history of ifa 2000 - usaid sari/energy...

53
RTE ©RTE(EDF)-CN2i 2002 Th hi t f IFA 2000 The history of IFA 2000 by Philippe ADAM RTE International RTE International March 2nd, 2007

Upload: hoangcong

Post on 16-Mar-2018

219 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Th hi t f IFA 2000The history of IFA 2000

by Philippe ADAM

RTE InternationalRTE International

March 2nd, 2007

Page 2: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

A brief view of the history of the interconnection

The interconnection of the French Transmission S t t t d i 1946 ith B l i d G t

of the French power system

System started in 1946 with Belgium and Germany at the 225 kV level.

A first DC interconnection with Great Britain was commissionned in 1961 (160MW connected to the 225 kV network)

The first interconnection in 400 kV started operation in 1964 with Spain.

225 kV network)

operation in 1964 with Spain.

In 2007, RTE operates 46 interconnection lines with its neighbouring countries (22 x 400 kV – 20 xwith its neighbouring countries (22 x 400 kV 20 x 225 kV – 4 x 270 kV DC).

Page 3: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

1964 2000

Page 4: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

A brief view of the history of the France to

The learning period : 1955 - 1975

England Interconnection

g p

The first study of a DC link between France and England (1950 – 1955)

The achievement of a first project IFA 160The achievement of a first project IFA 160 (decision : 1957 – commissionning : 1961)

A useful feedback from experience (1961 – 1975)

Page 5: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

The first project of a DC Interconnection between France to England (IFA 160)

+/- 100 kV between Lydd (GB) and Echinghen (F); 160 MW (8 x Gotland 1st DC link)

Mercury arc valve converters

Manufactured by ASEA (valves) and nationalManufactured by ASEA (valves) and national companies (cables, transformers and capacitors)

Submarine cables laid on the sea bed (50 – 60 m)

Page 6: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

March 2nd, 2007

Page 7: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

The experience gained with IFA 160The experience gained with IFA 160

DC cables were very often damaged by shipDC cables were very often damaged by ship anchors and trawlers : availability < 50%

1971 th i t l t t i i ll1971 : a thyristor valve prototype is occasionnally connected in the place of a mercury arc valve in Lydd converter station

1974 : replacement of a complete 80 MW mercury arc valves bridge by a thyristor valve bridge in Echinghenvalves bridge by a thyristor valve bridge in Echinghen converter station

Page 8: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

The first discussions on IFA 2000The first discussions on IFA 2000

1969 : first economic studies concluded that an optimal1969 : first economic studies concluded that an optimal size was 2200 MW in 1980, and 4000 MW in 1985.

1974 : new economic studies found that the optimum was 2000 MW in 1980.

1978 : studies showed that mutual assistance and fuel savings guarantied a 5 years return on money

1985 : updated studies showed that given the low cost of nuclear energy, 4 years was more probable figureof nuclear energy, 4 years was more probable figure

Page 9: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Theoretical daily load on the interconnection as shown by studies made in 1978made in 1978.

March 2nd, 2007

Page 10: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

The choice of HVDC for the interconnectionThe choice of HVDC for the interconnectionTechnical justification

Decoupling of the European and British power systems : each country keeps its own frequency control; no stability problemno stability problem.

Difficulty to install an overhead line, because of the density of the ship traffic on the Channel : submarinedensity of the ship traffic on the Channel : submarine cables are a better solution.

Over a transmission distance of 50 to 60 km, HVDC is more economical.

March 2nd, 2007

Page 11: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

LA = AC line cost

LC = DC line costLC = DC line cost

PA = AC substation cost

SC = DC converter station cost

I = total cost of DC solution

II = total cost of AC solution

d = breakeven distance

Page 12: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Main characteristics of the interconnectionMain characteristics of the interconnection

Geographical position.g p p

Position in the French Power Grid.

Structure of the interconnection

Structure of Les Mandarins converter station

Structure of Sellindge converter station

Page 13: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Geographical positionGeographical position.

Page 14: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

1984

Position in th F hthe French Power Grid.

1986

Page 15: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Structure of the interconnection

March 2nd, 2007

Page 16: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Structure of Les Mandarins converter stationStructure of Les Mandarins converter station

Page 17: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Structure of Sellindge converter stationStructure of Sellindge converter station

Page 18: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Some aspects of the p

design studiesg

Page 19: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

The main requirements

Transmission of bulk power essentiallyTransmission of bulk power, essentiallyCapacityModes of operationModes of operation

Control principles

Dynamic behaviourDynamic behaviourCompatibility of end functions and equipment

T l i ti b t t ti dTelecommunications between stations and control centers

Commissionning testsCommissionning tests

Page 20: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

The rating studiesThe rating studies

DC voltage : +/- 270 kV (optimum for 500 MW in 1978)1978)

DC current = 1852 A

T f d l 118 kV ( ) &Transformer secondary voltages = 118 kV (star) & 204 kV (delta)

