High-level risk assessment

APM Risk Conference, 25 Jan 2018

Simon White, Risk Consultant

Page 3: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

High-level risk assessment

• Risk assessment

• Some examples

– Example 1: £4bn, 6 years

– Example 2: £5bn, 5 years

– Example 3: £50m, 1.5 years

– Example 4: £50m, 1 years

– Example 5: £50m, 0.5 years

• Level of detail

• Logic / complexity

• Correlation

Page 4: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

RISK ASSESSMENT

Page 5: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Ways to assess risk

• Techniques to help assessment

Credit: from Centrica Energy’s PACE guidelines.

Page 6: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Quantitative risk assessment

• Never been done before

• Challenging conditions

• Uncertain regulations

• Early phase

• Been done before

• Easy conditions

• Established regulations

• Mid-execution

P10P50

P90

Base

P10P50

P90

Base

• “Cheaper but

more risky”

• “More expensive,

less risky”

Page 7: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Quantitative risk assessment

• Given the risk as we have expressed it:

– How much overall contingency is likely needed?

– Where is it likely needed?

– And when?

– What’s our biggest risk at P50?

– At P90?

– What contractual incentivisations are appropriate?

– How valuable is response x?

Page 8: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

EXAMPLES

Page 9: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Example 1

• ~£4bn, ~6 years

• Challenges:

– Extreme weather

– Very heavy single lift

– Two-week installation season

each year

Page 10: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Example 1

• ~20 cost lines

• Each cost split:

– Time-dependent part

– Non-time-dependent part

Page 11: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Example 1

• ~50 activities

• Lag tasks

• “Carryover” logic

Page 12: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Example 2

• >£1bn, ~5 years

• ~900 activities.

Page 13: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Example 2

• Rolling up risk

– We heavily rolled up the offshore hookup work.

– Mid-execution, when the hookup work had more detail, we used

the summary curve of the detailed hookup progress data, to

inform the risk assessments on our high-level bars.

Page 14: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Example 3

• ~£50m, ~18 months

• 1,600 activities

• Challenges:

– Inconsistent level of detail

– Planned in hours, not days

– Unrealistic logic

– Two distinct projects in P6, with duplicated

common activities

Page 15: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Example 3

• Many constrained dates

Page 16: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Example 3

High level of detail

Page 17: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Example 3

• Master execution schedule had 1,600 activities.

• We managed to prune it down to 900, by:

– Removing activities in the past

– Dissolving milestones

– Rolling up sequential work

Page 18: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Example 4

• ~£50m, ~1 year

• 500 activities

• Challenges:

– Planned in hours, not days

– Schedule logic quality

• We “rolled up” to 112 activities

• 40 cost lines

Page 19: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Example 4

• Rolling up by hand

Page 20: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Example 4

• Rolling up by hand

Page 21: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Example 5

• ~£50m, ~6 months

• 400 activities

Page 22: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Example 5

• Semi-qualitative scoring

TYPEIMPACT

LEVELDEFINITION

1Green

(low)

High Confidence of achieveving within 5 days of

Forecast Milestone

2Amber

(medium)

Confidence level with in 6 to 25 days delay to

Forecast Milestone

3Red

(high)> 25 days delay to Milestone

1Green

(low)Less than 25% probability

2Amber

(medium)Between 25% and 75% probabiilty

3Red

(high)More than 75% probabilityP

RO

BA

BIL

ITY

CRITICALITY

SC

HE

DU

LE

Page 23: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Example 5

• Risk against external dates

Page 24: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Example 5

• Schedule confidences for individual sections

Page 25: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

LOGIC / COMPLEXITY

Page 26: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Logic challenges

• Too much schedule detail

• Finish-driven logic

• Different calendars

• Too much cost detail

• Too much risk detail

Page 27: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Logic solutions

• “Roll up” activities and logic

– Use leads / lags

• Use forward-driven logic

– Use “stretching” (aka “non-contiguous scheduling”)

• Simplify calendars

– Aim for none at all, except windows / seasons

• “Roll up” costs

– Spread over hammocks

• Try and simplify risks

– Combine risks, focus on significant risks

Page 28: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Uncorrelated risk impacts

• Overall probability vs individual probabilities

– Individual probability 𝑝:

– Where:

• 𝑃 is the overall probability

• 𝑛 is the number of impacts

𝑝 = 1− 1− 𝑃 1𝑛

Page 29: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Uncorrelated risk impacts

• Example: Risk of equipment delay

– Impacts three procurement activities

– Impacts are uncorrelated

– Overall probability is 60%

Risk with uncorrelated impacts

Overall

probability

Number of

impacts

Chance of at

least one

impact

Chance of

no impacts

Chance of

not each

impact

Chance of

each impact Notes

001 Equipment delay 60% 3 60.0% 40.0% 73.7% 26.3% Probability was assessed as overall chance

… …

Page 30: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Distribution shapes

• Use the uniform distribution, or better

Single value 1-point estimateMore knowledge /

less uncertainty

Beta Pert(larger shape parameter,

default shape parameter of 4)

3-point estimate

Triangle / Trigen 3-point estimate

Beta Pert(smaller shape parameter)

3-point estimate

Uniform 2-point estimateLess knowledge /

more uncertainty

Credit: from Centrica Energy’s QRA training manual

Page 31: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

LEVEL OF DETAIL

Page 32: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Level of detail

• As examples

• Top down vs bottom up

• Consistency

• Correlation

Page 33: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

CORRELATION

Page 34: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Correlation and level of detail

Page 35: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Correlation and level of detail

• Roll a die

Page 36: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Correlation and level of detail

• Roll 2 dice

• Roll 3 dice

Page 37: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Correlation and level of detail

• and more …

Page 38: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

Correlation and level of detail

P90 = 98 would be 135

Page 39: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

SUMMARY

Page 40: High-level risk assessment - APM › media › 11737 › 8-simon-white.pdf · 2020-06-18 · High-level risk assessment • Risk assessment • Some examples –Example 1: £4bn,

High-level risk assessment

• Summary

– Keep perspective

– Keep high level

– Balance correctness and manageability

• Big project with …

– … a few big activities, a few big costs

– … lots of activities, lots of costs

• Care with words!

– “High-level assessment” vs “high level of detail”

– “Bring forward” vs “go forwards”