where do we stand with the non-conformities?. Hardware C ommissioning : where are we?. Roberto Saban. The major non-conformities. The helium guards of the level gauges of the SSSs Connection cryostats PIMs The hoses of the water cooled cables - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Hardware   C ommissioning : where are we?

Review of the commissioning of

Sector45Hardware Commissioning :

where are we?

Roberto Saban

where do we stand with the non-conformities?

Page 2: Hardware   C ommissioning : where are we?

• The helium guards of the level gauges of the SSSs

• Connection cryostats • PIMs • The hoses of the water cooled cables • Connections of the flexible water

pipes to the water cooled cables• Coupling between bus-bar cables• Jacks

The major non-conformities

March 3, 2008 Roberto Saban - eLTC - Where are we with HC?

2

Page 3: Hardware   C ommissioning : where are we?

The helium guards of the level gauges in the SSSs

March 3, 2008 Roberto Saban - eLTC - Where are we with HC? 3Courtesy JP.Tock

The pinch-off tube was blocking the closure of the interconnect. To progress, and transgressing the instructions given by CERN, IEG decided to rotate it to allow closure.

Sector To be replaced Done Remark1-2 24 12 Completed2-3 9 8 Completed3-4 3 3 Completed4-5 8 ? 0 During shutdown of 4-55-6 13 ? 0 After warm-up6-7 25 25 Completed7-8 7 7 Completed8-1 1 1 Completed

Suspected Done

Page 4: Hardware   C ommissioning : where are we?

Connection cryostat

March 3, 2008 Roberto Saban - eLTC - Where are we with HC? 4Courtesy JP.Tock

Page 5: Hardware   C ommissioning : where are we?

Connection cryostat

March 3, 2008 Roberto Saban - eLTC - Where are we with HC? 5Courtesy JP.Tock

Page 6: Hardware   C ommissioning : where are we?

Connection cryostat

March 3, 2008 Roberto Saban - eLTC - Where are we with HC? 6

The delay in 6-7 is due to setting-up of measurement procedures in parallel with 7-8 and the fire brigade exercise

Courtesy JP.Tock

1.5 mm

Measurement of displacement in SM18 on a test cryostat after the closure of a vacuum vessel (Displacement of about 1.5 mm). An attempt was made to compensate by welds on the other side but limited effect (0.3 mm)

Page 7: Hardware   C ommissioning : where are we?

• The friction coefficient is low

• No large differences with vacuum or temperature

• For the 3 tested pairs only few indications of stick slip of a single finger

• No buckled fingers BY CHANCE

Sliding force measurements of the RF contact of the PIMs at 15 K and in UHV

March 3, 2008 Roberto Saban - eLTC - Where are we with HC? 7Courtesy K.Artoos

... these friction tests give usthe last information needed to prove that the baseline design is safe. The simulations show that, for any given span within specification, much higher frictions would be needed to damage a conforming finger.

The conclusion

Page 8: Hardware   C ommissioning : where are we?

Sliding force measurements of the RF contact of the PIMs at 15 K and in UHV

March 3, 2008 Roberto Saban - eLTC - Where are we with HC? 8Courtesy K.Artoos

Page 9: Hardware   C ommissioning : where are we?

• The most optimistic scenario foresees a number of up to 24 damaged PIMs. It was decided that in any case if a damaged PIM is to be replaced in one V-line, the second PIM of the same interconnect will also be replaced.

• There are enough spares available at CERN to face even a pessimistic scenario. BINP have received the raw material for the production of some 500 spare sets of fingers, which will allow repairing two sectors before having to repair PIMs recovered from the LHC

Sector 45 consolidation: the PIMs

March 3, 2008 Roberto Saban - eLTC - Where are we with HC? 9Courtesy P.Strubin

Page 10: Hardware   C ommissioning : where are we?

Sector 45 consolidation: the PIMs

March 3, 2008 Roberto Saban - eLTC - Where are we with HC? 10

If a reasonable number of PIMs are found with buckled fingers: 1. Ball test to localise failed PIMs (2 per beam line) to an accuracy of one half cell

[Alternate V1/V2 everyday]2. Venting of the concerned vacuum sector 3. Opening of the QQBI IC of this sector4. Cutting of the PIM on the relevant line – Endoscopic inspection (+/- 100m)5. Installation of a replacement or dummy PIM - In parallel radar type measurement 6. Gamma-ray of the other PIM7. Loop to clear the whole sector8. Test of the photometer using cut PIMs if possible9. In parallel, preparation of replacing PIMs10. Rewelding of PIMs – Ball test to validate the sector11. Leak test of beam lines – Displace SSS downwards12. Reclosure of IC13. Pumping and leak test of insulation vacuum – RF reference measurements

Courtesy JP.Tock

Page 11: Hardware   C ommissioning : where are we?

