hazard & operability studies - seveso ii · hazard & operability studies ... yet it is in...
TRANSCRIPT
HAZARD & OPERABILITY STUDIES
INTRODUCTION
The technique of Hazard and Operability Studies, or in more common
terms HAZOPS, has been used and developed over approximately four
decades for 'identifying potential hazards and operability problems' caused
by 'deviations from the design intent' in both new and existing process
plants. Before progressing further, it might be as well to clarify some
aspects of these statements.
Potential Hazard AND Operability Problems
You will note the capitalised 'AND' in the heading above. Because of the
high profile of production plant accidents, emphasis is too often placed
upon the identification of hazards to the neglect of potential operability
problems. Yet it is in the latter area that benefits of a Hazop Study are
usually the greatest. To quote an example, a study was commissioned for
a new plant. Some two years previously, and for the first time, a similar
study had been carried out on different plant at the same site that was
then in the process of being designed. Before the latest review
commenced, the Production Manager expressed the hope that the same
benefits would accrue as before, stating that "in his twenty years of
experience, never had a new plant been commissioned with so few
problems, and no other plant had ever achieved its production targets and
break-even position in so short a time".
Deviation from Design Intent
To deal firstly with 'design intent', all industrial plant is designed with an
overall purpose in mind. It may be to produce a certain tonnage per year
of a particular chemical, to manufacture a specified number of cars, to
process and dispose of a certain volume of effluent per annum, etc. That
could be said to be the main design intent of the plant, but in the vast
majority of cases it would also be understood that an important subsidiary
intent would be to conduct the operation in the safest and most efficient
manner possible.
With this in mind equipment is designed and constructed which, when it is
all assembled and working together, will achieve the desired
goals. However, in order to do so, each item of equipment, each pump
and length of pipework, will need to consistently function in a particular
manner. It is this manner that could be classified as the 'design intent' for
that particular item. To illustrate, imagine that as part of the overall
production requirement we needed a cooling water facility. For this we
would almost certainly have cooling water circuit pipework in which would
be installed a pump as very roughly illustrated below.
A much simplified statement as to the design intent of this small section of
the plant would be "to continuously circulate cooling water at an initial
temperature of xx°C and at a rate of xxx litres per hour". It is usually at
this low level of design intent that a Hazop Study is directed. The use of
the word 'deviation' now becomes more easy to understand. A deviation
or departure from the design intent in the case of our cooling facility
would be a cessation of circulation, or the water being at too high an
initial temperature. Note the difference between adeviation and
its cause. In the case above, failure of the pump would be a cause, not a
deviation.
Industries in which the technique is employed
Hazops were initially 'invented' by ICI in the United Kingdom, but the
technique only started to be more widely used within the chemical process
industry after the Flixborough disaster in 1974. This chemical plant
explosion killed twenty eight people and injured scores of others, many of
those being members of the public living nearby. Through the general
exchange of ideas and personnel, the system was then adopted by the
petroleum industry, which has a similar potential for major disasters. This
was then followed by the food and water industries, where the hazard
potential is as great, but of a different nature, the concerns being more to
do with contamination rather than explosions or chemical releases.
The reasons for such widespread use of Hazops
Safety and reliability in the design of plant initially relies upon the
application of various codes of practise, or design codes and
standards. These represent the accumulation of knowledge and
experience of both individual experts and the industry as a whole. Such
application is usually backed up by the experience of the engineers
involved, who might well have been previously concerned with the design,
commissioning or operation of similar plant.
However, it is considered that although codes of practise are extremely
valuable, it is important to supplement them with an imaginative
anticipation of deviations that might occur because of, for example,
equipment malfunction or operator error. In addition, most companies
will admit to the fact that for a new plant, design personnel are under
pressure to keep the project on schedule. This pressure always results in
errors and oversights. The Hazop Study is an opportunity to correct these
before such changes become too expensive, or 'impossible' to accomplish.
Although no statistics are available to verify the claim, it is believed that
the Hazop methodology is perhaps the most widely used aid to loss
prevention. The reason for this can most probably be summarised as
follows:
It is easy to learn.
It can be easily adapted to almost all the operations that are carried
out within process industries.
No special level of academic qualification is required. One does not
need to be a university graduate to participate in a study.
