hierarchical planning framework (review)

55
Rough-Cut Capacity Planning Rough-Cut Capacity Planning in SCM in SCM EGN 5623 Enterprise Systems Optimization EGN 5623 Enterprise Systems Optimization (Professional MSEM) (Professional MSEM) Fall, 2011 Fall, 2011

Upload: tuari

Post on 12-Jan-2016

64 views

Category:

Documents


1 download

DESCRIPTION

Rough-Cut Capacity Planning in SCM EGN 5623 Enterprise Systems Optimization (Professional MSEM) Fall, 2011. Rough-Cut Capacity Planning in SCM Theories & Concepts EGN 5623 Enterprise Systems Optimization (Professional MSEM) Fall, 2011. Material programs Supplier selection Cooperation. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Hierarchical Planning Framework (review)

Rough-Cut Capacity Planning Rough-Cut Capacity Planning in SCMin SCM

EGN 5623 Enterprise Systems Optimization EGN 5623 Enterprise Systems Optimization

(Professional MSEM)(Professional MSEM)Fall, 2011 Fall, 2011

Page 2: Hierarchical Planning Framework (review)

Rough-Cut Capacity Planning Rough-Cut Capacity Planning in SCMin SCM

Theories & ConceptsTheories & Concepts

EGN 5623 Enterprise Systems Optimization EGN 5623 Enterprise Systems Optimization(Professional MSEM)(Professional MSEM)

Fall, 2011 Fall, 2011

Page 3: Hierarchical Planning Framework (review)

Hierarchical Planning Framework Hierarchical Planning Framework (review)(review)

Long term-Material programs- Supplier selection- Cooperation

- Plant location- Production systems- Subcontractors

- Physical distribution structure- Transportation strategy

- Product program- Strategic sales planning

-- Personnel training-- Contracts-- Material Requirements Planning

-- Master production Scheduling-- Capacity planning -- Distribution planning -- Mid-term sales planning

Mid term

-- Personnel scheduling-- Material ordering

-- lot-sizing- operations scheduling- shop floor control

- Warehouse replenishment- Transportation planning -- Mid-term sales planning

Short term

EXECUTION

Information FeedbackFlow of goods

Page 4: Hierarchical Planning Framework (review)

The APICS-Standard Planning The APICS-Standard Planning Framework (review)Framework (review)

Page 5: Hierarchical Planning Framework (review)

Production Process (review)Production Process (review)

Requirements for Production Planning:• to meet the demand• to consider the resource capacities and the

material availabilities• to improve utilisation of the resources• to lower the setup time• to minimize the stock, and• to minimize the work in process (WIP)• to improve stability of the plan

Page 6: Hierarchical Planning Framework (review)

Rough-cut Capacity PlanningRough-cut Capacity PlanningThe main goal in rough-cut capacity planning is to identify where overloading or under-loading of production capacity occurs and revise the MPS as required.

•Overloading means that too much production of products has been planned in the facility and insufficient capacity exists to produce planned quantities of products required in MPS.

•Under-loading means that not enough production of products has been planned to fully load the facility.

Page 7: Hierarchical Planning Framework (review)

Rough-Cut Capacity Planning in Rough-Cut Capacity Planning in APO-SNPAPO-SNP

Page 8: Hierarchical Planning Framework (review)

Order Life Cycle for Make-to-StockOrder Life Cycle for Make-to-Stock

Page 9: Hierarchical Planning Framework (review)

Order Life Cycle for Make-to-OrderOrder Life Cycle for Make-to-Order

Page 10: Hierarchical Planning Framework (review)

Forecast Consumption Mode and Forecast Consumption Mode and HorizonHorizon

(Backword consumption of 4 days and a forward consumption of 3 days)

Page 11: Hierarchical Planning Framework (review)

Transactional Data for Transactional Data for TransferringTransferring• Starting from a demand plan, SNP checks the resource

capacities and delivers a medium/long-term plan for the estimated sales volumes.

• The plan includes the quantities to be transported between locations (e.g., DC-customer, or plant-DC) and the quantities to be produced (and procured), taking available capacity into consideration.

• SNP creates planned orders, purchase requisitions, and stock transfers that can be transferred directly to the connected OLTP systems.

Page 12: Hierarchical Planning Framework (review)

Capacity LevellingCapacity LevellingCapacity leveling supports the following resource categories:

• Production resources• Transportation resources

Capacity levelling supports the following resource types:• Bucket resources• Single-mixed resources• Multi-mixed resources• Transportation resources

Page 13: Hierarchical Planning Framework (review)

Capacity LevellingCapacity Levelling

The planner can use the following methods to adjust the plan:•Backward scheduling of the capacity load to fulfill demand using high priorities without due date violations. This rescheduling does not create any orders in the production horizon.•Forward scheduling of the capacity load for lower priority demand and use of demand priorities to minimize due date violations •A combination of backward and forward scheduling of the capacity load.

