Page 1: @GUSTKWT - MyGUST...8) A large project network has four distinct (unconnected) paths to the last activity, respectively of 7, 8, 9 and 10 weeks. If the 10-week path is compressed to

@GUSTKWT - MyGUST.com

Page 2: @GUSTKWT - MyGUST...8) A large project network has four distinct (unconnected) paths to the last activity, respectively of 7, 8, 9 and 10 weeks. If the 10-week path is compressed to

@GUSTKWT - MyGUST.com

Page 3: @GUSTKWT - MyGUST...8) A large project network has four distinct (unconnected) paths to the last activity, respectively of 7, 8, 9 and 10 weeks. If the 10-week path is compressed to

@GUSTKWT - MyGUST.com

Page 4: @GUSTKWT - MyGUST...8) A large project network has four distinct (unconnected) paths to the last activity, respectively of 7, 8, 9 and 10 weeks. If the 10-week path is compressed to

@GUSTKWT - MyGUST.com

Page 5: @GUSTKWT - MyGUST...8) A large project network has four distinct (unconnected) paths to the last activity, respectively of 7, 8, 9 and 10 weeks. If the 10-week path is compressed to

@GUSTKWT - MyGUST.com

Page 6: @GUSTKWT - MyGUST...8) A large project network has four distinct (unconnected) paths to the last activity, respectively of 7, 8, 9 and 10 weeks. If the 10-week path is compressed to

@GUSTKWT - MyGUST.com

Page 7: @GUSTKWT - MyGUST...8) A large project network has four distinct (unconnected) paths to the last activity, respectively of 7, 8, 9 and 10 weeks. If the 10-week path is compressed to

@GUSTKWT - MyGUST.com

Page 8: @GUSTKWT - MyGUST...8) A large project network has four distinct (unconnected) paths to the last activity, respectively of 7, 8, 9 and 10 weeks. If the 10-week path is compressed to

@GUSTKWT - MyGUST.com