THE BASIC CONCEPT
Essentially the Hazops procedure involves taking a full description of a
process and systematically questioning every part of it to establish how
deviations from the design intent can arise. Once identified, an
assessment is made as to whether such deviations and their consequences
can have a negative effect upon the safe and efficient operation of the
plant. If considered necessary, action is then taken to remedy the
situation.
This critical analysis is applied in a structured way by the Hazop team, and
it relies upon them releasing their imagination in an effort to discover
credible causes of deviations. In practice, many of the causes will be
fairly obvious, such as pump failure causing a loss of circulation in the
cooling water facility mentioned above. However, the great advantage of
the technique is that it encourages the team to consider other less obvious
ways in which a deviation may occur, however unlikely they may seem at
first consideration. In this way the study becomes much more than a
mechanistic check-list type of review. The result is that there is a good
chance that potential failures and problems will be identified that had not
previously been experienced in the type of plant being studied.
Keywords
An essential feature in this process of questioning and systematic analysis
is the use of keywords to focus the attention of the team upon deviations
and their possible causes. These keywords are divided into two sub-sets:
Primary Keywords that focus attention upon a particular aspect
of the design intent or an associated process condition or
parameter.
Secondary Keywords that, when combined with a primary
keyword, suggest possible deviations.
The entire technique of Hazops revolves around the effective use of these
keywords, so their meaning and use must be clearly understood by the
team. Examples of often used keywords are listed below.
Primary Keywords
These reflect both the process design intent and operational aspects of the
plant being studied. Typical process oriented words might be as
follows. The list below is purely illustrative, as the words employed in a
review will depend upon the plant being studied.
Flow Temperature
Pressure Level
Composition Separate (settle, filter,
centrifuge)
React Mix
Reduce (grind, crush, etc.) Absorb
Corrode Erode
Note that some words may be included that appear at first glance to be
completely unrelated to any reasonable interpretation of the design intent
of a process. For example, one may question the use of the word
Corrode, on the assumption that no one would intend that corrosion
should occur. Bear in mind, however, that most plant is designed with a
certain life span in mind, and implicit in the design intent is that corrosion
should not occur, or if it is expected, it should not exceed a certain
rate. An increased corrosion rate in such circumstances would be a
deviation from the design intent.
Remembering that the technique is called Hazard & Operability Studies,
added to the above might be relevant operational words such as:
Isolate Drain
Vent Purge
Inspect Maintain
Startup Shutdown
This latter type of Primary Keyword is sometimes either overlooked or
given secondary importance. This can result in the plant operator having,
for example, to devise impromptu and sometimes hazardous means of
taking a non-essential item of equipment off-line for running repairs
because no secure means of isolation has been provided. Alternatively, it
may be discovered that it is necessary to shut down the entire plant just
to re-calibrate or replace a pressure gauge. Or perhaps during
commissioning it is found that the plant cannot be brought on-stream
because no provision for safe manual override of the safety system trips
has been provided.
Secondary Keywords
As mentioned above, when applied in conjunction with a Primary Keyword,
these suggest potential deviations or problems. They tend to be a
standard set as listed below:
Word Meaning
No The design intent does not occur (e.g. Flow/No), or the
operational aspect is not achievable (Isolate/No)
Less A quantitative decrease in the design intent occurs (e.g.
Pressure/Less)
More A quantitative increase in the design intent occurs (e.g.
Temperature/More)
Reverse The opposite of the design intent occurs (e.g. Flow/Reverse)
Also The design intent is completely fulfilled, but in addition some
other related activity occurs (e.g. Flow/Also indicating
contamination in a product stream, or Level/Also meaning
material in a tank or vessel that should not be there)
Other The activity occurs, but not in the way intended (e.g.
Flow/Other could indicate a leak or product flowing where it
should not, or Composition/Other might suggest unexpected
proportions in a feedstock)
Fluctuation The design intention is achieved only part of the time (e.g. an
air-lock in a pipeline might result in Flow/Fluctuation)
Early Usually used when studying sequential operations, this would
indicate that a step is started at the wrong time or done out
of sequence
Late As for Early
It should be noted that not all combinations of Primary/Secondary words
are appropriate. For example, Temperature/No (absolute zero or -273°C
!) or Pressure/Reverse could be considered as meaningless.
