and Silver) was revised and re-released in 2017.
This new suite of FIDIC contracts is described by FIDIC as second editions of the Red, Yellow
and Silver Books. While similar to their 1999 predecessors, these new versions are a
substantial revision and represent a significantly different proposition for an intending user to
consider.
The contracts have been expanded with the historic 20-clause structure replaced by 21
clauses in all three Books. A new feature of the 2017 forms is the inclusion of a set of criteria
known as the Golden Principles (GPs). Their purpose is to act as a benchmark which must be
met if a contract is to be regarded as a FIDIC contract. For example, if the Employer has
undertaken heavy amendment of key provisions, this may result in the contract not being
deemed a FIDIC contract. The GPs provide guidance on how to modify the General Conditions
(GCs) in the Particular Conditions (PCs). By definition, the provisions of a Contract that are
based on unamended GCs will comply with the GPs. However, if such provisions are
administered incorrectly, the intent of the GPs will not be achieved. The GPs are shown in
Figure 3.1.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
29
Figure 3.1: Golden Principles within FIDIC Contract Documents.
While these are not of legal effect, they will guide parties in negotiation to support their
contention that a contract is, or is not, to be regarded as a ‘real’ FIDIC contract.
FIDIC provides a helpful discussion document on the main changes included in the 2017
versions of the Books.
http://fidic.org/sites/default/files/press%20release_rainbow%20suite_2018_03_1.pdf
•The duties, rights, obligations, roles and responsibilities of all the ContractParticipants must be generally as set out in the General Conditions and appropriateto the project.
GP1
•Particular Conditions must be clear and unambiguous.
GP2
•The Particular Conditions must not change the balance of risk/reward allocationprovided for in the General Conditions.
GP3
•All specified time periods must be reasonable.
GP4
•All formal disputes must be referred to a DAAB as a condition precedent toarbitration.
GP5
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
30
3.4.1 Structure of Contract
FIDIC is usually divided in two parts:
• Part I consisting of the General Conditions, and
• Part II concerning the conditions of particular application (including guidelines for the
preparation of Part II clauses).
Part I contains the general terms of the contract, covering such issues as rights and
obligations of each party, procedure for payment, variation, certification and dispute resolution.
Part II of the contract is the conditions of particular application and is to be used to introduce
project specific clauses, such as language of the contract, choice of law, the name of the
person or company appointed to act as Engineer or Employer’s Representative for the project
among other terms. The Appendix contains a sample of documents to be used for the
procurement process.
In most FIDIC forms there is a default hierarchy for the documents forming the contract as
shown in Figure 3.2. The order of priority is as stated below and in the event of inconsistency
the first on the list takes precedence. The parties can rearrange the priority of documents or
stipulate that no priority or order of hierarchy will apply to the contract. This can be done in
Part II of the contract.
Figure 3.2: Hierarchy of Contract Documents.
Further documents (if any), listed in the Contract Agreement or in the Letter of Acceptance.
The Specification, Drawings and Schedules.
Part I – general conditions of contract
Part II – the conditions of particular application. Contract Data & Special Provisions
The Letter of Tender
The Letter of Acceptance (this is the formal acceptance of the contractor's tender and marks the formation of the contract)
The Contract Agreement
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
31
3.4.2 Role of Engineer
The Employer administers the contract through the services of a person, firm or company,
termed the Engineer. While appointed and paid for by the Employer, the position in respect of
Employer and Contractor spans from agency to complete independence. It is important that
the Engineer has no contractual link with the Contractor, but the duties in respect of both
parties are defined in the Contract. The consultancy contract between the Engineer and the
Employer will also provide important task definitions.
For the Contractor, the Engineer is a third party that is acting either on behalf of the Employer,
or impartially between the parties in certain positions, e.g. when fulfilling judicial tasks,
expressions of satisfaction with the works, and issuance of payment certificates.
A typical arrangement of the main relationships between parties is shown on Figure 3.3:
Figure 3.3: Relationship of Parties involved in a Contract
This dual duty has been recognised by international courts as not being inconsistent with one
another and as a result both should be observed and executed by the Engineer depending on
what the circumstances called for in any given situation. (Refer. Sutcliffe Appellant v Thackrah
and Others [1974] A.C. 727)
The Engineer has a duty of exercising due skill and care while carrying out his/her duties, as
may be expected by the standards of his/her professional position. This duty is due to the
Employer, with whom he has a contractual link, but there is a caveat as to the Engineer owing
such duty to the Contractor in tort, since the Contract interposes the Employer between
Contractor and Engineer and in law.
The role of the Engineer under FIDIC has been more clearly defined in the 2017 version. Table
3.3 summarises the role of the Engineer:
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
32
Table 3.3: The Role of the Engineer
Aspect Commentary Clauses
(FIDIC 2017)
Definition The engineer is defined as part of the “Employer’s Personnel” that is appointed by the Employer.
1.1.33 1.1.35
3.1
Qualification
The Engineer is required to be a professional engineer having suitable qualification, experience and competence at act as the Engineer under the Contract.
3.1 3.2
Duty
Except for otherwise stated in subsequent conditions the “Engineer shall act as a skilled professional and shall be deemed to act for the Employer”.
3.2
Contract
The Engineer has “no authority to amend the Contract”. Nor can he/she “relieve either Party of any duty, obligation ore responsibility under or in connection with the Contract” except as provided for “in these Conditions”.
3.2
Determinations
When seeking agreement between the parties or making determinations the Engineer “shall not be deemed to act for the Employer”, but “neutrally between the Parties” and “shall make a fair determination”.
3.7 3.7.2
Consultation
Obligations are placed on the Engineer to undertaken and facilitate meaningful consultation.
3.7.1
In summary, in the FIDIC 2017 form of contract the importance of the Engineer increases
through a stronger administrative role, with prescriptive and well-defined procedural steps
which specify the time limits and seek to remove ambiguity. Clarity and time limits are an
advantage to both Employer and Contractor. Further the dual role of the Engineer is clarified
by taking a clear position for his/her neutrality when making determinations that are unfettered
by influence of the Employer. To reflect common practice, the Engineer can now also be a
legal entity, rather than an individual.
3.4.3 Risk Management using the Contract
Proper risk allocations in construction contracts can help reduce adverse impacts on delivery
programme and costs and achieve management efficiency. FIDIC contracts, like other
standard forms of construction contract, seek to pre-allocate responsibilities for risks which
may transpire during the project delivery phase between the Employer and the Contractor.
Where the Employer assumes responsibility for a particular risk the Contractor is contractually
entitled to an extension to the Time for Completion and/or an addition to the Contract Price.
Where a responsibility for a particular risk is allocated to the Contractor, the occurrence of the
risk would not generate an entitlement to additional time or money to complete the Work.
Previous versions of FIDIC induced some confusion between;
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
33
• “risk” being the combination of likelihood and consequence, and
• the impact parties in terms of costs or time.
The FIDIC contract documents of 2017 seek to remove this confusion, but retain the well-
established general approach to risk being;
i. the Contractor is best suited to deal with risks associated with works
planning and execution, provision of labour, materials and construction
equipment, and safety of site operations;
ii. the Employer assumes the risk of providing the Site (and any information he
has collected about the Site) and ensuring it is available for the Contractor to
carry out his work, and the extra cost incurred by the Contractor due to the
occurrence of unforeseeable risks; and
iii. design risks are borne by the party responsible for providing the design.
Further, the Contractor remains responsible for any loss or damage to the Works until the
Employer formally takes over the site unless the loss or damage was caused by risks for which
the Employer is responsible and for which the Contractor has no liability (FIDIC 2017 Cl 17.1).
Risks that can induce significant time delays, where possible need early warning of such
events (FIDIC 2017, Cl 8.4) and mechanisms for assessing extensions of time (FIDIC 2017,
Cl 8.5). Such risks include those arising from aspects listed in Table 3.4;
Table 3.4: Type and Management of Risks
Aspect Commentary Clause
Natural Risks Typically risks concerning climatic conditions such as rainy or cold days, moderate floods and land instability.
17.2
Political and Social Risks
Most political and social risks are allocated to the Employer, e.g. war, civil commotions, disorders and strikes.
Economic Economic risks occur frequently during construction period, particularly the fluctuation of prices of materials, labour and equipment. (Cl 13.8).
13.8
Law Change
The Contractor is entitled to an Extension of Time and additional cost caused as a result of the changes in the laws that occur after the Base Date in the Contract. Therefore, under FIDIC Form, such legal change risks are basically retained by the Employer.
13.6
Labour / Material Shortages
The Contractor typically bears all the consequences of the risks of unavailability of the required personnel, materials and equipment, except for allowable Extensions of Time (EOT) in case of unforeseeable shortage.
4.1 6.1
Design Error The risk of faults, errors or omissions from the design as supplied by the Employer that could not be readily identified by the Contractor, largely lie with the Employer.
17.2
Behavioural
These are caused by one party's action or inaction that adversely impacts the project or other party. The Employer is responsible for his own behavioural risks, including the risks of Engineer who acts on the Employer's behalf, and the Contractor is responsible for his own risks, including those of the Sub-Contractor.
Multiple
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
34
Force Majeure
Force Majeure provisions are common in construction contracts. In FIDIC 2017 these have
been re-labelled “Exceptional Events” (FIDIC 2017, Cl 18). The definition and intent is however
largely unchanged;
Exceptional Event means an event or circumstance which;
i. is beyond a Party’s control;
ii. the party could not reasonably have provided against before entering the Contract;
iii. having arisen, such Party could not reasonably have avoided or overcome; and
iv. is not substantially attributable to the other Party.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
35
4.0 Management During Construction
The DHPS Hydropower Guidelines for “Construction Phase – Technical Aspects” as Part III
Section D of its 2018 Guidelines for Development of Hydropower Projects [9] apply in the
construction phase.
The Hydropower Guidelines discuss the many aspects of construction management including:
design, quality assurance and quality control programmes, cost monitoring, time-schedule
monitoring, risk management, commissioning, and project completion. The SPV/Project
Authority is required to consider the recommendations in the Hydropower Guidelines, where
implementing these strategies to improve construction management.
Effective management during construction is essential for minimising the impacts of various
issues as they arise during construction. Utilising the guidelines and bidding documents will
mitigate many issues identified in hydropower projects in Bhutan (refer Section 1.2). The
intention is to ensure the bidding documents and contract clearly:
• allocate risk during the contract works,
• set the performance requirements for the completed works and provide mechanisms
to validate (or reject) construction quality,
• set the time frame for completion,
• provide processes for payment,
• provide a process for dispute resolution, and
• if necessary, termination of the contract.
4.1 Roles
During the construction phase the three main parties are Employer, Engineer, and Contractor.
The Hydropower Guidelines detail the typical responsibilities for each party during the
construction phase. The core responsibilities typically associated with each party are
summarised below. Particular responsibilities can be defined in the contract, if required.
During construction the Employer’s responsibilities are typically:
• Cost and schedule changes
• Approval of design
• Approval of equipment when cost changes are involved
• Decisions on variations
• Decision on construction schedule adjustments
• Claim management decisions
• Approval of environmental, social, and health & safety compliance
• Decisions on risk management and approval of emergency plans
• Approve and submit reports to RGoB
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
36
The Employer shall appoint the Owner’s Engineer, who has the capacity and resources to
carry out the tasks. The typical duties of the Owner’s Engineer during construction are:
• Routine project management and documentation.
• Prepare design or approve design if no cost changes are involved.
• Approve temporary works.
• Approval of equipment when no cost changes are involved.
• Supervise the quality assurance and quality control.
• Advise on technical specification matters.
• Approval of equipment when no cost changes are involved.
• Approve or reject components, stages or milestones of the Works as required in the
Specification.
• Evaluate variation claims.
• Review contract interface issues.
• Monitor Contractor’s environmental, social, and health & safety compliance.
• Regularly update the Project Risk Register, propose risk mitigation measures, review
emergency plans, monitor implementation.
• Prepare reports on behalf of Employer and review contractor reports.
The Employer shall appoint the Engineer to the Contract. As noted in Section 1.1.4, the
Engineer to the Contract has the specific independent duties (set out in the FIDIC Red Book)
during construction, namely:
• Formal approvals required by the Contract
• Approve or reject completed works, equipment or components,
• Approve payment claims.
• Decide claims for cost extension or time.
• Determine contract interface issues.
The Contractor responsibilities are defined in the contract documents and typical
responsibilities during construction include:
• Preparation of temporary works.
• Preparation of equipment.
• Quality assurance and quality control programmes.
• Requests for payments and quotes for variations.
• Progress reports, construction schedules, progressing the works.
• Identify issues with contract interfaces.
• Issue claims
• Implement environmental, social, and health & safety measures.
• Prepare and implement emergency plans.
For more detailed information, the DHPS Hydropower Guidelines discuss strategies for each
party to successfully fulfil their responsibility. An extensive list of international references is
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
37
provided in the Hydropower Guidelines and all parties can benefit from implementing the
recommendations in these documents.
4.2 Risk Management
Even with robust guidelines and bidding documents, not all risk is eliminated and there is still
a need to manage risks during construction. The risk management process can be divided
into three components:
i. identification of risks,
ii. developing mitigation plans, and
iii. actively managing risks by implementing mitigation plans.
Risk management should involve all parties in order to create a comprehensive plan that
benefits everyone.
Identification of risks must start before construction begins. Information provided in the DPR
and tender documents forms the basis for creating an initial Project Risk Register, which
should be updated as new information becomes available. Project Risk Register (PRR) is a
simple and highly effective tool for facilitating the identification and management of project
risk. For a sample Risk Register refer to Table 1.4: Example of Simple Risk Register.
Developing mitigation plans for the identified risk is essential for avoiding or minimising the
potential impacts. Risks during construction can include hydrological, geological, construction
management, environmental, cultural and social, and health and safety. For a more detailed
list of risks, refer to DHPS Hydropower Guidelines Part III Section D [9].
Many issues previously experienced during hydropower projects in Bhutan can be mitigated
with appropriate planning and effective management during construction. Section 1.2
discusses issues that have arisen. Potential construction management actions that will avoid
future problems (or at least mitigate their effects) are listed below:
• Record all site conditions.
• Record all site exposures due to variable geology.
• Design changes before design issue causes delay of Works.
• Flood management during Works.
• Design resources for making changes.
• Capacity of SPV/Project Authority and Owner’s Engineer to supervise the Contractor
and subcontractors.
• Designer capacity and resources during construction to make timely decisions
• Scope control to minimise non-project-related work.
• Pricing review of Provisional Sums.
• Rate data to support variation negotiation.
