hep projects · 2018. 8. 22. · hep project portfolio the 2014 p5 report is the major guidance...
TRANSCRIPT
HEP ProjectsMike Procario
Director of Facilities Division
Office of High Energy Physics
HEP PI Meeting August 22, 2018
HEP Project Portfolio
The 2014 P5 report is the major guidance
that HEP used to develop its current project
portfolio.
Large projects greater than $50 million were
named.
Small projects were encouraged.
FACET II was added due to the priorities of
the Office of Science.
2August 22, 2018 HEP PI Meeting
P5 Recommended Projects
Complete existing projects.
CMS Phase 1 Upgrade
ATLAS Phase 1 Upgrade
Muon g-2
Muon to Electron Conversion
LSST
A broader generation 2 dark matter portfolio
HEP has implemented our direct detection of dark
matter with
ADMX
SuperCDMS
LZ
August 22, 2018 HEP PI Meeting 3
P5 Recommended Projects
The highest priority was given to High
Luminosity LHC
HL-LHC Accelerator Upgrade Project
HL-LHC ATLAS Upgrade Project
HL-LHC CMS Upgrade Project
DESI was recommended as the next dark
energy experiment.
Dark Matter G3 was recommended.
HEP has prioritized completing DM G2 over starting
DM G3
August 22, 2018 HEP PI Meeting 4
P5 Recommended Projects
Build a truly international LBNF/DUNE Recommended to be more capable than the CD-1 concept that already existed.
Invite international contributions to the facility.
Make the detectors truly international.
Upgrade the beam power at Fermilab with PIP-II.
Build a suite of small experiments.
Carry out a short baseline neutrino program.
Participate in CMB experiments in ways that utilize HEP strengths.
August 22, 2018 HEP PI Meeting 5
DOE Project Management
August 22, 2018 HEP PI Meeting 6
Projects with TPC < $5 million don’t fall under O413.3• Small projects are managed by the HEP Research DivisionDOE has just delegated oversight of project with TPC < $50 million to the labs. • Of current projects this applies to SuperCDMS and FACET II
0
2
4
6
8
10
12
14
16
Jan-0
6
May-0
6
Sep-0
6
Jan-0
7
May-0
7
Sep-0
7
Jan-0
8
May-0
8
Sep-0
8
Jan-0
9
May-0
9
Sep-0
9
Jan-1
0
May-1
0
Sep-1
0
Jan-1
1
May-1
1
Sep-1
1
Jan-1
2
May-1
2
Sep-1
2
Jan-1
3
May-1
3
Sep-1
3
Jan-1
4
May-1
4
Sep-1
4
Jan-1
5
May-1
5
Sep-1
5
Jan-1
6
May-1
6
Sep-1
6
Jan-1
7
May-1
7
Sep-1
7
Jan-1
8
May-1
8
Number of active projects per month
Number of HEP O413.3 Projects
August 22, 2018 HEP PI Meeting 7
P5 report issued
Tevatron and B factory running flat out
HEP Project Funding
August 22, 2018 HEP PI Meeting 8
-
50,000
100,000
150,000
200,000
250,000
300,000
HEP Project Funding$K
Major Items of Equipment (TPC) Line Item Construction (TPC) Total Project Funding
Mu2e, PIP II, LBNF/DUNE
All other
HEP Project Staff
Michael Procario, Director of HEP Facility Operations
Ted Lavine, Program Manager for Instrumentation FACET-II, LZ, Muon g-2, Mu2e, helping with PIP-II and LBNF/DUNE
Simona Rolli, Program Manager for Instrumentation LHC ATLAS Phase I, LHC CMS Phase I, SuperCDMS, HL-LHC projects
Kathy Turner, Program Manager for Cosmic Frontier* DESI
Helmut Marsiske, Program Manager for Detector R&D* LSST
Bill Wisniewski, half-time detailee from SLAC LBNF/DUNE
Mike Harrison, half-time detailee from BNL PIP-II
*Matrixed from HEP Research and Technology R&D Division
August 22, 2018 HEP PI Meeting 9
Current Project Portfolio >CD-3
August 22, 2018 HEP PI Meeting 10
Project Laboratory Type TPC($M)
Next Step Actual or Forecast
Manager
Muon g-2 Fermilab MIE 44 Completed January 2018 Lavine
LSST SLAC MIE 168 CD-4 March 2022 Marsiske
Mu2e Fermilab LIC 274 CD-4 December2022
Lavine
ATLAS Phase I Upgrade
BNL MIE 33 CD-4 September 2019
Rolli
CMS Phase I Upgrade
Fermilab MIE 33 CD-4B July 2019 Rolli
DESI LBNL MIE 56 CD-4 Q4 FY 2021 Turner
LZ LBNL MIE 56 CD-4 Q2 FY 2022 Lavine
FACET-II SLAC MIE 24.6 CD-4 September 2021
Lavine
SuperCDMS-SNOlab
SLAC MIE 18.6 CD-4 September 2021
Rolli
Current Project Portfolio < CD-3
August 22, 2018 HEP PI Meeting 11
Project Laboratory Type TPC($M)
Next Step Forecast Manager
HL LHC AUP Fermilab MIE 208 -252
CD-2 Q1 FY 2019 Rolli
HL LHC ATLAS BNL MIE 149-181
CD-2 Q3 FY 2019 Rolli
PIP II Fermilab LIC 653-928
CD-2 Q3 FY 2020 Procario/Harrison
LBNF/DUNE Fermilab LIC 1,260-1,860
CD-2 Q1 FY 2021 Procario/Wisniewski
HL LHC CMS Fermilab MIE CD-1 ? Rolli
Several projects are below the thresholds for DOE project management order. South Pole Telescope 3G fabrication was completed in Jan 2017. ADMX-G2 fabrication was completed in Feb 2017. Short Baseline Near Detector is still under construction. PROSPECT and ANNIE are small neutrino experiments supported under a special FOA.