HAZOP STUDY METHODOLOGY
In simple terms, the Hazop study process involves applying in a
systematic way all relevant keyword combinations to the plant in question
in an effort to uncover potential problems. The results are recorded in
columnar format under the following headings:
DEVIATION CAUSE CONSEQUENCE SAFEGUARDS ACTION
In considering the information to be recorded in each of these columns, it
may be helpful to take as an example the simple schematic below. Note
that this is purely representational, and not intended to illustrate an actual
system.
DEVIATION
The keyword combination being applied (e.g. Flow/No).
CAUSE
Potential causes that would result in the deviation occurring. For example
"Strainer S1 blockage due to impurities in Dosing Tank T1" might be a
cause of Flow/No.
CONSEQUENCE
The consequences that would arise, both from the effect of the deviation
such as "Loss of dosing results in incomplete separation in V1" and if
appropriate, from the cause itself, for example "Cavitation in Pump P1,
with possible damage if prolonged".
Always be explicit in recording the consequences. Do not assume that the
reader at some later date will be fully aware of the significance of a
statement such as "No dosing chemical to Mixer". It is much better to add
the explanation as set out above.
When assessing the consequences, one should not take any credit for
protective systems or instruments that are already included in the
design. For example, suppose the team had identified a cause of Flow/No
(in a system that has nothing to do with the one illustrated above) as
being spurious closure of an actuated valve. It is noticed that there is
valve position indication within the Central Control Room, with a software
alarm on spurious closure. They may be tempted to curtail consideration
of the problem immediately, recording something to the effect of "Minimal
consequences, alarm would allow operator to take remedial
action". However, had they investigated further they might have found
that the result of that spurious valve closure would be overpressure of an
upstream system, leading to a loss of containment and risk of fire if the
cause is not rectified within three minutes. It only then becomes apparent
how inadequate is the protection afforded by this software alarm.
SAFEGUARDS
Any existing protective devices that either prevent the cause or safeguard
against the adverse consequences would be recorded in this column. For
example, you may consider recording "Local pressure gauge in discharge
from pump might indicate problem was arising". Note that safeguards
need not be restricted to hardware… where appropriate, credit can be
taken for procedural aspects such as regular plant inspections (if you are
sure that they will actually be carried out!).
ACTION
Where a credible cause results in a negative consequence, it must be
decided whether some action should be taken. It is at this stage that
consequences and associated safeguards are considered. If it is deemed
that the protective measures are adequate, then no action need be taken,
and words to that effect are recorded in the Action column.
Actions fall into two groups:
1. Actions that remove the cause.
2. Actions that mitigate or eliminate the consequences.
Whereas the former is to be preferred, it is not always possible, especially
when dealing with equipment malfunction. However, always investigate
removing the cause first, and only where necessary mitigate the
consequences. For example, to return to the "Strainer S1 blockage due to
impurities etc." entry referred to above, we might approach the problem
in a number of ways:
Ensure that impurities cannot get into T1 by fitting a strainer in
the road tanker offloading line.
Consider carefully whether a strainer is required in the suction to
the pump. Will particulate matter pass through the pump without
causing any damage, and is it necessary to ensure that no such
matter gets into V1. If we can dispense with the strainer
altogether, we have removed the cause of the problem.
Fit a differential pressure gauge across the strainer, with perhaps
a high dP alarm to give clear indication that a total blockage is
imminent.
Fit a duplex strainer, with a regular schedule of changeover and
cleaning of the standby unit.
Three notes of caution need to be borne in mind when formulating
actions. Do not automatically opt for an engineered solution, adding
additional instrumentation, alarms, trips, etc. Due regard must be taken
of the reliability of such devices, and their potential for spurious operation
causing unnecessary plant down-time. In addition, the increased
operational cost in terms of maintenance, regular calibration, etc. should
also be considered (the lifetime cost of a simple instrument will be at least
twice its purchase price… for more complex instrumentation this figure
would be significantly greater). It is not unknown for an over-engineered
solution to be less reliable than the original design because of inadequate
testing and maintenance.
Finally, always take into account the level of training and experience of
the personnel who will be operating the plant. Actions that call for
elaborate and sophisticated protective systems are wasted, as well as
being inherently dangerous, if operators do not, and never will,
understand how they function. It is not unknown for such devices to be
disabled, either deliberately or in error, because no one knows how to
maintain or calibrate them.