To summarise, thorough investigation and good design combined with strong bidding
documents will reduce risks, but not entirely eliminate them. Using tools, such as a Project
Risk Register, and developing mitigation plans will help identify and manage risks during
construction.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
38
References
[1] World Bank and RGOB, “Bhutan Dam Safety Guidelines (Draft),” 2019.
[2] DHPS, DHPS, “Guidelines for Development of Hydropower Projects Part II,” Department
of Hydropower and Power Systems, Ministry of Economic Affairs, Bhutan, 2018.
[3] ASCE, “Geotechnical Baseline Reports for Construction: Suggested Guidelines,”
American Society of Civil Engineering, 2007.
[4] ICOLD, “Bulletin 129. Dam Foundations - Geologic Considerations, Investigation
Methods, Treatment, Monitoring,” International Commission on Large Dams, 2005.
[5] DHPS, “Guidelines for Development of Hydropower Projects, Part III Section C: Pre-
Construction Phase - Tendering & Awarding of Construction Contracts,” Royal
Government of Bhutan, Ministry of Economic Affairs, Department of Hydropower &
Power Systems, 2018.
[6] FIDIC, “Conditions of Contract for Construction, For Building and Engineering Works
Designed By The Employer,” International Federation of Consulting Engineers, 2017.
[7] FIDIC, “Conditions of Contract for Plant and Design-Build,” International Federation of
Consulting Engineers, 2017.
[8] FIDIC, “Conditions of Contract for EPC Turnkey Projects,” International Federation of
Consulting Engineers, 2017.
[9] DHPS, “Guidelines for Development of Hydropower Project, Part III Section D:
Construction Phase - Technical Aspects,” Royal Government of Bhutan, Ministry of
Economic Affairs, Department of Hydropower & Power Systems, 2018.
[10] Royal Audit Authority, “Audit Report of PHPA I, PHPA II, and MHPA,” RGOB, 2018.
Annex A Particular Conditions of Contract 39
Annex A: Recommended Particular Conditions of Contract
1.0 Particular Conditions of Contract:
The following are the recommended changes to Particular Conditions of the 2017 Red Book
FIDIC Contract to be applied to hydropower projects in Bhutan.
In several Sub-Clauses of the Particular Conditions the number of days has been modified
with respect to the “Information and Instructions for Bidders” and “General Conditions of
Contract” (hereinafter called GCC) used in previous contracts for hydropower projects in
Bhutan. It is essential to carefully select the proposed figures.
1.1 Clause 2: The Employer
Clause 2 provides clauses relevant to the Employer. There are no additions or changes
necessary for these clauses.
Note that under Sub-clause 2.4 (FIDIC 2017) “Employer’s Financial Arrangements” has been
further developed with the Employer required to describe financial arrangements in the
Contract Data. The Employer must notify the Contractor if there is a material change, and (at
the request of the Contractor) provide evidence that financial arrangements are in place to
enable payment.
1.2 Clause 3: The Engineer
Clause 3 provides clauses relevant to the Engineer. There are no additions or changes
necessary for these clauses.
The enhanced provisions provided in FIDIC 2017 and relevant to the Engineer are discussed
in Section 3.3.2 of the main document above.
1.3 Clause 4: The Contractor
Clause 4 provides clauses relevant to the Contractor.
The Sub-clause 4.2 deals with Performance Security. Paragraph 1.32 of the Information and
Instruction to Bidders states within 30 days hence this Sub-clause has been adjusted for
consistency. The second paragraph in this Sub-clause, immediately under the sub heading
4.2.1 Contractor Obligations, is worded in a generic form with respect to the country controlling
the project. This needs to be made specific to Bhutan by replacing the first paragraph under
4.2.1 with;
The Contractor shall deliver the Performance Security to the Employer, with a copy to the Engineer, within 30 days after receiving the Letter of Acceptance. The Performance Security shall be issued by any Banks in Bhutan or any international Banking Institutions with endorsement/counter guarantee by any Bank in Bhutan, approved by the Employer, and shall be in the form annexed to the Particular Conditions, or in another form approved by the Employer. The Performance Security shall be
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex A Particular Conditions of Contract 40
denominated in the currency in which the Contract Price is payable, or in a freely convertible currency acceptable to the Employer.
Sub-Clause 4.15 Access Route defines the Contractor’s responsibility around access routes.
Included in Sub-clause 4.15 is an alphabetical list ((a) to (e)) that includes for example; the
suitability of access routes, repairs, maintenance and signage and third-party claims.
The existing list is to be augmented by the inclusion of the following Clauses taken from Clause
30 ii) and iii) of the GCC to provide additional specificity around access route responsibilities;
(f) Special Loads. Should it be found necessary for the Contractor to move one or more loads of Constructional Plant, machinery or pre-constructed units or parts of units of work over part of a highway or bridge, the moving whereof is likely to damage any highway or bridge unless special protection or strengthening is carried out, then the Contractor shall, before moving the load on to such highway or bridge, give notice to the Engineer of the weight and other particulars of the load to be moved and his proposals for protecting or strengthening the said highway or bridge. Unless within fourteen days of the receipt of such notice, the Engineer shall, by counter-notice, direct that such protection or strengthening is unnecessary, then the Contractor will carry out such proposals or any modification thereof that the Engineer shall require and, unless there is an item or are items in the Bill of Quantities for pricing by the Contractor of the necessary works for the protection or strengthening aforesaid, the costs thereof shall be paid by the Employer to the Contractor.
(g) Settlement of Extraordinary Traffic Claims. If during the execution of the Works or
at any time thereafter the Contractor shall receive any claim arising out of the execution of the Works in respect of damage or injury to highways or bridges, he shall immediately report the same to the Engineer and thereafter the Employer shall negotiate the settlement of and pay all sums due in respect of such claim and shall indemnify the Contractor in respect thereof and in respect of all claims, proceedings, damages, costs, charges and expenses in relation thereto. Provided always that if and so far as any such claims or part thereof shall, in the opinion of the Engineer, be due to any failure on the part of the Contractor to observe and perform his obligations, then the amount certified by the Engineer to be due to such failure shall be paid by the Contractor to the Employer.
1.4 Clause 5: Sub-contracting
Clause 5 provides clauses relevant to the responsibilities of the Contractor in relation to sub-
contracts. There are no additions or changes required to these clauses.
1.5 Clause 6: Staff and Labour
Clause 6 provides clauses relevant to Staff and Labour particularly in terms of Contractor
responsibilities.
An addition shall be added at the end of Sub-clause 6.4 Labour Laws to make the overall
clause directly relevant to the laws of Bhutan.
The Contractor shall, in respect of labour employed by him, comply with the provision of the various labour laws of the country and shall indemnify the Employer in respect
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex A Particular Conditions of Contract 41
of all claims that may be made against the Employer for non-compliance thereof by the Contractor. Notwithstanding anything contained herein, the Engineer may take such actions as may be necessary for compliance of the various labour laws and recover the costs thereof from the Contractor.
Sub-clause 6.9 Contractor’s Personnel specifies the responsibility of the Contractor in terms of their personnel. Further it indicates where the Engineer may intervene on matters of personnel. This clause needs to be enhanced to provide specificity when considering the Contractor’s use of foreign personnel on projects in Bhutan as follows
Sub-Clause 6.9.1 Foreign Personnel
The Contractor shall submit to the Employer, the details and bio-data of all foreign personnel he proposes to bring into Bhutan for the performance of the Works under the Contract. Such data for each person shall, besides the proof of his citizenship, contain the name, his present address, his assignment and responsibility in connection with the Works, and a short resume of his qualifications, experience etc. in relation to the Works to be performed by him.
Any person unsuitable and unacceptable to the Employer shall not be brought to Bhutan. Any person, if found unsuitable or unacceptable to the Employer on a later date, shall within a reasonable time, be repatriated by the Contractor, who shall make alternative arrangements for providing a suitable replacement
No person brought to Bhutan for the purposes of the Works shall be repatriated without the consent of the Employer in writing, which shall be based on a written request from the Contractor for such repatriation giving reasons for such an action to the Engineer. The Employer may give permission for such repatriation provided it is satisfied that the progress of Works shall not suffer due to such repatriation/replacement.
The Contractor and his expatriate personnel shall observe/respect all Bhutanese Acts, Laws, Rules and Regulations and shall not in any way interfere with Bhutanese political and religious affairs and shall meticulously follow any other Rules and Regulations which the RGoB, the Employer and the Engineer may impose on them from time to time. The Contractor’s expatriate personnel shall work and live in close co-operation with their co-workers and the community and shall not engage themselves in any other employment either part time or full time nor shall they take part in any local politics.
The Employer will assist the Contractor, to the extent possible, in obtaining necessary permits to travel to Bhutan and back by issue of necessary certificates and other information needed by the RGoB and other agencies.
The Contractor shall, deliver to the Engineer, a return in detail in such form and at such intervals as the Engineer may prescribe showing the supervisory staff and the number of the several classes of labour from time to time employed by the Contractor on the site and such information in respect of constructional plant as the Engineer may require. The Contractor shall be responsible for observance by his Sub-Contractors of the foregoing provisions.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex A Particular Conditions of Contract 42
1.6 Clause 7: Plant, Materials and Workmanship
Sub-clause 7.1 Manner of Execution defines the Contractors responsibility associated with
matters including but not limited to; the supply, and testing of Plant, and the production and
testing of Material. The clause includes alphabetical list ((a) to (c)) that provides specifics on
this clause. To provide greater certainty around achieving timely progress under the contract
the following additions are required to this list.
(d) The Contractor shall initiate timely action to procure the materials well in advance so as to ensure that the progress of Works does not suffer for want of the materials on the site at least thirty days before these are intended to be used on Works. Any setback to the progress of the Works and consequent delay in completion of the Works on account of non-availability of materials on Site shall be the sole responsibility of the Contractor.
(e) Within thirty days after the issue of the Letter of Acceptance, the Contractor shall
submit a Schedule of the mobilization of the Constructional Plant conforming with the plant list submitted with his bid. He shall also indicate whether he owns the Constructional Plant or he proposes to purchase or hire the same and shall furnish proof that he shall be able to arrange this Constructional Plant whether from his own resources or on hire. He shall also submit a list of the Constructional Plant required during the first year along with a list of the orders for purchase/hire of this Constructional Plan.
Sub-clause 7.8 Royalties defines the Contractors responsibility to pay all royalties, rents and
other payments. To provide greater clarity, the following additions are required.
The Accepted Contract Amount shall be deemed to include royalty charges, rents and
other payments, and taxes, duties, levies etc. as applicable. The Contractor shall abide by
the applicable regulations on royalties and rents and applicable acts of Kingdom of Bhutan
and amendments thereof. A separate Tax Guidelines for hydropower projects, issued by
the Royal Government of Bhutan, shall also be applicable.
Each party hereby agrees to indemnify and keep indemnified and saved harmless at all the times the other party against any claims, action, proceedings, loss, cost, expenses or damage suffered or incurred by it by reason of the party which has failed to pay taxes, duties, levies etc. which it is obliged to pay pursuant to the provisions of this clause and/or applicable laws and/or arising out of its failure to comply with its obligations under such provisions and/or applicable laws.
1.7 Clause 8: Commencement, Delays and Suspension
The management of the contract programme and potential extensions of time (EOT) is a major
aspect of any construction contract and is dealt with in Clause 8 (FIDIC 2017). The importance
of the Contractor’s programme, for execution of the Works, has been further recognised in
FIDIC 2017 with the addition of greater requirements around initial and revised programmes.
Sub-clause 8.1 Commencement of Works defines the process for initiating the execution of
the works. To ensure that this is done with expediency, the Commencement Date as defined
in reference to the Letter of Acceptance needs to be reduced from “…within 42 days…” to
“…within 30 days…” such that the clause reads (with recommended change in bold).
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex A Particular Conditions of Contract 43
The Engineer shall give Notice to the Contractor stating the Commencement Date, not
less than 14 days before the Commencement Date. Unless otherwise stated in the
Particular Conditions, the Commencement Date shall be within 30 days after the
Contractor receives the Letter of Acceptance.
Sub-clause 8.3 Programme details the requirements around the submission of initial and
revised programme for the execution of the Works. For consistency the time defined in the
first sentence of Sub-clause 8.3 should be increased from 28 days to 30 days so that the first
sentence reads (with recommended change in bold).
The Contractor shall submit an initial programme for the execution of the Works to the
Engineer within 30 days after receiving the Notice under Sub-clause 8.1
[Commencement of Works]. The programme shall be prepared using an acceptable
scheduling software, latest version of Primavera or its equivalent softwares.
Further, Sub-clause 8.3, while dealing with revised programmes only requires that these be
submitted “whenever the programme ceases to reflect or is otherwise inconsistent with the
Contractors obligations”. To provide greater certainty that the programme is a true reflection
of anticipated progress the following shall be added to the end of Sub-clause 8.3.
The construction programme shall be revised at three monthly intervals or as
necessary, as the work progresses to meet this requirement and should include a chart
of the principal quantities of Work forecast for execution monthly, and a schedule of
payments expected to be made to the Contractor by the Employer.
The construction programme shall be of the critical path method, or equivalent, in the
form of a network diagram and activity listing. The network diagram shall show in detail
and in orderly sequence all activities, their descriptions, durations, and dependencies
or precedencies, necessary to the completion of the Works. The activity listing shall
show the following information for each activity on the network diagram:
a) Identification by activity number and description b) Duration c) Earliest start and finish dates d) Latest start and finish dates e) Total float time
Code numbers for critical path method type schedules shall consist of not more than
four digits.
The submission to and approval by the Engineer of such programmes or the furnishing
of such particulars shall not relieve the Contractor of any of his duties or responsibilities
under the Contract
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex A Particular Conditions of Contract 44
The Contractor shall, whenever required by the Engineer also provide in writing, for
his information a general description of the arrangements such as deployment of
modern and efficient machinery, skilled and unskilled labour and methods, which the
Contractor proposes to adopt for the execution of Works.
Sub-clause 8.7 Rate of Progress details a process by which the Engineer can instruct the
Contractor to produce a revised programme that demonstrates how progress will be expedited
to achieve completion of the Works within the relevant Time of Completion. To provide
additional specificity in this clause the following is to be added at the end of Sub-clause 8.7. It
is noted that this clause is re-numbered from Sub-clause 8.6 in the previous version of FIDIC.
To achieve the required progress, the Work may be required to be carried out round
the clock. The period of completion and number of working days shall not be affected
by the number of shifts each day. No extra amount on account of any shift work is
payable to the Contractor.
