high performance hospitals - using concrete frames and cladding

12
0.1 SMALL HEADLINE High Performance Hospitals USING CONCRETE FRAMES AND CLADDING

Upload: zerak

Post on 10-Apr-2015

1.863 views

Category:

Documents


6 download

TRANSCRIPT

Page 1: High Performance Hospitals - Using concrete frames and cladding

0.1

SMALL HEADLINEHighPerformanceHospitals

USING CONCRETE FRAMES AND CLADDING

Page 2: High Performance Hospitals - Using concrete frames and cladding

0.2

Photo captions to go here

1

Good hospital design can provide more efficient facilities and a

better environment for both staff and patients.

Concrete construction presents great opportunities for the project

team to meet the needs of the client by helping to improve the

function, value and whole life performance of the facility.

By checking that the design and construction process gives

timely consideration of the benefits discussed in this publication,

decision makers in the procurement process can ensure that extra

value is added to the building, often at no or little additional cost.

Front cover (left to right)

• The Great Western Hospital, Swindon: in-situ flat slab concrete frame with precast cladding. Photography: Gillian Bond.• Central Middlesex Hospital ACAD Centre: a concrete framed structure which is exposed in public areas. Photography: Nicholas Kane.

This page• The West Middlesex University Hospital: concrete walls clad in timber, render and brick. Design: Nightingale Associates; Photography: Charlotte Wood.

Page 3: High Performance Hospitals - Using concrete frames and cladding

0.2

Photo captions to go here

1

BUILDING BETTER HEALTHCAREHospitals are facilities that help medical staff in the efficient delivery of quality healthcare and provide a positive environment for speedy patient recovery. Good building design can provide more efficient facilities and a better environment for both staff and patients.

This publication examines the role of concrete construction in the current hospital development programme

to provide additional effective, high quality healthcare to meet the nation’s growing and changing needs. It

aims to inform decision makers in the procurement process about areas where concrete construction can help

improve the function, value and whole life cost of the facility.

A major government initiative is underway to provide 100 new hospital buildings by 2010. To meet this

ambitious target and also ensure best value, the plan is being funded by a mixture of public, private and local

NHS trust capital, with procurement under the Private Public Partnership, often involving ProCure21, PFI

and DBFO. These aim to promote better capital procurement and improve the service to patients through a

partnering programme between the NHS and the private sector. Construction partnerships will often design

the facilities and be financially involved with their operation and maintenance. This will help secure high-

quality designs and earlier access to new facilities, and ensure best value, both from initial and whole life cost

perspectives.

Recent research has confirmed that good design creates the best environment for patients, staff and visitors,

which promotes effective services and speedier recovery, resulting in more efficient use of resources. The design,

construction and operation of new facilities is now formally assessed using a variety of measures – not just

financial – encouraging more considered and holistic design and construction processes and better value solutions.

The new buildings will have to satisfy a range of complex and often conflicting needs, including the flexibility

to accommodate not only changes in demand, healthcare procedures, IT and working methods but also newly

emerging issues such as cross-infection and MRSA, daylighting, natural ventilation and sustainability.

Romford New Hospital: floor plan (level 3) showing the central core servicing the ward towers. Concrete framed ward tower under construction.

Page 4: High Performance Hospitals - Using concrete frames and cladding

2 3

The benefits of

using concrete:

• Reduces initial and running costs

• Speeds construction

• Minimises vibration

• Accommodates future changes

• Facilitates partition wall sealing

• Caters for easy services installation

• Enhances sustainability

• Promotes a good work environment

• Resists spread of fire and sound

• Improves air quality

CONCRETE FOR HOSPITAL CONSTRUCTIONWell-designed and effectively managed hospital buildings help support the work of

frontline staff, provide an appropriate environment for patient recovery, and so improve

efficiency. The choice and design of a building’s frame and cladding can have a surprisingly

large influence on the performance of the final building. An important example of this is

the effect on the provision of M&E services, which are generally the most critical item in

cost and construction time, and are a major factor in the costs of running, maintaining and

refurbishing a building over its life.