Considering all Keywords - The Hazop procedure
Having gone through the operations involved in recording a single
deviation, these can now be put into the context of the actual study
meeting procedure. From the flow diagram below it can be seen that it is
very much an iterative process, applying in a structured and systematic
way the relevant keyword combinations in order to identify potential
problems.
FULL RECORDING versus RECORDING BY EXCEPTION
In the early days of Hazop Studies, it was usual to record only the
potential deviations that carried with them some negative
consequence. This might well have been because such studies were only
for internal use within a company. Also, with manually handwritten
records, it certainly reduced the time taken, both in the study itself and
the subsequent production of the Hazop Report. Such methodology is
classed as "Recording by exception", where it is assumed that anything
not included is deemed to be satisfactory.
Latterly, it has become more the accepted practice to set down
everything, stating clearly each keyword combination applied to the
system. Where applicable, this would be followed by a statement
indicating either that no Cause could be identified, or alternatively that no
Consequence arose from the Cause recorded. This is classified as "Full
recording", and it results in a Hazop Report that demonstrates
unambiguously to outside parties that a rigorous study has been
undertaken. In addition, it produces a comprehensive document that will
greatly assist in the speedy assessment of the safety and operability of
later plant modifications (do they impinge upon a potential deviation that
was originally recognised as being credible, but which involved at that
time no negative consequences ?).
Bearing the above in mind, it is recommended that "Full recording" is
instituted. With the use of a computer, the previous concern regarding
time, both in the study and the reporting, is all but eliminated. To make
this methodology easier to handle efficiently, text macros should be set up
as follows:
1. No potential causes identified.
2. No significant negative consequences identified.
3. No action required - existing safeguards considered adequate.
These macros can be used in the appropriate circumstances to quickly
record the reason for not pursuing a keyword combination.
In addition to the above, the pseudo Secondary
words 'All' and 'Remainder' are often used. These are employed in the
following circumstances:
For a particular Primary Keyword (e.g. Flow), some combinations
have been identified as having credible Causes (e.g. Flow/No,
Flow/Reverse). Having explored all other relevant combinations
(Flow/Less, Flow/More, Flow/Other, etc.), no other Causes could
be identified. The combination "Flow/Remainder" is therefore
used, with the macro in (1) above.
Having explored all relevant combinations for a particular Primary
word, no potential deviations could be identified. The
combination "Flow/All" is therefore used, with the macro in (1)
above.
Use of these pseudo Secondary Keywords greatly improves the readability
of the final report, as it eliminates countless repetitive entries, all with a
similar format (i.e. Keyword combination with "No potential causes
identified"). However, to make it a robust system, the introduction to the
Hazop Report must list clearly the Secondary Keywords that were globally
applied to each Primary Keyword; in other words, the 'relevant
combinations'. This will give an unambiguous meaning to the words 'All'
and 'Remainder'.
Note that such an approach should only be adopted where no credible
Cause is identified. In cases where the potential deviation is considered
possible, but no significant consequence ensues, then both keywords
should be recorded, together with the actual Cause identified, and macro
(2) in the Consequence column.
THE HAZOP TEAM
The team who will conduct the Hazop study should consist of personnel
with a good understanding of the process and plant to be reviewed. The
group should ideally contain about six members, with perhaps an absolute
upper limit being set at nine. In a study in which both contractor and
client are participating, it is desirable to maintain a balance between the
two in terms of team membership so that neither side feels outnumbered.
The participants should consist of people from a range of disciplines, and
this aspect is one of the strengths of the Hazop methodology:
With a team of people, each with differing backgrounds and
experience, potential problems are likely to be identified that
might be missed by one or two people working on their own.
It is often the case that one person's solution can become a
problem to another department within the project. For example,
a Process Engineer conducting his own review in isolation may
identify a potential problem for which he considers that another
instrument and alarm would be desirable. When this requirement
is passed to the Control & Instrumentation Engineer, it transpires
that no suitable channels are available within the appropriate
section of the electronic control system, which has already been
ordered and is currently being manufactured by the vendor. A
protracted inter-departmental discussion and correspondence
then ensues as to possible alternative remedies, and the potential
cost penalty of re-specifying the control system. All of this could
have been settled within a few minutes had both departments
participated in the study.
