hitachi nuclear energy shitachi · mfn 09-023 supplement 3 enclosure 1 nrc rai 6.2-140 s05 provide...
TRANSCRIPT
SHITACHIGE Hitachi Nuclear Energy
Richard E. KingstonVice President, ESBWR Licensing
PO Box 780 M/C A-65Wilmington, NC 28402-0780USA
T 910 819 6192F 910 362 6192rick [email protected]
MFN 09-023 Supplement 3 Docket No. 52-010
November 16, 2009
U.S. Nuclear Regulatory CommissionDocument Control DeskWashington, D.C. 20555-0001
Subject: Response to PortionInformation Letter No.Certification ApplicationNumber 6.2-140 S05
of NRC Request for Additional375 Related to ESBWR Design
- Engineered Safety Systems - RAI
The purpose of this letter is to submit the GE Hitachi Nuclear Energy (GEH)response to the U.S. Nuclear Regulatory Commission (NRC) Request forAdditional Information (RAI) sent by the Reference 1 NRC letter. GEH responseto RAI Number 6.2-140 S05 is addressed in Enclosure 1.
Enclosure 2 contains markups to DCD Tier 1 and Tier 2 Section 6.2 as noted in
the Enclosure 1 response.
If you have any questions or require additional information, please contact me.
Sincerely,
Richard E. KingstonVice President, ESBWR Licensing
MFN 09-023 Supplement 3Page 2 of 2
Reference:
1. MFN 09-624, Letter from U.S. Nuclear Regulatory Commission to JeraldG. Head, Request for Additional Information Letter No. 375 Related toESBWR Design Certification Application, October 1, 2009
Enclosures:
1. MFN 09-023 Supplement 3 - Response to Portion of NRC Request forAdditional Information Letter No. 375 Related to ESBWR DesignCertification Application - Engineered Safety Features - RAI Number 6.2-140 S05
2. MFN 09-023 Supplement 3 - Response to Portion of NRC Request forAdditional Information Letter No. 375 Related to ESBWR DesignCertification Application - Engineered Safety Features - RAI Number 6.2-140 S05 - Markups to ESBWR DCD Tier 1 and Tier 2 Section 6.2
cc: AE Cubbage USNRC (with enclosures)JG Head GEH (with enclosures)DH Hinds GEH (with enclosures)SC Moen GEH (w/o enclosures)eDRFsection 0000-0108-5168
Enclosure I
MFN 09-023 Supplement 3
Response to Portion of NRC Request for
Additional Information Letter No. 375
Related to ESBWR Design Certification Application
Engineered Safety Systems
RAI Number 6.2-140 S05
MFN 09-023 Supplement 3Enclosure 1
NRC RAI 6.2-140 S05
Provide updated RAI response, clarify implementation of PCC pool refill, and confirmvent fan discharge submergence and fan performance
In response to RAI 6.2-140, Supplement 4, GEH provided detailed results for 30-daycontainment analysis, which credited PCCS, PCCS pool refill, PARS, and six drywellgas recirculation (DGR) fans beyond three days. However, GEH later changed thedesign basis requiring operating only four of six DGR fans and provided selected resultsin ESBWR DCD Revision 6.
A. The selected plots provided in ESBWR DCD Revision 6 are not sufficient for the staffto perform confirmatory analysis and complete the review. GEH should update RAI 6.2-140 response to include the four fan case, which represents the new design basis.
B. GEH's response to RAI 6.2-140, Supplement 4, shows varying of the PCC pool refillrates to maximize the PCCS heat transfer. GEH should clarify how it will implement thecontrolled PCC pool refill rates during the operation of ESBWR.
C. ESBWR DCD Revision 6 states that "The vent fan discharge line is > 0.22 m (9 in)and < 0.25 m (10 in) below the top of the drain pan lip." Confirm that the DGR fandischarge line would stay submerged during the 30 day analysis.
D. ESBWR DCD Revision 6 Table 6.2-49 lists the minimum DGR fan performancerequirements. Confirm that the DGR fan performance used in the containment analysisis bounded by the values listed in Table 6.2-49.
E. ESBWR DCD Revision 6 Figure 6.2-14el shows curve of analytical pressure limit.
a. Explain the regulatory significance of this curve.
b. Explain how this curve would be used in ESBWR design.
c. Explain the relevance of this curve to ITAAC, if any.
F. Update ESBWR DCD appropriately to include responses to parts B through D.
GEH Response
A. The plots provided in GEH's response to RAI 6.2-140S04 have been updated basedon the analysis presented in ESBWR DCD Revision 6. These plots, 6.2-140 S05-C1-6and 6.2-140 S05-D1-26, are presented below using the same naming convention forfigure titles used in Supplement 4 of this RAI.
1 of 37
MFN 09-023 Supplement 3Enclosure 1
B: In the TRACG analysis, the PCC pool level was not kept at the highest possiblelevel. Therefore, the containment pressure could be higher at times because of higherpool saturation temperature and lower PCC heat transfer. This trend is shown in theresponse to RAI 6.2-140S04.
In the response to Supplement 4 of this RAI, GEH presented a plot showing the PCCpool level with respect to time (Figure 6.2-140 S04-B1). The analysis currentlypresented in ESBWR DCD Revision 6 contains a PCC pool refill control scheme thatmaintains the level in the pool closer to the top of the PCC tubes (DCD Rev. 6 Figure6.2-14e10). Using the information from the TRACG calculation presented inSupplement 4 of RAI 6.2-140, a DW pressure adder of 25 kPa (3.6 psi) is applied to theDW Pressure curves reported in ESBWR DCD Rev. 6 to adjust the results consideringthe highest possible PCC pool level. The effect of this adder is shown in Figure 6.2-140S05-2 below.
C: An error was discovered in the ITAAC Table 2.15.4-2, Item 14, which describes thelocation of the PCCS vent fan discharge as an elevation below the drain pan lip. Theintent of this ITAAC is to define this elevation within a tolerance such that the ITAACcan be met in a way that ensures the submergence does not exceed what it is in theanalysis. Therefore, the acceptance criteria in this item, as well as the text in Tier 2,Section 6.2.2.2.2 will be changed to consistently read:
"The elevation of the discharge on the PCCS vent fan line is 24 cm (9.4 in)below the top of the drain pan lip with a tolerance of 1.4 cm (0. 6 in)."
The TRACG analysis presented in ESBWR DCD Rev. 6 for the post-72 hour scenariodoes not maintain a 10 inch submergence of the vent fan discharge lines. However, asensitivity study on the effect of the submergence was performed. The difference inPCC vent fan discharge elevation and GDCS pool level is seen to decrease over timeas shown in Figure 6.2-140 S05-C5 below. However, the GDCS pool level illustrated inFigure 6.2-140 S05-C5 also confirms that the vent fan discharge does not becomeuncovered. The fan outlet is set in TRACG to a constant elevation of 20.91 m(referenced to Vessel Zero.) From the figure, the GDCS pool level in Ring 7,corresponding to the 4 vent fan pool, appears to reach a final level of 20.92 m.However, due to the fact that the discharge line is very close to being uncovered, ananalytical DW pressure adder was developed as a safety margin.