Although every new facility has specific requirements, a typical list of needs to be

considered might be:

• Value/cost – how well it performs its function in terms of helping staff and patients in

relation to initial and running costs and residual value

• Speed – how quickly it can be brought into use

• Flexibility – how easily it can accommodate or be adapted for changing needs

• Sustainability issues – both during construction and in use.

Behind these requirements lie some particularly important considerations, some of which

are specific to healthcare buildings, and include:

• Vibration – operating theatres and night wards require the designer to pay special

attention to reducing vibration

• Services – often the most expensive and slowest element to construct

• Partition walls – installing and sealing literally miles of these to the frame

• Work environment – proven to affect staff morale and patient recovery

• Further issues such as sound, fire resistance and air quality.

Today’s concrete frames are ideally suited to support the requirements of modern hospital

buildings; and by playing an important background role in the operation and performance

of the building, concrete frames can help reduce running costs and maintenance.

The following sections consider these issues further and discuss how concrete’s properties

can help resolve them.

SPEED AND PROGRAMME

The use of concrete is highly compatible with fast programme construction due to easy

mobilisation at the start and the use of modern methods of construction, including

sophisticated formwork systems, post-tensioning and precast elements. With traditional

methods of construction, concrete frames were erected on a floor-to-floor cycle of

two to three weeks. With modern methods it is common to achieve this in one week.

Concrete frames normally require no disruptive fire protection after erection, and can be

made sufficiently watertight for early installation of M&E services (the longest phase of

construction in hospitals) and other follow-on trades.

The use of concrete flat slab floors provides flush soffits that simplify service provision.

This encourages the swift installation of prefabricated services, where major savings in

cost and time come from factory-tested assemblies and fewer joints on site. Prefabricated

bathroom pods can be installed and set flush by recessing them into the floor slab.

Exposed concrete walls look good and provide fabric energy storage (European Institute of Health and Medical Sciences). Courtesy of The Concrete Society.

Page 5: High Performance Hospitals - Using concrete frames and cladding

2 3

VIBRATION CONTROL

Vibration control is especially important in areas

such as operating theatres, night wards and intensive

care units, and is an important factor in the design

and specification of building frames. Concrete can

easily be designed for the most complete control of

vibration over whole areas, often without the need for

significantly thicker floor slabs, giving great flexibility

for change in use. A recent independent study* into

the vibration performance of different structural

forms has provided new insight into the additional

mass and stiffness required to upgrade a basic ‘office‘

structure to meet the higher criteria of hospitals. This

is summarised in the diagram opposite.

The concrete solutions can meet vibration criteria with

only small increases in mass and depth and hence cost,

compared with steel frame solutions. They also help

the D&B team avoid the risks, often associated with

other materials, of having to seek modifications to NHS

vibration criteria. This is done to avoid the cost penalties

of providing this extra mass and stiffness.

FLEXIBILITY AND ADAPTABILITY

Healthcare methods, provision of IT, patient

expectations, and standards of environment and

equipment are all changing rapidly; so flexibility of use

of new buildings is a major design requirement. For

instance, less invasive surgery is likely to continue to

change the required proportions of theatre, recovery

and ward space. The use of concrete construction

automatically ensures many of the qualities that aid

flexibility.

For services and future stairs or lifts, holes in both

normal and post-tensioned slabs can easily be

designed-in and either formed during construction or

cut out later as required. For vibration, larger areas can

be designed to meet stringent criteria for operating

theatres at little extra cost, permitting future flexibility.

Early consideration of these benefits during design can

optimise flexibility at little or no extra expense.

SOUNDIt has been shown that patient comfort is an

important factor in recovery. Concrete’s mass and

damping qualities are easily used to achieve the

required acoustic performance, which provides a

restful and productive environment that is isolated

from the noise and vibrations resulting from normal

hospital routines. In concrete buildings, floor and

ceiling finishes are rarely dictated by acoustic

requirements; these are delivered by the performance

of the concrete slab.