A spirit of co-operation and common purpose is engendered that
crosses departmental boundaries, and this will persist even after
the Hazop Study has been completed. Personnel will understand
better the views, concerns and constraints within which other
disciplines have to work, and will take these into account when
making decisions affecting the project.
The actual composition of the Hazop team will vary according to the type
of plant being reviewed. One person who should always be included is a
representative from Operations. He or she should have first hand
experience of day-to-day operations on either the plant being reviewed, or
one that is very similar in nature. The contribution of this team member
to the discussion can be invaluable, as it introduces an operational
perspective to other participants who may have never, for example, had
to climb down into a vessel wearing breathing apparatus to carry out
repairs or an inspection.
To summarise, a team should be selected so that a balanced approach to
the study is ensured. In addition, the intention should be that questions
raised during the meeting can be answered immediately, rather than
having to resort to the time consuming process of referring to outside
expertise. It is not of course necessary for the same people to participate
in the study from beginning to end. If the "core" of the group consisted of
five people, for example, additional members could be called in from
session to session as and when their particular expertise was needed.
As with all group activities, there needs to be a person appointed who will
be in overall charge; with Hazop Studies this person is usually called the
Chairman or Study Leader. Ideally, he should not have been too closely
associated with the project under review as there might be a risk of him
not being sufficiently objective in his direction of the team. As the
Chairman's role is of vital importance in the smooth and efficient progress
of the study, he should be carefully chosen and be fully conversant with
the Hazop methodology.
Another important member of the team will be the Secretary. His
contribution to the discussion may well be minimal, as his main function
during the sessions will be to record the study as it proceeds. He will
therefore need to have sufficient technical knowledge to be able to
understand what is being discussed.
(Note to the reader: The above few paragraphs, as well as some that follow, are rather
male-specific, referring as they do to 'he', ' him' and 'his'. This is purely to avoid the
grammatical contortions involved with repeatedly referring to 'he or she', 'his or her',
etc., up to three times in a single sentence. Note that there are many excellent female
Study Leaders and Secretaries, who have organised, guided and participated in very successful Hazop Reviews).
PREPARATORY WORK
It is most important that, before a study commences, work that can be
conveniently done beforehand is carried out. This is not only essential in
some respects for the proper structuring of the study and the team, but
will also greatly increase the efficiency of the Hazop and thus retain the
interest and enthusiasm of the participants.
This preparatory work will be the responsibility of the Chairman, and the
requirements can be summarised as follows:
1. Assemble the data
2. Understand the subject
3. Subdivide the plant and plan the sequence
4. Mark-up the drawings
5. Devise a list of appropriate Keywords
6. Prepare Node Headings and an Agenda
7. Prepare a timetable
8. Select the team
Assemble the data
All relevant documentation should be collected beforehand. Typically this
might consist of:
1. A Process Flow Diagram.
2. A comprehensive Process Description containing operating
parameters, flow rates, volumes, etc., as well as a brief summary
of how each plant item functions.
3. P&IDs.
4. Cause & Effect Charts setting out how control and trip systems
operate.
5. Details of vendor packages if available.
6. Plant layout diagrams.
Understand the subject
The Chairman should take as much time as is necessary to gain a good
understanding of how the plant is meant to operate, by studying the
assembled data and if necessary talking to the design personnel
involved. As he performs this task, it is very likely that he will notice
potential problem areas. Private notes should be made of these, as they
might possibly be missed during the course of the study. In such an
event, it can only serve to enhance the Chairman's status within the group
if he demonstrates his grasp of the subject by pointing out potential
problems that the team have overlooked.
This stage of preparation is perhaps the most important, because it is the
foundation upon which the other steps in the preparation process will be
built. Without a reasonable understanding of how the plant functions, it
will be impossible to plan a sensible study strategy, decide how long the
review is likely to take, or who needs to be included in the study team.
Some proponents of the Hazop methodology state that there is no need
for the Chairman to have any knowledge of the plant being reviewed, his
function being only to ensure that the meeting progresses smoothly. An
analogy to this approach would be a leader attempting to guide an
expedition without a map, no plan of action other than to get to the
destination, and with no knowledge of the terrain to be traversed. Such a
person would command very little respect from other members of the
team, and at the first sign of trouble he would likely be sidelined and
marginalised by those with a better understanding of the situation. Once
that has happened it will be almost impossible for him to regain control of
the group.
