Heidrun CTD Campaign #1
ICoTA European Intervention Conference, Aberdeen
12th & 13th Nov 2014Bård Marius Johansen, Statoil CTD Engineer
AGENDA
• Heidrun and the CTD project
− Bård Marius Johansen (4 min)
• Equipment and methods
− Manfred Sach (13 min)
• Operational results and future for CTD
− Bård Marius Johansen (13 min)
• Q&A
2
Heidrun CTD project
• Motivated by the need for more drainage points.
• Independent and parallel operations with the main rig.
• Extensive topside equipment development/modification.
− Mud plant positioned on Equipment Support Frame
− Well Intervention Tower reinforcement and modification
− Work-Over Riser Tensioner
3
2014-064 Classification:
Three-well pilot campaign
5
• 5 ⅞” hole drilled through 7” tubing and completed with 3 ½” tubing / OH screens
• Overbalanced drilling with WBM and mud-pulse telemetry for communication
• Three-well learning curve with increasing complexity:
• Success criterion for CTD 1: One completed well in three attempts
Well OHlength
EOHC*length
FormationAt KOP
Dog-legseverity
A-19 A 263 m n/a Ile sandstone 7.7º/30m
A-9 C 336 m 105 m Ror shale 10.0º/30m
A-33 A 350 m 70 m Springar shale 10.9º/30m
* Expandable Open Hole Clad
Primary objective: Learning
6
Planned CTDwell A-33 A
7
Over to Baker Hughes
Manfred’s slides
BJ Services Company
Heidrun CTD Campaign 1ICoTA Well Intervention Conference, Aberdeen 12th & 13th Nov. 2014
Norway GeoMarket
Manfred Sach | CTD Project ManagerBaker Hughes | Norway Geomarket | Pressure [email protected]
http://www.bakerhughes.com | Advancing Reservoir Performance
© 2014 Baker Hughes Incorporated. All Rights Reserved. ICoTA Well Intervention Conference, Aberdeen 12 & 13th Nov. 2014
Agenda
• The nature of the project
• Services provided
• Equipment developed and used
• Summary
Agenda
© 2014 Baker Hughes Incorporated. All Rights Reserved. 2 ICoTA Well Intervention Conference, Aberdeen 12 & 13th Nov. 2014
• No CT Drilling in Norway since many years
– Norsk Hydro - Hermod (Grane) 1995
– Statoil Gullfaks 1997 and Saga Snorre 1998/99
• Largest CT project ever undertaken by Statoil
• Scope not comparable to any current CTD project around the world
• Covers the scope for 3.5 / 4.0” drillpipe TTRD
– Through 7” monobore completion
– Using 2 7/8” CT
• Do what a drilling rig does !!!
– Well preparation
– Casing exit
– Drilling
– Completion
The nature of the project
© 2014 Baker Hughes Incorporated. All Rights Reserved. 3 ICoTA Well Intervention Conference, Aberdeen 12 & 13th Nov. 2014
Agenda Services provided
• Baker Hughes provided services – surface and downhole
– Coiled Tubing
– Fluid pumping and handling
– Wellbore intervention / preparation, casing exit and fishing
– Tubular handling services – BHA’s and completion
– Directional drilling
– MWD
– Completion / screen services
– Beacon onshore support – data integration – onshore evaluation / optimisation
© 2014 Baker Hughes Incorporated. All Rights Reserved. 4 ICoTA Well Intervention Conference, Aberdeen 12 & 13th Nov. 2014
Agenda Equipment developed /used
• Baker Hughes provided services - surface
– Hybrid, heavy duty CT unit – 120 k injector head
• Complete new build - mainly run on electric – verified working envelope as expected in electric mode
• Performed very well with exception of injector-head
• Full data integration and remote functionality for all equipment (fibre network ring)
• Data transfer onshore for remote analysis / supervision / decision making
© 2014 Baker Hughes Incorporated. All Rights Reserved. 5 ICoTA Well Intervention Conference, Aberdeen 12 & 13th Nov. 2014
Agenda Equipment developed /used
• Baker Hughes provided services - surface– Data integration from / to Coiled Tubing / pumping / mud system / directional drilling / mud
logging
– Data transfer onshore for remote analysis / supervision / decision making
© 2014 Baker Hughes Incorporated. All Rights Reserved. 6 ICoTA Well Intervention Conference, Aberdeen 12 & 13th Nov. 2014
Agenda Equipment developed /used
• Baker Hughes provided services - surface
– Purpose build, portable / temporary mud system
• Complete new build - performed very well – allows independent operation of platform rig’s mud system
• Required it’s own support structure due to weight and size
• Accompanied by purpose build, continuous service, portable mud pumps - very well suited for the type
of operation
© 2014 Baker Hughes Incorporated. All Rights Reserved. 7 ICoTA Well Intervention Conference, Aberdeen 12 & 13th Nov. 2014
Agenda Equipment developed /used