PARTITION WALLSHospitals require literally miles of partition walls and

their construction is a major factor in cost, time and the

consequent disruption to other construction procedures.

Sealing walls at the soffits of the floor above is

particularly important. The use of flat slabs simplifies

this, reducing partition costs by up to 4% of the frame

cost before considering additional programme savings.

* Hospital floor vibration study. Comparison of possible floor structures with respect to NHS vibration criteria. Research Report, Arup, 2004. Available for download from www.concretecentre.com

����

����

����

���

��

����

�����

�������

������

������

������

Vibration control:�����������������������

����������

���������������������������

������

����

�����

�������

������

������

������

50%

40%

30%

20%

10%

0%

Vibration control:����������������������������%

incr

ease

���������������������������

������

The above diagram shows the increases in mass and construction depth needed to upgrade an office frame to hospital vibration criteria for night wards and operating theatres.

Concrete structures reduce vibration cost-effectively. Courtesy of the National Society for Epilepsy.

Page 6: High Performance Hospitals - Using concrete frames and cladding

5

In a building, the

environmental impact

of construction

materials is typically

one tenth of that

caused by operation

over its life.

Concrete flat slabs are ideal for highly serviced buildings.

SERVICESThe choice of material and design of a building’s frame and cladding can have a

surprisingly influential role on the services, which are generally the most critical element

in construction cost and time.

Concrete flat slabs are ideal for highly serviced areas in hospitals, such as operating

theatres and intensive care units. They allow complete freedom to prefabricate, install

and maintain services without having to thread ducts under or through intrusive down-

stand beams. Openings in the slab for service risers can be simply accommodated during

design; they can be formed during casting or cut later to suit. For the longest spans, wide

shallow beam solutions provide large areas uninterrupted by secondary beams and the

freedom to route ducts under the shallow main beams.

For the less heavily serviced areas, designers are now encouraged to use concrete’s

thermal mass properties to reduce air-conditioning. This then reduces capital,

refurbishment and running costs.

SUSTAINABLE CONSTRUCTIONConcrete has much to offer those who aim for sustainable construction. It has the

potential to reduce both the initial cost and running expenses by:

• Reducing the need for air-conditioning through fabric energy storage, and the use of

daylighting and natural ventilation. Concrete has an excellent track record in passively

cooled buildings.

• Reducing the need for heating through airtight construction.

• Reducing maintenance through providing durable walls, columns and cladding.

Other sustainable aspects of concrete construction include:

• UK manufactured reinforcing steel is made from 100% recycled scrap, unlike structural steel.

• Cement manufacture is increasingly using waste-derived fuels (such as scrap tyres),

thereby saving energy and relieving pressure upon landfill facilities.

• Replacement materials, which would otherwise go to landfill, are being incorporated

into both cement and concrete to reduce their environmental impact.

• Aggregates are often extracted locally, and ready-mixed concrete is typically made

no more than 15 miles from any project. This reduces the environmental impacts

associated with transportation.

• Unlike some materials, impacts arising from reinforced concrete generally occur in the UK,

rather than being ‘hidden’ abroad, and so are recognised and minimised for global benefit.

• The energy and carbon dioxide emissions ‘embodied’ in a concrete frame are slightly

less than those in a steel frame. More importantly, however, the energy used and CO2

emitted during a building’s operation are some 50 times greater than those embodied in

its structural frame. By using the excellent thermal properties of concrete it is possible to

make significant whole life savings in energy, carbon dioxide emissions and operating costs.

• On demolition of a building, concrete and reinforcement can be recycled.

• Concrete buildings are adaptable, durable and have many inherent qualities (sound,

fire and vibration performance), and hence are ‘long life, loose fit’ sustainable buildings.

By the use of thermal modelling, solar shading and passive ventilation techniques

to complement its concrete frame, the designers of Derby PFI hospital are aiming

for an annual energy target of 55 GJ/100 m3 p.a. – making it one of the most

energy-efficient acute hospitals in the UK.

