heat rate

25
Disclaimer This training presentation is provided as a reference for preparing for the PJM Certification Exam. Note that the following information may not reflect current PJM rules and operating procedures. For current training material, please visit: http://pjm.com/training/training-material.aspx PJM©2014

Upload: matias-alonso-urrutia-ortiz

Post on 01-Oct-2015

212 views

Category:

Documents


0 download

DESCRIPTION

Presentación.

TRANSCRIPT

  • Disclaimer

    This training presentation is provided as a reference for preparing for the PJM Certification Exam.

    Note that the following information may not reflect current PJM rules and operating procedures.

    For current training material, please visit: http://pjm.com/training/training-material.aspx

    PJM2014

  • PJM 2011 www.pjm.com 1

    Interconnection Training Program

    Load Scheduling

    Incremental Loading Tables

    LS2

    Clement Lovasik

    State & Member Training

    Winter, 2011

  • PJM2011 www.pjm.com 2

    LS 2 Objectives

    Describe how incremental loading tables are derived and used for least cost dispatch of generating units to match load demand.

    Describe the two modes of submitting bids for generating resources cost based and price based

    Describe how a cost based incremental loading curve for a generating unit is developed, given the units incremental heat rate and fuel cost

    Develop and use an incremental loading table for a sample system given unit data

    Describe the least cost method for dispatching generating units for a sample system given an

    incremental loading table for the system

  • Cost Based Bids

    Generation offers to the PJM market are capped at the

    units production cost plus a 10% adder

    Start up and no load costs can be updated daily

    Offer developed using guidelines of the Cost Development

    Task Force (CDTF)

    CDTF Rules laid out in PJM Manual 15

    Cost based bids are used to cost cap the unit should the

    units used to control for a contingency fail the Three Pivotal

    Supplier Test

    All generators must have a cost based bid on file in eMKT

  • PJM2011 www.pjm.com 4

    Historic LMP-Capped / Negotiated Offers

    Historic LMP-Capped Offers

    Generation offers using historic LMPs at the generation bus where energy is injected

    Value is determined by calculating the average LMP at the generation bus during all hours over the past six months in

    which the resource was dispatched above minimum.

    Negotiated Offers

    Offer is based on a negotiated value with the PJM Market Monitor

    Case-by-case basis

  • PJM2011 www.pjm.com 5

    Price Based Offers

    Offer is based on what the generation owner believes the

    market will bear

    Start-up and no-load costs can be updated every 6 months

    Prior to March 31 for period April 1 to September 30

    Prior to September 30 for period October 1 to March 31

    Units may file with MMU for cost-based start-up and no-loads

    which may be updated daily

    When switching to Priced Based offers a unit may not

    switch back to another type of offer

  • PJM2011 www.pjm.com 6 www.pjm.com

    Parameter-Limited Schedules

    What are Parameter-Limited Schedules?

    Parameter-Limited Schedules are limitations that could

    be imposed on the parameters that generators submit as

    part of their offer.

    All cost based offers are PLS

    Price based schedules can be PLS or non-PLS

    These pre-determined limits are used when

    certain operational circumstances exist.

  • www.pjm.com

    Parameter Limited Schedules

    For each unit class, minimum acceptable operating parameters include:

    Turn Down Ratio (Ratio of Eco Max MW to Eco Min MW)

    Minimum Down Time

    Minimum Run Time

    Maximum Daily Starts

    Maximum Weekly Starts

    Future parameters MAY include: Hot Start Notification Time, Warm Start Notification Time, Cold Start Notification Time

    Some parameters will be set based

    on operating history of the unit

    compared to % of PJM-defined unit

    class

    The initial Minimum Down Time for each unit is based on

    the minimum of the Minimum Down Times submitted over

    the prior 24 months, if the resultant minimum down time is

    less than or equal to 110 percent of the PJM-defined unit

    class Minimum Down Time. If Minimum Down Time

    submitted for a unit is more than 110 percent of the PJM-

    defined unit class Minimum Down Time, then the units Minimum Down Time will be set equal to 110 percent of

    the PJM defined unit class Minimum Down Time.

    i.e.

  • PJM2011 www.pjm.com 8

    Heat Rate

    Measure of efficiency of a unit in converting heat energy to electrical energy.