Page 14: Hierarchical Planning Framework (review)

Capacity Levelling ProfileCapacity Levelling ProfileThe main settings in the capacity leveling profile are scheduling direction, prioritization, and method.

•Scheduling Direction controls whether Forward, Backward or Combined scheduling is used. •Prioritization for the heuristic run defines how leveling determines the sequence of orders. The two possible choices for prioritization (to be sorted by ascending or descending order) are

• by order size or • by product priority.

•The three Method choices are • Heuristic, • Optimizer or • Badi (Business Aided-in).

Page 15: Hierarchical Planning Framework (review)

Time-based Capacity Time-based Capacity LevellingLevelling

Page 16: Hierarchical Planning Framework (review)

Capacity LevellingCapacity Levelling

Page 17: Hierarchical Planning Framework (review)

Heuristics-based Capacity LevellingHeuristics-based Capacity Levelling

• Heuristic-based capacity leveling compares, period by period, the capacity load on a resource with the requested load, either from the beginning or from the end of the planning horizon – depending on which scheduling direction is selected (forward or backward scheduling).

• If the resource is found overloaded, the system first selects all the activities or orders that cause the overload in this period. It then sorts these orders according to the priority that is defined and shifts orders or partial orders, one by one into subsequent or previous periods until the required maximum resource utilization is reached.

Page 18: Hierarchical Planning Framework (review)

Heuristics-based Capacity LevellingHeuristics-based Capacity Levelling

• For forward scheduling, the system moves the orders so far that the first activity using the resource to be leveled only begins after the overloaded period.

• For backward scheduling, the system moves the orders so far that the last activity using the resource to be leveled actually ends before the overloaded period.

• The system takes the lot sizes and rounding values defined in the master data into account when moving the orders.

Page 19: Hierarchical Planning Framework (review)

SNP Heuristic as Location, Network, SNP Heuristic as Location, Network, and Multi-Level Heuristicand Multi-Level Heuristic

Page 20: Hierarchical Planning Framework (review)

Scheduling in SNP HeuristicScheduling in SNP Heuristic

Page 21: Hierarchical Planning Framework (review)

Period FactorPeriod Factor

Page 22: Hierarchical Planning Framework (review)

Production Scheduling for Production Scheduling for Multiple BOM LevelsMultiple BOM Levels

Page 23: Hierarchical Planning Framework (review)

Scheduling in CTMScheduling in CTM

Page 24: Hierarchical Planning Framework (review)

Heuristics-based Capacity LevellingHeuristics-based Capacity Levelling

• Only orders that cause overloads are changed.

• This proves advantageous when a lot of orders exist but only some of them overload the resource.

• Prioritization is done by product or by product quantity.

• Select “Capacity Leveling” from the menu to balance the required work loads.

Page 25: Hierarchical Planning Framework (review)

Benefits of SNP with SCMBenefits of SNP with SCMThe benefits of Supply Network Planning with SAP SCM are as follows:1.Cross-plant medium-term rough-cut planning2.Cross-plant optimization of resource utilization

• Simultaneous planning of procurement, production and distribution

• Simultaneous material planning and finite capacity scheduling of production, storage, and transportation resources

3.Planning of critical components and bottleneck resources4.Prioritization of demands and receipts5.Collaborative supply planning over the Internet

Page 26: Hierarchical Planning Framework (review)

Linear Programming (LP) Linear Programming (LP)

EGN 5623 Enterprise Systems Optimization EGN 5623 Enterprise Systems Optimization(Professional MSEM)(Professional MSEM)

Fall, 2011 Fall, 2011

Page 27: Hierarchical Planning Framework (review)

Operation Research (OR)Operation Research (OR)Operation research refers to the application of quantitative methods and techniques to business problems in order to best utilize a company’s resources.

OR is used by many leading companies in recent years to optimize their limited resources in order to maximize their profits or minimize their costs.

Linear programming (LP) is one of the most important tools of operation research.

Page 28: Hierarchical Planning Framework (review)

Linear Programming (LP)Linear Programming (LP)

Five common types of LP problems:

•Product mixed•Ingredient mix•Transportation•Production plan•Assignment

Page 29: Hierarchical Planning Framework (review)

Five common types of LP problemsFive common types of LP problems

Page 30: Hierarchical Planning Framework (review)

Five common types of LP problemsFive common types of LP problems

Page 31: Hierarchical Planning Framework (review)

Steps in Formulating LP ProblemsSteps in Formulating LP Problems1. Define the objective2. Define the decision variables3. Write the mathematical function for the objective

(objective function)4. Write a one- or two-word description of each constraints5. Write the right-hand side (RHS) of each constraint,

including the unit of measure.6. Write<=, =, or >= for each equation7. Write all the decision variables on the left-hand side of

each constraints8. Write the coefficient for each decision variable in each

constraint.