Sub-clause 8.8 Delay Damages defines the payment of Delay Damages by the Contractor.
For consistency the following addition to the end of Sub-clause 8.8 is necessary. It is noted
that this clause is re-numbered from Sub-clause 8.7 in the previous version of FIDIC.
Payment of delay damages by the Contractor will be valued in accordance with the
appropriate Schedule
1.8 Clause 9: Testing on Completion
Clause 9 details the obligations placed on the Contractor associated with testing on
completion of the works. No additions or changes are required for this clause. It is worth noting
however that FIDIC 2017 places additional requirements on the Contractor, particularly around
the provision to the Engineer of a detailed test programme.
1.9 Clause 10: Employer’s Taking Over
Clause 10 defines the conditions and process for the Employer to take over the Works. No
additions or changes are required for this clause.
1.10 Clause 11: Defects after Taking Over
Clause 11 provides conditions relevant to addressing defects up until the expiry date of the
relevant Defects Notification Period. No additions or changes are required for this clause.
FIDIC 2017 has expanded Clause 11 in the area of;
• the removal of Plant off-site to facilitate the remedy of defects Sub-clause 11.5;
• undertaking further tests after remediating defects Sub-clause 11.6; and
• the Contractors rights of access after the Employer has taken over Sub-clause 11.7.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex A Particular Conditions of Contract 45
1.11 Clause 12: Measure and Evaluation
Clause 12 defines how the Works will be measured and valued and contains specific linkages
to handle disputes under Sub-clause 3.7 Agreement and Determination.
The following adjustments to the thresholds provided in Sub-clause 12.3 are required.
The threshold pertaining to the measured quantity of an item in 12.3 (b) (i) shall be increased
from 10% to 30% and 12.3 (b) (iii) increased from 1% to 10% such that the full text reads, with
the changes highlighted in bold.
(b) (i) The measured quantity of an item is changed by more than 30% from the quantity of this item in the Bill of Quantities or other Schedules,
(b) (ii) [unchanged] (b) (iii) This change in quantity directly changes the Cost per unit quantity of this item
by more than 10%, and (b) (iv) [unchanged].
1.12 Clause 14: Contract Price and Payment
Clause 14 provides details of the payment process and details associated on costs.
Sub-clause 14.1 The Contract Price provides an alphabetical list of conditions ((a) to (d)). The
last condition (d) needs to be enhanced through the following additions shown in bold.
(d) the Contractor shall submit to the Engineer, within 28 days after the Commencement Date, a proposed breakdown of each lump sum price and every item in the Schedules which has a total amount exceeding 0.1% of the Accepted Contract Amount. The Engineer may take the breakdown into account when preparing Payment Certificates but shall not be bound by it.”
Sub-clause 14.2 Advanced Payments defines how payments made in advance of the
Commencement of Works will be progressed. For completeness the second paragraph should
be adjusted to include “Constructional Plant” as follows and shown in bold;
After receiving the Advanced Payment Certificate, the Engineer shall make an
advanced payment, as an interest-free loan for mobilisation and for Constructional
Plants (and design, if any). The amount of the advance payment and the currencies
in which it is to be paid shall be stated in the Contract Data
Further the following addition is required to provide increased specificity.
Advances for execution of the Works, if required by the Contractor, will be granted in
the following cases provided that the advances given or taken for particular Work are
spent only for that Work.
Advance for Mobilisation.
Advance, to the percentage stated in the Contract Data, of the Contract Price can be
granted for the following preliminary and enabling Works;
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex A Particular Conditions of Contract 46
a) Construction of colonies, store and workshops etc. including camps, labour sheds and stores etc. provided to the Contractor by the Employer on cost recoverable basis.
b) Mobilisation of labour c) Overhaul, dismantling and transportation of Contractor’s Constructional Plant to
the Site including procurement of spare parts. d) Construction of enabling Works and foundations for the Constructional Plant etc.
The advance to the extent of half of total value admissible will be released within one
month of the date of signing of Agreement. The rest of the advance will be released in
two equal instalments commensurate with the progress of above cited preliminary and
enabling Works on the certificate of the Engineer.
The advance will be disbursed on production of the irrevocable Bank Guarantee on
the Proforma from any Banks in Bhutan or any international Banking Institutions.
The advance is recoverable, and the deduction of the advance shall be made on
prorate percentage basis from the interim payments certified by the Engineer under
the Contract. The deduction shall commence in the next Interim Payment Certificate
following that in which the total of all such payments to the Contractor has reached
10% (ten percent) of the Contract Price until such time as the advance has been fully
repaid, provided always that the entire amount of advance shall be completely
deducted by the time the total of all payments to the Contractor has reached 80%
(eighty percent) of the Contract Price.
Advance for Constructional Plant.
Advance to the extent of 90% (ninety percent) of the cost of new Constructional Plant
paid by the Contractor for which the Contractor shall produce satisfactory evidence,
subject to the maximum percentage stated in the Contract Data, will be granted on the
following Conditions;
a) The Constructional Plant for which advance is required shall be approved by
the Engineer. b) The advance against new indigenous Constructional Plant will be released after
the equipment has reached the Site and is duly hypothecated in favour of the Employer.
c) The advance against imported Constructional Plant will be released on
production of documents as a proof thereof, provided the Constructional Plant is fully insured from the port to the Site and hypothecated in favour of the Employer.
d) The advance to the extent of 90% against the new Constructional Plant can
also be released to the Contractor against invoice, at his request, on production of Bank Guarantee for an amount equal to the amount of advance. This bank guarantee shall be released after the equipment reaches the site, is duly
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex A Particular Conditions of Contract 47
hypothecated in favour of the Employer and such plant and equipment is insured for its full value against all risks at the Contractor’s cost.
The advance is recoverable, and the deduction of the advance shall be made on
prorate percentage basis from the interim payments certified by the Engineer under
the Contract. The deduction shall commence in the next Interim Payment Certificate
following that in which the total of all such payments to the Contractor has reached 10
(ten) percent of the Contract Price until such time as the advance has been fully repaid,
provided always that the entire amount of advance shall be completely deducted by
the time the total of all payments to the Contractor has reached 80% (eighty percent)
of the Contract Price.
The first paragraph under Sub-heading 14.2.1 Advance Payment Guarantee is generic in
terms of country and jurisdiction. This needs to be replaced with the following specific to
Bhutan. Note, the first sentence is unchanged
The Contractor shall obtain (at the Contractor’s cost) an Advance Payment Guarantee
in amounts and currencies equal to the advance payment, and shall submit it to the
Employer with a copy to the Engineer. This guarantee shall be issued by the Banks in
Bhutan or any international Banking Institutions approved by the Employer, and shall
be in the form annexed to the Particular Conditions or in another form approved by the
Employer.
Sub-clause 14.3 Application for Interim Payments provides the process for the Contractor to
submit a Statement to the Engineer following each payment period as stated in the Contract
Data. The following additional condition, specific to Bhutan, is to be included at the end of
Sub-clause 14.3.
If the Contractor expressly requests in writing, he will be permitted to convert the
Retention Money recovered from his Interim Payment Certificates into interest bearing
Government Securities of interest-bearing deposits with a Scheduled banks in Bhutan
or any international banking institutions taken out in the name of Engineer or into Bank
Guarantee in instalments of Ngultrum one million in favour of the Employer issued by
the Banks in Bhutan or international banking institutions or any Scheduled banks in
Bhutan or any international banking institutions.
Sub-clause 14.5 Plant and Material intended for the Works details how allowance for Plant
and Material is made under Sub-clause 14.3 Application for Interim Payment. In the last
paragraph of Sub-clause 14.5 the specified percentage can be reduced from 80% to 75% as
shown in full below with change in bold.
The amount so agreed or determined shall take account of the evidence and
documents required under this Sub-clause and of the contract value of the Plant and
Materials. If sub-paragraph (b) above applies, the Engineer shall have no obligation to
certify any payment under this Sub-clause until the Employer has received the bank
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex A Particular Conditions of Contract 48
guarantee in accordance with sub-paragraph (b)(iii) above. The sum to be certified by
the Engineer in an IPC shall be the equivalent of seventy five percent (75%) of the
agreed or determined amount.
Sub-clause 14.7 Payment defines the requirement on the Employer to pay the Contractor. The
56 day periods stated in Sub-clause 14.7 is to be replaced with 60 days as shown in full and
highlighted in bold. IPC refers to Interim Payment Certificate and FPC refers to Final Payment
Certificate.
(b) the amount certified in each IPC issued under; (i) Sub-clause 14.6 [Issue of IPC], within the periods stated in the Contract Data
(if not stated, 60 days) after the Engineer receives the Statement and supporting documents; or
(ii) [unchanged]
(c) The amount certified in the FPC within the period stated in the Contract Data (if not stated, 60 days) after the Employer receives the FPC.
All payments to be made by the Employer to the Contractor (advance, Interim Certificate Payments
and Final Bill) shall be released and credited into a designated Escrow Account with the following
conditions:
a) A designated Escrow Account shall be opened by the Contractor after Notification
of Award with Nationalized/Scheduled Commercial Bank in Bhutan. Particulars of the
Escrow Account shall be submitted by the Contractor to the Employer before
submitting request for mobilization advance. Any charges for Escrow Account must
be borne by the Contractor.
b) The Employer shall release payments into the Escrow Accounts only.
c) In case of financial crunch or other exigency, the Employer may make direct payment
to the vendor in the interest of the project with the consent of the Contractor.
Sub-clause 14.8 Delayed Payment provides details of the Contractors rights if they do not
receive payment in accordance with Sub-clause 14.7 Payment. To provide certainty to both
parties, condition (c) in the alphabetical list ((a) to (c)) in Sub-clause 14.8 needs to be modified
as follows with the chance indicated in bold;
(a) [unchanged] (b) [unchanged] (c) In the absence of such rate at either place interest shall accrue to the
Contractor on a daily basis at a simple rate of ten percent per annum (365 days) commencing ninety days after the date on which the Contractor submitted the application for payment.
Sub-clause 14.9 Release of Retention Money defines the process for the release of retention
money. A consequential addition arising from the recommended addition to Sub-clause 14.3
is the following addition.
If the Contractor, according to the Sub-Clause 14.3 of the Particular Conditions, has
converted the Retention Money into Government Securities or into Bank Guarantee
the guarantee mentioned in the fifth paragraph of the Sub-Clause is not required.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex A Particular Conditions of Contract 49
1.13 Clause 15: Termination by Employer
Clause 15 defines the process to follow should the Contractor fail to carry out any obligation
under the Contract. No additions or changes are necessary for Clause 15. It is noted that
FIDIC 2017 has been enhanced from previous versions with more detail to improve process
clarity and transparency.
1.14 Clause 16: Suspension and Termination by Contractor
Clause 16 defines the process to follow should the Engineer or Employer fail to carry out their
obligations under the Contract. No additions or changes are necessary for Clause 15. As with
Clause 15, Clause 16 has also been enhanced in FIDIC 2017.
1.15 Clause 17: Care of the Works and Indemnities
Clause 17 defines responsibility and liability for the works. No additions or changes are
necessary for Clause 17. It is noted that Clause 17 has been renamed from Risk and
Responsibility in previous versions and re-ordered to address difficulties experienced by
users.
1.16 Clause 18: Exceptional Events
Clause 18 covers circumstances that are beyond a Party’s control. No additions or changes
are necessary for Clause 18. Note that Clause 18 replaces Clause 19 Force Majeure in
previous versions. The change in title and sequence in the Contract is to achieve consistency
between the updated versions and other FIDIC documents.
1.17 Clause 19: Insurance
Clause 19 defines responsibilities associated with insurance cover. It is noted that Clause 19
by way of sequence was Clause 18 in previous versions of FIDIC.
Sub-clause 19.2 Insurance to be Provided by the Contractor specifies the various insurance
covers the Contractor shall provide. Within the Sub-clause, sub-heading 19.2.5 Injury to
Employees needs to include the following additional condition;
It shall be mandatory for the Contractor to place the insurance for ‘Accident or Injury
to Workmen’ with any Insurance Company in Bhutan.
1.18 Clause 20: Employers and Contractors Claims
Clause 20 deals with claims. No additions or changes are necessary for Clause 20. It is noted
however that previous versions of FIDIC also included Disputes in Clause 20. Disputes are
now provided for in the subsequent Clause 21. This has been done to remove the perception
that Claims automatically progress to Disputes. Further the process for Contractor and
Employers Claims are now dealt with in the same way.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex A Particular Conditions of Contract 50
1.19 Clause 21: Disputes and Arbitration
Clause 21 deals the process for addressing disputes. As noted above this is a new Clause
having been separated from Clause 20 in previous versions
For consistency there are a couple of incidences where time allowances need to be adjusted.
Firstly, in the first paragraph Sub-clause 21.1 Constitution of the DAAB from 28 days to 30
days as follows with change highlighted in bold.
Disputes shall be decided by a DAAB (Disputes Avoidance/Adjudication Board) in
accordance with Sub-clause 21.1 [Obtaining DAAB’s Decision]. The Parties shall
jointly appoint the member(s) of the DAAB within the time stated in the Contract Data
(if not stated 30 days) after the date the Contractor received the Letter of Acceptance.
Then, in the first paragraph Sub-clause 21.2 Failure to Appoint DAAB Members change sub-
point (c) from 42 days to 30 days as follows with change highlighted in bold
(a) [unchanged] (b) [unchanged] (c) the Parties fail to agree the appointment of a replacement within 30 days after
the date on which the sole member or one of the three members declines to act or is unable to act as a result of death, illness, resignation or termination of appointment; or.
(d) [unchanged] Sub-clause 21.6 Arbitration deals with situation where there is dissatisfaction or non-compliance with a DAAB decision and matters proceed to arbitration. The first paragraph of Sub-clause 21.6 needs to be amended by replacing the reference to “international arbitration” as follows with change highlighted in bold. Unless settled amicably, and subject to Sub-Clause 3.7.5 [Dissatisfaction with Engineers
Determination], Sub-Clause 21.4.4 [Dissatisfaction with DAAB’s Decision], Sub-Clause 21.7
[Failure to Comply with DAAB’s Decision] and Sub-Clause 21.8 [No DAAB in Place], any
Dispute in respect of which the DAAB’s decision (if any) has not become final and binding
shall be finally settled by the Arbitral Tribunal of Bhutan under the Alternate Dispute
Resolution Act of Bhutan.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex A Particular Conditions of Contract 51
1.20 Particular Conditions - Part A: Contract Data
Contract Data [ All italicized text and any enclosing square brackets is for use in preparing the form and should be deleted from the final product.]
