Page 1: H. Danared | Sw/Fr Coordination Committee | Page 1 Swedish/French Coordination Committee Håkan Danared Saclay, 13 January 2015

H. Danared | Sw/Fr Coordination Committee | Page 1

Swedish/French Coordination Committee

Håkan DanaredSaclay, 13 January 2015

Page 2: H. Danared | Sw/Fr Coordination Committee | Page 1 Swedish/French Coordination Committee Håkan Danared Saclay, 13 January 2015

H. Danared | Sw/Fr Coordination Committee | Page 2

An in-kind contribution is by definition a non-cash contribution by a member country to ESS

It can be in the form of:

• Technical components for the facility (also personnel needed to perform the testing, installation and/or integration)

• R&D work (also personnel needed to perform the work)

• Personnel made available for specific tasks during the construction phase

• Other products and services relevant for the completion of the facility

In-Kind Contributions

Page 3: H. Danared | Sw/Fr Coordination Committee | Page 1 Swedish/French Coordination Committee Håkan Danared Saclay, 13 January 2015

H. Danared | Sw/Fr Coordination Committee | Page 3

Target station154 M€

Accelerator522 M€

NSS/Instruments350 M€

In-kind

Cash

Total construction cost: 1.843 billion €

ESS In-kind Contributions Potential

Page 4: H. Danared | Sw/Fr Coordination Committee | Page 1 Swedish/French Coordination Committee Håkan Danared Saclay, 13 January 2015

H. Danared | Sw/Fr Coordination Committee | Page 4

• Suitable in-kind contributions are defined by ESS Programme Plan

• Values laid down in the cost-book

• Each IKC is subject to a written contract between ESS and delivering partner

• Each contract to follow a fixed structure

• The delivering party is wholly responsible for the contribution (technical, financial, commercial perspective)

• In-Kind Review Committee to evaluate and recommend all IKC contract proposals

• ESS Council to approve all in-kind contracts

• Based on final approval Member Country gets accredited the value of the contract

General Principles

Page 5: H. Danared | Sw/Fr Coordination Committee | Page 1 Swedish/French Coordination Committee Håkan Danared Saclay, 13 January 2015

H. Danared | Sw/Fr Coordination Committee | Page 5

Schedule 2

Schedule 1

1. Deliverables2. Time

schedule and delivery of project

3. Reporting4. Excluded

background

Legal and commercial terms and conditions

1. Definitions2. Work

programmes3. Obligations4. Organization5. …6. …7. …Etc.

Schedule X

Framework for handling In-

Kind Contributions

1 Agreement (General Terms and Conditions)

Signed only once with each partner

1. Agreement (General Terms and Conditions)

2. Framework for handling in-kind contributions

STCapproved

1 Agreement (General Terms and Conditions)

Added separately for each WP/WU

3. Schedule (Technical Annex) IKRCreviewed

IKC Agreement with 3 4 sections

Contract Structure

1 Agreement (General Terms and Conditions)

Added optionally for each WU/deliverable

4. Statements of Work ACCapproved

Page 6: H. Danared | Sw/Fr Coordination Committee | Page 1 Swedish/French Coordination Committee Håkan Danared Saclay, 13 January 2015

H. Danared | Sw/Fr Coordination Committee | Page 6

Cost, Scope, Schedule

ESS Cost Book

ACCSYS Requirements Level 1

ACCSYS High Level Master Schedule

Deliverables within a technical appendix defined, as usual, by cost, scope and schedule

Page 7: H. Danared | Sw/Fr Coordination Committee | Page 1 Swedish/French Coordination Committee Håkan Danared Saclay, 13 January 2015

H. Danared | Sw/Fr Coordination Committee | Page 7

• Since the launch of Expressions of Interest in spring 2013, discussions on in-kind are going on with 24 organizations. Out of these, 19 could deliver true in-kind contributions and 5 (?) will likely have to be paid from ESS cash budget.

• Possible in-kind partners to Accelerator have been identified in Denmark, Estonia, France, Germany, Italy, Norway, Poland, Spain, Sweden, Switzerland, UK.

• Value of items discussed with these partners represents 49% of accelerator budget, excluding cash contributions and paid contracts.

In-Kind to Accelerator

• Next step with many partners is to agree on technical details and write Scopes of Work.

• At the same time, political issues need to be solved at higher levels.

• Signed In-Kind Agreements are needed during 2015 in most cases.