An environmental review of design and construction of the Great Western Hospital

Swindon by environmental award winner, Carillion, achieved a cost saving of £1.8m.

This considered materials used, waste targets and energy in use. The hospital

incorporates a high thermal mass concrete frame and concrete cladding. Excavated

clay material was treated with lime and cement to provide a sub-base for the roads and

car parks, saving the costs of removal from site. The building is designed to consume

30% less energy in use and generate 50% less construction waste than a typical

hospital: it is discussed in detail on page 8.

4

Page 7: High Performance Hospitals - Using concrete frames and cladding

5

WORK ENVIRONMENT The look and feel of a hospital is known to affect

patient and staff well-being and hence healthcare

performance. Uplifting architecture in public areas,

involving the use of exciting structurally efficient

exposed soffits, columns and walls can all add to

the character and ambience of a building. This

avoids having to develop an artificial architectural

veneer that adds to first costs, maintenance, and

refurbishment.

Concrete is inert with no harmful off-gassing, and

its structural form is commonly associated with

enhanced natural ventilation and daylighting. It

provides robust surfaces for walls, partitions, columns,

soffits and cladding that are easily sealed for cleaning

where required.

Aesthetics, ease of cleaning and a healthy atmosphere all

lead to enhanced user satisfaction of concrete hospitals.

FIREConcrete is inherently fire resistant, and unlike some

materials normally requires no added fire protection.

This avoids the delays and disruptions of follow-on

trades caused by site applied protection or repair on

site of damaged off-site applied protection. Concrete’s

fire protection is provided at no extra cost and does

not require the use of intumescent paints.

The inherent fire resistance results in concrete often

performing in excess of design requirements for occupant

safety. This over-performance benefits the building

‘owner’ as repairs and the period before re-use following

a fire are minimised.

AIR TIGHTNESSWith concrete, the flat soffits enable the partitions

between rooms to be sealed easily, helping prevent

airborne cross contamination between compartments.

Large panel external cladding reduces the number of

external joints and so cuts air loss and saves energy.

MAINTENANCE AND REFURBISHMENTWhole life costs can be reduced by the use of concrete

which provides long life cladding, durable walls and

columns with direct finishes, and easily accessed

services under flat soffits. Cladding can be designed to

last the nominal design life of the building, with only

periodic inspection of the external seals.

By using the exposed soffits, suspended ceilings and

air conditioning may be reduced or avoided, lowering

maintenance and refurbishment costs.

ANCILLARY BUILDINGS The use of techniques such as ‘tunnel form’ and

precast wall and floor panels introduces further mass

production methods into concrete construction.

Both are fast, economic, highly-mechanised and

increasingly popular. For repetitive room layouts, such

as staff residences, they are ideal because of excellent

sound and fire properties and low maintenance

durable finishes.

Concrete is also ideal for car parks due to its

robustness and corrosion resistance. It is a popular

choice with users, with modern design taking

advantage of concrete’s clear span capabilities to

provide easy access/parking, and bright clean soffits

that help security and boost user confidence.

The light and airy reception at the Great Western Hospital, Swindon. Photography: Gillian Bond.

Modern methods of concrete construction are ideal for staff accommodation.

Exploiting the benefits of concrete is simple and

comes at little or no added cost. It just requires

early awareness and consideration of the

potential gains and for decisions to be made at

the correct stage in the design process.

Page 8: High Performance Hospitals - Using concrete frames and cladding

6 7

DESIGNConcrete frames are available in a broad range of structural forms to suit all needs and

can be constructed in precast or in-situ concrete, or a combination of the two, known

as hybrid concrete construction.

Currently, flat slab construction, typically on grids of 7.2 to 8.4 m on a 1.2 m module,

is the preferred choice for many hospitals with its speed, vibration performance and

ability to best facilitate the installation of services and partition walls. Increasingly, the

flat slabs are post-tensioned to reduce slab thickness and provide potential for longer

spans of up to 12 m if necessary.

Some alternatives to flat slab construction are shown below.

