heco companies experience with distributed pv...

23
HECO Companies Experience with Distributed PV Lisa Dangelmaier April 11 2012 PJM/EPRI/NREL Inverter-based Gen Interconnection Workshop – Distribution Reliability Needs/Studies

Upload: others

Post on 24-Apr-2020

7 views

Category:

Documents


0 download

TRANSCRIPT

  • HECO Companies Experience with Distributed PVLisa DangelmaierApril 11 2012

    PJM/EPRI/NREL Inverter-based Gen Interconnection Workshop – Distribution Reliability Needs/Studies

  • DG Growth from 2009 to 2011

    2Summary of Interconnected Distribution Level Penetration on Major Island Grids* DG Penetration = Installed DG MW / Max Feeder Load 2010 data

    *

  • Tracking Tremendous Growth in Distributed PV

    3

    Red areas indicate circuits with > 15% PV penetration

  • Local Circuit Impact – light load, or large projects lead to export

    Concerns:1. The above graphs illustrate the need to assess the feeder loading not only at peak periods but also on the days

    where the loads are not as high (light load Sundays) – Rule 14H 2. Circuit peaks often not coincident with System peaks 4

  • Improved Models to Account for PV as Generation vs Negative Load

    Enables more accurate modeling of DG resources for planning

    Consistent distribution system model expedites modeling and analysis process

    Allows for “what-if” analysis to stay ahead of system change and minimize risks of stranded assets

    5

    Translate feeder level impacts to system level

  • Interface Between T&D Models

    6

    SynerGEEUnbalanced Distribution

    Aggregated BEW PV Sites

    SynerGEE Balanced System

    46 kV/12 kV

    Aggregated BEW System/PV Sites

    PSLF Models

    PowerWorldBalanced

    138 kV/46 kV Model

    PSS/E138 kV Model

    PPLUS

    Generic PV/Inverter User- Defined

    Model

    PSS/E400+Sites

    PV Data

    Individual12 kV Feeder

    46 kV System 138 kV System Generation

    Reso

    urce

    s

    7000

    +Si

    tes

    900Sites

    Data Transfer Point

    Distribution Planning

    ResourcePlanning

    Transmission Planning

    Note: Line ratings shown for Oahu system for illustration

    Industry Partners: SMUD/HECO High Penetration PV Initiative, BEW Engineering, GL Noble Denton, GIS & EMS providers

  • Modeled Variability : 30% PV Penetration Island Wide (light load)

    7

    Color-coded impacts at distribution substations

    Simulated results at 30% PV penetration across the islands and impacted areas

  • Impact of Variability On LTC Operations

    Highlighted % of total days with tap changer count above n > 5 for months of January to June

    Increase in count correspond with highest variability months- May and April (light load months)

    8

  • Impact of Increasing Distributed PV on Apparent Demand

    9

    MW

    Midnight Midnight12 noon

    Min-Max output of dispatchable and base generating units

    Excess Energy –curtailed

    Energy Shortfall must be met by fast starting units

    SCADA, feeder caps or new monitoring to account for DG contributions

    Typical Hawaii load profile –Evening Peaking

    Output of intermittent units

    Supply exceeds Demand at Lower Demand Periods –Encroaching into Daytime

    Supply does not meet demand at maximum load

    DG (PV) changing system daytime load shape

    Curtailment ReliabilityMasked Loads

  • 2008 difference

    2011 difference

    Comparison of 2008 and 2011 Weekend Actual Loads (HELCO)

    • Weekday comparison: evening peak has not significantly changed between 2008 and 2011 but daytime demand has.

    • Weekend comparison (light load day): difference between daytime peak and evening peak has increased. 10

    Source: HELCO

  • Monitoring solar availability and variability at 2 sec SCADA rate. Operators observe correlation of solar irradiance and demand change.

    LM-1 solar availability sensors

    11

    Hawaii

    Piloting Control Room Situational Awareness Tools to "See" Variability

  • 12

    59.6

    59.7

    59.8

    59.9

    60

    60.1

    60.2

    0

    0.5

    1

    1.5

    2

    2.5

    3

    13:20:00 13:21:00 13:22:00 13:23:00 13:24:00 13:25:00 13:26:00 13:27:00 13:28:00 13:29:00 13:30:00

    Freq

    uenc

    y (H

    z)

    Momentary Fault, Auto-Reclose 6500 Line 2/7/2012 13:20Load Response based on Per Unit Pre-fault Load

    FEEDER 11 MW

    FEEDER 12 MW

    Frequency (Hz)

  • PPA, SIA, larger FIT Interconnection Requirements

    13

    •Wind/solar forecasting data•Off-normal frequency ride-through•SCADA telemetry and control (500/250 KVA)•Does not apply to small projects (NEM, smaller FIT)•Working on voltage-ride-through requirements

  • Questions/Comments??