    Ratio of heat supplied by fuel (MBTU) to MWhr of electrical energy delivered by a unit. MBTU stands for one million BTUs, which can also be

    expressed as one decatherm.

    BTU stands for British Thermal Units

    As heat rate increases, efficiency decreases.

  • PJM2011 www.pjm.com 9

    Heat Rate

    Heat Rate = MBTU = Heat Input (MBTU)

    MWhr MW Output (MWhr)

    Heat Rate = 312 MBTU/hr = 10.4 MBTU

    30 MW MWhr

    EXAMPLE:

  • PJM2011 www.pjm.com 10

    Heat Rate

    Optimum efficiency is normally at about 80% of full load.

    Efficiency is less at lower loads due to heat required to keep boiler hot an turbine spinning.

    At higher loads, losses in the turbine reduce efficiency.

  • PJM2011 www.pjm.com 11

    Incremental Heat Rate

    IHR = Incremental Heat Rate

    IHR is significant to economic power system operation.

    IHR is the change in heat input to a unit needed to produce a given change in generation.

    IHR of a unit increases steadily with generation.

  • PJM2011 www.pjm.com 13

    Incremental Heat Rate

    IHR = Increment of heat input (MBTU)

    Increment of Power Output (MWhr)

  • PJM2011 www.pjm.com 14

    Incremental Heat Rate

    Increment of heat input =

    392 MBTU/hr - 312MBTU/hr = 80 MBTU/hr

    Increment of power output =

    40 MW - 30 MW = 10 MW

    IHR = Increment of heat input (MBTU)

    Increment of Power Output (MWhr)

    IHR = 80 MBTU/hr = 8.0 MBTU

    10 MW MWhr

  • PJM2011 www.pjm.com 15

    Incremental Cost

    Incremental cost for a unit at a given level of generation is the cost per MW to produce the next increment of

    power output.

    Is calculated by taking the product of the incremental heat rate and the fuel cost.

  • INCREMENTAL COST (LAMBDA)

    POWER OUTPUT IHR INC. COST

    (MW) (MBTU/MWhr) ($/MWhr)

    20

    30 7.6 (7.6*2.3) = 17.5

    40 8.0 (8.0*2.3) = 18.4

    50 8.4 (8.4*2.3) = 19.3

    60 8.8 (8.8*2.3) = 20.2

    70 9.2 (9.2*2.3) = 21.2

    80 10.2 (10.2*2.3) = 23.5

    90 11.6 (11.6*2.3) = 26.7

    100 12.7 (12.7*2.3) = 29.2

    Inc. Cost = IHR * Fuel Cost

    $/MWhr = MBTU/MWhr * $/MBTU

    Fuel Cost = $2.30 / MBTUKEY

  • PJM2011 www.pjm.com 18

    Incremental Cost

    Incremental Cost = MBTU x Fuel Cost

    MWhr

    Incremental Cost = 8.0 MBTU x 2.3 = 18.4 $/MWhr

    MWhr

  • MBTU P

    POWER MBTU

    Relationship between Incremental Cost and Incremental Heat Rate

    Cost for an Increment of Power P = Increase in MBTU needed to produce P Incremental Cost = IHR X Fuel Cost

    ($)

    MWhr (MBTU) MWhr

    X ($)

    MBTU

  • Fuel Generating Unit Electrical Energy

    $ X MBTU

    MBTU MWhr

    $ MWhr

    =

  • PJM2011 www.pjm.com 21

    For Economic operation of a power system all generating units should be dispatched

    at equal incremental cost.

    Rate 1 Unit 1 Unit 2 Unit 3 Total 14.0 100 100 100 300 15.0 200 200 200 600 16.0 250 250 250 750 17.0 300 300 300 900

    18.0 350 350 350 1050

    PRINCIPLE OF ECONOMIC DISPATCH

    Principle of Economic Dispatch

  • PJM2011 www.pjm.com 22

    Load (MW x 1000)

    1 3 5 7 9 11 13 15 17 19 21 23

    50

    46

    42

    38

    34

    30

    22

    26

    $5

    $10

    $15

    $20

    $25

    $30

    $35

    $40

    $45

    Hour of Day

    Dispatching Generation to Meet Load

  • PJM2011 www.pjm.com 23

    Exercise GT-2.1

  • PJM2011 www.pjm.com 24

    Questions

    ???