• Prestressing of concrete beams and floor units provides fast, light and economical

solutions.

• Ribbed in-situ slabs on wide shallow beams are lighter than flat slabs, but not so

versatile and take longer to construct.

• Hybrid concrete construction combines the best qualities of precast concrete

(accuracy, high quality finishes, off-site manufacture) with those of in-situ

construction (flexibility for late changes, mouldability, robustness, two-way

spanning, local manufacture).

For each hospital the most effective solution can be determined only after considering

all design, construction and use parameters. The benefits of using concrete discussed

in this publication provide a useful guide for designers when comparing construction

types. For the structural engineer, assistance is available from the design tool, Concept

(see back cover).

Design loadings need to be agreed between client, architect and structural engineer

early in the design process. Allowances for larger point loads for ceiling-hung

equipment and heavy-weight blockwork partitions are often required. Vibration criteria

for operating theatres and night wards will often dictate structural design. The client

may choose to have larger areas designed to these tighter criteria to permit future

space planning flexibility.

When considering penetrations through slabs for services, the needs of the services

engineer must be co-ordinated with those of the structural engineers, who should

incorporate them into their design. Working with the design team, the client will need to

decide how much flexibility it is reasonable to build in. For future flexibility, ‘soft spots’

are generally designed in; polystyrene knock out slots, cast-in lightweight blocks or

cast-in markers are all commonly used. These, together with the design drawings, aid

those making future modifications.

In reinforced concrete, holes near columns can be situated at the faces of the columns,

rather than being restricted to the corners so as not to clash with beams. This avoids

the need to offset pipe work back to column faces or use oversized clad columns to

hide pipe work on column corners.

Off-site manufactured bathroom pods are commonly used. To incorporate these with

the required falls, pods may be set on the slab with a traditional screed used elsewhere.

However, it is common to omit the thick screed and at most have a thin bed levelling

screed. To obtain the falls into the wet area, the slab is locally cast with a recess of

30 to 50 mm into which the pod is placed.

In line with Government policies, various hospital design guides* promote important,

non-financial aspects to consider. These include:

• Air quality (optimisation of natural ventilation)

• Daylighting (improving natural light penetration and minimising solar gain)

• Integration of passive cooling and sustainable construction into design

• Aesthetics.

Flat slab concrete

construction is the

preferred framing

option for many

hospitals as it

provides speed

and flexibility.

* NEAT evaluation toolkit (NHS Estates); Better health buildings (Centre for Healthcare Design); and Design

evaluation toolkit (Department of Health).

Concrete options for hospital frames.

Solid flat slab (may be post-tensioned)

Ribbed slab with integral beams

Hybrid – precast floor units on in-situ beams and columns

Page 9: High Performance Hospitals - Using concrete frames and cladding

6 7

PROCUREMENTThe specialist frame contractors should be involved

early in the procurement process to allow the design

to reflect the economies of their preferred form of

construction, balanced against whole project value. This

will depend on the contractor’s previous experience, the

availability of equipment and the opportunity to tailor

design details to the construction method.

For instance, many specialists have their own

prestressing firm (or preferred partner), allowing

them to provide fast and cost effective prestressed

frames. Others may have their own stock of special

formwork, giving them an edge in another form of

concrete construction. Alternatively, precast elements

that can be swiftly erected may be best. This needs

early involvement of the precaster to obtain the best

programme and economies through repetition of

components and hence mould use.

Partnering, DBFO and modern methods of

construction in concrete are highly compatible with

the above approaches as they encourage integration,

rather than the traditional separation, of the design-

construct process. This minimises construction risk,

with its consequences of higher tender prices, extra

programme allowances and potential over-runs.

Concrete is regularly used for new construction

alongside existing working buildings. Construction and

forming methods, and deliveries can be adapted to

suit congested areas, and precast or self-compacting

concrete can be used where construction noise is an

issue.

CLADDING IN CONCRETEPrecast concrete cladding can be designed with a wide

range of finishes, from brick to reconstructed stone.