Subdivide the plant and plan the sequence
In all but the simplest of plants, it is too much to expect any study team
to deal with all aspects and operations in the process
simultaneously. Therefore, it must be split into manageable sections
(commonly referred to as Nodes, but sometimes called Tables because of
the tabular means of recording the study). Also, the sequence in which
these sections are studied is important.
With continuous plant, one usually progresses from upstream to
downstream, with services such as drains, vent headers, instrument air,
cooling water, etc. being considered separately and last. With regard to
splitting the plant into sections, there is no need to consider each line and
every single minor item of equipment under a separate Node. This will be
wasteful of time, and boring and tedious for the team.
Instead, endeavour to group smaller items into logical units. Therefore, a
minor pump with its suction, discharge and kick-back lines might be
grouped together in a Node. However, with a major compressor, the
recycle line and its in-line cooler should perhaps be studied
separately. Also, when studying a vessel the Node should encompass
those inlet/outlet lines up to and including any control/isolation valve/s, all
level bridles, as well as vent lines up to the PSV.
If a number of streams converge on a vessel, the study sequence should if
at all possible deal with all of those streams before the vessel is
considered. The rule is "never study a vessel until the incoming
deviations are known".
With batch operations, an entirely different approach is needed. In such a
case the plant drawings are an accessory rather than the prime focus of
the study. Of greater importance instead will be a detailed flowchart or
operational sequence of steps to be accomplished. It is these batch
sequences that will need to be split into manageable sections, and
keywords may well target sequential operations such as Prepare, Charge,
React, Transfer, Centrifuge, Dry etc. This methodology is required
because an individual plant item is very likely to be put into differing
states and serve different purposes at various stages of the sequence.
Mark the drawings
When the study strategy has been decided, the plant items encompassed
by each Node should be marked in distinctive and separate colours, with
the Node Numbers alongside in the same colour. Lines should be
paralleled, and equipment and vessels outlined in the chosen
colour. Where a Node spans two or more drawings, the colour used
should remain constant.
This prior marking is a departure from the more usual practise of doing
such work whilst the study progresses. However, it serves two
purposes. Firstly, it will save time during the meeting, both in the actual
marking and the discussion as to where a Node should begin and
end. Secondly, the Chairman will be assured that in planning the study
strategy nothing has been inadvertently missed.
Devise a list of appropriate Keywords
Having completed the work above, it will be a simple matter to formulate
a comprehensive list of the Keywords required to cover all aspects of the
process to be studied.
Some companies, because most of the plant that they operate is of a
similar nature, will have a standard set of Keywords. Such a list should be
checked to ensure that it is covers all aspects of the system to be
studied. Any redundant Keywords should be removed. For example, if
the subject of the review is to be a pumping station, the inclusion of a
keyword such as 'Absorb' is unnecessary.
The finalised list should be duplicated and a copy given to every team
member. Also included should be a schedule of appropriate keyword
combinations (i.e. which Secondary keywords will be applied with each
Primary keyword). Where there are likely to be semantic problems as to
what meaning/s a particular combination is intended to convey, then a full
explanation should be given.
When devising the list, bear in mind that the smaller the number of words
utilised, the more speedy the study. That is not to say that aspects of the
process should be discounted. Instead, to illustrate what is meant,
imagine a plant containing a separation vessel, some pump suction filters,
and an environmental scrubber. Rather than have three keywords
'Separate', 'Filter', 'Absorb', have instead one keyword 'Separate'... that,
after all, is the basic function of all those equipment items. Similarly,
'Temperature' can cover heat transfer aspects of Heaters, Coolers, and
Heat Exchangers.
Prepare Node Headings and Agenda
Node Headings reference the relevant drawings, and contain a brief
description of the design intent of the relevant plant section, with process
parameters, flow rates, and any other potentially informative details.
The agenda is a list of those headings. A copy should be handed to each
team member. In addition to being informative and an aid to full
participation, it will serve to put into perspective the amount of work to be
accomplished in the time allotted. Hopefully this will induce an
appropriate sense of urgency.
Prepare a timetable
For all but a one day study, the Chairman should devise a timetable
showing what needs to be accomplished at each study meeting if the
schedule is to be maintained. In devising this schedule he will need to call
upon his experience when assessing how much time the review will
take. A great deal will depend upon the complexity of the plant as well as
the experience of the team.