Similar to the technique described in paragraph B above, an adder of 15 kPa (2.2 psi) isapplied to the TRACG DW pressure response values as reported in ESBWR DCD Rev.6. The basis for the additional pressure comes from a study conducted to gauge theeffect of submergence of the discharge outlet on DW pressure. Shown in Figure 6.2-140S05-1 below, the DW pressure is seen to increase with increased submergence.The vertical section around 14 inches of submergence occurs early in vent fanoperation and can be ignored. An adjustment factor is determined, consideringsubmergence and decay heat as primary contributors to DW pressure. The DWpressure at the end of the increased submergence test case was 281 kPa; that resultsin a difference from the base case at the same time of -12kPa. The submergenceeffect is then calculated as being 12 kPa divided by the difference in submergence of10.5 inches, or 1.14 kPa/inch submergence. The stated submergence should be heldat 10 inches, so multiplying the submergence effect value by 10 inches yields an adderto 11.4 kPa that is rounded up to 15 kPa. The effect of this adder plus the adder
2 of 37
MFN 09-023 Supplement 3Enclosure 1
described in paragraph B is shown in Figure 6.2-140S05-2 below. This figure will alsobe added to the DCD as indicated in the attached markups as Figure 6.2-14e13. Toreduce redundancy, Figures 6.2-14el and 6.2-14e2 will be modified by removing theAnalytical Pressure Limit Curve.
D.: To provide additional assurance that the fan performance is bounding, a sixth datapoint (at 1,570 CFM) will be added to DCD Tier 2, Table 6.2-49. The sixth data pointprovides enough data to cover the range of fan performance and bounds the TRACGdata points shown in Figure 6.2-140S05-D6 below. Please see attached markups.
E(a): The Analytical Pressure Limit curve shown in ESBWR DCD Rev. 6 Figure 6.2-14e13 represents a system performance acceptance criterion. This curve is included toaccommodate variations in IC/PCC pool levels, PCC vent fan discharge submergencevariation, PCC vent fan performance characteristics and variations, PCC heatexchanger efficiency, and TRACG modeling, for example those discussed in B and Cabove. This curve indicates system performance consistent with the GDC 38 criteria torapidly reduce pressure and maintain a reduced pressure.
E(b): The curve defines an acceptance criteria for the analysis; it indicates that thepressure is rapidly reduced and does not approach the design pressure after PCC ventfan have been activated. Furthermore, any subsequent analysis performed during thedetailed design phase must fall below this criterion.
E():" There is no ITAAC that applies to this curve as a test, analysis, or acceptancecriteria.
3 of 37
MFN 09-023 Supplement 3Enclosure 1
450
Design DW and WWV Pressure
400 +
350 -4
300 -
250 -
Wwl Pres-r (L-ve 31.Ring 7) P993107RPV Pr--ur (Leve 21, R, ng 1 ) P992101Desgn Presure200
150 -
100
0 24 48 72 96 120 144 168 192 216 240 264 288 312 336 360 384 408 432 456 480 504 528 552 576 600 624 648 672 696 720Time (hr)
Figure 6.2-140 S05-Cl Main Steam Line Break, I DPV Failure (Bounding Case) - Containment Pressures (30days).
450
400-
350
300
250
200
150
100
50
74,0Time (hr)
6.0
Figure 6.2-140 S05-Cla Main Steam Line Break, I DPV Failure (Bounding Case)- Containment Pressures(72-76 hr).
4 of 37
MFN 09-023 Supplement 3Enclosure 1
m0 Tn. -
200
180
160 1
140
4i n
100
806
BDWGe~Te~~ Gf~ Terfp TV9~31O~S~pp PoeT Tenp fl§92~O7
60
40 1
20
00 24 48 72 96 120 144 168 192 216 240 264 288 312 336 360 384 408 432 456 480 604 528 552 576 600 624 648 672 696 720
Time (hr)
Figure 6.2-140 S05-C2 Main Steam Line Break, I DPV Failure (Bounding Case) - ContainmentTemperatures (30 days).
200- I
180 - Bul, DW Gee TeeBWeT."A Gae Te-p TV9-3"-1
160Sep PoB Te UTL992907
160
140 -T--
12 TZ
4 100
&- =F
OU
604-:
40 t
20 -
I0 S i 1 I I Ii I IIi i i i i i ! ! ! I I I I 1 1 1 ! I
72.0 72.5 73.0 73.5 74.0Time (hr)
745 75.0 75.5 76.0
Figure 6.2-140 S05-C2a Main Steam Line Break, IDPV Failure (Bounding Case) - ContainmentTemperatures (72-76 hr).
5 of 37
MFN 09-023 Supplement 3Enclosure 1
80i
ý 1 1. 1 1 1 1 1 1. 1 1 1 1 1 1 1 1 1 1. 1 ý ý. I I I I ý I I I 1 1. 1. 1 ý ý I 1 1. ý I 1 1. ý 1. 1 1. 1 1 1. 1 1
70 -
60
504
-40 -
30
20
T o tat P o e TO TP O 00 001T".PCCS Power
10) +
C) I I . . . .
0 24 48 72 96 120 144 168 192 216 240 264 288 312 336 360 384 408 432 456 480 604 528 552 576 600 624 648 672 696 720Time (hr)
Figure 6.2-140 S05-C3 Main Steam Line Break, I DPV Failure (Bounding Case) - PCCS Heat Removalversus Decay Heat (30 days).
T.a
80
70+ Th -o'TOýTPOOOOO
6"
50 t
Z40
30
I
W)
10
U -+ ] • I I I I I I I I
72 73 74Time (hr)
75 76
Figure 6.2-140 S05-C3a Main Steam Line Break, 1 DPV Failure (Bounding Case) - PCCS Heat Removalversus Decay Heat (72-76 hr).
6 of 37
MFN 09-023 Supplement 3Enclosure 1
300i I I .I I .I . .i . .i . , , i , . I, I l , , , I r , , i , , , , , i , , , , ! . . . . . . . . . . . . . . . . . . . .
250
2OO
150
100
50 ! I..> --......
GOICS 1rpa -Le 34.Rig 7) PA993407G4.20 A-r~pece (Leel 340R1n 8) PAg93408
- W Head (LevI 35, Rang 1) PA993501DW Annu52s (Level 30, Rng 6) PAg93006
4----
g
0 24 48 72 96 120 144 168 192 216 240 264 288 312 336 360 384 408 432 456 480 504 528 552 576 600 624 648 672 696 720Time (hr)
Figure 6.2-140 S05-C4 Main Steam Line Break, I DPV Failure (Bounding Case) - Drywell and GDCSNoncondensable Gas Pressures (30 days).
300 ,,
250 -
200 4:
0.
0.
150
GOCS Airspce (Level 341Ring 7) R P0A3407GDCS AirSpace (Level 34'Rin 0) P0093408DW Head (Level 35. Ring 1) PA993501DW Anvviv (Level 30. Ring 6) Pl003006
[7---i
100 +
50 -
0
72.0i . . . i . . I . . . . I .
72.5 73.0 73.5 74 0Time (hr)
74,5 75.0 75.5 76.0
Figure 6.2-140 S05-C4a Main Steam Line Break, 1 DPV Failure (Bounding Case) - Drywell and GDCSNoncondensable Gas Pressures (72-76 hr).
7 of 37
MFN 09-023 Supplement 3Enclosure 1
25
24
23 -1
.22
w421
--GDCS wte levl (L7 33,34. n99 8) )ZLV993408JVent F (r Outet i GDCS POol Ring 8
L
204
19-1
1848 96 144 192 240 288 336 384
Time (hr)432 480 528 576 624 672 720
Figure 6.2-140 S05-C5 Main Steam Line Break, 1 DPV Failure (Bounding Case) - GDCS Pool Water Level(30 days).