Panels are secure, highly durable, low maintenance and

long life; especially compared with lightweight metal

alternatives. They can have glazing fitted in the factory

and be designed for installation without scaffolding.

Recently, some new hospitals have been criticised

for problems caused by excessive heat or cold. Using

concrete cladding to control solar gain and thermal

loss can help avoid this.

Panels can be large and self-supporting between

columns if desired, thereby simplifying the frame and

maximising airtightness. Sandwich panels (factory

insulated between two concrete skins) provide

significant extra thermal mass due to their solid inner

wall and have a durable inner face, suitable for direct

decoration.

With most cladding systems, hospitals will have to

allow for the major cost of recladding – and loss of

use of the facilities during this work – within their

design life. However, concrete panels can be designed

to require only periodic inspection of the external

seals, with any replacement of seals to be carried out

without scaffolding or closure of the building.

Precast cladding panels provide opportunities for rapid

construction, just-in-time delivery and minimal waste,

with low construction risk. Again, for best economy,

the cladding should be considered early in conjunction

with the specialist supplier. This will ensure best value

by optimising repeat mould use and fixing/interface

details with the frame.

The Great Western Hospital case study on page 8

illustrates the use of concrete cladding.

Concrete sandwich panel being hoisted into position.

700

500

300

100

Inde

x o

f co

st

Labour content & cost

1 10 20 30

Cost of precast units drops with repeated use of moulds – Cast in concrete, Architectural Cladding Association, 2003.

Casts per mould

The effect of repetition on cost of casting precast concrete structural or cladding units

Page 10: High Performance Hospitals - Using concrete frames and cladding

8 9

Today most hospitals

are built in concrete

because of vibration

performance,

simple services

installation and cost

effectiveness for the

required spans.

Cladding on elevation.

Factory installed glazing avoided the use of scaffolding.

CASE STUDIESTHE GREAT WESTERN HOSPITAL, SWINDON

The Great Western Hospital is a £100 million, PFI project on the outskirts of Swindon,

providing 55,000 m2 of space for the Swindon and Marlborough NHS Trust. The design and

build consortium, which included contractor Carillion, will operate it over the next 27 years,

and put great efforts into choosing the most appropriate components on the basis of user

needs and whole life cost. The six-storey L-shaped building is an environmental flagship

project, featuring an in-situ concrete frame and precast concrete cladding.

Concrete frame - strength and simplicity An in-situ concrete flat slab frame on a nominal 7.2 by 7.2 m column grid was chosen for speed

and buildability. It also maximised the service zones, provided inherent fire protection and delivered

energy savings through the exploitation of the frame’s thermal mass. Finite element design of the

300 mm deep floors provided for large cast-in and drilled service openings without downstand

beams. The frame was constructed ahead of programme in only 38 weeks.

Designing the interface Early involvement between engineers TPS Consult, frame contractor Duffy Construction and

precast cladding contractors Trent Concrete, resulted in an efficient and economical system for

the concrete cladding panels that then became self-supporting between columns. The design

of the cladding and frame accommodated not only operating theatres, ITUs, offices and wards,

but also provided flexibility for future changes in use.

Precast cladding - maximising prefabrication Architect Whicheloe Macfarlane HDR (now part of BDP) chose the 7600 m2 of rich cream-

coloured precast concrete cladding to simulate the local natural stone. Its high quality finish

and careful detailing contributes to the clean and attractive lines of the building.

One of the primary reasons for specifying precast concrete was to avoid external scaffolding,

significantly reducing cost and allowing earlier access for following trades. The factory

pre-glazed 7.2 m panels were each erected in one movement and the large size minimised

the number of just-in-time deliveries, joints and fixings. Cladding was installed ahead of

programme in only 19 weeks.

The resulting early enclosure provided a dry envelope and allowed the follow-on weather-

sensitive trades to start earlier – especially important in hospital construction with complex

M&E services to install. This, together with the freedom provided by a flat soffit, helped speed

installation and minimise M&E costs that amounted to a third of total construction cost.

