gyromat in tunnelling practice
DESCRIPTION
The presentation will Show you how a gyroscope is working and why it is very useful to use a gyro in tunnelling. Several examples from practice will explain this.TRANSCRIPT
Geosystems at HxGN LIVE Increasing accuracy in high precision survey with DMT GYROMAT 5000 in combination with LEICA high-end total station
Volker Schäpe, Volker Schultheiß, Norbert Benecke
Version Date: 04.06.14
Please insert a picture (Insert, Picture, from file).
Size according to grey field (10 cm x 25.4 cm).
Scale picture: highlight, pull corner point
Cut picture: highlight, choose the cutting icon from the picture tool bar, click on a
side point and cut
DMT GmbH & Co. KG Company profile
DMT is an international technology service provider in the fields of natural resources, safety and infrastructure DMT was founded in 1990 as a merger of 3 companies founded in 1864 In the year 2007 DMT joint the TÜV NORD Group
TÜV Nord Group Headquarters in Hannover, Germany ~1.056 Mio. € annual turnover in 2013 ~9.925 Employees in 70 countries
DMT Group Headquarters in Essen, Germany ~113 Mio. € annual turnover in 2013 ~720 employees
Development department for geo-instruments like GYROMAT 5000 Service department for surveying tasks
1. Introduction of GYROMAT 5000
2. Application for GYROMAT 5000: high accuracy tunnel survey
3. Examples and case studies
Content
DMT GYROMAT 5000 + LEICA total station High precision north finding gyroscope
1. Introduction of GYROMAT 5000
2. Application for GYROMAT 5000: high accuracy tunnel survey
3. Examples and case studies
Content
DMT GYROMAT 5000 + LEICA total station High precision north finding gyroscope
DIN 18723 Teil 7 (1990) (German Standard for Industry 18723 Part 7 from 1990) A gyroscope (northseeking gyro) is a pendulous suspended, electronic driven gyro, which spin vector is influenced by gravity and earth rotation. It will directed to astronomic north. Implementation of gyro into the GYROMAT
Gyro axis
Suspension tape
ω
Introduction of GYROMAT 5000 Principle of a gyroscope
Highest measuring accuracy.. 0,8 mgon (= 1,2 cm / 1 km)
Short measuring time ………. 6 – 9 minutes
Weight without total station … 11,5 kg
Fully automatic measuring sequence
Preorientation-free measuring method
Individual theodolite equipping with LEICA high-end total stations like TPS1100, TPS1200, TS11, TS15, TS30, TM30 TS50, MS50, TM6100A and others with accuracy better than 1”
GYROMAT 5000 The most accurate precision-surveying gyroscope in the world
1. Introduction of GYROMAT 5000
2. Application for GYROMAT 5000: high accuracy tunnel survey
3. Examples and case studies
Content
DMT GYROMAT 5000 + LEICA total station High precision north finding gyroscope
Requirements on accuracy of tunnel/roadway position depend on: Used tunneling method (e.g. TBM or blasting ) Use of the tunnel in operation (e.g. high speed railway tunnel / roadway tunnel)
Examples for challenging requirements in accuracy: Predefined demounting construction position with 5 cm variance for the TBM Required alignment accuracy better than 5 cm at each tunnel position for high
speed railway tunnels Required accuracy of 10 cm for cut-through of two underground roadways
High accuracy tunnel survey Requirements on position measurement in tunnels
Establishment of an efficient Survey System including:
Surface network, created e.g. by GNSS
Transfer of surface network into the tunnel via open traverse lines:
Survey point distances in the tunnel range between 50 m and > 200 m Survey points are mostly located at flanks, rarely in the middle of the tunnel Deviations and errors propagate with every survey point Failures in positioning increase with tunnel length
Deviations are unavoidable! In particular:
refraction error plumbing error error propagation
will lead into lateral deviation
High accuracy tunnel survey Surveying and directions in tunneling, some considerations
Target building
Plumbing Error
α β1
β2 β3
q
B S
QL
Real direction with plumbing error q Theoretical direction without plumbing error
Tunnel length [m]
Lateral deflection Plumb error: 1 mm Base length: 10 m
Lateral deflection Plumb error: 1,5 mm
Base length: 8 m
300 4,2 cm
8,0 cm
1.000
14,1 cm
26,5 cm
10.000
141,4 cm
265,2 cm
β1
β2
β3
Start shaft
High accuracy tunnel survey Improvement of accuracy by the use of GYROMAT 5000
Refraction in a tunnel
Theoretical straight-lined beam Real tunnel situation: different
layers of temperatures between the tunnel walls and tunnel centre lead into refraction In reality: curved beam Disregard of refraction leads
into position error QR
Start shaft
Influence of refraction Theoretical position
QR A1
A2
A‘2 A‘1 Δ Δ
North North
Solution: GYROMAT 5000 delivers the absolute north direction for every point. The refraction can be identified
High accuracy tunnel survey Improvement of accuracy by the use of GYROMAT 5000
Gyro supported traverse line in the tunnel
Error propagation
Survey points Traverse line Gyro surveyed polygon side
50 – 200 m 500 – 1.000 m
High accuracy tunnel survey Improvement of accuracy by the use of GYROMAT 5000
1. Introduction of GYROMAT 5000
2. Application for GYROMAT 5000: high accuracy tunnel survey
3. Examples and case studies
Content
DMT GYROMAT 5000 + LEICA total station High precision north finding gyroscope
Water supply tunnel for a 420 MW hydropower plant Length: 25,8 km, diameter: 7 – 8 m Driven by two TBM from two sites: intake and outlet 1 Gyro campaign 1 km before planned cut-through Driving status while survey: intake tunnel: 7,5 km
outlet tunnel: 17,5 km Extreme environmental conditions while survey:
temperature up to 42О C; air humidity: 99% Result: determination of significant lateral deviation in
both tunnels of up to 2,5 m at calculated cut-through position
By the way: in consideration of the environmental conditions, 2,5 m lateral deviation is good result for open traverses over these large distances.