• Baker Hughes provided services - downhole
– 2nd generation spoolable DuraLinkTM CT connector (patented)
• Required to reduce weight of 2 7/8” CT reel from 45t to within platform crane capacity of 32t
• Performed extremely very well – no premature change-out of connector
• Facilitated pass-through of wireline cutter (RCT) for recovery of stuck CT
Picture above shows spoolable
DuraLinkTM CT connector during FEA
bending simulation
© 2014 Baker Hughes Incorporated. All Rights Reserved. 8 ICoTA Well Intervention Conference, Aberdeen 12 & 13th Nov. 2014
Agenda Equipment developed /used
• Baker Hughes provided services - downhole
– Abrasive CT cutter for stuck pipe
contingencies (patented)
• Development originated from identified high
risk of stuck CT
• Saved about 8 days of downtime on A-33
and avoided cutting of CT at surface when
leak above release tool developed
• Great safety improvement, avoiding CT crew
working above injector head (at height)
• Excellent planning focus on stuck CT
contingencies
Picture shows CT end recovered after activation of abrasive CT cutter
© 2014 Baker Hughes Incorporated. All Rights Reserved. 9 ICoTA Well Intervention Conference, Aberdeen 12 & 13th Nov. 2014
Agenda Equipment developed /used
• Baker Hughes provided services - downhole
– New 5 3/8” Delta Whipstock system implemented
• Required size did not exist
• Compatible with drilling BHA dog-leg capability
• Two reliable casing windows created
• Very CT friendly system – mills / swarf – not adopted from
an existing drillpipe system
© 2014 Baker Hughes Incorporated. All Rights Reserved. 10 ICoTA Well Intervention Conference, Aberdeen 12 & 13th Nov. 2014
Agenda Equipment developed /used
• Baker Hughes provided services - downhole
– First time use of 4.75” AutoTrakTM , SENTIO and acoustic caliper on CT
• Great interfacing between CT and DD/MWD – 4.75” top part of CT BHA
• Very efficient data integration between surface an downhole
• A rotary steerable drill-pipe BHA on CT
• Good interaction between DD and CT Driller
Mod Stab
CoPilot AutoTrak Steering Unit
UBHStabilzerMotor Top Stab
OnTrak Mod. Motor
BCPM (Pulser & Power supply)
X/O StopSub NCxx x T2
PDC
CT interface• Quick-Connect• Circulation sub.• Release tool etc.
© 2014 Baker Hughes Incorporated. All Rights Reserved. 11 ICoTA Well Intervention Conference, Aberdeen 12 & 13th Nov. 2014
• Rein Atle Edland, Sascha Schwartze
• Øystein Meling, Fernando Parra, Eivind Hagen, Cato Oppheim, Eric Ericcson
• Alistair Macleod, Mike Kuchel, Even Hestnes
• Freddy Jenssen, Iain France, Stephen Young, Jørgen Bruntveit
• Alf Jacobsen, Otto Omundsen
• Henry Egeland
• Terje Øvermo
• Robert Jessiman
• Eva Nilskog
• And many, many more……
Acknowledgements
• Excellent offshore personnel performance– No major HSE issues during the entire campaign – two incidents with low
severity - pinched finger - person stepped into hole on top of ESF structurewith one leg
– 248 days offshore
– KPI of 92.8% for deliveries through CT contract
© 2014 Baker Hughes Incorporated. All Rights Reserved. 12 ICoTA Well Intervention Conference, Aberdeen 12 & 13th Nov. 2014
Summary
• What does an operator get from such project ?– Simplified contractors view after 1st CTD Heidrun campaign
Delivery Benefit
A 2nd, independentdrilling operation
Increased utilisation of offshore platform resourcesMaximising number of side-tracks drilled in a given
timeframeAccelerated in-fill drilling
A method ofcounteracting theproduction decline
More stabilised productionTarget reservoir portions less attractive for platform main rig
and within CTD reach
A reliable futuremethod for reservoirdevelopment
Potential certainly exists, but the jury is still outMost on-shore locations who used CTD on a frequent basis
had to go though significant learning curve
A ’’lightning’’ fastdrilling operation
Equipment and support intense, within complex offshoreenvironment
© 2014 Baker Hughes Incorporated. All Rights Reserved. 13 ICoTA Well Intervention Conference, Aberdeen 12 & 13th Nov. 2014
Questions…later…back to Bård Marius
21
CoiledTubing
Fluid pumpingand handling
Wellboreintervention,casing exitand fishing
Tubularhandlingservices
Directionaldrilling
MWDCompletion
ScreensBeacon servicesData integration
© 2014 Baker Hughes Incorporated. All Rights Reserved. 14 ICoTA Well Intervention Conference, Aberdeen 12 & 13th Nov. 2014
A-19 A operation
22
3000
3050
3100
3150
3200
325003/09/2013 10/09/2013 17/09/2013 24/09/2013 01/10/2013
Mill and polish window,cure losses, BHA trip.