26
241- GDCS water I.eI (Le-e4 33.34. R4n 8) DZLuV99M4080
VerM FWen Ouet GDCS Pool RIr 8
23+
•22
w(21 H-
20+
19-4-
18 I - I I I i I I I I I I I ! i I I I I I I I I I I I I I I I72.0 725 73,0 73.5 74.0
Time (hr)74.5 75.0 75.5 76.0
Figure 6.2-140 S05-C5a Main Steam Line Break, 1 DPV Failure (Bounding Case) - GDCS Pool Water Level(72-76 hr).
8 of 37
MFN 09-023 Supplement 3Enclosure 1
34,0
335- PCC Po water Lel DZLV993604
Too of 9CC Tubes DOZV993704
3/4 PCC Tubes DZLV99380433.0 Middle DZLV993904
114 PCC Tubes DZLV994004- - -Bodof PCC Tubes DZLV994104
32.5
320
31.5
-6 31.0
30 5
300
29.5
290
285
0 24 48 72 96 120 144 168 192 216 240 264 288 312 336 360 384 408 432 456 480 504 528 552 576 600 624 648 672 696 720Time (hr)
Figure 6.2-140 S05-C6 Main Steam Line Break, 1 DPV Failure (Bounding Case) - PCCS Water Level (30days).
340-
33 5PCC 909 Water LOevl DZLV993604Top of PCC Tubes DZLV9g3704
334 V4 PCC Tubes DZLV99380433.0dl D 5090ZV93904
114 PCC Tubos DZLV994004
Xilo 41 PCC Tubes DZLV9N4104
32.5
32.0
31.5
" 310
305
30,0
29.5
29 0
285
280 I , I72.0 725 73.0 735 740 745 750 75.5 760
Time (hr)
Figure 6.2-140 S05-C6a Main Steam line Break, IDPV Failure (Bounding Case) - PCCS Water Level (72-76hr).
9 of 37
MFN 09-023 Supplement 3Enclosure 1
30
27
24
21
118
S15
, 12
Mess Floe Rete to PCCS Pool MFL0390001
9
6
3
0
48 96 144 192 240 288 336 384Time (hr)
432 480 528 576 624 672 720
Figure 6.2-140 S05-DI Main Steam
30
27
Line Break, 1DPV Failure (Bounding Case), Mass Flow Rate to PCCSPool (30 Days).
L Mess FlW Rate to PCCS Pool MFLO39O01 I
24-1-
21
i18
S15-
12
3-
0 I I I I , . I 1 ! [ ! 1 ! 1 1 ! 1 i I i I I I iiI I I I I I i I I I 1 1 I
72.0 72.5 73.0 73,5 74 0Time (hr)
74.5 75.0 75.5 76 0
Figure 6.2-140 S05-DIa Main Steam Line Break, 1DPV Failure (Bounding Case), Mass Flow Rate to PCCSPool (72 hr-76 hr).
10 of 37
MFN 09-023 Supplement 3Enclosure 1
c•mo
1700
1600
1500
1400
1300
1200
1100
1000
900
u 800
700
> 600
500
400
300
200
100
0 48 96 144 192 240 288 336 384 432 480 528 576 624 672 720Time (hr)
Figure 6.2-140 S05-D2 Main Steam Line Break, 1DPV Failure (Bounding Case), PCCS RecirculationVolumetric flow Rate (30 Days).
990 -
890 -
790 -
690 -
590
Ir490
U..~390-
S290
- (4) VOL FIO RaW per FAN VFLOO8500001
100 -
90 -
-10 -
72.0 725 73.0 73.5 74.0Time (hr)
745 75.0 75.5 76 0
Figure 6.2-140 S05-D2a Main Steam Line Break, IDPV Failure (Bounding Case), PCCS RecirculationVolumetric flow Rate (72 hr-76 hr).
11 of 37
MFN 09-023 Supplement 3Enclosure 1
15
14
13
1.2
1.1
1.0
09
0.8
0.7
0,6
~0.5-0.4
80,3
0.2
0.1
0.0
-0.1
-0.2
-0.3
-0.4
-0.5
T- 2 M .. e ... A .... I
4) ýMes FOe Pete I- FAN MF
0 48 96 144 192 240 288 336 384 432Time (hr)
480 528 576 624 672 720
Figure 6.2-140 S05-D3 Main Steam Line Break, IDPV Failure (Bounding Case), PCCS Recirculation Massflow Rate (30 Days).
0.9
0.8
07
0.6
0.5
0.4
0.3
0.2
00
: -01
-02
-0.3
-04
-0.5
-0.6
-07
-0.8
-0.9
-10
1 2)Mes le , 'e e AN ML5)~2ý4)MeFeePeeeFN FLR00
72.0 72.5 73.0 735 74.0Time (hr)
74.5 75.0 75.5 76 0
Figure 6.2-140 S05-D33a Main Steam Line Break, 1DPV Failure (Bounding Case), PCCS Recirculation Massflow Rate (72-76 hr).
12 of 37
MFN 09-023 Supplement 3Enclosure 1
30 .
27
24
21
18
S15
LU
9
6
3
0 48 96 144 192 240 288 336 384 432 480 528Time (hr)
576 624 672 720
Figure 6.2-140 S05-D4 Main Steam Line Break, 1DPV Failure (Bounding Case), PCCS Condensate MassFlow Rate to GDCS (30 Days).
33
30
27
24
ý21-
18
U-15-
(2ý PCCS Moss FeW Pe"te LDratr) to OS Pool MFL046 0007t4t PCCS M-o Foe Rote roain) to GDCS Pool tFLOM84007TOTAL PCCS Mass Floe Rate ([a,,) to GDCS Pool
12
9
6
3
0
72.0 72.5 73.0 73.5 74.0Time (hr)
745 750 75.5 760
Figure 6.2-140 S05-D4a Main Steam Line Break, 1DPV Failure (Bounding Case), PCCS Condensate MassFlow Rate to GDCS (72 hr-76 hr).
13 of 37
MFN 09-023 Supplement 3Enclosure 1
3000
2900
2800
2700
2600
2500
2400
€"2200
2100
2000
S1900z
1800
1700
1600
1500
1400
1300
1200
1100
1000
0 48 96 144 192 240 288 336 384 432 480 528 576 624 672 720Time (hr)
Figure 6.2-140 S05-D5 Main Steam Line Break, IDPV Failure (Bounding Case), PCCS Vent Fan Head (30Days).
3000
2900I- (4) HEAD pe Fan, HEAD08500001
2800
2700
2600
S2500
2400
2300
2200
2100
2000 -720
. . .. I . . .I . I . . . I I72.5 73,0 735 74 0
Time (hr)74.5 750 75.5 76 0
Figure 6.2-140 S05-D5a Main Steam Line Break, IDPV Failure (Bounding Case), PCCS Vent Fan Head (72hr-76 hr).
14 of 37
MFN 09-023 Supplement 3Enclosure 1
2.0
18
1.5
1.3
1.0
zI.
08
05
0.3
0.0
* VOL now.~v£ FAN4 IP(4) VHOP08500001
Ce
I i i ( b I II I iI i I :I ) ! I I Ii I I I I [ I i ! ii I ! i ! ! !