Not IKC, 22%

Planned IKC, 49%

Potential IKC, 26%

Cash ”IKC”, 3%

Page 8: H. Danared | Sw/Fr Coordination Committee | Page 1 Swedish/French Coordination Committee Håkan Danared Saclay, 13 January 2015

H. Danared | Sw/Fr Coordination Committee | Page 8

Partner Institutions

True in-kind

CEACNRSCockcroft InstDaresbury LabElettraESS-BilbaoGSIHuddersfield UnivIFJ PANINFN CataniaINFN LegnaroINFN MilanNCBJRALTallinn UTTU LodzUniv OsloWarsaw UTWroclaw UT

Cash in-kind

Aarhus UnivDESYLund UnivPSIUppsala Univ

Page 9: H. Danared | Sw/Fr Coordination Committee | Page 1 Swedish/French Coordination Committee Håkan Danared Saclay, 13 January 2015

H. Danared | Sw/Fr Coordination Committee | Page 9

CEA

• Agreement (not contract) with CEA for RFQ, cavities and cryomodules, beam instrumentation and controls. Agreed value 72 055k€ for Accelerator.

• Heads of Agreement for urgent items:

• Doppler Shift Measurement Unit for the Low Energy Beam Transport Line• Emittance Measurement Unit for the Low Energy Beam Transport Line• Proton Source and LEBT Control System• RFQ Prototyping and Copper• High Beta Elliptical Cavity Cryomodule Technology Demonstator H-ECCTD,

• Signed by ESS, sent to CEA, returned to ESS, sent to CEA again.

• Technical annexes for in-kind contract to be elaborated.

Page 10: H. Danared | Sw/Fr Coordination Committee | Page 1 Swedish/French Coordination Committee Håkan Danared Saclay, 13 January 2015

H. Danared | Sw/Fr Coordination Committee | Page 10

CNRS

• Agreement (not contract) with CNRS on spoke cavities and cryomodules and cryo distribution for the spoke linac. Agreed value 19 899 k€.

• Controls (signal processing) for spoke cryomodules needed but not agreed. Costing for this to be developed.

• Additional scope on cryo distribution for elliptical linac offered to CNRS.

• Waiting for technical appendix for HoA with CNRS.

• Technical annexes for in-kind contract to be elaborated.

Page 11: H. Danared | Sw/Fr Coordination Committee | Page 1 Swedish/French Coordination Committee Håkan Danared Saclay, 13 January 2015

H. Danared | Sw/Fr Coordination Committee | Page 11

High-Level Schedule

Page 12: H. Danared | Sw/Fr Coordination Committee | Page 1 Swedish/French Coordination Committee Håkan Danared Saclay, 13 January 2015

H. Danared | Sw/Fr Coordination Committee | Page 12

Denmark

• Contract (not in-kind) on HEBT design and design and delivery of rastering magnet system under development, now 2nd iteration between Legal Offices.

• Technical Annex and Statement of Work essentially complete.

• Aim to sign contract before end of the year.

Page 13: H. Danared | Sw/Fr Coordination Committee | Page 1 Swedish/French Coordination Committee Håkan Danared Saclay, 13 January 2015

H. Danared | Sw/Fr Coordination Committee | Page 13

Estonia

• Visit to Tallinn University of Technology took place 2 October.

• Collaboration on alternative development of high-voltage module for klystron modulators proposed, but their development time would be too long.

• Collaboration on high-voltage module for IOT modulators proposed instead, waiting for reply.

• Value of in-kind contribution approximately 50 k€, additional financing with Estonian funds.

Page 14: H. Danared | Sw/Fr Coordination Committee | Page 1 Swedish/French Coordination Committee Håkan Danared Saclay, 13 January 2015

H. Danared | Sw/Fr Coordination Committee | Page 14

Germany

• Contracts with DESY paid with cash for now, with expectation of recognition as ”in kind” later.

• Contract on BPM pickup bodies and feedthroughs and on BPM and BCM FPGA firmware to be signed by ESS within 1-2 weeks(?). Total value roughly 100 k€.

• Slow progress in LLRF discussions(?). Proposed meeting not held yet.

• On-going discussions on consultancy and manpower for RF test stand.

• MoU signed with FAIR, mentioning beam instrumentation, cryogenics, vaccum and controls.