Page 32: Hierarchical Planning Framework (review)

Formulating LPFormulating LP

Page 33: Hierarchical Planning Framework (review)

Formulating LPFormulating LP

Page 34: Hierarchical Planning Framework (review)

Formulation LPFormulation LP

Page 35: Hierarchical Planning Framework (review)

Formulation of ProblemFormulation of Problem

Page 36: Hierarchical Planning Framework (review)

Objective and ConstraintsObjective and Constraints

Page 37: Hierarchical Planning Framework (review)

Steps in Graphical Solution Steps in Graphical Solution MethodMethod

Page 38: Hierarchical Planning Framework (review)

Graphical SolutionGraphical Solution

Page 39: Hierarchical Planning Framework (review)

Graphical SolutionGraphical Solution

Page 40: Hierarchical Planning Framework (review)

Graphical SolutionGraphical Solution

Page 41: Hierarchical Planning Framework (review)

Graphical SolutionGraphical Solution

Page 42: Hierarchical Planning Framework (review)

Transportation (Network) ProblemTransportation (Network) Problem

Page 43: Hierarchical Planning Framework (review)

Requirement Assumption Requirement Assumption

Page 44: Hierarchical Planning Framework (review)

Feasible Solutions PropertyFeasible Solutions Property

Page 45: Hierarchical Planning Framework (review)

Cost AssumptionCost Assumption

Page 46: Hierarchical Planning Framework (review)

Parameter Table for Parameter Table for Transportation ProblemTransportation Problem

Supply

S1

S2

.Sm

Page 47: Hierarchical Planning Framework (review)

Transportation Problem ModelTransportation Problem Model

Any problems (whether involving transportation or not) fits the model for a transportation problem if it can be described completely in term of a parameter table like Table 8.5 and it satisfies both the requirements assumption and cost assumption.

The objective is to minimize the total cost of distributing the units. All the parameters of the model are included in this parameter table.

Page 48: Hierarchical Planning Framework (review)

Objective Function & ConstraintsObjective Function & Constraints

Page 49: Hierarchical Planning Framework (review)

Rough-Cut Planning in SCM Rough-Cut Planning in SCM

SAP Implementation SAP Implementation

EGN 5623 Enterprise Systems Optimization EGN 5623 Enterprise Systems Optimization(Professional MSEM)(Professional MSEM)

Fall, 2011 Fall, 2011

Page 50: Hierarchical Planning Framework (review)

Planning Book and ViewsPlanning Book and Views

Page 51: Hierarchical Planning Framework (review)

Capacity Check viewCapacity Check viewNow switch to the CAPACITY CHECK view. In the Selection profile section double click on ## RESOURCES. Double click on the work center (plant ##A1). Switch the TB Profile to 12MONTH. We appear to have enough capacity in the work center at the aggregated monthly level.

Now change the TB Profile to 180 DAYS. We are overloaded in the first couple days as SCM has tried to produce all that is needed to satisfy safety stock in those days.

Page 52: Hierarchical Planning Framework (review)

Capacity LevellingCapacity Levelling

Scroll over to the next capacity usage. We are also overloaded in thoseperiods. Multilevel Heuristic does not take capacity into consideration. Select

Page 53: Hierarchical Planning Framework (review)

Key Figures and Categories in Key Figures and Categories in SNP Standard Planning BookSNP Standard Planning Book

Page 54: Hierarchical Planning Framework (review)

HW 4: Exercises:HW 4: Exercises:1. Module 5 (Section 2)

Work centersCreate integration model for work centers in SAP ERP systemActivate integration model for work centers in SAP ERP systemConfirm data transfer for work centers in SCM system

Purchasing Info Records (PIR)Create integration model for PIR in SAP ERP systemActivate integration model for PIR in SAP ERP systemConfirm data transfer in SCM system

2. Model 6 (Section 2)Production process model (PPM)Production data structure (PDS)

Setting for PDS in SCM systemCreate integration model for PDS in SAP ERP system

Page 55: Hierarchical Planning Framework (review)

HW 4: Exercises:HW 4: Exercises:Activate integration model for PDS in SAP ERP systemConfirm data of PDS transfer in SCM systemCreate integration model for PDS SNP transferActivate integration model for PDS SNP transferConfirm data transfer (PDS SNP) in SCM system

3. Model 7 (Section 2)Transactional data in SAP ERP system

Create integration model for Planned Independent Requirement (PIR) in SAP ERP system

Activate integration model for PIRConfirm data transfer (PIR) in SCM system