Sector 45 consolidation: the plan

March 3, 2008 Roberto Saban - eLTC - Where are we with HC? 11

1 Plug-in modules 7 weeks2 Photometer test 3 days3 Y lines 3 weeks4 Helium guards 2 weeks5 Leaks 3 weeks ?6 Triplet 5L 8 weeks7 Q5R4 2 weeks ? 8 Connection Cryostats 5 weeks9 CC splices 1 day

10 DFBs cables ?

Sector 4-5 Consolidation

Scheduled to start on March 17, 2008and last for 8 weeks

Courtesy JP.Tock

Page 12: Hardware   C ommissioning : where are we?

Results from the mixing of circuits in three conductor superconducting bus bar cables

Coupling between bus-bar cables

March 3, 2008 Roberto Saban - eLTC - Where are we with HC? 12

Q7

HCMATM

DFBA Position

DFBAH 4RDFBAI 5LDFBAO 8L

DFBAA 1LDFBAP 8R

DFBL Position

DFBLD 5LDFBLA 1RDFBLB 1L

Decision to go ahead: pending!

Page 13: Hardware   C ommissioning : where are we?

• The corrosion observed on one of the cables of the DFBX right of Point 8 has not been observed elsewhere

• Flohe and Continental have agreed to replace all the hoses since they are not compliant with the specs.

• Nevertheless, in the light of the damage that could be caused to equipment (DFBs, power converters, etc), it was decided to postpone the campaign to when and if it becomes really necessary.

• TS and purchasing are negotiating with Flohe an arrangement.

Water cooled cables

March 3, 2008 Roberto Saban - eLTC - Where are we with HC? 13

Page 14: Hardware   C ommissioning : where are we?

The connection was glued with Loctite but because of the torque exerted by the flexible on the junction, they started to leak

flexible water pipes and water cooled cables

March 3, 2008 Roberto Saban - eLTC - Where are we with HC? 14

The answer is a rotating union system which cancels the torque and is being installed everywhere in the machine.

Page 15: Hardware   C ommissioning : where are we?

Jacks & concrete

March 3, 2008 Roberto Saban - eLTC - Where are we with HC? 15

Result in a tilt of 1.5 mrad and a longitudinal displacement of - 5 mm

Always in the neighbourhood of an SSS which contains a vacuum barrier

Page 16: Hardware   C ommissioning : where are we?

The Sector 45 Commissioning Review

16March 3, 2008

The introduction The overview of Sector 45Safety & accessThe systems:

Cryogenics, DFBs and current leadsPowering, Power Converters, Quench Protection System, 600 A and 13 kA Energy ExtractionThe tests and the analysis:Powering tests and Magnet Performance Panel The tools:Post-Mortem, Logging, Sequencer, Tracking data and progress after the testsSummary and discussions

Roberto Saban - eLTC - Where are we with HC?

Page 17: Hardware   C ommissioning : where are we?

The months to come

March 3, 2008 Roberto Saban - eLTC - Where are we with HC? 17

ICC February 15th

fewThe few months to come

Page 18: Hardware   C ommissioning : where are we?

March 3, 2008 Roberto Saban - eLTC - Where are we with HC? 18

ICC February 15th

The strategic questionsSectors in parallel versus circuit types in parallel

7 TeV versus a lower value which is straightforward to achieve? What lower value?

Systematic commissioning of every circuit to nominal current versus maximum currents determined by the machine optics and the target beam energy

Page 19: Hardware   C ommissioning : where are we?

• we know how to repair the mechanical non conformities

• there is an intervention plan which is compatible with the present schedule

• for the coupling between bus bars in some of the DFBs (which was not observed during the commissioning campaign) a decision is pending

Non conformities: a summary

March 3, 2008 Roberto Saban - eLTC - Where are we with HC? 19

Page 20: Hardware   C ommissioning : where are we?

• A lot of progress in terms of safety, tools, procedures, organization, integration of the teams

• A reduction of the commissioning time was observed mainly thanks to the automatic control and analysis tools which were developed and to the simplification of the procedures

• A further reduction is expected to be achieved essentially by:1. Commissioning the circuits to an easily achievable

lower beam energy2. Commissioning each circuit to a nominal current

determined by the optics3. Further simplification of the commissioning procedures

The Sector 45 Review: a summary

March 3, 2008 Roberto Saban - eLTC - Where are we with HC? 20