As a rough guide, with straightforward plant and with P&IDs that are not
too 'cluttered', on average three drawings can be studied in a day. If the
system to be reviewed is complex, or if each P&ID seems to have been
drawn with the intention of not wasting any space (i.e. as many plant
items as would fit are included on the drawing), then almost certainly only
two or perhaps even one drawing will be completed in a day.
Be prepared for time slippage at the start of the study. Progress is always
slow to begin with, whilst the team are acclimatising themselves to this
novel role of casting critical eyes over their own or their colleague's design
efforts. After the first day everything will speed up, and the schedule
should be on target by the end of the week. Do not, however, allow the
timetable to reflect this expectation of a slow start... better for the team
to realise that they must increase their efforts, rather than go home
thinking that this first slow day is the norm.
Select the team
Having gained a good appreciation of what will be involved in the study,
both in terms of content and timetable, the Chairman can ensure that the
core team members have suitable expertise and will be available for the
duration of the review. In addition, he can also ascertain which personnel
with additional expertise are likely to be needed during the course of the
meetings, and when their assistance will be required. With regard to the
latter aspect, in certain circumstances the study sequence may need to be
tailored around the availability of such personnel.
RUNNING A HAZOP STUDY
After all the above preparation, the Chairman should be in a position to
easily guide an efficient and comprehensive study through to a successful
conclusion. However, there are a few guidelines to remember:
It is always a temptation for team members to illustrate their
ideas by quickly drawing on the master P&ID that has been so
carefully marked up. Establish the rule right at the beginning
that this is forbidden, even in pencil.
Similarly, with tie-ins and vendor packages, a team member may
endeavour to help by roughly illustrating the
upstream/downstream plant or the internal workings of the
package. Be firm in the rejection of such help... it is dangerous
to pretend to have studied something when all that is available is
a few scribblings on a sheet of paper.
If the schedule is slipping, resist the temptation to hasten the
process by listing potential causes and consequences
yourself. All that results is that the team sits back and listens to
you dictating to the Secretary, and they will continue to do so
until you force them to participate again.
Do not allow a separate meeting to develop, with two team
members conversing in low voices at the corner of the table. If
this happens, stop the general discussion and ask them to share
with the rest of the team the benefit of their deliberations (always
assume that they are discussing something directly relevant to
the study, although the likelihood is otherwise). This will usually
elicit an apology and bring them back to full participation.
If they persist, request that the rest of the team members be
completely silent whilst the private discussion continues. If even
this does not produce the required result, call a coffee
break. Then speaking privately to the persons concerned, politely
but firmly insist that they leave the meeting. Such members
usually have nothing to contribute to the study, and they will only
irritate and demotivate the remainder of the team.
Ensure that all team members participate, even those who might
well feel unsure of themselves. Do this by asking questions such
as "Do you agree with that solution, Bob?", or "What severity
would you attach to this consequence, Fred?". Alternatively, and
less potentially contentious, you could request "John, could you
help the Secretary by summarising in a few words the agreed
action". Once such team members realise that they are not going
to be contradicted as soon as they open their mouths, they
participate to the best of their ability.
Recognise and reward with praise the team member/s who
contribute to the discussion wholeheartedly and
sensibly. However, do not allow them to overshadow the rest of
the team.
If discussion wanders away from the matter under consideration,
re-focus the attention of the team either by requesting that the
Secretary read out what he has recorded, or by asking for an
action to be formulated. The latter usually concentrates the mind
and encourages the team members to get to the heart of the
problem.
Where a particularly intractable problem arises, or consequences
of a serious nature are uncovered, too often an inordinate
amount of time is devoted to formulating potential
remedies. Solutions and counter solutions are proposed and
discussed, there is much speculation as to costs and other related
aspects, and generally no satisfactory conclusion is
reached. Before too much time is wasted, such situations should
be dealt with by placing an action upon a specific person to
investigate and report upon what alternatives are available,
together with the advantages/disadvantages of each. Any
discussion, gathering of additional data, reliability calculations,
etc. can thereby be accomplished outside of the Hazop meeting,
allowing the team to progress steadily with the review.