N i l fi i d ti ti l 15° & 18°Nominal firing and extinction angles = 15° & 18°

Converter transformer power = 618 MVA

Reactive power consumption = 1 200 MVAr

Page 21: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

The rating studies (continued)The rating studies (continued)

Valve design :

-12 valves per pole

- 96 thyristor levels in series

- 2 thyristors in parallel

Thyristor characteristics :Thyristor characteristics :

- diameter = 77 mm

- max repetitive voltage (direct &reverse) = 4.5 kV

- max repetitive current @ 70°C = 1350 A

Smoothing reactors = 370 mH

Page 22: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

The system studiesThe system studies

Insulation coordination

System stability

Harmonic filtering and reactive power compensation

System stability

Converter behaviour on system faults

Overvoltages

Subsynchronous interactions

AC system protection behaviour

Page 23: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

I l ti di tiInsulation coordination

Page 24: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

H iHarmonic filtering and reactive power pcompensation

- global distorsion < 1.6%

dd h i- odd harmonic voltage rate < 1% 160 MVAr /- even harmonic voltage rate

160 MVAr / filter

g< 0.6% rank = 11 & 13 rank = 3

Page 25: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

System stability

Power

Transient stability of close nuclear groupsgroups

Rotor angleRotor angle

Page 26: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

C t b h i t f ltConverter behaviour on system faults

AC voltage Mandarins

DC voltage Mandarins pole

DC current Mandarins poleDC current Mandarins pole

DC voltage on the cable

DC voltage Sellindge pole

DC current Sellindge pole

3 phase short circuit at the converter station bus @ Import

AC voltage Sellindge

3 phase short circuit at the converter station bus @ Import from the UK at full load (dc simulator result).

Page 27: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Overvoltagesg

Overvoltages at LesOvervoltages at Les Mandarins 400 kV bus after a 3 phase fault resulting in the loss of two feeding lines and thelines and the blocking of the converters

Without filter tripping

EMTP simulation

Page 28: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Overvoltages (continued)O e o ages (co ued)

Overvoltages at LesOvervoltages at Les Mandarins 400 kV bus after a 3 phase fault resulting in the loss of two feeding lines and thelines and the blocking of the converters

With filter tripping

EMTP simulation

Page 29: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Subsynchronous interactions

Damping of torsionnal oscillation on Gravelines turbo-generator shaft.

Without the With the Without the interconnection interconnection

Page 30: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

AC system protection behavioury p

Fault currents asFault currents as seen by protections with the presence of AC filtAC filters.

Page 31: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Controls

Page 32: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

The equipment designThe equipment design

studiesstudies

Page 33: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

HVDC cables

Submarine cable

Land cableLand cable

Specific means and machines to manufacturemachines to manufacture, lay and embed the submarine cables.

Page 34: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Page 35: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Thyristor valves

Quadrivalve structure

Page 36: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Thyristor valves

Valve module

Page 37: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Converter transformers and smoothing reactors

Single phase 3 windings 206 MVA unit 277 kV – 1852 ASingle phase 3 windings 206 MVA unit 277 kV 1852 A

Page 38: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Filter and capacitor bank and its protections

Page 39: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Testing facilities : thyristor valves

High DC voltage teststests

Heating tests

Page 40: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Testing facilities : thyristor valves (continued)

S th ti t t i it d ltSynthetic test circuits and results

Page 41: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Testing facilities : smoothing reactor

HV DC tests

Mechanical tests

Page 42: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Testing facilities : cables

Endurance tests : 6000 hours @ 420 kVDC, 250 thermal cycles (1 kA)@ , y ( )

Page 43: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Testing facilities : DC simulator

> Control compatibility tests on EDF DC simulator

> Preparation of the on site commissioning tests

Page 44: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Testing facilities : site tests

EDF R&D monitoring and testing facilities at Les Mandarins in 1986Mandarins in 1986.

Page 45: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Project organisation and management

Planning

P j t tProject team

Page 46: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

PlanningPlanning

Page 47: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Project teamProject team

Project leader : EDF generation & transmission di i i N t k i i d t t (CERT)division – Network engineering department (CERT)

Design studies : EDF R&D division (ERMEL)

Testing : EDF R&D division (ERMEL)

Main manufacturers : CGEE AlsthomMain manufacturers : CGEE Alsthom + Câbles de Lyon & Pirelli

C di ti ith CEGB t i ittCoordination with CEGB : steering committee + technical committee + operational

Page 48: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Cost of the interconnection

Investment cost : 6 billions FF (1981) = 1,8 B€ (2001)

Operation and maintenance annual cost = 5 M€ (2005)

Page 49: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

20 years later, thank you for your kind attention !

Page 50: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Page 51: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Page 52: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002

Page 53: History of IFA 2000 - USAID SARI/Energy Integrationsari-energy.org/oldsite/PageFiles/What_We_Do/activities/Sri_Lankan... · Th hi t f IFA 2000The history of IFA 2000 ... 1957 –commissionning

R T E© RTE(EDF)-CN2i 2002