Gilgel Gibe II tunnel in Ethiopia Case study: water supply tunnel
Achieved lateral deviation: < 5 cm
Scenario without correction: Lateral deviation of > 2,5 m which corresponds to a third of total tunnel width
Possible consequence of scenario above: Additional construction efforts to correct the direction which would had exceeded multiple the costs and time for gyro campaign
Result of cut-through after correction of driving direction:
Gilgel Gibe II tunnel in Ethiopia Case study: water supply tunnel
690 MW hydropower plant, supplied by two different water reservoirs in the sub-arctic east part of Island mountain region. Total tunnel length: 72 km Driving with 3 TBM from different
starting points Allowance of horizontal deviation
at cut-through positions: < 20 cm Allowance of deviation from the
target direction for every section of 100 m: < 15 cm
Kárahnjúkar Hydro-Electric Project (Island) Case study: water supply tunnel
Challenges for this survey
Extreme length of single tunnel sections Complex geometry with curves and branches leads
to sightings close to the tunnel wall Extreme environmental conditions:
- Outside temperatures below -20О C - Inside temperature range from 0О C to > 40О C High variation of air temperature at tunnel
entrances or ventilation holes Air humidity nearly 100 % Partly water suddenly flows in with temperatures
up to 51О C Facing considerable, unpredictable and
unavoidable refractions at the traverse
Kárahnjúkar Hydro-Electric Project (Island) Case study: water supply tunnel
Challenges in surveying and alignment
Kárahnjúkar Hydro-Electric Project (Island) Case study: water supply tunnel
Kárahnjúkar Hydro-Electric Project (Island) Case study: water supply tunnel
Challenges in surveying and alignment
Kárahnjúkar Hydro-Electric Project (Island) Case study: water supply tunnel
Challenges in surveying and alignment
Kárahnjúkar Hydro-Electric Project (Island) Case study: water supply tunnel
Challenges in surveying and alignment
Faultless operation of GYROMAT 3000 and Leica total stations TCA1800 and TS30 even with the extreme weather conditions
Keeping the required accuracy for all cut-through so that extensive rework could be avoided. 20 cm was allowed, 5 cm was achieved
Results:
Kárahnjúkar Hydro-Electric Project (Island) Case study: water supply tunnel
Challenges for this survey
Extreme total length of 57 km
High demands on accuracy of max. 10 cm lateral deviation at every point
Tunnel work with TBMs from 5 access points. Entrance Sedrun via 800 m deep shaft
Gotthard Basistunnel (Switzerland) High speed railway tunnel
Quelle: R. Stengele (Swissphoto AG)
Gyro campaign in the driving Bodio (15,7 km) 8 Gyro campaigns in
December 2003 and August 2006 with GYROMAT 624 single azimuth surveys in
total with only 22 outliers; 3,5% which were eliminated Determination of 44 reference
azimuths on the surface network and 38 azimuths in the underground network with 602 single survey results
Gotthard Basistunnel (Switzerland) High speed railway tunnel
Gotthard Basistunnel (Switzerland) High speed railway tunnel
Gotthard Basistunnel (Switzerland) High speed railway tunnel
Gotthard Basistunnel (Switzerland) High speed railway tunnel
Cut-through Bodio – Faido on 26.10.2006
Gotthard Basistunnel (Switzerland) High speed railway tunnel
Achieved deviation at cut-through Bodio – Faido (15,7 km) Lateral: 9,1 cm Vertical: 2,3 cm
Cut-through Bodio – Faido on 26.10.2006
Different voices about the result: Building engineering: This deviation can be compensated by optimizing the interior work Railway engineering: This deviation can be compensated by minimal track moving over 300 m Surveyor: Considerable result Insurance: Risks remain under control
Gotthard Basistunnel (Switzerland) High speed railway tunnel
Sewer tunnel project of the City of Portland (Oregon/USA) constructed by TBM (Herrenknecht)
Length of 5,5 km with no remarkable incline or curves, diameter: 5 m
After the short distance of only 500 m tunneling two different survey campaigns one by contractor’s surveyor one by client’s surveyor
showed lateral differences of more than 25 cm
Combined Sewer Overflows Tunnel, Portland, USA West side CSO tunnel project
Problem: Tunneling starts from a haulage shaft of
50 m depth and 18 m diameter Start-up baseline for survey of only 11 m
length Plumbing error of only 2 mm causes
large lateral errors Feared result without measurements:
breakthrough disaster
Measurements: Turning the traverse into right orientation
by only two GYROMAT campaigns Reached result: successful breakthrough
with an accuracy of a few millimeters
Combined Sewer Overflows Tunnel, Protland, USA West side CSO tunnel project
Guidance system for TBM
Source: VMT GmbH
Tunnel survey System
Efficient survey system
Resume
Every tunneling project signifies an investment of several million Euro/Dollars Tunnel survey take place under difficult environmental conditions Small errors have a great impact on the technical and economical success of
the project The nightmare of a tunnel driver can be avoided by three steps:
High accuracy tunnel construction
QR
Gyro control survey as insurance
α β1
β2 β3
q QL β1
β2
β3
DMT GmbH & Co. KG Exploration & Geosurvey Contact: Norbert Benecke Am Technologiepark 1 45307 Essen, Germany Phone: +49 201 172 2012 Fax: +49 201 172 1791 E-mail: [email protected] Internet: www.dmt.de
Thank you for your attention