[Note: bold figures reflect Usual International practice] Conditions Sub-
clause Data
Employer’s name and address 1.1.31 & 1.3
______________________________
______________________________ ______________________________ Engineers name and address 1.1.35 &
1.3 ______________________________
______________________________ ______________________________ Bank’s name ______________________________ Borrowers name ______________________________ Time for Completion 1.1.84 _______days Defects Notification Period (DNP) 1.1.27 365 days Electronic transmission systems 1.3 ______________________________ Governing Law 1.4 ______________________________ Ruling language 1.4 English Language for communications 1.4 English Time for access to the Site 2.1 _____ days after Commencement Date Engineer's Duties and Authority 3.2 Variations resulting in an increase of the
Accepted Contract Amount in excess of ____% shall require approval of the Employer.
Performance Security 4.2 The performance security will be in the
form of a _____ in the amount of ____% 5-10% of the Accepted Contract Amount. [Insert either one of “demand guarantee” or “performance bond” and percentage of Accepted Contract Amount]
Normal working hours 6.5 ______________________________
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex A Particular Conditions of Contract 52
Conditions Sub-clause
Data
Delay damages for the Works 8.8 & 14.15(c)
_____ % of the Contract Price per day.
Maximum amount of delay damages
8.8 _____ % of the final Contract Price [10%]
Adjustments for Changes in Cost 13.7 Period “n” applicable to the adjustment
multiplier “Pn”: 3 [Insert the period if different from one (1) month]
Advance for Mobilization 14.2 ______ %, Percentage of the Accepted
Contract Amount [0-5%]
Advance for Constructional Plant 14.2 ______ %, Percentage of the Accepted
Contract Amount [0-10%] Repayment amortization rate of advance payment
14.2.3 ______ %
Percentage of Retention 14.3 (iii) ______ % Limit of Retention Money 14.3 (iii) ____ % of the Accepted Contract
Amount [5%] Plant and Materials 14.5(b)(i) Plant and Materials for payment when
shipped en route to the Site 14.5(c)(i) Plant and Materials for payment when
delivered to the Site Minimum Amount of Interim Payment Certificates (IPCs)
14.6.2 1% of the Accepted Contract Amount
Maximum total liability of the Contractor to the Employer
17 [Select one of the two options below as appropriate] The product of ______ [insert a multiplier less or greater than one] times the Accepted Contract [or] ____ [Insert amount of the maximum total liability]
Periods for submission of insurance
[Insert period for submission of evidence of insurance and policy. Period may be from 14 days to 28 days]
evidence of insurance 19.1 _______days relevant policies 19.1 _______days
Maximum amount of deductibles for insurance of the Employer’s risks
19.1 [Insert maximum amount of deductibles]
Minimum amount of third party insurance
19.2.4 [Insert amount of third party insurance]
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex A Particular Conditions of Contract 53
Conditions Sub-clause
Data
Date by which the DAAB shall be appointed
21.1 28 days after the Commencement Date
The DAAB shall be comprised of 21.1 Three (3) members Failure to Appoint DAAB Members
21.2 Appointment (if not agreed) to be made by Chief Justice, Thimphu High Court
1.21 Schedules relating to Particular Conditions to be used in Tender
Documents
SCHEDULE 1: Table of adjustment data SCHEDULE 2: Liquidated Damages for Delay
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex A Particular Conditions of Contract 54
SCHEDULE 1
Table of adjustment data
Coefficients to be used in the Sub-Clause 13.8 “Adjustments for Changes in Cost”
Coefficient Value Index
A …… Non-adjustable portion
B …… Labour
C …… Cement
D …… Steel
E …… All commodities
F …… Fuel and lubricants
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex A Particular Conditions of Contract 55
SCHEDULE 2
Liquidated Damages for Delay
Should the Contractor fail to complete the separable portions of the Work identified below or
to complete the whole of the Work within the periods and dates specified under the Contract,
the Contractor shall pay to the Employer as fixed liquidated damages the sums shown below
for any calendar day or a part of a calendar day of delay under the Contract.
If the liquidated damages are levied on any items of work on account of delay in some
Milestone and if, the Contractor achieves the next Milestone within specified time, the
liquidated damages already levied for that item of work shall be refunded.
Milestone No.
Description Time for
completion (days)
Amount of Liquidated damages per day
1 …… xx Ngultrum …. per day subject to a
maximum of. …
2 …… yy
3 …… zz
… …… …
… Completion of the Works as a whole
---
Annex B Documents to be submitted by Bidders
Annex B: DOCUMENTS TO BE SUBMITTED BY B IDDERS
1 LETTER OF TENDER
2 SCHEDULE OF COST INDEXATION
3 TABLE OF ADJUSTMENT DATA
4 B ILL OF QUANTITIES
5 DAYWORK SCHEDULE
6 SUMMARY OF SPECIFIED PROVISIONS
7 GRAND SUMMARY
8 TECHNICAL PROPOSAL
9 S ITE ORGANISATION
10 METHOD STATEMENTS
11 MOBILIZATION SCHEDULE
12 CONSTRUCTION SCHEDULE
13 ES MANAGEMENT STRATEGIES
14 H&S MANAGEMENT STRATEGIES
15 CODE OF CONDUCT FOR CONTRACTORS
16 EQUIPMENT
17 CONTRACTOR ’S REPRESENTATIVE
18 B IDDER ’S QUALIFICATIONS FOLLOWING PREQUALIFICATION
19 B IDDER INFORMATION FORM
20 B IDDER ’S JV INFORMATION FORM
21 H ISTORICAL CONTRACT NON-PERFORMANCE
22 ENVIRONMENTAL AND SOCIAL PERFORMANCE
23 F INANCIAL S ITUATION AND PERFORMANCE
24 AVERAGE ANNUAL CONSTRUCTION TURNOVER
25 CURRENT CONTRACT COMMITMENTS
26 FORM OF B ID SECURITY – DEMAND GUARANTEE
27 FORM OF B ID SECURING DECLARATION
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 57
Letter of Tender
INSTRUCTIONS TO BIDDERS: DELETE THIS BOX ONCE YOU HAVE COMPLETED THE
DOCUMENT
The Bidder must prepare this Letter of Tender on stationery with its letterhead clearly showing the
Bidder’s complete name and business address.
Note: All italicized text in is to help Bidders in preparing this form.
Date of this Bid submission: [insert date (as day, month and year) of Bid submission]
Request for Bid (RFB) No.: [insert identification]
Alternative No.: [insert identification No if this is a Bid for an alternative]
To: [insert complete name of Employer]
We, the undersigned, declare that:
(a) No reservations: We have examined and have no reservations to the bidding document, in accordance with Instructions To Bidders (ITB);
(b) Eligibility: We meet the eligibility requirements and have no conflict of interest in accordance with ITB;
(c) Bid-Securing Declaration: We have not been suspended nor declared ineligible by the Employer based on execution of a Bid-Securing or Proposal-Securing Declaration in the Employer’s country in accordance with ITB;
(d) Conformity: We offer to execute in conformity with the bidding document and in accordance with the construction schedule the following Works: [insert a brief description of the Works];
(e) Bid Price: The total price of our Bid, excluding any discounts offered in item (f) below is: [Insert one of the options below as appropriate]
Option 1, in case of one lot: Total price is: [insert the total price of the Bid in words
and figures, indicating the various amounts and the respective currencies];
Or
Option 2, in case of multiple lots: (a) Total price of each lot [insert the total price of
each lot in words and figures, indicating the various amounts and the respective
currencies]; and (b) Total price of all lots (sum of all lots) [insert the total price of all lots
in words and figures, indicating the various amounts and the respective currencies];
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 58
(f) Discounts: The discounts offered and the methodology for their application are:
(i) The discounts offered are: [Specify in detail each discount offered.]
(ii) The exact method of calculations to determine the net price after application of
discounts is shown below: [Specify in detail the method that shall be used to apply
the discounts];
(g) Bid Validity Period: Our Bid shall be valid for a period specified in BDS (or as amended if applicable) from the date fixed for the Bid submission deadline specified in BDS (or as amended if applicable), and it shall remain binding upon us and may be accepted at any time before the expiration of that period;
(h) Performance Security: If our Bid is accepted, we commit to obtain a Performance Security [and an Environmental and Social (ES) Performance Security, Delete if not applicable] in the forms in accordance with the bidding document;
(i) One Bid Per Bidder: We are not submitting any other Bid(s) as an individual Bidder, and we are not participating in any other Bid(s) as a Joint Venture member or as a subcontractor, and meet the requirements of ITB, other than alternative Bids submitted in accordance with ITB;
(j) Suspension and Debarment: We, along with any of our subcontractors, suppliers, consultants, manufacturers, or service providers for any part of the contract, are not subject to, and not controlled by any entity or individual that is subject to, a temporary suspension or a debarment imposed by the Employer’s country. Further, we are not ineligible under the Employer’s country laws or official regulations or pursuant to a decision of the United Nations Security Council;
(k) State-owned enterprise or institution: [select the appropriate option and delete the other] [We are not a state-owned enterprise or institution] / [We are a state-owned enterprise or institution but meet the requirements of ITB];
(l) Commissions, gratuities, fees: We have paid, or will pay the following commissions, gratuities, or fees with respect to the Bidding process or execution of the Contract: [insert complete name of each Recipient, its full address, the reason for which each commission or gratuity was paid and the amount and currency of each such commission or gratuity]
Name of Recipient Address Reason Amount
(If none has been paid or is to be paid, indicate “none.”)
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 59
(m) Binding Contract: We understand that this Bid, together with your written acceptance thereof included in your Letter of Acceptance, shall constitute a binding contract between us, until a formal contract is prepared and executed;
(n) Not Bound to Accept: We understand that you are not bound to accept the lowest evaluated cost Bid, the Most Advantageous Bid or any other Bid that you may receive;
(o) Fraud and Corruption: We hereby certify that we have taken steps to ensure that no person acting for us or on our behalf engages in any type of Fraud and Corruption;
(p) Potential DAAB Members: We hereby propose the following three persons, whose curriculum vitae are attached, as potential Dispute Avoidance/Adjudication Board (DAAB) members (Refer FIDIC Clause 21.1):
Name Address
1. ……......
2. ………..
3. ………
Name of the Bidder:*[insert complete name of person signing the Bid]
Name of the person duly authorized to sign the Bid on behalf of the Bidder:**[insert
complete name of person duly authorized to sign the Bid]
Title of the person signing the Bid: [insert complete title of the person signing the Bid]
Signature of the person named above: [insert signature of person whose name and capacity
are shown above]
Date signed [insert date of signing] day of [insert month], [insert year]
Date signed ________________________________ day of _______________________, __
*: In the case of the Bid submitted by joint venture specify the name of the Joint Venture as
Bidder
**: Person signing the Bid shall have the power of attorney given by the Bidder to be attached
with the Bid
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 60
Schedule of Cost Indexation
[Note to Employer: It is recommended that the Employer is advised by a professional with
experience in construction costs and the inflationary effect on construction costs when
preparing the contents of the Schedule of Cost Indexation. In the case of very large and/or
complex works contracts, it may be necessary to specify several families of price adjustment
formulae corresponding to the different works involved]
[The formulae for price adjustment shall be of the following general type:]
Pn= a + b Ln / Lo + c En/ Eo + d Mn/Mo + ........
where:
“Pn” is the adjustment multiplier to be applied to the estimated contract value in the relevant
currency of the work carried out in period “n”, this period being a month unless otherwise
stated in the Contract Data;
“a” is a fixed coefficient, stated in the relevant table of adjustment data, representing the non-
adjustable portion in contractual payments;
“b”, “c”, “d”, ... are coefficients representing the estimated proportion of each cost element
related to the execution of the Works as stated in the relevant table of adjustment data; such
tabulated cost elements may be indicative of resources such as labour, equipment and
materials;
“Ln”, “En”, “Mn”, ... are the current cost indices or reference prices for period “n”, expressed in
the relevant currency of payment, each of which is applicable to the relevant tabulated cost
element on the date 49 days prior to the last day of the period (to which the particular Payment
Certificate relates); and
“Lo”, “Eo”, “Mo”, ... are the base cost indices or reference prices, expressed in the relevant
currency of payment, each of which is applicable to the relevant tabulated cost element on the
Base Date.
The cost indices or reference prices stated in the Table of Adjustment Data shall be used. If
their source is in doubt, it shall be determined by the Engineer. For this purpose, reference
shall be made to the values of the indices at stated dates (quoted in the fourth and fifth columns
respectively of the table).
If the currency in which the Contract price is expressed is different from the currency of the
country of origin of the indices, a correction factor will be applied to avoid incorrect adjustments
of the Contract price. The correction factor shall be: Z0 / Z1, where,
Z0 = the number of units of currency of the origin of the indices which equal to one unit of the
currency of the Contract Price on the Base date, and
Z1 = the number of units of currency of the origin of the indices which equal to one unit of
the currency of the Contract Price on the Date of Adjustment.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 61
Table of Adjustment Data
[In Tables A, B, and C, below, the Bidder shall; (a) indicate its amount of local currency
payment, (b) indicate its proposed source and base values of indices for the different foreign
currency elements of cost, (c) derive its proposed weightings for local and foreign currency
payment, and (d) list the exchange rates used in the currency conversion.
In the case of very large and/or complex works contracts, it may be necessary to specify
several families of price adjustment formulae corresponding to the different works involved.]
Table A. Local Currency
Index
code*
Index
description*
Source of
index*
Base value
and date*
Bidder’s
related
currency
amount
Bidder’s
proposed
weighting
Nonadjustable — — — a: *
b: *
c: *
d: *
e: *
Total 1.00
[* To be entered by the Employer. Whereas “a” should a fixed percentage, b, c, d and e should
specify a range of values and the Bidder will be required to specify a value within the range
such that the total weighting = 1.00].
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 62
Table B. Foreign Currency (FC)
State type: ....................... [If the Bidder is allowed to receive payment in foreign currencies
this table shall be used. If Bidder wishes to quote in more than one foreign currency (up to
three currencies permitted) then this table should be repeated for each foreign currency.]
