  • 8/6/2019 HEAD BANGERS Project for 2011 Final Report

    1/12

    HEAD BANGERSFinal report

    Compiled by:

    Robert Barendilla S209914904

    Daniel Basson S2053845

    Thanyani Murundwa S209919086

    Sanele Mxoli S209404547

  • 8/6/2019 HEAD BANGERS Project for 2011 Final Report

    2/12

    Contentsy Main Objectives....Pg1

    y Requirements...Pg1

    y Constrains.Pg2

    y Concept selection..Pg3

    y Parts list.......Pg4

    y Price list.......Pg5

    y Estimated weights.Pg6

    y Materials and calculations.Pg6

    y AppendixA-Linear responsibility chart, Gantt chart, Evaluation

    matrix, Schedule calendar

    y Appendix B-Exploded isometricand 1st/3rdangle drawings

    y Appendix C-Minutes of Project plan meeting

  • 8/6/2019 HEAD BANGERS Project for 2011 Final Report

    3/12

    Main objectives;

    Students are required to design a vehicle that will compete in a series of races and tests

    of durability and endurance. The vehicle will advance down a two meter track and no

    external controls or assistance to motion is given to the vehicle once activated. Students

    work in groups of four and they delegate the workload according to individual skill set.We will design concepts of the vehicle and compile a final draft of the vehicle based on

    constrains as detailed later in the report. This will test the members of the group in the

    processes of engineering and designing concepts, material selection and final assembly

    of the vehicle.

    REQUIREMENTS:

    Initial Requirements

    - 3 hand sketched vehicle concept drawings

    - Evaluation matrix

    - Linear Responsibility chart

    - Gantt chart

    Drawing Requirements

    - An explode view isometric assembly drawing is required including the:

    1. Body

    2. Chassis(motor, battery, switches, gears)3. Wheels

    4. All assembly parts to be labeled with assembly number

    5. All dimensions and tolerances to be shown of non purchased parts and

    purchased parts that have been modified

    - Parts list showing the weight each part

    - Parts list showing the estimated price of each part

    - Drawing views

    1. 1st angle drawing of vehicle

    2. 3rd angle drawing of vehicle

    Calculations

    - We are required to estimate the speed of the motor in revs/min by timing a run of

    the vehicle

  • 8/6/2019 HEAD BANGERS Project for 2011 Final Report

    4/12

    Constraints:

    - Only four or less students are to build a vehicle for the head bangers 2011

    project for machine design 2.

    - Only one 9-V DC battery can be used for all the races that the team will

    participate in.- The vehicle has to race down the race track and back only by a on and off switch

    on the vehicle itself.

    - The vehicle is to be switched on, move forward, hit the wall, shift from forward to

    reverse on its own and race back the track to finish the race.

    - The vehicle may not be control by any external controls once the switch on it has

    been activated.

    - The vehicle must not exceed 300mm in length once it is on the race track.

    - The whole vehicle is to be built from bottom to top and no purchased vehicle may

    be used as it is, only parts like motors, wheels, small gears may be used into thebuilt vehicle.

    - The chassis of the vehicle is to be built as an original and no purchased chassis

    may be used.

    - Only DC electric motor may be used and more than one motor may be used.

    - The vehicle is to be built that it may only move as a single unit.

    - No slingshot anchor-type vehicle may be used also a ball that can be thrown

    down the race track.

  • 8/6/2019 HEAD BANGERS Project for 2011 Final Report

    5/12

    Parts list

    Part Qty Description

    Chassis 1 Polyethelene

    Bumper 1 Aluminium

    Wheels 4 Rubber

    Mag wheels 4 Polyethylene

    Axel 2 Aluminium

    Bearing blocks 2 Polyethylene

    Battery 1

    Bumper block 1 Polyethylene

    ISO 4014 - M3.5 x 20 2 Hexagon head bolt - Product grades A and B

    ISO 4014 - M2.5 x 20 8 Hexagon head bolt - Product grades A and B

    ISO 4032 - M3.5 2 Hexagon nuts, style 1 - Product grades A and B

    ISO 4032 - M2.5 8 Hexagon nuts, style 1 - Product grades A and B

    Switch stand(Toggle) 1 Aluminium

    Switch-stand(On/off) 1 Aluminium

    Toggle switch 1

    On/off switch 1

  • 8/6/2019 HEAD BANGERS Project for 2011 Final Report

    6/12

    Price list

    Combined costs Of Vehicle (Rands)

    Motor R128.95

    Batteries R45.95

    Complete chassis manufacturing cost R345.00

    Wheels R60

    Toggle Switch R80

    On/off Switch R20

    Gear Train R105

    Total R784.90

    Price paid by Each Member of the group R196.25

    y Prices Quoted from The RC SHOPAt 6th

    Avenue Walmer Shopping centre

  • 8/6/2019 HEAD BANGERS Project for 2011 Final Report

    7/12

    Car weights

    Actual weight of car 2.0kg

    Estimated weight of parts

    Chassis(Including all polyurethane parts) 0.9kg

    Wheels 0.2kg

    Axle(shafts) 0.1kg

    Electrical mechanisms(switches, wires) 0.3kg

    Gearbox and motor 0.5kg

    Materials used

    Chassis, blocks Polyurethane

    Bumper, shaft Aluminium

    Wheels Rubber

    Calculations

    We ran the car over a 5 meter length and timed it to 2.35 seconds. We calculated

    the linear speed of the car to be 2.13 m/s.