HEP Budgets and Project
The Administration and the Congress have been
out of sync on budgets the last two years.
FACET II and SuperCDMS were ready for CD-2 much
earlier than they were approved.
DOE needed to know that the funds to support them would be
available so we had to wait for the appropriations to pass.
FACET II was also de-scoped to fit the budget.
HEP will look to follow up with upgrades to achieve all of the planned
capability.
Other projects like LBNF/DUNE, DESI, SuperCDMS, HL-
LHC projects saw additional funds provided by
Congress.
August 22, 2018 HEP PI Meeting 12
Request versus Enacted
FY 18 PB Request FY 18 EnactedEnacted vs
Request
DESI 5,700 20,000 +14,300
FACET-II 2,000 10,000 +8,000
HL-LHC Accelerator 27,000 27,000 ---
HL-LHC ATLAS 6,000 12,000 +6,000
HL-LHC CMS 6,000 12,000 +6,000
LSSTcam 9,800 9,800 ---
LZ 14,100 14,100 ---
SuperCDMS-SL 2,000 7,400 +5,400
LBNF/DUNE 55,000 96,000 +41,000
Mu2e 44,400 44,400 ---
PIP-II 14,000 24,100 +10,100
August 22, 2018 HEP PI Meeting 13
Current Status
All projects past CD-
3 are well on their
way to successful
completion.
They should start
coming on line next
year.
August 22, 2018 HEP PI Meeting 14
DESI
Mu2e
LSST
SuperCDMS
HL-LHC AUP and HL-LHC ATLAS had
successful CD-1 reviews and are moving on
to CD-2.
HL-LHC CMS needs to improve the planning
of their MIP Timing Detector and there will
another review before CD-1 is approved.
August 22, 2018 HEP PI Meeting 15
Current Status continued
LBNF/DUNE is busy refurbishing the infrastructure at SURF, so that the excavation can begin.
ProtoDUNE single phase is about to start its run at CERN.
Design work continues across the entire project.
August 22, 2018 HEP PI Meeting 16
ProtoDUNE APA ready to be installed.
PIP II just received CD-1 on July 23, 2018.
August 22, 2018 HEP PI Meeting 17
A prototype of a single spoke resonator
What’s Next?
CMB-S4 was recommended by P5. DOE HEP and NSF AST, NSF PHY, and NSF polar programs sponsored a AAAC concept definition task force to make recommendations on how to pursue this project.
On the DOE side the labs are coordinating some critical R&D and a Pre-Project Design Group (PPDG) chaired by Jim Yeck.
PPDG and the collaboration are coordinating closely.
DOE and NSF coordinating.
August 22, 2018 HEP PI Meeting 18
What’s Next?
Light dark matter is a big topic of discussion
these days.
HEP has started a DM-New Initiatives BRN
Study (2018-2019) to
Assess the science landscape for dark matter
particle searches, AND
Identify which high impact science areas would be
suitable to be pursued with small projects in the
HEP program (i.e. that need HEP infrastructure and
capabilities).
August 22, 2018 HEP PI Meeting 19
University Roles
University groups are expected to take on
appropriate roles for HEP projects.
There is not enough expertise in the lab system
to tackle all of our projects with universities.
UCSB is known for their work on silicon detectors.
Penn is known for electronics.
Minnesota is know for organizing undergrad students to
produce large numbers of detectors.
Faculty, postdocs, and grad students are supported
under research funding.
Engineers and techs are paid by the project.
August 22, 2018 HEP PI Meeting 20
Examples of University Project Work
August 22, 2018 HEP PI Meeting 2121Front Back
Array assembly at Brown
Brown University is leading the phototube procurement, testing and assembly of phototube arrays for LZ.
Some universities on Mu2e
August 22, 2018 HEP PI Meeting 22
Cosmic Ray Veto Mechanical Prototype with University of Virginia faculty, postdocs, technicians, and students who assembled it
Minnesota students assembling a Mu2e tracker panel.
University work on DESI
August 22, 2018 HEP PI Meeting 23
The fiber positioner team at Michigan
They built 5000 of these for the DESI focal plane.
OSU Professor Klaus Honscheid
Commissioning instrument from OSU
University Roles
Decisions on what scope to assign to a
university group is left to the project
director.
The project director consults with the collaboration
on who can best carry out the scope, but the
project director is accountable for delivering the
project on time and within budget.
Being an excellent scientist does not imply that you
are an excellent project manager.
People who are excellent at both do exist.
August 22, 2018 HEP PI Meeting 24