Index
code
Index
description
Source of
index
Base
value
and date
Bidder’s
related
source
currency in
type/amoun
t
Equivalent
in FC1
Bidder’s
proposed
weighting
Nonadjustable — — — a: ________*
b: ________*
c: ________*
d: ________*
e: ________*
Total 1.00
[* To be entered by the Employer. Whereas “a” should a fixed percentage, b, c, d and e should
specify a range of values and the Bidder will be required to specify a value within the range
such that the total weighting = 1.00]
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 63
Table C. Summary of Payment Currencies
Table: Alternative A
For ……………………….[insert name of Section of the Works]
Name of
payment
currency
A
Amount of
currency
B
Rate of
exchange
(local currency
per unit of
foreign)
C
Local currency
equivalent
C = A x B
D
Percentage of
Total Bid Price
(TBP)
100xC
TBP
Local currency
1.00
Foreign
currency #1
Foreign
currency #2
Foreign
currency #
Total Bid Price
[To be entered
by the Employer]
[To be entered by
the Employer]
Provisional
sums
expressed in
local currency
TOTAL BID
PRICE
(including
provisional
sum)
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 64
Table: Alternative B
To be used only with Alternative B Prices directly quoted in the currencies of
payment. (refer to ITB)
Summary of currencies of the Bid for ___________ [insert name of Section of the Works]
Name of currency Amounts payable
Local currency:
Foreign currency #1:
Foreign currency #2:
Foreign currency #3:
Provisional sums expressed in local currency
____________________________________
[To be entered by the Employer]
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 65
Bill of Quantities
Bill No. 1: General Items
Item no. Description Unit Quantity Rate Amount
Total for Bill No. 1
(carried forward to Summary, p. )
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 66
Bill No. 2: Earthworks
Item no. Description Unit Quantity Rate Amount
Total for Bill No. 2
(carried forward to Summary, p. )
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 67
Bill No. 3: Culverts and Bridges
Item no. Description Unit Quantity Rate Amount
Total for Bill No. 3
(carried forward to Summary, p. )
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 68
Daywork Schedule
General
Dayworks are subject to FIDIC 2017 Red Book Sub-Clause 13.5 of the General Conditions. Work shall not be executed on a daywork basis except by written order of the Engineer. Bidders shall enter basic rates for daywork items in the Schedules, which rates shall apply to any quantity of daywork ordered by the Engineer. Nominal quantities have been indicated against each item of daywork, and the extended total for Daywork shall be carried forward as a Provisional Sum to the Summary Total Bid Price. Unless otherwise adjusted, payments for daywork shall be subject to price adjustment in accordance with the provisions in the Conditions of Contract.
Daywork Labour
1. In calculating payments due to the Contractor for the execution of daywork, the hours for labour will be reckoned from the time of arrival of the labour at the job site to execute the particular item of daywork to the time of return to the original place of departure, but excluding meal breaks and rest periods. Only the time of classes of labour directly doing work ordered by the Engineer and for which they are competent to perform will be measured. The time of gangers (charge hands) actually doing work with the gangs will also be measured but not the time of foremen or other supervisory personnel.
2. The Contractor shall be entitled to payment in respect of the total time that labour is employed on daywork, calculated at the basic rates entered by the Contractor in the Schedule of Daywork Rates: 1. Labour, together with an additional percentage payment on basic rates representing the Contractor’s profit, overheads, etc., as described below:
(a) The basic rates for labour shall cover all direct costs to the Contractor, including
(but not limited to) the amount of wages paid to such labour, transportation time,
overtime, subsistence allowances, and any sums paid to or on behalf of such
labour for social benefits in accordance with [country of Borrower] law. The basic
rates will be payable in local currency only.
(b) The additional percentage payment to be quoted by the bidder and applied to costs
incurred under (a) above shall be deemed to cover the Contractor’s profit,
overheads, superintendence, liabilities, and insurances and allowances to labour,
timekeeping, and clerical and office work, the use of consumable stores, water,
lighting, and power; the use and repair of stagings, scaffolding, workshops, and
stores, portable power tools, manual plant, and tools; supervision by the
Contractor’s staff, foremen, and other supervisory personnel; and charges
incidental to the foregoing. Payments under this item shall be made in the following
currency proportions:
(i) foreign: percent (to be stated by bidder).5
(ii) local: percent (to be stated by bidder).
5 The bidder shall state the percentage in a common foreign currency equivalent required for payment and the exchange rates and official sources used.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 69
Daywork Materials
1. The Contractor shall be entitled to payment in respect of materials used for daywork (except for materials for which the cost is included in the percentage addition to labour costs as detailed heretofore), at the basic rates entered by the Contractor in the Schedule of Daywork Rates: 2. Materials, together with an additional percentage payment on the basic rates to cover overhead charges and profit, as follows:
(a) the basic rates for materials shall be calculated on the basis of the invoiced price,
freight, insurance, handling expenses, damage, losses, etc., and shall provide for
delivery to store for stockpiling at the Site. The basic rates shall be stated in local
currency, but payment will be made in the currency or currencies expended upon
presentation of supporting documentation.
(b) the additional percentage payment shall be quoted by the bidder and applied to
the equivalent local currency payments made under (a) above. Payments under
this item will be made in the following currency proportions:
(i) foreign: percent (to be stated by the bidder);6
(ii) local: percent (to be stated by the bidder);
(c) the cost of hauling materials for use on work ordered to be carried out as daywork
from the store or stockpile on the Site to the place where it is to be used will be
paid in accordance with the terms for Labour and Construction in this schedule.
Daywork Contractor’s Equipment
1. The Contractor shall be entitled to payments in respect of Contractor’s Equipment already on Site and employed on daywork at the basic rental rates entered by the Contractor in the Schedule of Daywork Rates: 3. Contractor’s Equipment. Said rates shall be deemed to include due and complete allowance for depreciation, interest, indemnity, and insurance, repairs, maintenance, supplies, fuel, lubricants, and other consumables, and all overhead, profit, and administrative costs related to the use of such equipment. The cost of drivers, operators, and assistants will be paid for separately as described under the section on Daywork Labour. [Note to the Employer: An alternative, sometimes adopted for administrative convenience, is to include the cost of drivers, operators, and assistants in the basic rates for Contractor’s Equipment. The last sentence of this paragraph should then be modified accordingly.]
2. In calculating the payment due to the Contractor for Contractor’s Equipment employed on daywork, only the actual number of working hours will be eligible for payment, except that where applicable and agreed with the Engineer, the travelling time from the part of the Site where the Contractor’s Equipment was located when ordered by the Engineer to be employed on daywork and the time for return journey thereto shall be included for payment.
6 The bidder shall state the percentage in a single foreign currency equivalent and the exchange rates and official sources used.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 70
3. The basic rental rates for Contractor’s Equipment employed on daywork shall be stated in
local currency, but payments to the Contractor will be made in currency proportions, as follows:
(a) foreign: percent (to be stated by the bidder).7
(b) local: percent (to be stated by the bidder).
7 The bidder shall state the percentage in a single foreign currency equivalent and the exchange rates and official sources used.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 71
Schedule of Daywork Rates: 1. Labour
Item no. Description Unit Nominal
quantity
Rate Extended
amount
Subtotal
D122 Allow percenta of Subtotal for Contractor’s overhead,
profit, etc., in accordance with paragraph 3 (b) above.
Total for Daywork: Labour
(carried forward to Daywork Summary, p. )
a. To be entered by the Bidder.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 72
Schedule of Daywork Rates: 2. Materials
Item no. Description Unit Nominal
quantity
Rate Extended
amount
Subtotal
Allow percent of Subtotal for Contractor’s overhead,
profit, etc., in accordance with paragraph 4 (b) above.
Total for Daywork: Materials
(carried forward to Daywork Summary, p. )
a. To be entered by the Bidder.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 73
Schedule of Daywork Rates: 3. Contractor’s Equipment
Item no. Description Nominal
quantity
(hours)
Basic hourly
rental rate
Extended
amount
Allow percenta of Subtotal for
Contractor’s overhead, profit, etc., in
accordance with paragraph 5 above.
Total for Daywork: Contractor’s Equipment
(carried forward to Daywork Summary, p. )
a. To be entered by the Bidder.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 74
Daywork Summary
Amounta
( )
%
Foreign
1. Total for Daywork: Labour
2. Total for Daywork: Materials
3. Total for Daywork: Contractor’s Equipment
Total for Daywork (Provisional Sum)
(carried forward to Bid Summary, p. )
a. The Employer should insert local currency unit.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 75
Summary of Specified Provisional Sums
Bill no. Item no. Description Amount
1
2
3
4
[To be entered by the Employer] provisional sums for
the Employer’s portion of DAAB costs
[To be entered by the Employer; Delete if not
applicable:] provisional sums for additional ES
outcomes.
etc.
Total for Specified Provisional Sums
(carried forward to Grand Summary (B), p. )
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 76
Grand Summary
Contract Name:
Contract No.:
General Summary Page Amount
Bill No. 1:
Bill No. 2:
Bill No. 3:
—etc.—
Subtotal of Bills (A)
Total for Daywork (Provisional Sum)* (B)
Specified Provisional Sums not included in subtotal of billsii (C) [sum]
Total of Bills Plus Provisional Sums (A + B + C) i (D)
Add Provisional Sum for Contingency Allowance (if any) ii (E) [sum]
Bid Price (D + E) (Carried forward to Letter of Tender) (F)
i) All Provisional Sums are to be expended in whole or in part at the direction and discretion of the
Engineer in accordance with Sub-Clauses 13.4 and 13.5 of the General Conditions (refer: 2017
FIDIC Red Book).
ii) To be entered by the Employer.
* For evaluation purposes, Provisional Sum, other than Daywork will be excluded
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 77
Technical Proposal
- Site Organization
- Method Statement
- Mobilization Schedule
- Construction Schedule
- Environmental and Social (ES) Management Strategies and
Implementation Plans (ES – MSIP).
- Health and Safety (HS) Management Strategies and
Implementation Plans (HS – MSIP)
- Code of Conduct for Contractor’s Personnel (ES)
- Equipment
- Key Personnel Schedule
- Others
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 78
Site Organization
[insert Site Organization information]
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 79
Method Statement
[insert Method Statement]
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 80
Mobilization Schedule
[insert Mobilization Schedule]
In accordance with the General Conditions, Sub-Clause 4.1 (refer: 2017 FIDIC Red Book), the
Contractor shall not carry out mobilization to Site unless the Engineer gives consent that
appropriate measures are in place to address environmental and social risks and impacts,
which as a minimum shall include applying the Management Strategies and Implementation
Plans (MSIPs) and Code of Conduct for Contractor’s Personnel, submitted as part of the Bid
and agreed as part of the Contract.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 81
Construction Schedule
[insert Construction Schedule]
The construction schedule shall include the following key milestones:
• No-objection to the Contractor’s MSIPs, which collectively form the C_ESMP, in accordance with the General Conditions of Contract Sub-Clause 4.1 (refer: 2017 FIDIC Red Book).
• Constitution of the DAAB
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 82
ES Management Strategies and Implementation Plans
(ES-MSIP)
The Bidder shall submit comprehensive and concise Environmental and Social Management
Strategies and Implementation Plans (ES-MSIP) as required by ITB. These strategies and
plans shall describe in detail the actions, materials, equipment, management processes etc.
that will be implemented by the Contractor, and its subcontractors.
In developing these strategies and plans, the Bidder shall have regard to the ES provisions of
the contract including those as may be more fully described in the Works Requirements.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 83
H&S Management Strategies and Implementation Plans
(HS-MSIP)
The Bidder shall submit comprehensive and concise Health and Safety Management
Strategies and Implementation Plans (ES-MSIP) as required by ITT. These strategies and
plans shall describe in detail the processes, actions and management processes etc. that will
be implemented by the Contractor, and its subcontractors.
In developing these strategies and plans, the Bidder shall have regard to the H&S provisions
of the contract including those as may be more fully described in the Works Requirements.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 84
Code of Conduct for Contractor’s Personnel (ES) Form
CODE OF CONDUCT FOR CONTRACTOR’S PERSONNEL
We are the Contractor, [enter name of Contractor]. We have signed a contract with [enter
name of Employer] for [enter description of the Works]. These Works will be carried out at
[enter the Site and other locations where the Works will be carried out]. Our contract requires
us to implement measures to address environmental and social risks related to the Works,
including the risks of sexual exploitation and assault and gender-based violence.
This Code of Conduct is part of our measures to deal with environmental and social risks
related to the Works. It applies to all our staff, labourers and other employees at the Works
Site or other places where the Works are being carried out. It also applies to the personnel of
each subcontractor and any other personnel assisting us in the execution of the Works. All
such persons are referred to as “Contractor’s Personnel” and are subject to this Code of
Conduct.
This Code of Conduct identifies the behavior that we require from all Contractor’s Personnel.
Our workplace is an environment where unsafe, offensive, abusive or violent behavior will not
be tolerated and where all persons should feel comfortable raising issues or concerns without
fear of retaliation.
Note to the Employer:
The following minimum requirements shall not be modified. The Employer may
add additional requirements to address identified issues, informed by relevant
environmental and social assessment.
The types of issues identified could include risks associated with: labor influx, spread
of communicable diseases, and Sexual Exploitation and Assault (SEA) etc.
Delete this Box prior to issuance of the bidding documents.
Note to the Bidder:
The minimum content of the Code of Conduct form as set out by the Employer
shall not be substantially modified. However, the Bidder may add requirements as
appropriate, including to take into account Contract-specific issues/risks.
The Bidder shall initial and submit the Code of Conduct form as part of its bid.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 85
REQUIRED CONDUCT
Contractor’s Personnel shall:
1. carry out his/her duties competently and diligently;
2. comply with this Code of Conduct and all applicable laws, regulations and other requirements, including requirements to protect the health, safety and well-being of other Contractor’s Personnel and any other person;
3. maintain a safe working environment including by:
a. ensuring that workplaces, machinery, equipment and processes under each person’s control are safe and without risk to health;
b. wearing required personal protective equipment;
c. using appropriate measures relating to chemical, physical and biological substances and agents; and
d. following applicable emergency operating procedures.
4. report work situations that he/she believes are not safe or healthy and remove himself/herself from a work situation which he/she reasonably believes presents an imminent and serious danger to his/her life or health;
5. treat other people with respect, and not discriminate against specific groups such as women, people with disabilities, migrant workers or children;
6. not engage in any form of sexual harassment including unwelcome sexual advances, requests for sexual favors, and other unwanted verbal or physical conduct of a sexual nature with other Contractor’s or Employer’s Personnel;
7. not engage in Sexual Exploitation, which means any actual or attempted abuse of position of vulnerability, differential power or trust, for sexual purposes, including, but not limited to, profiting monetarily, socially or politically from the sexual exploitation of another.