-0.3
-0,5
-100 150 400 650 900 1150 1400Volumetric Flow CFM
1660 1900 2150 2400
Figure 6.2-140 S05-D6 Main Steam Line Break, 1DPV Failure (Bounding Case), PCCS VentFlow vs. Head (30 Days).
Fan, Volumetric
ax.
z:F
2.0
1.8
1.5
1.3
1.0
0.8
05
0.3
0.0
-0.3
-0.5
L VOL ow s FAN HE)D (4) RHOP08500001
C",
.100 150 400 650 900 1150 1400Volumetric Flow CFM
1650 1900 2150 2400
Figure 6.2-140 S05-D6a Main Steam Line Break, IDPV Failure (Bounding Case), PCCS Vent Fan,Volumetric Flow vs. Head (72 hr-76 hr).
15 of 37
MFN 09-023 Supplement 3Enclosure 1
20
18
16
14
S12
10
8
6
V[ u ror F-ow 1 MIF0100V03vacuum Brea1er Fow 2 0FLO420002
4
2
00 48 96 144 192 240 288 336 384 432 480 528 576 624 672
Time (hr)720
Figure 6.2-140 S05-D7 Main Steam Line Break, IDPV Failure (Bounding Case) PCCS Vent Fan, DW-WWVacuum Breaker (30 Days).
18
16 t [ Vcuum Breaecr Flow 1 MFLO100003
Vacuum Bra.er Flow 2 MFLO420003
14-4-
•-12
0. 10
8
•6
4-
2-
0 4-720 72.5
1730
Time (s)
1715 74,0
Figure 6.2-140 S05-D7a Main Steam Line Break, 1DPV Failure (Bounding Case) PCCS Vent Fan, DW-WWVacuum Breaker (72 hr-74 hr).
16 of 37
MFN 09-023 Supplement 3Enclosure 1
010
0.09
008
007
0.06
0.05
0.04
0,03
0.02
1 001
0,00
j. -0.01
4 -0.02
-0.03
-0.04
-0.05
-0.06
-0.07
-0.08
-0.09
-0.10
OW-WW Le.We FR., MFL01800V
-- I F
0 48 96 144 192 240 288 336 384Time (hr)
432 480 528 576 624 672 720
Figure 6.2-140 S05-D8 Main Steam Line Break, IDPV Failure (Bounding Case) PCCS Vent Fan, DW-WWLeakage (30 Days).
0.1
0.c
0.0
00
00
0.0
0.0
0.0
0.0
n,0.0
0.
0-0i-0.
-0ý
-0.1
-0.'
-0.'
-0.
-0.
0 - . . . . . . . . . .
9
8 DW-WYA'LeBeW Fkw NLO01W3
07
6
05
04
13
02
)010-
01
02
03
04
05
06
07
08
29
10 .1 1 1 11 1 .. . . 1 1 11
72.0 72 5 73.0 735 74.0Time (hr)
74,5 75.0 75.5 76 0
Figure 6.2-140 S05-D8a Main Steam Line Break, 1 DPV Failure (Bounding Case) PCCS Vent Fan, DW-WWLeakage (72 hr-76 hr).
17 of 37
MFN 09-023 Supplement 3Enclosure 1
• '-'NC Gas in Drywall
3900
3600
3300
3000
2700
2400/
S-2100 / / -- NC Gas Mass ALP9922O ]
.1800 //
1500
1200
900J
600
300
0-+0 48 96 144 192 240 288 336 384 432 480 528 576 624 672 720
Time (hr)
Figure 6.2-140 S05-D9 Main Steam Line Break, IDPV Failure (Bounding Case), DW Total NoncondensableGas Mass (30 Days).
NC Gas in Drywall3000-
2700
2400
2100
1800
-NC G. M-s ALP992T201
1500
1200
900
600
300
0 ,
72.0 72.5 73,0 73,5 74 0 74.5 7560 75.5 76 0Time (hr)
Figure 6.2-140 S05-D9a Main Steam Line Break, IDPV Failure (Bounding Case), DW Total NoncondensableGas Mass (72 hr-76 hr).
18 of 37
MFN 09-023 Supplement 3Enclosure 1
16
14
12
NC Gas in WW Airspace
I . . . . I . . . . I . . . . I . . . . I . . . . !
10
8I I-NC Gas Mass (loINn WNW A~rspace)I
6
4-
2
0 I I • [ I I I . . . .
0 48 96 144 192 240 288 336 384Time (hr)
432 480 528 576 624 672 720
Figure 6.2-140 S05-DlO Main Steam
16. ..
Line Break, IDPV Failure (Bounding Case), Total WW NoncondensableGas Mass in Air Space (30 Days).
NC Gas in WW Airspace
14 -
12 +
10 -
a
6
4
2
I- NC Gas Mass (ThI, Pn 5Arspase)
0
72.0I I . . . . I . . .I . I I. . . . I I
72.5 73.0 73.5 74.0Time (hr)
74.5 7560 75.5 76,0
Figure 6.2-140 S05-DI0a Main Steam Line Break, IDPV Failure (Bounding Case), Total WWNoncondensable Gas Mass in Air Space (72 hr-76 hr)
19 of 37
MFN 09-023 Supplement 3Enclosure 1
340 . .I I. .
33,5PCC Pc/l Water Level oZLVOg3604Top of PCC Tubes DZLV993704
33.0 3/4 PCC Tubes DZLV993804
Moddle DZLV993904Vt4 PCC Tubes DZLV994004
Bo f PCC Tubes DZL 994104
32.5
320
31.5
- 31.0
295
290
28.5
0 48 96 144 192 240 288 336 384 432 480 528 576 624 672 720Time (hr)
Figure 6.2-140 S05-DI I Main Steam Line Break, 1DPV Failure (Bounding Case), PCC Pool 2 Phase Level(30 Days).
34.0 . . . . . .
335PCC Poo' Water Le-el DZLV9g3604
Top of PýCC TubeS DZLV9g370433.0 3/4 PCC Tubes DZLV993804
Middle DZLV9939O41/4 PCC Tubes DZLV994004
Bo1om of PCC Tubes D03V994104
32.5
320
315
5@ 31.0
30.5
30.0
29.5
29 0
28.5
28,0 11111111111. 1111, , I ,72.0 725 73.0 735 740 74.5 75.0 75.5 76.0
Time (hr)
Figure 6.2-140 S05-DI la Main Steam Line Break, IDPV Failure (Bounding Case), PCC Pool 2 Phase Level(72 hr-76 hr).
20 of 37
MFN 09-023 Supplement 3Enclosure 1
34,,, 0 ..? ,.?. .. .. . . .. .
335
33 0
32.5
32,0
31 5
30Z5
30.0
295
29 0
28 5
28.0 I0 48 96 144 192 240 288 336 384
Time (hr)
Figure 6.2-140 S05-D12 Main Steam Line Break, IDPV Fail
• ' ' [ . . . . I . . . . I . . . . I •rlllllJ•411iF
PCC Poo Water Leve CollapsedTop of PCC Tbes
314 PCC TubesMiddle
1/4 PCC TubesPotto of PCC Tubes
4 I 48 528 576 624 672432 480 528 576 624 672 720
(30 Days).lure (Bounding Case), PCC Pool Level Collapsed
340
33,5
33.0
32.5
32.0
31 5
*j 310
30 5
30.0
29.5
290
28 5
28&0 - I
72.0
PCC Pool water Laval Coftapsed
Top of PTCC Tues
304 PCT TabesMO ddla
1/4 PCC TabesBolom of PCC TPe5
i ! i I I I I I [ F i I i f f i i i i i I I I I I I ! ! i I ! i I I i
72.5 73.0 735 740Time (hr)
I I I I I I I I I • ] I ] • ( I I
74,5 75.0 75.5 760
Figure 6.2-140 S05-D12a Main Steam Line Break, iDPV Failure (Bounding Case), PCC Pool Level Collapsed(72 hr-76 hr).
