hamanasi truss installation graphics 22-28 february 2014
DESCRIPTION
HAMANASI Truss Installation Graphics 22-28 February 2014 . DAY 1 22 February 2014. Move Crane I nto Position. DAY 1. Set Up Staging Area. DAY 1. DAY 2 23 February 2014. Fly and Fit Truss #1. DAY 2. Fly and Fit Truss #2. DAY 2. Fly and Fit Truss #3. DAY 2. - PowerPoint PPT PresentationTRANSCRIPT
Truss Instellation
HAMANASI Truss Installation Graphics22-28 February 2014 DAY 122 February 2014Move Crane Into PositionDAY 1Set Up Staging AreaDAY 1DAY 223 February 2014Fly and Fit Truss #1
DAY 2Fly and Fit Truss #2
DAY 2Fly and Fit Truss #3
DAY 2Install Rafter Plates + Purlins
DAY 2Fly and Fit Hip Truss - #1
DAY 2DAY 324 February 2014Fly Hip Truss - #2
DAY 3Fly and Fit End Rafter
DAY 3Fly and Fit Hip Truss - #3
DAY 3Fly and Fit Hip Truss - #4
DAY 3DAY 425 February 2014Fit Hip Rafter Plates
DAY 4Fit Hip Purlins
DAY 4l
DAY 4Assemble Widows Walk Walls
DAY 4DAY 526 February 2014Fly Widows Walk Walls - #1
DAY 5Fly Widows Walk Wall - #2
DAY 5Fit Center Beam
DAY 5Fit Center Beam
DAY 5Finish Widows Walk
DAY 627 February 2014Clean Up Loose endsDAY 6DAY 728 February 2014Load Out and Contingency DAY 7NOTESTruss Packaging For Transport