    V =

    V =

    = 2.13 m/2

  • 8/6/2019 HEAD BANGERS Project for 2011 Final Report

    8/12

    Wheel diameter 0.046m

    =

    =

    = 92.61 rad/s

    =

    N =

    =

    = 884.36rpm(wheels)

    VR =

    =

    = 1.714

    RPM motor = RPM wheel x VR

    = 884.36 x 1.714

    = 1515.79 rpm

  • 8/6/2019 HEAD BANGERS Project for 2011 Final Report

    9/12

    Appendix BCharts

    Linear Responsibility ChartNo Tasks Danie Robert Sanele Thanyani

    1.0 Management

    1.1 Overall leadership 1 2 3 3

    1.2 Team meeting minutes 1 3 3 2

    1.3 Financial accounts 1 2

    2.0 Procurement

    2.1 Motor 3 1 2 3

    2.2 Gears 3 3 1 22.3 Chassis 2 3 3 1

    4.0 Electrical

    4.1 Circuit design 3 1 3 1

    4.1.1 Build and test circuit 2 1 3 3

    4.2 Add circuit to chassis 1 2 3 3

    5.0 Drawings

    5.1 Concept sketches 3 1 2 3

    5.2 Initial 3D drawing 3 3 1 2

    5.3 Final drawing 3 3 1 2

    5.3.1 Individual parts 3 3 2 1

    5.3.2 Scenes, 3D isometric 3 1 3 2

    5.3.3 Parts list 3 2 1 3

    6.0 Construction

    6.1 Build chassis 1 2 3 3

    6.2 Assemble drive train 3 2 3 1

    6.3 Assemble electronics 3 3 1 2

    7.0 Testing7.1 Test assembled car 1 3 2 3

    7.2 Modify and re-test 3 2 3 1

    8.0 Final report 1 1 1 1

    1. Primary responsibility 2. Secondary responsibility 3. Review

    Changes to chart

  • 8/6/2019 HEAD BANGERS Project for 2011 Final Report

    10/12

    Appendix CMinutes of Project plan

    meeting

    1st REPORT Minutes

    Agenda/Subject: Head bangers meeting regarding first practical report.

    Date : 25 February 2011

    Time : 12:30

    Attendees: Robert Barendilla, Thanyani Murundwa, Danie Basson, Sanele Mxoli

    To ensure that all the requirements of the first report could be met. It was decided that

    each team member must free hand sketch a chassis of a battery operated vehicle. This

    drawing must show all relevant parts of the vehicle such as drive train, motor, wheels

    and switches based on their own individuals designs and concepts. Three of the four

    chassis design concepts will be used for the first report.

    The following tasks were handed out to the relevant team members. They are as

    follows:

    y Robert Barendilla :The requirements section for the report and the responsibility

    chart,y Thanyani Murundwa : The constrained section.

    y Danie Basson: Gantt chart and Minutes.

    y Sanele Mxoli: Objectives and Evaluation matrix.

    Conclusion

    All relevant team members must hand in their tasks on the 02March 2011

  • 8/6/2019 HEAD BANGERS Project for 2011 Final Report

    11/12

    2nd REPORT MINUTES

    Agenda/Subject: Head bangers meeting regarding second practical report.

    Date: 22 March 2011

    Time: 12:25

    Attendees: Robert Barendilla, Thanyani Murundwa, Danie Basson, Sanele Mxoli

    What we as group 5 agreed upon is that every member must make a chart that are

    required for the second report. Each group member was given a week to make sure that

    the task that they had to do, Should be done in the correct manner. Also every member

    within the group must make sure that they bring their work at the team meeting that

    followed.

    The following tasks were handed out to the relevant team members. They are as

    follows:

    y Robert Barendilla Linear responsibility chart,

    y Thanyani Murundwa: Calendar, Meeting Minutes.

    y Danie Basson: Gantt chart.

    y Sanele Mxoli: Price list and evaluation matrix.

    Conclusion

    All relevant team members must hand in their tasks on the 22 March 2011

  • 8/6/2019 HEAD BANGERS Project for 2011 Final Report

    12/12