21 of 37
MFN 09-023 Supplement 3Enclosure 1
140
130
120
110
100
90
2-PCCS Pool R04
- 136 TLgg3604_ .37 TL993704L38 TL993804
- L39 TL993904140 TL904004L41 TL994104
80
70
60
50
40i
0 48 96 144 192 240 288 336 384Time (hr)
432 480 528 576 624 672 720
Figure 6.2-140 S05-D13 Main Steam Line Break, IDPV Failure (Bounding Case), PCC Pool WaterTemperature (2-PCCS Pool) (30 Days).
140
130 -1-
I I . I I ý
2-PCCS Pool R04
1. 36 Th993884
1. 37 T1.8937041.384 Th994104
1.38 Th9938041.40~ Th893904
1. 41 Th994004
120 -
110 +
100
83"-_. 90 -
80 -
70+
60
50 1
4072.0 725 73.0 735 740
Time (hr)
7 75 7 I I I I I745 75.0 75.5 76,0
Figure 6.2-140 S05-DI3a Main Steam Line Break, 1DPV Failure (Bounding Case), PCC Pool WaterTemperature (2-PCCS Pool) (72 hr - 76 hr).
22 of 37
MFN 09-023 Supplement 3Enclosure 1
140
130
120
110
100
90
80
70
60
50
40
4-PCCS Pool R6
L36 Thg93606L37 TL 93706L38 TL993806L39 TL93906W4 Th9~4006L41 TL994106
0 48 96 144 192 240 288 336 384Time (hr)
432 480 528 576 624 672 720
Figure 6.2-140 S05-D14 Main Steam Line Break, 1DPV Failure (Bounding Case), PCC Pool WaterTemperature (4-PCCS Pool) (30 Days).
140
130
120 -
110-
~90-
4-PCCS Pool R6
L36 TL993606L37 TL993706
L38 TL993806- L39 TL993906
L40 TL994006L41 TL994106
i..-
80 +
70
60±
50
40 I ~ ~~~~ i I I I I I I I i I [ f I I I I t I I I I I I I I I I I I i I
72.0 I . . . . . . . . . . I .72.5 73.0 73.5 74,0Time (hr)
74,6 75.0 75.5I • f I
76.0
Figure 6.2-140 S05-Dl4a Main Steam Line Break, IDPV Failure (Bounding Case), PCC Pool WaterTemperature (4-PCCS Pool) (72 hr-76 hr).
23 of 37
MFN 09-023 Supplement 3Enclosure 1
Sup Pool Temperature
2U0 ,
180 -
160 +
140 4
120
1 1oo0
I- an
TL992507TL9 2607TL 99 2707TL921117TL992907
du
60
40 -
20
00 48 96 144 192 240 288 336 384
Time (hr)432 480 528 576 624 672 720
Figure 6.2-140 S05-D15 Main Steam Line Break, IDPV Failure (Bounding Case), Suppression PoolTemperature (R7) (30 Days).
200 ,Sup Pool Temperature
180
-T11121111T19 2607T L992 707TL992807TL992907
160
140
120
-9 100
•80
60
40±
204-
072.0
I . . . .I I ý . . . I I I ý I I ,72.5 73.0 73,5 740
Time (hr)74.5 75.0 75.5 76.0
Figure 6.2-140 S05-DI15a Main Steam Line Break, IDPV Failure (Bounding Case), Suppression PoolTemperature (R7) (72 hr - 76 hr).
24 of 37
MFN 09-023 Supplement 3Enclosure 1
200
180
160
140
120
2100
'80
-- TL992608
TL992708Th99ý2ýOý -
60
40
20
00 48 96 144 192 240 288 336 384 432 480 528 576 624 672 720
Time (hr)
Figure 6.2-140 S05-D16 Main Steam Line Break, IDPV Failure (Bounding Case), Suppression Pool LiquidTemperature (R8) (30 Days).
200 . , ,
180 4 TLq92508TL992608
TL992708
L992808160 t
140
120U
1i 100
80
60+
40
20 +
0 I I l i l l l l l l lI Il t I II
72.0 72.5 73.0 73.5 74.0
Time (hr)745 75.0 75.5 76.0
Figure 6.2-140 S05-DI6a Main Steam Line Break, IDPV Failure (Bounding Case), Suppression Pool LiquidTemperature (R8) (72 hr-76 hr).
25 of 37
I--- MFN 09-023 Supplement 3Enclosure 1
140 •. .
130
120
110
100
G- 90
80
70
60
50
40
240 288 336 384 432 480 528 576 624 672Time (hr)
Figure 6.2-140 S05-D17 Main Steam Line Break, IDPV Failure (Bounding Case), Wetwell Airspace VaporTemperature (L29-L31) (30 Days).
140 . . .
130
120
110
100
U90-
80
VWW Region
70
604-
50 T L29 8ý07 TV992907 -- 129 ROB TV992908 U30 807 7V993007L30 R08 TV993008 L31 P07 TV993107 - L3t R08 00993108
40 II[lllll[[l[l[•l[•l[lilllllllll•lill[ll
72.0I I . . . I . . . . I . . .I I,
725 7310 735 74 0Time (hr)
F I I I 7i574.5 75 0 755 760
Figure 6.2-140 S05-DI7a Main Steam Line Break, 1DPV Failure (Bounding Case), Wetwell Airspace VaporTemperature (L29-L31) (72 hr-76 hr).
26 of 37
MFN 09-023 Supplement 3Enclosure 1
200
180
160
140
120
100
s-
80
60
GDCS Pool Liquid Temperatures
. .. .I ' I i I I I I " I " " " , ,- I I -I I I I - - -- I --- I----------
40
20
0
0 48 96 144 192 240 288 336 384Time (hr)
432 480 528 576 624 672 720
Figure 6.2-140 S05-D18 Main Steam Line Break, IDPV Failure (Bounding Case), GDCS Liquid Temperature(R7) (30 Days).
200 .. . . . . .
180 GDCS Pool Liquid Temperatures - T0
I I
160 f
140
120
a -
0.100-E-
80
60±
404-
20 -
0 i i i I i I I I I I I I I I I I I I I I I -! !
72.0 72.5 73.0 735 740Time (hr)
74.5 75.0 75.5 76.0
Figure 6.2-140 S05-D18a Main Steam Line Break, IDPV Failure (Bounding Case), GDCS LiquidTemperature (R7) (72 hr - 76 hr).
27 of 37
MFN 09-023 Supplement 3Enclosure 1
210
180 GDCS Pool Liquid Temperatures Ii.... r3i40a
160
140 / -
120 -
-.100
80
60
40
20
0
0 48 96 144 192 240 288 336 384 432 480 528 576 624 672 720Time (hr)
Figure 6.2-140 S05-D19 Main Steam Line Break, IDPV Failure (Bounding Case), GDCS Liquid Temperature(R8) (30 Days).