8. not engage in Sexual Assault, which means sexual activity with another person who does not consent. It is a violation of bodily integrity and sexual autonomy and is broader than narrower conceptions of “rape”, especially because (a) it may be committed by other means than force or violence, and (b) it does not necessarily entail penetration;
9. not engage in any form of sexual activity with individuals under the age of 18, except in case of pre-existing marriage;
10. complete relevant training courses that will be provided related to the environmental and social aspects of the Contract, including on health and safety matters, and Sexual Exploitation and Assault (SEA);
11. report violations of this Code of Conduct; and
12. not retaliate against any person who reports violations of this Code of Conduct, whether to us or the Employer, or who makes use of the [Project Grievance [Redress] Mechanism].
RAISING CONCERNS
If any person observes behavior that he/she believes may represent a violation of this Code of Conduct, or that otherwise concerns him/her, he/she should raise the issue promptly. This can be done in either of the following ways:
1. Contact [enter name of the Contractor’s Social Expert with relevant experience in handling gender-based violence, or if such person is not required under the Contract, another individual designated by the Contractor to handle these matters] in writing at this address [ ] or by telephone at [ ] or in person at [ ]; or
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 86
2. Call [ ] to reach the Contractor’s hotline (if any) and leave a message.
The person’s identity will be kept confidential, unless reporting of allegations is mandated by the country law. Anonymous complaints or allegations may also be submitted and will be given all due and appropriate consideration. We take seriously all reports of possible misconduct and will investigate and take appropriate action. We will provide warm referrals to service providers that may help support the person who experienced the alleged incident, as appropriate. There will be no retaliation against any person who raises a concern in good faith about any behavior prohibited by this Code of Conduct. Such retaliation would be a violation of this Code of Conduct.
CONSEQUENCES OF VIOLATING THE CODE OF CONDUCT
Any violation of this Code of Conduct by Contractor’s Personnel may result in serious consequences, up to and including termination and possible referral to legal authorities.
FOR CONTRACTOR’S PERSONNEL:
I have received a copy of this Code of Conduct written in a language that I comprehend. I
understand that if I have any questions about this Code of Conduct, I can contact [enter name
of Contractor’s contact person with relevant experience in handling gender-based violence]
requesting an explanation.
Name of Contractor’s Personnel: [insert name]
Signature: __________________________________________________________
Date: (day month year): _______________________________________________
Countersignature of authorized representative of the Contractor:
Signature: ________________________________________________________
Date: (day month year): ______________________________________________
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 87
Equipment
The Bidder shall provide adequate information to demonstrate clearly that it has the capability
to meet the requirements for the key equipment. A separate Form shall be prepared for each
item of equipment listed, or for alternative equipment proposed by the Bidder.
Bidder’s Name: Date:
JV Member’s Name_________________________
RFT No. and title: ___________________________ Page __ _of__ __pages
Item of equipment
Equipment
information
Name of manufacturer
Model and power rating
Capacity
Year of manufacture
Current
status
Current location
Details of current commitments
Source Indicate source of the equipment
Owned Rented Leased Specially manufactured
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 88
Omit the following information for equipment owned by the Bidder.
Owner Name of owner
Address of owner
Telephone Contact name and title
Fax Telex
Agreements Details of rental / lease / manufacture agreements specific to the project
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 89
Contractor’s Representative and Key Personnel
Schedule
Bidders should provide the names and details of the suitably qualified Contractor’s
Representative and Key Personnel to perform the Contract. The data on their experience should
be supplied using the Form PER-2 below for each candidate.
Bidder’s Name: Date:
JV Member’s Name_________________________
RFT No. and title: ___________________________ Page __ _of__ __pages
Contractor’ Representative and Key Personnel
1. Title of position: Contractor’s Representative
Name of candidate:
Duration of
appointment:
[insert the whole period (start and end dates) for which this position will
be engaged]
Time
commitment: for
this position:
[insert the number of days/week/months/ that has been scheduled for
this position]
Expected time
schedule for this
position:
[insert the expected time schedule for this position (e.g. attach high
level Gantt chart]
2. Title of position: [Environmental Specialist]
Name of candidate:
Duration of
appointment:
[insert the whole period (start and end dates) for which this position will
be engaged]
Time
commitment: for
this position:
[insert the number of days/week/months/ that has been scheduled for
this position]
Expected time
schedule for this
position:
[insert the expected time schedule for this position (e.g. attach high
level Gantt chart]
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 90
3.
Title of position: [Health and Safety Specialist]
Name of candidate:
Duration of
appointment:
[insert the whole period (start and end dates) for which this position will
be engaged]
Time
commitment: for
this position:
[insert the number of days/week/months/ that has been scheduled for
this position]
Expected time
schedule for this
position:
[insert the expected time schedule for this position (e.g. attach high
level Gantt chart]
4. Title of position: [Social Specialist]
Name of candidate:
Duration of
appointment:
[insert the whole period (start and end dates) for which this position will
be engaged]
Time
commitment: for
this position:
[insert the number of days/week/months/ that has been scheduled for
this position]
Expected time
schedule for this
position:
[insert the expected time schedule for this position (e.g. attach high
level Gantt chart]
5. Title of position: Gender Based Violence Expert
Where a Project SEA risks are assessed to be high, Key Personnel shall include a
gender-based violence expert with relevant experience in addressing sexual
exploitation and assault cases
Name of candidate
Duration of
appointment:
[insert the whole period (start and end dates) for which this position
will be engaged]
Time commitment: for
this position:
[insert the number of days/week/months/ that has been scheduled
for this position]
Expected time
schedule for this
position:
[insert the expected time schedule for this position (e.g. attach high
level Gantt chart]
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 91
6. Title of position: [insert title]
Name of candidate
Duration of
appointment:
[insert the whole period (start and end dates) for which this position will
be engaged]
Time
commitment: for
this position:
[insert the number of days/week/months/ that has been scheduled for
this position]
Expected time
schedule for this
position:
[insert the expected time schedule for this position (e.g. attach high
level Gantt chart]
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 92
Resume and Declaration for Contractor’s
Representative and Key Personnel
Bidder’s Name: Date:
JV Member’s Name_________________________
RFT No. and title: ___________________________ Page __ _of__ __pages
Position [#1]: [title of position from Form PER-1]
Personnel
information
Name:
Date of birth:
Address:
E-mail:
Professional qualifications:
Academic qualifications:
Language proficiency:[language and levels of speaking, reading and writing
skills]
Details Address of employer:
Telephone:
Fax:
Contact (manager / personnel
officer):
Job title:
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 93
Summarize professional experience in reverse chronological order. Indicate particular technical
and managerial experience relevant to the project.
Project Role Duration of
involvement Relevant experience
[main
project
details]
[role and
responsibilities on the
project]
[time in role] [describe the experience relevant to this
position]
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 94
Declaration
I, the undersigned [ insert either “Contractor’s Representative” or “Key Personnel” as
applicable], certify that to the best of my knowledge and belief, the information contained in
this Form PER-2 correctly describes myself, my qualifications and my experience.
I confirm that I am available as certified in the following table and throughout the expected
time schedule for this position as provided in the Bid:
Commitment Details
Commitment to duration of
contract:
[insert period (start and end dates) for which this
Contractor’s Representative or Key Personnel is
available to work on this contract]
Time commitment: [insert period (start and end dates) for which this
Contractor’s Representative or Key Personnel is
available to work on this contract]
I understand that any misrepresentation or omission in this Form may:
1. be taken into consideration during Bid evaluation;
2. result in my disqualification from participating in the Bid;
3. result in my dismissal from the contract.
Name of Contractor’s Representative or Key Personnel: [insert name]
Signature: __________________________________________________________
Date: (day month year): _______________________________________________
Countersignature of authorized representative of the Bidder:
Signature: ________________________________________________________
Date: (day month year): ______________________________________________
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 95
Bidder’s Qualification following Prequalification
The Bidder shall update the information given during the corresponding prequalification
exercise to demonstrate that he continues to meet the criteria used at the time of
prequalification regarding:
(a) Eligibility
(b) Pending Litigation
(c) Financial Situation
For this purpose, the Bidder shall use the relevant forms included in this Section.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 96
Bidder Information Form
Date: _________________
RFB No. and title: _________________
Page ______of _______________pages
Bidder's name
In case of Joint Venture (JV), name of each member:
Bidder's actual or intended country of registration:
[indicate country of Constitution]
Bidder's actual or intended year of incorporation:
Bidder's legal address [in country of registration]:
Bidder's authorized representative information
Name: _____________________________________
Address: ___________________________________
Telephone/Fax numbers: _______________________
E-mail address: ______________________________
1. Attached are copies of original documents of
Articles of Incorporation (or equivalent documents of constitution or association), and/or
documents of registration of the legal entity named above, in accordance with ITB.
In case of JV, letter of intent to form JV or JV agreement, in accordance with ITB.
In case of state-owned enterprise or institution, in accordance with ITB documents
establishing:
• Legal and financial autonomy
• Operation under commercial law
• Establishing that the Bidder is not under the supervision of the Employer 2. Included are the organizational chart, a list of Board of Directors, and the beneficial
ownership. [If required under BDS ITB, the successful Bidder shall provide additional
information on beneficial ownership, using the Beneficial Ownership Disclosure Form.]
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 97
Bidder's JV Information Form
(to be completed for each member of Bidder’s JV)
Date: _______________
RFB No. and title: ________________
Page ________ of ___________ pages
Bidder’s JV name:
JV member’s name:
JV member’s country of registration:
JV member’s year of constitution:
JV member’s legal address in country of constitution:
JV member’s authorized representative information
Name: ____________________________________
Address: __________________________________
Telephone/Fax numbers: _____________________
E-mail address: _____________________________
1. Attached are copies of original documents of
Articles of Incorporation (or equivalent documents of constitution or association), and/or
registration documents of the legal entity named above, in accordance with ITB.
In case of a state-owned enterprise or institution, documents establishing legal and financial
autonomy, operation in accordance with commercial law, and that they are not under the
supervision of the Employer, in accordance with ITB.
2. Included are the organizational chart, a list of Board of Directors, and the beneficial ownership. [If
required under BDS ITB, the successful Bidder shall provide additional information on beneficial
ownership for each JV member using the Beneficial Ownership Disclosure Form.]
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 98
Historical Contract Non-Performance, and Pending
Litigation
[This form should be used only if the information submitted at the time of
prequalification requires updating. The following table shall be filled in for the Bidder
and for JVs, each member of the Joint Venture]
Bidder’s Name: Date:
JV Member’s Name_________________________
RFT No. and title: ___________________________ Page __ _of__ __pages
Non-Performed Contracts in accordance with Evaluation and Qualification Criteria of the
Prequalification document
Contract non-performance did not occur since 1st January [insert year]
Contract(s) not performed since 1st January [insert year]
Year Non-
performed
portion of
contract
Contract Identification
Total Contract
Amount (current
value, currency,
exchange rate
and US$
equivalent)
[insert
year]
[insert amount
and percentage]
Contract Identification: [indicate complete contract
name/ number, and any other identification]
Name of Employer: [insert full name]
Address of Employer: [insert street/city/country]
Reason(s) for nonperformance: [indicate main
reason(s)]
[insert amount]
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 99
Pending Litigation, in accordance with Evaluation and Qualification Criteria
No pending litigation
Pending litigation
Year of
dispute
Amount in
dispute
(currency)
Contract Identification Total Contract
Amount
(currency), USD
Equivalent
(exchange rate)
Contract Identification: _________
Name of Employer: ____________
Address of Employer: __________
Matter in dispute: ______________
Party who initiated the dispute: ____
Status of dispute: ___________
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 100
Environmental and Social Performance Declaration
[This form should be used only if the information submitted at the time of
prequalification requires updating. The following table shall be filled in for the
Bidder, each member of a Joint Venture and each Specialized Subcontractor]
Bidder’s Name: Date:
JV Member’s Name_________________________
RFT No. and title: ___________________________ Page __ _of__ __pages
Environmental and Social Performance Declaration
in accordance with Qualification Criteria, and Requirements of the Prequalification document
No suspension or termination of contract: An employer has not suspended or terminated a
contract and/or called the performance security for a contract for reasons related to
Environmental and Social (ES) performance.
Declaration of suspension or termination of contract: The following contract(s) has/have
been suspended or terminated and/or Performance Security called by an employer(s) for
reasons related to Environmental and Social (ES) performance. Details are described below:
Year Suspended
or terminated
portion of
contract
Contract Identification
Total Contract
Amount (current
value, currency,
exchange rate
and US$
equivalent)
[insert
year]
[insert amount
and percentage]
Contract Identification: [indicate complete contract
name/ number, and any other identification]
Name of Employer: [insert full name]
Address of Employer: [insert street/city/country]
Reason(s) for suspension or termination: [indicate
main reason(s) e.g. gender-based violence; sexual
exploitation or assault breaches]
[insert amount]
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 101
[insert
year]
[insert amount
and percentage]
Contract Identification: [indicate complete contract
name/ number, and any other identification]
Name of Employer: [insert full name]
Address of Employer: [insert street/city/country]
Reason(s) for suspension or termination: [indicate
main reason(s)]
[insert amount]
… … [list all applicable contracts]
…
Performance Security called by an employer(s) for reasons related to ES performance
Year Contract Identification
Total Contract
Amount (current
value, currency,
exchange rate and
US$ equivalent)
[insert
year]
Contract Identification: [indicate complete contract name/ number, and
any other identification]
Name of Employer: [insert full name]
Address of Employer: [insert street/city/country]
Reason(s) for calling of performance security: [indicate main reason(s)
e.g. gender-based violence; sexual exploitation or assault breaches]
[insert amount]
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 102
Financial Situation and Performance
1. Bidder’s Name: Date:
2. JV Member’s Name_________________________
3. RFT No. and title: ___________________________ Page __ _of__ __pages
4. Financial data (This form should be used only if the information submitted at the time of
prequalification requires updating)
Type of Financial information
in
(currency)
Historic information for previous _________years,
______________
(amount in currency, currency, exchange rate, USD
equivalent) Year 1 Year 2 Year 3 Year4 Year 5
Statement of Financial Position (Information from Balance Sheet)
Total Assets (TA)
Total Liabilities (TL)
Total Equity/Net Worth (NW)
Current Assets (CA)
Current Liabilities (CL)
Working Capital (WC)
Information from Income Statement
Total Revenue (TR)
Profits Before Taxes (PBT)
Cash Flow Information
Cash Flow from Operating
Activities
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 103
2. Sources of Finance
Specify sources of finance to meet the cash flow requirements on works currently in
progress and for future contract commitments.
No. Source of finance Amount (US$ equivalent)
1
2
3
1. Financial documents
The Bidder and its parties shall provide copies of financial statements to demonstrate that they
continue to meet the financial requirements at the time of prequalification.