Sustainability Carillion intended The Great Western Hospital to be a flagship sustainability project.

Environmental considerations dictated materials used, construction techniques and waste

handling. At Swindon, the thermal mass of the concrete frame contributes further to

sustainability objectives by maximising its fabric energy storage properties, and the cladding

helps moderate solar gain and heat loss.

Whole life valueWhole life costings and lifetime performance are of critical importance in PFI projects. The

precast cladding not only gave greater certainty in terms of quality, cost and programme time,

but also provided a highly durable, self-finished façade requiring little or no maintenance.

Because of early specialist involvement and value engineering it cost only around 55% of the

cost for basic curtain walling.

Both the frame and cladding at Swindon were erected ahead of programme, and the Great

Western Hospital was delivered on time and on budget in little over three years from start of

construction.

Page 11: High Performance Hospitals - Using concrete frames and cladding

8 9

COVENTRY AND DERBY PFI HOSPITALS A large 127,000 m2 six-storey acute hospital forms part

of the £334m Coventry New Hospitals PFI contract with

Innisfree. Skanska is constructing the 6000 room building

with 300 mm deep flat slab in-situ concrete floors,

supported on a typical column grid of 7.2 by 7.2 m,

increased to 8.5 m in some areas. The structural form was

chosen for minimum construction depth, with a flat soffit

to allow uninterrupted services distribution and easy

fixing and acoustic/smoke sealing at wall partition heads.

Arup’s flexible design allowed for up to two holes

in the slab on opposite faces of internal columns

– either cast-in, or post drilled to allow flexibility for

future clinical replanning. Floor finishes are applied

to a 6 mm levelling screed on the as-cast concrete

slab, in which 35 mm deep recesses allow for shower

and bathroom floor finishes to falls. Detailed analysis

confirmed that floors could satisfy HTM vibration

criteria without any increase in depth under operating

theatres, further increasing flexibility. The frame also

supports rooftop plant rooms.

Derby PFI Hospital, another six-storey hospital by the

same team, will provide 1,159 beds and 128,000 m2

of new hospital buildings, including 35 operating

theatres. Like Coventry, a 300 mm flat slab concrete

frame was chosen for reasons of ease of partition

and services installation under a flat soffit, ‘blanket’

vibration control to cover wards and theatres, and

service holes for flexibility for clinical re-planning.

The design incorporated 15 m wide blocks surrounding

courtyards, producing column grids varying from

6.0 by 6.5 m to 8.5 by 8.5 m. Concrete columns,

precast in steel moulds, increased speed of erection

and allowed direct paint finishes, so helping reduce

programme time and risk. Arup’s design supported

‘roll-out’ reinforcement mats and contractor detailing

to increase construction efficiency.

ROMFORD NEW HOSPITAL

The in-situ frame at the Coventry Hospital.

9

This hospital is being constructed by Carillion Health

for The Hospital Company under a PFI contract with the

Oxford Radcliffe Hospitals NHS Trust. The 45,000 m2

six-storey frame extends the existing hospital to provide

three new sections for the Children’s Hospital, a Head

and Neck Centre, and a theatre block with laboratories.

Concrete columns, mostly precast, support 250 mm

thick post-tensioned flat slab concrete floors that

match existing hospital levels, with stability provided

by the concrete cores. TPS Consult’s flat slab design

approach maximises services zones and flexibility

within the ceiling voids. Post tensioning was chosen for

programme speed and cost.

Square precast columns vary between 500 and 600 mm,

with larger circular feature columns up to three storeys

high in the concourse and entrance. The 250 mm thick

post-tensioned concrete slabs span from 6.6 to 9.0 m,

depending on the grid layout of each section of hospital

and accommodate 4 by 6 m services riser voids. The

slabs are increased to a thickness of 300 mm for

theatre, laboratories and plant areas to cater for heavier

loadings and vibration control.

The post-tensioned slab provides knock out points to

accommodate services for future hospital flexibility. These

will generally provide two holes, situated on opposite or

adjacent column faces. All cast-in requirements and post

drilled holes are co-ordinated with the tendon layout

(which is clearly marked on slab surface and soffit).

