hangar one update 2010/07/08, moffett restoration advisory board
DESCRIPTION
Presentation by Mike Schulz of AMEC Earth and Environmental (Navy contractor) on the Hangar One Removal Action.TRANSCRIPT
![Page 1: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/1.jpg)
1
Former NAS Moffett FieldFormer NAS Moffett Field
Hangar 1 Removal Action UpdateHangar 1 Removal Action Update
Mike Schulz, PMP
AMEC Earth & Environmental, Inc.
July 8, 2010RAB Meeting
![Page 2: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/2.jpg)
Presentation OverviewPresentation Overview
• Project Objective and Approach• Progress to Date
Community Outreach Biological Survey Asbestos Survey Mobilization
• Future Activities• Schedule• Questions
Work Plans Coating Condition Survey Pre-construction
Sampling
2
![Page 3: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/3.jpg)
3
• Control release of PCBs from Hangar 1 in accordance with EE/CA (July 2008) and Action Memorandum (December 2008)Demolition of interior structuresRemoval of contaminated sidingApplication of weather-resistant coating to steel frame
Project Objective
![Page 4: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/4.jpg)
4
Project Approach
• Use of interior scaffold system to promote safety and contaminant control
• Use of the hangar shell as containment during interior demolition and coating
• Epoxy coating system with proven performance• Rigorous air monitoring program
![Page 5: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/5.jpg)
5
• RAB presentation November 2009• Fact Sheet January 2010• NASA briefing January 2010• Video documentation• RAB tour July 2010
Community Outreach Update
![Page 6: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/6.jpg)
RAB Tour of Cork RoomRAB Tour of Cork Room
6
![Page 7: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/7.jpg)
Work Plan StatusWork Plan Status
• Accident Prevention Plan (February 2010)
• Final Sampling and Analysis Plan (April 2010)
• Final Work Plan (June 2010)
• Biological Hazard Abatement Plan
7
![Page 8: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/8.jpg)
Biological Survey Biological Survey
• Biological surveys conducted January – April 2010• Final Biological Survey Report submitted May 2010• Species observed:
8
White-throated Swift Common Raven Barn Owl Cliff Swallow House Finch Burrowing Owl Coyote, Gray Fox, Red Fox Black-tailed Jack Rabbit California Ground Squirrel
Inactive Cliff Swallow nest
![Page 9: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/9.jpg)
Biological Survey RecommendationsBiological Survey Recommendations
• Recommendations approved by California Department of Fish & Game and US Fish & Wildlife Service
9
Remove inactive nests Protect active Raven nest Periodic nesting surveys Monitor and protect
Burrowing Owls
Inspection of clamshell doors for Swift nests
![Page 10: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/10.jpg)
Burrowing Owl LocationsBurrowing Owl Locations
10
Construction fence approximately 175 Feet north of active burrow
![Page 11: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/11.jpg)
Coating Condition SurveyCoating Condition Survey
• Evaluated condition of existing coating on steel frame in accordance with Society of Protective Coatings TU-3: Rust Corrosion Peeling/Blistering Cracking/Checking Chalking Film Thickness Adhesion
• Evaluated performance of new coating system adhesion Patch tests
11
Patch test on new coating
![Page 12: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/12.jpg)
Coating Condition Survey ResultsCoating Condition Survey Results
• Adhesion of existing coating very good at all locations tested – Average adhesion strength of 603 psi– 200 psi is acceptable
• Recommended coating system:– Carbomastic 15 (CM15) aluminum epoxy mastic– Surface preparation by low-pressure water cleaning and
localized abrasive blasting or power tool cleaning– Application by spray, brush, or roller at 3 – 10 mils
• Excellent adhesion of CM15 coating system demonstrated in all tests (550 psi – 675 psi)
12
![Page 13: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/13.jpg)
PrePre--Construction SamplingConstruction Sampling
• Soil Areas– 110 samples collected from soil areas– 20 samples >1,000 μg/kg PCB action limit– PCB contamination restricted to upper 6
inches– Contaminated soil will be excavated and
disposed off site• Storm Drain Trench Sediment
– 4 samples collected from the storm drain– All samples exceed PCB action limit– Sediment will be removed by vacuum
methods and disposed off site
13
![Page 14: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/14.jpg)
Baseline Sampling ResultsBaseline Sampling Results
14
![Page 15: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/15.jpg)
Asbestos SurveyAsbestos Survey
• Inspection of all building materials completed in May 2010• Over 300 samples collected• Asbestos-Containing Materials include:
Floor tile Pipe insulation Drywall and plaster on walls Roofing on interior buildings Mastics under flooring Fire doors, file cabinets and safes Window sealants and caulk Gaskets on electrical fixtures Sealant between siding and steel frame
15
![Page 16: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/16.jpg)
Examples of Asbestos MaterialsExamples of Asbestos Materials
16
Drywall Mastic under flooring
Duct tape and wrap Light fixture gaskets
![Page 17: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/17.jpg)
17
Asbestos Abatement Controls
• Compliance with OHSA and Cal. Code of Regulations (CCR Title 8)
• Install containment barriers and negative air pressure
• Air monitoring supervised by Certified Industrial Hygienist
• Post abatement inspection and clearance sampling
• All work under direction of California Asbestos Consultant
![Page 18: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/18.jpg)
1818
Air Monitoring Plan - Interior
![Page 19: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/19.jpg)
1919
Air Monitoring Plan - Exterior
![Page 20: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/20.jpg)
MobilizationMobilization
• Temporary construction fence• Owl buffer zone • Utility termination • Decontamination areas • Lay down areas• Storm water controls • Air monitoring stations • Command post • Worker orientation• Ellis Gate open
20
![Page 21: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/21.jpg)
21
Site Plan
![Page 22: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/22.jpg)
Preservation of Historic ArtifactsPreservation of Historic Artifacts
22
![Page 23: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/23.jpg)
Future ActivitiesFuture Activities
• Continue biological monitoring• Complete decontamination of salvaged items• Asbestos abatement• Demolition of interior structures• Repair of secondary structural steel members • Scaffold installation• Siding removal and coating • Community outreach meetings• Fact sheets
23
![Page 24: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/24.jpg)
24
Interior Demolition
• Combination of manual and machine demolition methods• Designed to protect structural integrity of the hangar
![Page 25: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/25.jpg)
25
Siding Removal Plan
• Phase work in 6 Zones• Start on the south end
• Work from roof to ground• Coordinated with coating
![Page 26: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/26.jpg)
26
ScheduleSchedule
• Start asbestos abatement anticipatedJuly 2010
• Start interior demolition anticipatedOctober 2010
• Start siding removal Spring 2011
• Complete siding removal and coating Winter 2011
• Submit final report Spring 2012
![Page 27: Hangar One Update 2010/07/08, Moffett Restoration Advisory Board](https://reader034.vdocuments.net/reader034/viewer/2022051611/54b60b354a7959e6128b4781/html5/thumbnails/27.jpg)
27
Questions
Point of Contact
Kathryn Stewart, P.E.BRAC Environmental Coordinator
(619) [email protected]