Wiper trip to surface, BOP test.
Differentially stuck, unstickCT, wait for new mud,displace to 1.12 sg WBM.
Mud pump failure.
Slow progressdue to stringers.
Permanentlystuck duringwiper trip.
A-09 C Operation
23
• An old inner completion installed shallower than expected obstructing the KOP
• Attempts to cut and retrieve the inner completion on CT were unsuccessful
• A-09 CTD Cancelled
3275.0
3300.0
3325.0
3350.0
3375.0
17.12.2013 24.12.2013 31.12.2013 07.01.2014 14.01.2014 21.01.2014 28.01.2014 04.02.2014 11.02.2014 18.02.2014
Time-depth curve A-33 A
2014-06-0524 Classification: Open
Mill window.Polish window and extend rathole.
BOP test, change end connector.
Started underreaming pilot hole.
Wiper trip to surface.Wiper trip to surface, changechipped bit. Wait for main rigto pull production riser.
Unable to enter with MFC.
2nd UR run.SDN caliper run.OH Clad run.
2nd Cladexpansionattempt.
2nd MFC run
25
CTD #1
BIT / WORT*
Integration of CTD with platform systems / organization
Logistics – material handling
Parallel operation, independent of main rig
Mud plant reliability
Topside CT equipment reliability
Rig-up / rig-down efficiency
Operational efficiency
HSE
Planned and achieved learning points - topside
– demonstrated – demonstrated with need for improvement
* In operation
26
A-19 A A-9 C A-33 A
Whipstock / window (single string)
Whipstock / window (dual string)
Drilling – telemetry / directional control
Drilling – hole cleaning
Drilling – differential sticking
OH Clad – installation
OH Clad – expansion N
Completion
Production
Planned and achieved learning points - downhole
– not attemptedN – failed attempt
– demonstrated – demonstrated with need for improvement
27
Lesson #1 – Hole Cleaning
• No cuttings came out while drilling, only during wiper trips
• The more frequent wiper trips in A-33 A proved successful in 5 ⅞” hole
• Underreamed and overgauge hole in shale was impossible to clean
28
Lesson #2 – Differential sticking
• Both stuck incidents in A-19 A had elements of differential sticking.
• Time consuming displacement operation to free coil on first stuck incident (6 hrs)
• A N2 bubble technique was developed and full-scale tested for use in A-33 A:
− Reduce BHP with N2 bubble unloading well
− BHP controlled to remain in overbalance
• N2 bubble technique test took less than 1.5 hrs to administer
• Not required to demonstrate technique in a drilling scenario
• This technique will be our preferred first contingency to unstick differentially stuck
pipe in CTD campaign #2.
29
Lesson #3 – Shale Stability
• 3 SND (ultrasonic caliper log) passes made,
good agreement between passes.
• In-consistent hole geometry
• Sandstone interval at bottom is logged to be 7”.
5 7/8" 7"
30
Future for CTD on Heidrun
• Original scope for CTD2 was to drill sidetracks in live wells with comingled
production .
• Adjusted scope after CTD1
− Reduce well complexity
− Success in dead wells need to be proven prior to extending scope
• Many well candidates on Heidrun identified for CTD
• Challenge: When will our candidate wells die?
• Hopefully a second campaign will be initiated in the relative near future
CTD has a future on Heidrun!
Heidrun CTD Campaign #1
Bård Marius JohansenCTD EngineerE-mail [email protected]: +47 995 12 387
www.statoil.com