Stairs are mostly precast concrete, housed in the cores,

and there is a feature semi-circular in-situ entrance stair.

Individual large-diameter bored concrete piles up to

1200 mm across and 35 m long directly support precast

columns, avoiding the cost and disruption of pile caps.

JOHN RADCLIFFE HOSPITAL, OXFORD

Post tensioning ducts in place for the slab at Romford.

Flat concrete soffits at the John Radcliffe Hospital, showing tendon marking.

Catalyst Healthcare is constructing this new 800-bed

five-storey hospital under a £200m PFI project for

Barking, Havering and Redbridge Hospitals NHS Trust.

Four circular ward towers rise three storeys above two

podium floors that contain administration, diagnostic,

and treatment facilities including operating theatres. A

central service core tower separates staff, patient and

visitor flows, and houses staff facilities.

The in-situ concrete frame supports 250 to 300 mm

thick concrete flat slab floors on a column grid of 8.1

to 9.0 m span. Columns are mainly circular with a

diameter of 400 mm. The post-tensioned flat slab

maximises space for services, encouraging their

prefabrication, and giving greater flexibility for routing

and penetration of the slab. It also copes well with the

circular floor plate and irregular cantilever edges of up

to 3 m in length. The flat slab brought savings of

around £800,000 by simplifying the fixing and sealing

of partition wall heads. All five current UK hospitals by

Bovis Lend Lease use concrete flat slab frames for

similar reasons.

Shearheads (steel cruciforms within the depth of

the slab) have been adopted for additional flexibility

for service penetration at columns – holes can be

constructed on all four axes on internal columns.

Bathroom pods are recessed into the slab which uses a

thin levelling screed.

The concrete frame facilitates fast construction,

avoiding delay to services associated with site-applied

fireproofing and allowing swift partition installation.

It also meets vibration criteria without seeking

dispensations.

Page 12: High Performance Hospitals - Using concrete frames and cladding

Help and advice on concrete construction for hospitals are available from [email protected] or visit www.concretecentre.com

Ref. TCC/03/13

ISBN 1-904818-25-0

First published 2005

© The Concrete Centre 2005

The Concrete Centre, Riverside House,

4 Meadows Business Park, Station Approach, Blackwater, Camberley, Surrey GU17 9AB

National Helpline 0700 4 500 500 or 0700 4 CONCRETE

All advice or information from The Concrete Centre is intended for those who will evaluate the significance and limitations of its contents and take responsibility for its use and application. No liability (including that for negligence) for any loss resulting from such advice or information is accepted. Readers should note that all Centre publications are subjectto revision from time to time and should therefore ensure that they are in possession of the latest version.

www.concretecentre.com

Kings College Hospital: feature staircase in the new Golden Jubilee Wing, an in-situ flat slab concrete framed building. Design: Nightingale Associates; photography: Charlotte Wood.

CI/SfB

UDC

69.057.52:728.5

FURTHER READINGEcoconcrete: The contribution of cement and concrete

to a more sustainable built environment.

British Cement Association, 2001, 21 pages.

Ref. 97.381.

Economic concrete frame elements – a handbook for

the rapid sizing of concrete frames.

British Cement Association, 1997, 128 pages.

Ref. 97.358.

Concept – an invaluable design tool for the

conceptual design of reinforced concrete frames in

five minutes.

The Concrete Centre, 2004. Ref. TCC/03/012.

Best practice guidance for hybrid concrete

construction.

The Concrete Centre, 2004, 64 pages. Ref. TCC/03/09.

Concrete and fire – using concrete to achieve safe,

efficient buildings and structures.

The Concrete Centre, 2004, 13 pages.

Ref. TCC/05/01.

Cast in concrete II - a guide to the design of precast

concrete and reconstructed stone.

Susan Dawson, Architectural Cladding Association,

2003, 96 pages. Ref. BPCF 1.

CI/SfB

UDC

725.5119.057.52:728.5