The financial statements shall:
(a) reflect the financial situation of the Bidder or in case of JV member, and not an
affiliated entity (such as parent company or group member).
(b) be independently audited or certified in accordance with local legislation. (c) be complete, including all notes to the financial statements. (d) correspond to accounting periods already completed and audited.
Attached are copies of financial statements8 for the ____________years required above; and
complying with the requirements
8 If the most recent set of financial statements is for a period earlier than 12 months from the date of bid, the reason for this should be justified.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 104
Average Annual Construction Turnover
(This form should be used only if the information submitted at the time of
prequalification requires updating)
Bidder’s Name: Date:
JV Member’s Name_________________________
RFT No. and title: ___________________________ Page __ _of__ __pages
Annual turnover data (construction only)
Year Amount
Currency
Exchange rate USD equivalent
[indicate year] [insert amount and indicate
currency]
Average
Annual
Construction
Turnover
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 105
Current Contract Commitments / Works in Progress
Bidders and each member to a JV should provide information on their current
commitments on all contracts that have been awarded, or for which a letter of intent or
acceptance has been received, or for contracts approaching completion, but for which
an unqualified, full completion certificate has yet to be issued.
Bidder’s Name: Date:
JV Member’s Name_________________________
RFT No. and title: ___________________________ Page __ _of__
__pages
Current Contract Commitments
No. Name of Contract Employer’s Contact
Address, Tel, Fax
Value of
Outstanding
Work
[Current US$
Equivalent]
Estimated
Completio
n Date
Average Monthly
Invoicing Over
Last Six Months
[US$/month)]
1
2
3
4
5
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 106
Form of Bid Security – Demand Guarantee
Bidder’s Name:__________________________
Beneficiary: __________________________
Request for Bids No: ________________________________________
Date: __________________________
BID GUARANTEE No.: __________________________
Guarantor: ________________________________________________
We have been informed that __________________________ (hereinafter called "the
Applicant") has submitted or will submit to the Beneficiary its Bid (hereinafter called "the Bid")
for the execution of ________________ under Request for Bids No. ___________ (“the
RFB”).
Furthermore, we understand that, according to the Beneficiary’s conditions, Bids must be
supported by a Bid guarantee.
At the request of the Applicant, we, as Guarantor, hereby irrevocably undertake to pay the
Beneficiary any sum or sums not exceeding in total an amount of ___________
(____________) upon receipt by us of the Beneficiary’s complying demand, supported by the
Beneficiary’s statement, whether in the demand itself or a separate signed document
accompanying or identifying the demand, stating that either the Applicant:
(a) has withdrawn its Bid during the period of Bid validity set forth in the Applicant’s
Letter of Tender (“the Bid Validity Period”), or any extension thereto provided by
the Applicant; or
(b) having been notified of the acceptance of its Bid by the Beneficiary during the Bid Validity
Period or any extension thereto provided by the Applicant, (i) has failed to execute the
contract agreement, or (ii) has failed to furnish the Performance Security and, if required,
the Environmental and Social (ES) Performance Security, in accordance with the
Instructions to Bidders (“ITB”) of the Beneficiary’s Bidding document.
This guarantee will expire: (a) if the Applicant is the successful Bidder, upon our receipt of
copies of the contract agreement signed by the Applicant and the Performance Security and,
if required, the Environmental and Social (ES) Performance Security, issued to the Beneficiary
in relation to such contract agreement; or (b) if the Applicant is not the successful Bidder, upon
the earlier of (i) our receipt of a copy of the Beneficiary’s notification to the Applicant of the
results of the Bidding process; or (ii) twenty-eight days after the end of the Bid Validity Period.
Consequently, any demand for payment under this guarantee must be received by us at the
office indicated above on or before that date.
This guarantee is subject to the Uniform Rules for Demand Guarantees (URDG) 2010
Revision, ICC Publication No. 758.
_____________________________
[signature(s)]
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex B Documents to be submitted by Bidders 107
Form of Bid-Securing Declaration
Bidder’s Name: Date:
JV Member’s Name_________________________
RFT No. and title: ___________________________ Page __ _of__ __pages
Bid No.: ________________ Alternative No.: ________________
To:
We, the undersigned, declare that:
We understand that, according to your conditions, Bids must be supported by a Bid-Securing
Declaration.
We accept that we will automatically be suspended from being eligible for Bidding, or
submitting Proposals in any contract with the Employer for the period of time of
______________ starting on _________, if we are in breach of our obligation(s) under the Bid
conditions, because we:
(a) have withdrawn our Bid during the period of Bid validity specified in the Letter of Tender;
or
(b) having been notified of the acceptance of our Bid by the Employer during the period of
Bid validity, (i) fail or refuse to execute the Contract, if required, or (ii) fail or refuse to
furnish the Performance Security and, if required, the Environmental and Social (ES)
Performance Security, in accordance with the ITB.
We understand this Bid-Securing Declaration shall expire if we are not the successful Bidder,
upon the earlier of (i) our receipt of your notification to us of the name of the successful Bidder;
or (ii) twenty-eight days after the expiration of our Bid.
Name of the Bidder*
Name of the person duly authorized to sign the Bid on behalf of the Bidder** _______
Title of the person signing the Bid ______________________
Signature of the person named above ______________________
Date signed ________________________________ day of ___________________, _____
*: In the case of the Bid submitted by joint venture specify the name of the Joint Venture as
Bidder
**: Person signing the Bid shall have the power of attorney given by the Bidder attached to the
Bid
[Note: In case of a Joint Venture, the Bid-Securing Declaration must be in the name of all members to
the Joint Venture that submits the Bid.]
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex C Documents to be used for Contract Award 108
Annex C – Documents to be used for Contract Award
1 NOTIFICATION OF INTENTION TO AWARD
2 LETTER OF ACCEPTANCE
3 CONTRACT AGREEMENT
4 PERFORMANCE SECURITY
5 ENVIRONMENTAL AND SOCIAL (ES) PERFORMANCE SECURITY
6 ES DEMAND GUARANTEE
7 ADVANCE PAYMENT SECURITY
8 RETENTION MONEY SECURITY
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex C Documents to be used for Contract Award 109
Notification of Intention to Award
[This Notification of Intention to Award shall be sent to each Bidder that submitted a
Bid.]
[Send this Notification to the Bidder’s Authorized Representative named in the Bidder
Information Form]
For the attention of Bidder’s Authorized Representative
Name: [insert Authorized Representative’s name]
Address: [insert Authorized Representative’s Address]
Telephone/Fax numbers: [insert Authorized Representative’s telephone/fax numbers]
Email Address: [insert Authorized Representative’s email address]
[IMPORTANT: insert the date that this Notification is transmitted to Bidders. The
Notification must be sent to all Bidders simultaneously. This means on the same date
and as close to the same time as possible.]
DATE OF TRANSMISSION: This Notification is sent by: [email/fax] on [date] (local time)
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex C Documents to be used for Contract Award 110
Notification of Intention to Award Employer: [insert the name of the Employer]
Project: [insert name of project]
Contract title: [insert the name of the contract]
Country: [insert country where RFB is issued]
Request for Bid (RFB) No: [insert RFB reference number from Procurement Plan]
This Notification of Intention to Award (Notification) notifies you of our decision to award
the above contract. The transmission of this Notification begins the Standstill Period. During
the Standstill Period you may:
a) request a debriefing in relation to the evaluation of your Bid and/or
b) submit a Procurement-related Complaint in relation to the decision to award the contract.
1. The successful Bidder
Name: [insert name of successful Bidder]
Address: [insert address of the successful Bidder]
Contract price: [insert contract price of the successful Bid]
2. Other Bidders [INSTRUCTIONS: insert names of all Bidders that submitted a Bid. If the Bid’s price was evaluated include the evaluated price as well as the Bid price as read out.]
Name of Bidder Bid price Evaluated Bid price (if applicable)
[insert name] [insert Bid price] [insert evaluated price]
[insert name] [insert Bid price] [insert evaluated price]
[insert name] [insert Bid price] [insert evaluated price]
[insert name] [insert Bid price] [insert evaluated price]
[insert name] [insert Bid price] [insert evaluated price]
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex C Documents to be used for Contract Award 111
3. Reason/s why your Bid was unsuccessful
[INSTRUCTIONS: State the reason/s why this Bidder’s Bid was unsuccessful. Do NOT include: (a) a point by point comparison with another Bidder’s Bid or (b) information that is marked confidential by the Bidder in its Bid.]
4. How to request a debriefing
DEADLINE: The deadline to request a debriefing expires at midnight on [insert date] (local time).
You may request a debriefing in relation to the results of the evaluation of your Bid. If you decide to request a debriefing your written request must be made within three (3) Business Days of receipt of this Notification of Intention to Award.
Provide the contract name, reference number, name of the Bidder, contact details; and address the request for debriefing as follows:
Attention: [insert full name of person, if applicable]
Title/position: [insert title/position]
Agency: [insert name of Employer]
Email address: [insert email address]
Fax number: [insert fax number] delete if not used
If your request for a debriefing is received within the three (3) Business Days deadline, we will provide the debriefing within five (5) Business Days of receipt of your request. If we are unable to provide the debriefing within this period, the Standstill Period shall be extended by five (5) Business Days after the date that the debriefing is provided. If this happens, we will notify you and confirm the date that the extended Standstill Period will end.
The debriefing may be in writing, by phone, video conference call or in person. We shall promptly advise you in writing how the debriefing will take place and confirm the date and time.
If the deadline to request a debriefing has expired, you may still request a debriefing. In this case, we will provide the debriefing as soon as practicable, and normally no later than fifteen (15) Business Days from the date of publication of the Contract Award Notice.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex C Documents to be used for Contract Award 112
5. How to make a complaint
Period: Procurement-related Complaint challenging the decision to award shall be submitted by midnight, [insert date] (local time).
Provide the contract name, reference number, name of the Bidder, contact details; and address the Procurement-related Complaint as follows:
Attention: [insert full name of person, if applicable]
Title/position: [insert title/position]
Agency: [insert name of Employer]
Email address: [insert email address]
Fax number: [insert fax number] delete if not used
At this point in the procurement process, you may submit a Procurement-related Complaint challenging the decision to award the contract. You do not need to have requested, or received, a debriefing before making this complaint. Your complaint must be submitted within the Standstill Period and received by us before the Standstill Period ends.
In summary, there are four essential requirements:
1. You must be an ‘interested party’. In this case, that means a Bidder who submitted a Bid in this bidding process, and is the recipient of a Notification of Intention to Award.
2. The complaint can only challenge the decision to award the contract.
3. You must submit the complaint within the period stated above.
4. You must include, in your complaint, all of the information required by the Procurement Regulations.
6. Standstill Period
DEADLINE: The Standstill Period is due to end at midnight on [insert date] (local time).
The Standstill Period lasts ten (10) Business Days after the date of transmission of this Notification of Intention to Award.
The Standstill Period may be extended as stated in Section 4 above.
If you have any questions regarding this Notification please do not hesitate to contact us.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex C Documents to be used for Contract Award 113
On behalf of the Employer:
Signature: ______________________________________________
Name: ______________________________________________
Title/position: ______________________________________________
Telephone: ______________________________________________
Email: ______________________________________________
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex C Documents to be used for Contract Award 114
Letter of Acceptance
[letterhead paper of the Employer]
[date]
To: [name and address of the Contractor]
This is to notify you that your Bid dated [date] for execution of the [name of the Contract and
identification number, as given in the Contract Data] for the Accepted Contract Amount
[amount in numbers and words] [name of currency], as corrected and modified in accordance
with the Instructions to Bidders, is hereby accepted by our Agency.
You are requested to furnish (i) the Performance Security and an Environmental and Social
Performance Security [Delete ES Performance Security if it is not required under the
contract] within 28 days in accordance with the Conditions of Contract, using for that purpose
one of the Performance Security Forms and the ES Performance Security Form, [Delete
reference to the ES Performance Security Form if it is not required under the contract]
and (ii) the additional information on beneficial ownership in accordance with ITB, within eight
(8) Business days using the Beneficial Ownership Disclosure Form, included in Contract
Forms, of the Bidding Documents.
Authorized Signature:
Name and Title of Signatory:
Name of Agency:
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex C Documents to be used for Contract Award 115
Attachment: Contract Agreement
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex C Documents to be used for Contract Award 116
Contract Agreement
THIS AGREEMENT made the ________ day of ________________________, _____,
between ______________________________________of __________________________
(hereinafter “the Employer”), of the one part, and ______________________ of
_____________________ (hereinafter “the Contractor”), of the other part:
WHEREAS the Employer desires that the Works known as
_______________________________ should be executed by the Contractor, and has
accepted a Bid by the Contractor for the execution and completion of these Works and the
remedying of any defects therein,
The Employer and the Contractor agree as follows:
1. In this Agreement words and expressions shall have the same meanings as are
respectively assigned to them in the Contract documents referred to.
2. The following documents shall be deemed to form and be read and construed as part
of this Agreement. This Agreement shall prevail over all other Contract documents.
(a) the Letter of Acceptance;
(b) the Letter of Tender;
(c) the addenda Nos ________(if any);
(d) the Particular Conditions;
(e) the General Conditions;
(f) the Specification;
(g) the Drawings; and
(h) the completed Schedules and any other documents forming part of the contract, including, but not limited to:
i. the ES Management Strategies and Implementation Plans; and
ii. the HS Management Strategies and Implementation Plans; and
iii. Code of Conduct for Contractor’s Personnel (ES).
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex C Documents to be used for Contract Award 117
3. In consideration of the payments to be made by the Employer to the Contractor as
specified in this Agreement, the Contractor hereby covenants with the Employer to execute
the Works and to remedy defects therein in conformity in all respects with the provisions of
the Contract.
4. The Employer hereby covenants to pay the Contractor in consideration of the
execution and completion of the Works and the remedying of defects therein, the Contract
Price or such other sum as may become payable under the provisions of the Contract at the
times and in the manner prescribed by the Contract.
IN WITNESS whereof the parties hereto have caused this Agreement to be executed in
accordance with the laws of _____________________________ on the day, month and
year specified above.
Signed by ________________________________________________ (for the Employer)
Signed by __________________________________________________ (for the
Contractor)
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex C Documents to be used for Contract Award 118
Appendix to the Contract Agreement:
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex C Documents to be used for Contract Award 119
Performance Security
Option 1: Demand Guarantee
[Guarantor letterhead or SWIFT identifier code]
Beneficiary: [insert name and Address of Employer]
Date: _ [Insert date of issue]
PERFORMANCE GUARANTEE No.: [Insert guarantee reference number]
Guarantor: [Insert name and address of place of issue, unless indicated in the letterhead]
We have been informed that ________________ (hereinafter called "the Applicant") has
entered into Contract No. _____________ dated ____________ with the Beneficiary, for the
execution of _____________________ (hereinafter called "the Contract").