    14

    Mahalo

    Dora Nakafuji, [email protected] of Renewable Energy PlanningSystem Integration DepartmentHawaiian Electric Co

    Lisa [email protected] Superintendent, Production Dept., Hawaii Electric Light Co

    HECO MECO HELCO

    Family of HEI Utilities

    For more information please contact:

    mailto:[email protected]�mailto:[email protected]

  • BACKUP MATERIALS

    15

  • Recommendations: Identified Gaps & Enhancements to Interconnection Process

    Analysis Type Normal Detail Level EnhancementSTEADY STATE STUDIES

    Load Flow - Back-feed potential

    Peak Load ConditionsComment on equipment setting

    (LTC and LDC)

    Minimum Daytime LoadInvestigate equipment settings and

    impact of changingIrradiance data for capacity vs.

    generated power

    Tap Changer CyclingStep Maximum output to Minimum

    Output at Peak Load, 1% limit in voltage change specified to impact LTC

    Time sequential analysis with measured irradiance data over seconds and time delay of LTC

    Peak and Minimum daytime load conditions

    16

    Analysis Type Normal Detail Level EnhancementDYNAMIC STUDIES

    Dynamic/Stability Studies - All PV trip

    Not normally completedMultiple sites/nodal/cluster studies,

    PV is dynamic Inverter

    Dynamic/Stability Studies - N-1

    Not normally completedFull dynamic analysis on range of

    site sizes and configurations

  • Field Validation

    17

    Ramp tracking through afternoon

    Cloud variability during day peak

    Morning load risetracked

    Source: HELCO17

  • Visibility to DG (Data to Output Probability)

    18

    Capturing statistical variation of PV with respect to time and by geographic location.

  • Nodal Estimation Approach to Expedite PV Integration Studies

    19

    • Characterize discrete and aggregated circuit load profiles at 12 kV substation (residential, industrial, commercial)

    • Expedite circuit evaluations and aggregate DG impacts for planning

    • Use reference LM-1 sensors to estimate solar resource output at location

    • Extend solar forecasting to account for aggregated impact of behind-the-meter generationHiP-PV Industry Partners: SMUD, BEW

    Engineering, GL Noble Denton, NREL, EPRI

  • Growth of Variable Distributed Gen

    20

  • 21

    Excess Energy Curtailment (Feb 2011)

    0.000

    20.000

    40.000

    60.000

    80.000

    100.000

    120.000

    140.000

    160.000

    180.000

    200.000M

    W

    TIME

    Wind

    Geothermal

    Hydro

    Diesels

    CT

    Combined CycleSteam

    SYSTEM LOAD

    Curtailment of wind and geothermal

  • 22

    59.6

    59.7

    59.8

    59.9

    60

    60.1

    60.2

    60.3

    0

    0.5

    1

    1.5

    2

    2.5

    3:03:18 3:04:18 3:05:18 3:06:18 3:07:18

    Freq

    uenc

    y (H

    z)

    MW

    / M

    VA

    R

    Thursday Dec 22 2011

    Momentary Fault, Auto-Reclose 6500 Line 12/22/2011 03:03Load Response based on Per Unit Pre-fault Load

    FEEDER 11 MW

    FEEDER 12 MW

    Frequency (Hz)

  • Situational Awareness & Decision Support for Operations

    23

    • Improve operational awareness of ramp (0-2hr) conditions and impacts

    • Animated images of global horizontal irradiance

    • Visual to measured data• NWP forecast for next 6 hours

    • Animated visible satellite image

    • Actual satellite image for last 6 hours• Simulated forecast of visible image for next 6

    hours

    Forecasting Industry Partners: EPRI, AWS TruePower, US DOE WFIP, SCE, SMUD, CaISO, UH Manoa, UCSD

    SolarSENSE

    ������HECO Companies Experience with Distributed PV�Lisa Dangelmaier�April 11 2012DG Growth from 2009 to 2011Tracking Tremendous Growth in Distributed PVLocal Circuit Impact – light load, or large projects lead to export Improved Models to Account for PV as Generation vs Negative LoadInterface Between T&D ModelsModeled Variability : 30% PV Penetration Island Wide (light load)Impact of Variability On LTC OperationsImpact of Increasing Distributed PV on Apparent Demand Comparison of 2008 and 2011 Weekend Actual Loads (HELCO)Piloting Control Room Situational Awareness Tools to "See" Variability Slide Number 12PPA, SIA, larger FIT Interconnection RequirementsSlide Number 14Slide Number 15Recommendations: Identified Gaps & Enhancements to Interconnection ProcessField ValidationVisibility to DG �(Data to Output Probability)Nodal Estimation Approach to Expedite PV Integration StudiesGrowth of Variable Distributed GenExcess Energy Curtailment �(Feb 2011)Slide Number 22Situational Awareness & Decision Support for Operations