20 0 . . . . . . . . . . . . . . . . . I
180 GDCS Pool Liquid Temperatures
160
140 -- - ---
120
0100
80
60
40
20
720 725 73.0 735 740 745 75.0 755 760Time (hr)
Figure 6.2-140 S05-D19a Main Steam Line Break, IDPV Failure (Bounding Case), GDCS LiquidTemperature (R8) (72 hr-76 hr).
28 of 37
MFN 09-0Enclosure
160 -
150
140
130
120
110
23 Supplement 31
IGDCS Pool Adr Space
GDCS PoP N' Tomperatre L34 R7 (2) TV40
IDCS Pool Tepe Orature L34 R8 (4) TV=93408
-100
90
80
70
60
50
0 48 96 144 192 240 288 336 384 432 480 528 576 624 672 720Time (hr)
Figure 6.2-140 S05-D20 Main Steam Line Break, 1DPV Failure (Bounding Case), GDCS Air Space VaporTemperature (30 Days).
150
140
130 +
120
110
100-
90
80
70
60
50
IGDCS Pool Air Space
GDCS Pool Per Tnperte.ee L34 P7)2) TV99340 0--GCS POe) pr T-mfntree L 34 P8 )4) T933408
4 0 + + I ! I I I I , , I I i d I I , i ! Ii 1 ! ! I I ! I ! I
720 72.5 73.0 735 74.0 74,5 75.0 75.5 760Time (hr)
Figure 6.2-140 S05-D20a Main Steam Line Break, IDPV Failure (Bounding Case), GDCS Air Space VaporTemperature (72 hr - 76 hr).
29 of 37
MFN 09-023 Supplement 3Enclosure 1
30 .PCCS Inlet Flows
1- TO FCC Inlet Floss MFLO220001ToIN NC Gas Flos MFLO830001
25 -4-
20 -
e15
10-
5 +
n SI I l 1 ' l 1 l l l j l ! l ! i i I l l i l l i i 1 1i P l l I Lý I E l l l l I E l l l! l! ! l ! l 1 l1 l
0 48 96 144 192 240 288 336 384 432 480 528 576 624 672 720Time (hr)
Figure 6.2-140 S05-D21 Main Steam Line Break, IDPV Failure (Bounding Case), Total PCCS Inlet FlowRates (30 Days).
- -' PCCS Inlet Flows
T~ Colr CC 5 Fl-s MFL.02200017Total PNC Gas Flo- WI-OO30001
35 -
30 -
i25
20
* 15
10-
5 -
0 1 !I :I f i I I I 4=72.0 72.5 73.0 73.6 74.0 74.5 75.0 75.5 76.0
Time (hr)
Figure 6.2-140 S05-D21a Main Steam Line Break, 1DPV Failure (Bounding Case), Total PCCS Inlet FlowRates (72-76 hr).
30 of 37
MFN 09-023 Supplement 3Enclosure 1
180DW Gas Temperature
1o -4
S140 -
120
TV993006TV993106TV993206TV993306TV993406
100
0 48 96 144 192 240 288 336 384 432 480 528 576 624 672 720Time (hr)
Figure 6.2-140 S05-D22 Main Steam Line Break, 1DPV Failure (Bounding Case), Upper DrywellTemperatures (R6) (30 Days).
DW Gas Temperature18 0' I 'I ' ' , , , , , ,
TV9923O6TVZ9ý29T 993006
T.106
TV9.3206TV993406160 +
1
• 140-
&
120 +
1 o 1 ! 1 1 1 1 1 i , I , , I I , , , I i I I i , , , I , , !72.0 725 73.0 735 740 745 750 75.5 760
Time (hr)
Figure 6.2-140 S05-D22a Main Steam Line Break, IDPV Failure (Bounding Case), Upper DrywellTemperatures (R6) (72 hr -76 hr).
31 of 37
MFN 09-023 Supplement 3Enclosure 1
180
DW Gas Temperature
160
140
I,-
-- TV992206
TV992406TV992570TV992606TV"92706
120
100
0 48 96 144 192 240 288 336 384Time (hr)
432 480 528 576 624 672 720
Figure 6.2-140 S05-D23 Main Steam Line Break, IDPV Failure (Bounding Case), Lower DrywellTemperatures (R6) (30 Days).
180 r rDW Gee Temperature
160
TV992206Tvggý2306TV992406TV992506
- V2606TV992706
a
140
C.
120 +
100
72.0I . . .I I I I . . . . I . . .I I '
72,5 73.0 73,5 74.0Time (hr)
I 7 4 I I I , I I7. 5745 75.0 75.5 76.0
Figure 6.2-140 S05-D23a Main Steam Line Break, 1DPV Failure (Bounding Case), Lower DrywellTemperatures (R6) (72 hr-76 hr).
32 of 37
MFN 09-023 Supplement 3Enclosure 1
c•eo
Steam Mesa in Drywall18
16
14
13
I- Steam Mass Total. 'P)g2201
17
5
4
2
0
0 48 96 144 192 240 288 336 384 432 480 528 576 624 672 720Time (hr)
Figure 6.2-140 S05-D24 Main Steam Line Break, IDPV Failure (Bounding Case), DW Steam Mass (30 Days).
Steam Mass in Drywall
18
16 -
144
13
Z7
5 - I- Steam Mass (TOta) ALP992201 I
4
2
00 . . .I I. .II I .I . i I. . . . ý . . . I '
72.0 72 5 73.0 735 74,0Time (hr)
74,5 750 75.5 760
Figure 6.2-140 S05-D24a Main Steam Line Break, IDPV Failure (Bounding Case), DW Steam Mass (72 hr -76 hr).
33 of 37
MFN 09-0Enclosure
2400
2160
1920
1680
1440
1200
960
720
480
240
00
23 Supplement 31
Steam Mess in WW Airspace
Steeas Mass (Total)
I I ~I I I I .I • ; I [ i i i t
I I . . . i . . I . . . I . . .I . . . .I I , r . . . , I I I I I r ... . I .. . .. . I . . . . i . . .I I . . . .I I I . . . .48 96 144 192 240 288 336 384 432 480 528 576 624 672 720
Time (hr)
Figure 6.2-140 S05-D25 Main Steam
2400
2160 I
1920 -
1680... "-
1440
1200
960
720
480
240
0
Line Break, IDPV Failure (Bounding Case), WW Steam Mass (30 Days).
Steam Mass in WW Airspace
[- Steals Mass (Total)]
! i i I I ! I I ! I I I I I I I I
72.0 72.5 73.0 73.5 74.0Time (hr)
74.5 75.0 75.5 760
Figure 6.2-140 S05-D25a Main Steam Line Break, 1DPV Failure (Bounding Case), WW Steam Mass (72 hr -76 hr).
34 of 37
MFN 09-023 Supplement 3Enclosure 1
18
16
14
12
1-
6-
4-
WW NC Mess ALP992907WW*DW NC M-ss ROA992907WW.DWVGDCS NC Mass ALP992908WWODW-GDCS*DWH NC Mass ROA992908
0 48 96 144 192 240 288 336 384 432 480 528 576 624 672 720Time (hr)
Figure 6.2-140 S05-D26 Main Steam Line Break, 1DPV Failure (Bounding Case), Noncondensable Gas Mass(30 Days).