Furthermore, we understand that, according to the conditions of the Contract, a performance
guarantee is required.
At the request of the Applicant, we as Guarantor, hereby irrevocably undertake to pay the
Beneficiary any sum or sums not exceeding in total an amount of ___________ ( ),1
such sum being payable in the types and proportions of currencies in which the Contract Price
is payable, upon receipt by us of the Beneficiary’s complying demand supported by the
Beneficiary’s statement, whether in the demand itself or in a separate signed document
accompanying or identifying the demand, stating that the Applicant is in breach of its
obligation(s) under the Contract, without the Beneficiary needing to prove or to show grounds
for your demand or the sum specified therein.
This guarantee shall expire, no later than the …. Day of ……, 2… 2, and any demand for
payment under it must be received by us at this office indicated above on or before that date.
1 The Guarantor shall insert an amount representing the percentage of the Accepted Contract Amount specified in the Letter of Acceptance, less provisional sums, if any, and denominated either in the currency(cies) of the Contract or a freely convertible currency acceptable to the Beneficiary. 2 Insert the date twenty-eight days after the expected completion date as described in GC Clause 11.9 (refer: 2017 FIDIC Red Book). The Employer should note that in the event of an extension of this date for completion of the Contract, the Employer would need to request an extension of this guarantee from the Guarantor. Such request must be in writing and must be made prior to the expiration date established in the guarantee. In preparing this guarantee, the Employer might consider adding the following text to the form, at the end of the penultimate paragraph: “The Guarantor agrees to a one-time extension of this guarantee for a period not to exceed [six months][one year], in response to the Beneficiary’s written request for such extension, such request to be presented to the Guarantor before the expiry of the guarantee.”
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex C Documents to be used for Contract Award 120
This guarantee is subject to the Uniform Rules for Demand Guarantees (URDG) 2010
Revision, ICC Publication No. 758, except that the supporting statement under Article 15(a) is
hereby excluded.
_____________________
[signature(s)]
Note: All italicized text (including footnotes) is for use in preparing this form and
shall be deleted from the final product.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex C Documents to be used for Contract Award 121
Performance Security
Option 2: Performance Bond
By this Bond____________________ as Principal (hereinafter called “the Contractor”)
and______________________________________________________________] as Surety
(hereinafter called “the Surety”), are held and firmly bound unto_____________________] as
Obligee (hereinafter called “the Employer”) in the amount of __________________, for the
payment of which sum well and truly to be made in the types and proportions of currencies in
which the Contract Price is payable, the Contractor and the Surety bind themselves, their
heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these
presents.
WHEREAS the Contractor has entered into a written Agreement with the Employer dated the
day of , 20 , for ___________________ in
accordance with the documents, plans, specifications, and amendments thereto, which to the
extent herein provided for, are by reference made part hereof and are hereinafter referred to
as the Contract.
NOW, THEREFORE, the Condition of this Obligation is such that, if the Contractor shall
promptly and faithfully perform the said Contract (including any amendments thereto), then
this obligation shall be null and void; otherwise, it shall remain in full force and effect.
Whenever the Contractor shall be, and declared by the Employer to be, in default under the
Contract, the Employer having performed the Employer’s obligations thereunder, the Surety
may promptly remedy the default, or shall promptly:
(1) complete the Contract in accordance with its terms and conditions; or
(2) obtain a Bid or Bids from qualified Bidders for submission to the Employer for
completing the Contract in accordance with its terms and conditions, and upon
determination by the Employer and the Surety of the lowest responsive Bidder,
arrange for a Contract between such Bidder and Employer and make available as
work progresses (even though there should be a default or a succession of defaults
under the Contract or Contracts of completion arranged under this paragraph)
sufficient funds to pay the cost of completion less the Balance of the Contract Price;
but not exceeding, including other costs and damages for which the Surety may be
liable hereunder, the amount set forth in the first paragraph hereof. The term
“Balance of the Contract Price,” as used in this paragraph, shall mean the total
amount payable by Employer to Contractor under the Contract, less the amount
properly paid by Employer to Contractor; or
(3) pay the Employer the amount required by Employer to complete the Contract in
accordance with its terms and conditions up to a total not exceeding the amount of
this Bond.
The Surety shall not be liable for a greater sum than the specified penalty of this Bond.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex C Documents to be used for Contract Award 122
Any suit under this Bond must be instituted before the expiration of one year from the date of
the issuing of the Taking-Over Certificate.
No right of action shall accrue on this Bond to or for the use of any person or corporation
other than the Employer named herein or the heirs, executors, administrators, successors,
and assigns of the Employer.
In testimony whereof, the Contractor has hereunto set its hand and affixed its seal, and the
Surety has caused these presents to be sealed with its corporate seal duly attested by the
signature of its legal representative, this day of 20
.
SIGNED ON on behalf of
By in the capacity of
In the presence of
SIGNED ON on behalf of
By in the capacity of
In the presence of
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex C Documents to be used for Contract Award 123
Environmental and Social (ES) Performance Security
ES Demand Guarantee
[Guarantor letterhead or SWIFT identifier code]
Beneficiary: [insert name and Address of Employer]
Date: _ [Insert date of issue]
ES PERFORMANCE GUARANTEE No.: [Insert guarantee reference number]
Guarantor: [Insert name and address of place of issue, unless indicated in the letterhead]
We have been informed that ________________ (hereinafter called "the Applicant") has
entered into Contract No. _____________ dated ____________ with the Beneficiary, for the
execution of _____________________ (hereinafter called "the Contract").
Furthermore, we understand that, according to the conditions of the Contract, a performance
guarantee is required.
At the request of the Applicant, we as Guarantor, hereby irrevocably undertake to pay the
Beneficiary any sum or sums not exceeding in total an amount of ___________ ( ),1
such sum being payable in the types and proportions of currencies in which the Contract Price
is payable, upon receipt by us of the Beneficiary’s complying demand supported by the
Beneficiary’s statement, whether in the demand itself or in a separate signed document
accompanying or identifying the demand, stating that the Applicant is in breach of its
Environmental and Social (ES) obligation(s) under the Contract, without the Beneficiary needing
to prove or to show grounds for your demand or the sum specified therein.
This guarantee shall expire, no later than the …. Day of ……, 2… 2, and any demand for
payment under it must be received by us at this office indicated above on or before that date.
This guarantee is subject to the Uniform Rules for Demand Guarantees (URDG) 2010
Revision, ICC Publication No. 758, except that the supporting statement under Article 15(a) is
hereby excluded.
1 The Guarantor shall insert an amount representing the percentage of the Accepted Contract Amount specified in the Letter of Acceptance, less provisional sums, if any, and denominated either in the currency (cies) of the Contract or a freely convertible currency acceptable to the Beneficiary. 2 Insert the date twenty-eight days after the expected completion date as described in GC Clause 11.9 (refer: 2017 FIDIC Red Book). The Employer should note that in the event of an extension of this date for completion of the Contract, the Employer would need to request an extension of this guarantee from the Guarantor. Such request must be in writing and must be made prior to the expiration date established in the guarantee. In preparing this guarantee, the Employer might consider adding the following text to the form, at the end of the penultimate paragraph: “The Guarantor agrees to a one-time extension of this guarantee for a
period not to exceed [six months] [one year], in response to the Beneficiary’s written request for such extension, such request to be presented to the Guarantor before the expiry of the guarantee.”
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex C Documents to be used for Contract Award 124
_____________________
[signature(s)]
Note: All italicized text (including footnotes) is for use in preparing this form and
shall be deleted from the final product.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex C Documents to be used for Contract Award 125
Advance Payment Security
Demand Guarantee
[Guarantor letterhead or SWIFT identifier code]
Beneficiary: [Insert name and Address of Employer]
Date: [Insert date of issue]
ADVANCE PAYMENT GUARANTEE No.: [Insert guarantee reference number]
Guarantor: [Insert name and address of place of issue, unless indicated in the letterhead]
We have been informed that ________________ (hereinafter called “the Applicant”) has
entered into Contract No. _____________ dated ____________ with the Beneficiary, for the
execution of _____________________ (hereinafter called "the Contract").
Furthermore, we understand that, according to the conditions of the Contract, an advance
payment in the sum ___________ ( ) is to be made against an advance payment
guarantee.
At the request of the Applicant, we as Guarantor, hereby irrevocably undertake to pay the
Beneficiary any sum or sums not exceeding in total an amount of ___________ ( ) 1 upon receipt by us of the Beneficiary’s complying demand supported by the Beneficiary’s
statement, whether in the demand itself or in a separate signed document accompanying or
identifying the demand, stating either that the Applicant:
(a) has used the advance payment for purposes other than the costs of mobilization in respect of the Works; or
(b) has failed to repay the advance payment in accordance with the Contract conditions, specifying the amount which the Applicant has failed to repay.
A demand under this guarantee may be presented as from the presentation to the Guarantor
of a certificate from the Beneficiary’s bank stating that the advance payment referred to above
has been credited to the Applicant on its account number ___________ at
_________________.
The maximum amount of this guarantee shall be progressively reduced by the amount of the
advance payment repaid by the Applicant as specified in copies of interim statements or
payment certificates which shall be presented to us. This guarantee shall expire, at the latest,
upon our receipt of a copy of the interim payment certificate indicating that ninety (90) percent
of the Accepted Contract Amount, less provisional sums, has been certified for payment, or
1 The Guarantor shall insert an amount representing the amount of the advance payment and denominated either in the currency(ies) of the advance payment as specified in the Contract, or in a freely convertible currency acceptable to the Employer.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex C Documents to be used for Contract Award 126
on the ___ day of _____, 2___,2 whichever is earlier. Consequently, any demand for payment
under this guarantee must be received by us at this office on or before that date.
This guarantee is subject to the Uniform Rules for Demand Guarantees (URDG) 2010
Revision, ICC Publication No. 758, except that the supporting statement under Article 15(a) is
hereby excluded.
____________________
[signature(s)]
Note: All italicized text (including footnotes) is for use in preparing this form and
shall be deleted from the final product.
2 Insert the expected expiration date of the Time for Completion. The Employer should note that in the event of an extension of the time for completion of the Contract, the Employer would need to request an extension of this guarantee from the Guarantor. Such request must be in writing and must be made prior to the expiration date established in the guarantee. In preparing this guarantee, the Employer might consider adding the following text to the form, at the end of the penultimate paragraph: “The Guarantor agrees to a one-time extension of this guarantee for a period not to exceed [six months][one year], in response to the Beneficiary’s written request for such extension, such request to be presented to the Guarantor before the expiry of the guarantee.”
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex C Documents to be used for Contract Award 127
Retention Money Security
Demand Guarantee
________________________________ [Guarantor letterhead or SWIFT identifier code]
Beneficiary: ___________________ [Insert name and Address of Employer]
Date: ________________[Insert date of issue]
RETENTION MONEY GUARANTEE No.: [Insert guarantee reference number]
Guarantor: [Insert name and address of place of issue, unless indicated in the letterhead]
We have been informed that ________________ [insert name of Contractor, which in the case of
a joint venture shall be the name of the joint venture] (hereinafter called "the Applicant") has entered
into Contract No. _____________ [insert reference number of the contract] dated ____________
with the Beneficiary, for the execution of _____________________ [insert name of contract and
brief description of Works] (hereinafter called "the Contract").
Furthermore, we understand that, according to the conditions of the Contract, the Beneficiary
retains moneys up to the limit set forth in the Contract (“the Retention Money”), and that when
the Taking-Over Certificate has been issued under the Contract and the first half of the
Retention Money has been certified for payment, payment of [insert the second half of the
Retention Money or if the amount guaranteed under the Performance Guarantee when the
Taking-Over Certificate is issued is less than half of the Retention Money, the difference
between half of the Retention Money and the amount guaranteed under the Performance
Security and, if required the ES Performance Security] is to be made against a Retention
Money guarantee.
At the request of the Applicant, we, as Guarantor, hereby irrevocably undertake to pay the
Beneficiary any sum or sums not exceeding in total an amount of ___________ [insert amount
in figures] ( ) [amount in words]1 upon receipt by us of the Beneficiary’s complying
demand supported by the Beneficiary’s statement, whether in the demand itself or in a
separate signed document accompanying or identifying the demand, stating that the Applicant
is in breach of its obligation(s) under the Contract, without your needing to prove or show
grounds for your demand or the sum specified therein.
A demand under this guarantee may be presented as from the presentation to the Guarantor
of a certificate from the Beneficiary’s bank stating that the second half of the Retention Money
1 The Guarantor shall insert an amount representing the amount of the second half of the Retention Money or if the amount guaranteed under the Performance Guarantee when the Taking-Over Certificate is issued is less than half of the Retention Money, the difference between half of the Retention Money and the amount guaranteed under the Performance Security and denominated either in the currency(ies) of the second half of the Retention Money as specified in the Contract, or in a freely convertible currency acceptable to the Beneficiary.
Royal Government of Bhutan Guidelines for Bidding Documents for Hydropower Projects - 2020
Annex C Documents to be used for Contract Award 128
as referred to above has been credited to the Applicant on its account number ___________
at _________________ [insert name and address of Applicant’s bank].
This guarantee shall expire no later than the …. day of ……, 2… 2, and any demand for
payment under it must be received by us at the office indicated above on or before that date.
This guarantee is subject to the Uniform Rules for Demand Guarantees (URDG) 2010
Revision, ICC Publication No. 758, except that the supporting statement under Article 15(a) is
hereby excluded.
____________________
[signature(s)]
Note: All italicized text (including footnotes) is for use in preparing this form and
shall be deleted from the final product.
2 Insert the same expiry date as set forth in the Performance Security, representing the date twenty-eight days after the completion date described in GC Clause 11.9 (refer: 2017 FIDIC Red Book). The Employer should note that in the event of an extension of this date for completion of the Contract, the Employer would need to request an extension of this guarantee from the Guarantor. Such request must be in writing and must be made prior to the expiration date established in the guarantee. In preparing this guarantee, the Employer might consider adding the following text to the form, at the end of the penultimate paragraph: “The Guarantor agrees to a one-time extension of this guarantee for a period not to exceed [six months][one year], in response to the Beneficiary’s written request for such extension, such request to be presented to the Guarantor before the expiry of the guarantee.”