The Chairman should be independent and unbiased, and should
not be perceived as constantly favouring one section of the team
as opposed to another. This is of particular importance when
personnel from both client and contractor are participating. If a
difficult situation arises, where, for example, there is a heated
dispute over whether an action should be undertaken, in some
cases one of the parties to the dispute will request that the
Chairman makes the final decision. If, in the Chairman's
estimation, the reasons on one side of the argument are so
strong as to be indisputable, then he should say so. On the other
hand, should the situation be finely balanced, then the dispute
can be defused by careful wording of an action.
Take as an example the situation where the client wishes to have
an additional High Level Alarm, but the contractor strongly
disputes its necessity. Consider the following actions:
o "Fit a High Level Alarm". In the view of the contractor, the
Chairman has sided with the client. He may, wrongly or
otherwise, perceive this to be a biased decision.
o The action "Justify the requirement for a High Level Alarm"
is addressed to the client. The Chairman favours the
contractor's argument, but is not dismissing altogether the
views of the client. Both parties are likely to be content
with this formula.
o The action "Justify the absence of a High Level Alarm" is
addressed to the contractor. The Chairman favours the
client's argument, but is not dismissing altogether the views
of the contractor. As before, neither party will have cause
to feel aggrieved.
By effectively postponing a final decision until a later review
of Action Responses, it is often the case that the two sides
will get together after passions have cooled to discuss the
matter rationally. Almost invariably the situation will then
be amicably resolved.
THE REPORT
The Hazop Report is a key document pertaining to the safety of the
plant. The number of man-hours spent on the study is usually
considerable. It is crucial that the benefit of this expert study is easily
accessible and comprehensible for future reference in case the need arises
to alter the plant or its operating conditions.
The major part of such a report is of course the printed Minutes, in which
is listed the team members, meeting dates, Keywords applied, and of
course every detail of the study teams findings. However, it is usual to
include with this a general summary. The contents of such a summary
might typically be:
An outline of the terms of reference and scope of the study.
A very brief description of the process that was studied.
The procedures and protocol employed. The Keyword
combinations applied should be listed, together with the
explanatory meanings given to the team at the start of the
study. Also the fact that Action Sheets have been produced and
responses will be recorded should be explained. A brief
description of the Action File (described in the following section)
should be included.
General comments. If, for example, the team were assured that
high point vents and low point drains would be universally
provided, mention that statement and its source. If certain
details of vendor packages were not available, explain and list the
items that were not reviewed.
Results. This usually states the number of recommended actions.
Also included in the Hazop Report would be an Appendix containing:
Master copies of the drawings studied.
Copies of technical data used.
Cause and Effect charts (i.e. matrices showing the executive
action of safety related instruments and trips).
Any calculations produced.
Relevant correspondence between departments, from contractor
to vendor, or client to contractor.
Each of the above should be signed and dated by the Chairman.
THE ACTION FILE AND REVIEW MEETINGS
The Hazop Report is compiled as soon as possible after the end of the
study, and once completed does not change. On the other hand the
Action File is only started at the end of the study, and its contents will
continue to change perhaps for many months, until the very last action
has been reviewed and accepted as having been satisfactorily discharged.
Essentially, this Action File is a binder, or perhaps some electronic form of
storage. Initially, at the end of the study, it will be empty. As completed
and signed Action Response Sheets are returned, they are housed in the
binder folder. Periodically, the returned responses will be input into the
data file (either manually or electronically, according to the system being
used).
By the time the first review meeting is convened there should be no
outstanding (i.e. overdue) responses. The Secretary would prepare a
listing of all responses received, making a copy for each review team
member. During the review meeting responses will either be accepted
and marked as having been discharged, or in a small number of cases
further action would need to be taken.
At the end of the first review, where further action had been required,
Action Sheets for these would be produced for distribution. In due course
these would be completed, signed and returned, and these further
responses would be input into the data file and housed in the Action File
as before.
The procedure for the second review meeting is the same as for the first,
except that the number of responses would of course be much smaller. If
some of those responses were still not found to be satisfactory, then the
process as outlined above would be carried out again.
It can be seen that the Action File represents a record of the state of
completion of Hazop recommendations at any point in time. When all
action responses have been reviewed and accepted, it finally becomes a
static record containing the complete history of the implementation of the
Hazop Study's findings.