18
16 +
14+
12
l1o
8
6 ± - WW NC Mess .LP92907"W"W.W NC M'ss ROA992907WW÷DW.GDCS NC MOss ALP992908WW-DW"GDCS*fWH NC Mass ROA992908
4 -
2
72.0 725 73.0 735 740Time (hr)
745 750 75.5 76&0
Figure 6.2-140 S05-D26a Main Steam Line Break, 1DPV Failure (Bounding Case), Noncondensable Gas Mass(72 hr - 76 hr)
35 of 37
MFN 09-023 Supplement 3Enclosure 1
450
0.
5 10 15 20 25
Discharge Submergence (in)
Figure 6.2-140S05-1 DW Pressure as a Function of PCC Vent Fan Submergence450
400
350
300
0.
250
0. 200
150
100
50
072 108 144 180 216 252 288 324 360 396 432 468 504 540 576 612 648 684 720
Time (hr)
Figure 6.2-140S05-2 ESBWR DW Pressure with Appropriate Safety Adders
36 of 37
MFN 09-023 Supplement 3Enclosure 1
DCD Impact
The following DCD Sections will be revised as noted in the attached markup:
" DCD Tier 1, Table 2.15.4-2
" DCD Tier 2, Section 6.2.1.1.3.5.1
" DCD Tier 2, Section 6.2.2.2.2
" DCD Tier 2, Figure 6.2-14el
* DCD Tier 2, Figure 6.2-14e2
* DCD Tier 2, Figure 6.2-14e13
* DCD Tier 2, Table 6.2-49
37 of 37
Enclosure 2
MFN 09-023 Supplement 3
Response to Portion of NRC Request for
Additional Information Letter No. 375
Related to ESBWR Design Certification Application
Engineered Safety Features
RAI Number 6.2-140 S05
Markups to ESBWR DCD
Tier I and Tier 2 Section 6.2
26A6641AB Rev. 07ESBWR Design Control Document/Tier I
Table 2.15.4-2
ITAAC For The Passive Containment Cooling System
Design Commitment Inspections, Tests, Analyses Acceptance Criteria
11. The PCCS vent fans flow rate is For each PCCS vent fan line, a flow rate * The tested and analyzed flow ratessufficient to meet the beyond 72 test will be performed with the are greater than or equal to thehours containment cooling containment at pre-operational ambient flow rates of the design basisrequirements following a design conditions. Flow measurements will be LOCA containment analysisbases LOCA. taken on flow to the GDCS pools. An model for the PCCS vent fan lines
analysis of the test configuration will be at containment pre-operationalperformed. ambient conditions.
12. The PCCS vent fans can be remotely PCCS vent fans will be started using The PCCS vent fans start when manuallyoperated from the MCR. manually initiated signals from the MCR. initiated signals are sent from the MCR.
13. The PCCS drain piping is installed to Inspection(s) will be conducted of as-built Based on inspection(s) of as-built PCCSallow venting of non-condensable PCCS drain piping to ensure there are no drain piping, the as-built piping conformsgases from the PCCS drain lines to elevated piping loops or high-point traps to a design that allows venting of non-the PCCS condenser vent lines to in piping runs to the GDCS pools. condensable gases from the PCCS drainprevent collection in the PCCS drain lines to the PCCS condenser vent lines.lines.
14. The elevation of the PCCS vent fan A visual inspection will be performed of The elevation of the discharge on thedischarge point is submerged within the PCCS vent fan discharge point relative PCCS vent fan line 24 cm (9.4 in) belowthe drain pan located in the GDCS to the lip of the drain pan. the top of the drain pan lip with apool at an elevation below the lip of tolerance of 1.4 cm (0. 1the drain pan. 0.5 in) and <241 em (E-1 em) below the top
of the drain pa li.
2.15-53
26A6642AT Rev. 07ESBWR Design Control Document/Tier 2
A loss of all power generation buses is not the limiting assumption and the effects of continuedfeedwater injection is more limiting, as it can potentially add water to the wetwell and compressthe wetwell air space. The ESBWR design incorporates features that mitigate this challenge byisolating reactor inventory sources outside of containment and provides a method of GDCSinitiation based on LOCA condition detection. These features ensure that containment remainswithin design pressure for the entire 72-hour event duration. These features also ensureacceptable performance for the full spectrum of LOCA events within containment, with orwithout the assumption of loss of external injection capability. Additionally, although powergeneration buses are considered available to add feedwater or High Pressure Control Rod Drive(HP CRD) injection, no credit is given for heat removal systems powered by these buses. Table6.2-7h shows the sequence of events for the Main Steam Line Break with failure of one SRV andwith offsite power available. Figures 6.2-14j 1 through 6.2-14m3 show the pressure, temperature,DW and GDCS airspace pressure responses and PCCS heat removal for this analysis. Thenoncondensable mass and the void fraction in the DW and GDCS are presented in Figures 6.2-14nl through 6.2-14o3. The detailed discussion on the chronology of progression is given inAppendix 6E.5. The cases analyzed without offsite power and water addition assume higherinitial pressure, and result in higher pressure as shown in Table 6.2-5. The highest value ofMaximum DW Pressure in Table 6.2-5 is the calculated peak containment internal pressure forthe design basis loss of coolant accident.
6.2.1.1.3.5.1 Post-LOCA Containment Cooling and Recovery Analysis
For post-LOCA containment cooling and recovery, the Main Steam Line Break with failure ofone DPV is selected. The analysis results are not sensitive to the event selection (failure of oneDPV versus one SRV) due to the fact that these two cases are nearly the same in transientresponses up to 72 hours and the containment pressure and temperature are rapidly reduced uponthe activation of the nonsafety-related Structure, System, or Components (SSC).
After the first 72 hours of the accident, the following nonsafety-related SSCs are utilized to keepthe reactor at safe stable shutdown conditions, to rapidly reduce containment pressure andtemperature to a level where there is acceptable margin, and then to maintain these conditionsindefinitely:
(1) SSCs to refill the IC/PCCS pools;
(2) PCCS Vent Fans;
(3) Passive Autocatalytic Recombiner System (PARS); and
(4) Power supplies to the PCCS Vent Fans and the IC/PCCS pool refill pumps.
Once a state of safe, stable reactor shutdown is reached, containment pressure and temperatureare maintained with sufficient margin to containment design limits for a long period of time.Figure 6.2-14el through Figure 6.2-14el0a show key parameters for the long term pressurereduction and maintenance phase. PARS function at 72 hrs and 4 of 6 PCC vent fans arecredited in the calculation. A containment system performance acceptance criteria ("AnalyticalPressure Limit" curve) is shown on Figure 6.2 14el which considers variations in IC/PCC poolfrom minimum to maximum and fan discharge submergence variations during the simulation.
To bound uncertainties and variations in the IC/PCC pool level from minimum to maximum andfan discharge submergence variations during the simulations, an adiustment is determined and
6.2-11
26A6642AT Rev. 07ESBWR Design Control Document/Tier 2
added to the base results. Figure 6.2-14el 3 compares the adjusted pressure to the containmentsystem performance acceptance criteria. The containment pressure is reduced and remainsbelow the acceptance criteria.
Other non-safety related, non-Regulatory Treatment of Non-safety Systems (RTNSS) SSCs canbe placed in service to bring the reactor to cold shutdown conditions and to further reduce thecontainment pressure and temperature. These SSCs include the FAPCS as the preferred method,and the RWCU/Shutdown Cooling (SDC) system in the unlikely event there is fuel damage(Subsections 9.1.3 and 5.4.8, respectively). The RWCU/SDC and the FAPCS system are notpart of the primary success path for post-LOCA containment cooling. Calculations ofRWCU/SDC performance are provided here to show its ability to cooldown the reactor andcontainment. In the unlikely event of fuel damage, where the RWCU/SDC system is used, theReactor Building HVAC Accident Exhaust Filter Units are a required support system for limitingonsite and offsite dose.