Page 15: H. Danared | Sw/Fr Coordination Committee | Page 1 Swedish/French Coordination Committee Håkan Danared Saclay, 13 January 2015

H. Danared | Sw/Fr Coordination Committee | Page 15

Italy

• On-going collaboration with INFN Catania on ion source, LEBT and WP3 management.

• On-going collaboration with INFN Legnaro on DTL.

• Proposal expected from INFN Milan within a few days on procurement and manufacturing follow-up of elliptical cavities.

• Discussions with Elettra on spoke amplifiers, beam instrumentation, and warm magnets with power supplies. Interest expressed by Elettra on manpower for installations.

• Italian process towards in-kind contracts taking place between INFN, Elettra and CNR. Contracts expected to be signed in spring 2015.

Page 16: H. Danared | Sw/Fr Coordination Committee | Page 1 Swedish/French Coordination Committee Håkan Danared Saclay, 13 January 2015

H. Danared | Sw/Fr Coordination Committee | Page 16

Norway

• Beam instrumentation has been discussed, unclear if it can materialize.

• Postdoc/ion source expert may be contributed as in-kind during two years.

Page 17: H. Danared | Sw/Fr Coordination Committee | Page 1 Swedish/French Coordination Committee Håkan Danared Saclay, 13 January 2015

H. Danared | Sw/Fr Coordination Committee | Page 17

Poland

• Recent decision in Council of Ministers for participation in ESS construction, so discussions with Poland expected to speed up.

• Institute of Nuclear Physics, IFJ PAN (Krakow) intends to contribute manpower for tests, installations, etc. Need to know scope fairly soon to plan for their staff.

• Lodz University of Technology have been collaborating with Warsaw University of Technology for LLRF to XFEL and propose to give a similar contribution to ESS.

• National Centre for Nuclear Research, NCBJ (Swierk) has on-going collaboration on design of collimators and are expected to deliver gamma blocker.

• Warsaw University of Technology will collaborate on phase-reference line and most likely on LLRF.

• Wroclaw University of Technology are ready to sign a HoA on cryogenic distribution (design as an initial stage), excluding the spoke linac. A pre-financing agreement is necessary, but no one has been in the position to sign such an agreement on the Polish side.

Page 18: H. Danared | Sw/Fr Coordination Committee | Page 1 Swedish/French Coordination Committee Håkan Danared Saclay, 13 January 2015

H. Danared | Sw/Fr Coordination Committee | Page 18

Spain

• HoA signed for MEBT, agreed value 4464 k€.

• Good progress on HoA appendix for RF of normal-conducting linac. Signature expected before the end of the year.

• Also discussion on beam instrumentation beyond that of the MEBT.

• Work on the Technical Annexes of the In-Kind Agreement should now start.

Page 19: H. Danared | Sw/Fr Coordination Committee | Page 1 Swedish/French Coordination Committee Håkan Danared Saclay, 13 January 2015

H. Danared | Sw/Fr Coordination Committee | Page 19

Sweden

• On-going collaboration on prototype spoke cavity and cryomodule test in the FREIA hall at Uppsala University.

• Draft contract for the next phase of the collaboration sent to Uppsala. This includes tests of spoke cavities and cryomodules, tests of spoke valvebox and 704 MHz RF tests originally foreseen to be performed in Lund.

• On-going collaboration with Lund University on development of LLRF. Prototyping of klystron modulators agreed, and contract for an RF test stand is being finalized.

Page 20: H. Danared | Sw/Fr Coordination Committee | Page 1 Swedish/French Coordination Committee Håkan Danared Saclay, 13 January 2015

H. Danared | Sw/Fr Coordination Committee | Page 20

Switzerland

• Discussions on beam instrumentation taking place with PSI.

Page 21: H. Danared | Sw/Fr Coordination Committee | Page 1 Swedish/French Coordination Committee Håkan Danared Saclay, 13 January 2015

H. Danared | Sw/Fr Coordination Committee | Page 21

United Kingdom

• Beam instrumentation is being discussed with Cockcroft Institute

• Discussions with Daresbury Lab on vacuum (technical scope almost final), elliptical cavities (details being elaborated) and beam instrumentation

• Huddersfield University will provide waveguides and related equipment for the superconducting linac

• Beam instrumentation is being discussed with RAL/ISIS

• All UK contributions go through the STFC. Legal part of IK agreement expected to be signed this year. Technical appendices to follow.