Containment pressure and temperature responses which represent a postulated accident recoveryevolution, with RWCU/SDC (fuel damage assumed) providing the cold shutdown function areshown in Figures 6.2-14ell and 6.2-14e12. These response curves are based on theRWCU/SDC operating in suppression pool cooling mode for 24 hours, beginning seven daysafter a LOCA, followed by vessel injection via the normal RWCU/SDC midvessel suction line,with suction from the suppression pool. The heat removal for this mode of RWCU/SDCoperation is provided by the non-regenerative heat exchanger (NRHX). A conservative heatexchanger capacity was assumed which is well within the capability of the RWCU/SDC NRHX.Table 6.2-48 lists the RWCU/SDC NRHX data used in the analysis. There is no requirement tostart the recovery actions at seven days, since the reactor is already in a safe stable shutdowncondition, and containment pressure and temperature are in a non-upward trending state, withsufficient margin to containment design limits.
The accident recovery analysis shows that after being in suppression pool cooling for 24 hoursand then injecting into the reactor vessel for approximately 10 hours, the suppression pool hasequilibrated with the reactor bulk water temperature at cold shutdown conditions.
6.2.1.1.4 Negative Pressure Design Evaluation
During normal plant operation, the inerted WW and the DW volumes remain at a pressureslightly above atmospheric conditions. However, certain events could lead to a depressurization
-transient that can produce a negative pressure differential in the containment. A DWdepressurization results in a negative pressure differential across the DW walls, vent wall, anddiaphragm floor. A negative pressure differential across the DW and WW walls means that theRB pressure is greater than the DW and WW pressures, and a negative pressure differentialacross the diaphragm floor and vent wall means that the WW pressure is greater than the DWpressure. If not mitigated, the negative pressure differential can damage the containment steelliner. The ESBWR design provides the vacuum relief function necessary to limit these negativepressure differentials within design values. The events that may cause containmentdepressurization are:
Post-LOCA DW depressurization caused by the ECCS (for example, GDCS) flooding ofthe RPV and cold water spilling out of the broken pipe or cold water spilling out ofbroken GDCS line directly into DW.
6.2-12
26A6642AT Rev. 07ESBWR Design Control Document/Tier 2
The PCCS condensers are located in a large pool (IC/PCCS pool) positioned above the ESBWRDW.
Each PCCS condenser is configured as follows (Figures 3G. 1-7 1a and 3G. 1-71 b).
A central steam supply pipe is provided which is open to the DW airspace at its lower end. Theopen end of this pipe is provided with a debris filter with holes no greater than 25 mm (1 inch).The maximum inlet velocity during a LOCA is estimated to be no greater than 106 m/s (348 ft/s).The steam supply feeds two horizontal headers through two branch pipes at its upper end. Steamis condensed inside vertical tubes and the condensate is collected in two lower headers.
The vent and drain lines from each lower header are routed through the DW through a singlepassage per condenser module as shown on the figures.
The condensate drains into an annular duct around the vent pipe and then flows in a line thatconnects to a large common drain line, which also receives flow from the other header. The ventline goes to the suppression pool and is submerged below the water level.
A Passive Containment Cooling vent fan is teed off of each PCCS vent line and exhausts to theGDCS pool. The fan aids in the long-term removal of noncondensable gas from the PCCS forcontinued condenser efficiency. The minimum fan performance requirements are shown inTable 6.2-49. The fans are operated by operator action and are powered by a reliable powetsource which has a diesel generator backed up by an ancillary diesel, if necessary, without theneed to enter the primary containment. The discharge of each PCCS vent fan is submergedbelow the GDCS pool water level to prevent backflow that could otherwise interfere with thenormal venting of the PCCS. The vent fan discharge line terminates in a drain pan within theGDCS pool so that the gas seal is maintained after the GDCS pool drains. The vent fandischarge line is 24 cm (9.4 in) below the top of the drain pan lip with a tolerance of 1.4 cm (0.6in > 0.22 m (9 in) and < 0.25 f (10 in) below the top of the drain pan lip. To further preventreverse flow through an idle fan, a check valve is installed downstream of the fan.
The PCCS condensers receive a steam-gas mixture supply directly from the DW. The PCCScondensers are initially driven by the pressure difference created between the DW and thesuppression pool during a LOCA and then by gravity drainage of steam condensed in the tubes;so they require no sensing, control, logic or power-actuated devices to function. In order toensure the PCCS can maintain the DW to WW differential pressure to a limit less than the valuethat causes pressure relief through the horizontal vents, the vent line discharge point is set at anelevation submerged below low water level and at least 0.85 m (33.5 in) and no greater than0.900 m (35.4 in) above the top of the uppermost horizontal vent. The PCCS condensers are anintegral part of the safety-related containment and do not have isolation valves.
The drain line is submerged in the GDCS pool to prevent back-flow of steam and gas mixturefrom the DW to the vent line, which would otherwise short circuit the flow through the PCCScondenser to the vent line. It also provides long-term operational assurance that the PCCScondenser is fed via the steam supply line. The drain line terminates in the same drain pan as thevent fan discharge to replace any evaporation loss in the drain pan after the GDCS pool drains.
Each PCCS condenser is located in a subcompartment of the IC/PCCS pool, and all poolsubcompartments communicate at their lower ends to enable full use of the collective waterinventory independent of the operational status of any given IC/PCCS sub-loop.
6.2-28
26A6642AT Rev. 07ESBWR Design Control Document/Tier 2
Design DW and WW Pressure
400
350W&-- 1 Wet ..ll (~ L-v1 31 .Ring 7) P993107RPV P-esume (L-I 21, Ring 1) P292101
300 .
250
100
50
0 24 48 72 96 120 144 168 192 216 240 264 288 312 336 360 384 408 432 456 480 504 528 552 576 600 624 648 672 696 720Time (hr)
450.. . .I.. . . .. . . I
Design DW and WV Pressure
400
350 "" D Pressure (eVe 34 Reg 5) P99340//~~~R Ieg rerwetweeg Presue (Leve1l 31,Pg 7) Pg93107
-RPV Pressre (Lee 21. RPng 1) P992101
300
a:
150
100
50
0
0 24 48 72 96 120 144 168 192 216 240 264 288 312 336 360 384 408 432 456 480 504 528 552 576 600 624 648 672 696 720Time (hr)
Figure 6.2-14e1. Drywell, Wetwell and RPV Pressures (720 hr)
6.2-297
26A6642AT Rev. 07ESBWtR
450
Design Control Document/Tier 2
. . . .
Design DW and WWV Pressure
400
350 -
300
250
200-
ISO W~re P-essure (Le-e 31.Ring T) P993107
- RPVPissum (Level 21,RiN 1) P992101Dealgn PressureAnau5t5al Pressue Lit
100
50
0
450
I . . I i M a i I 9 6 A i I i d & i I $ & K i i i A a i72 84 96 108 120 132 144
Time (hr)
Design OW and WW Pressure
400
350
300
1 250
I20090
150
100
50
0-
Sryeel Pressure (Level 34.11-g 5) P993405wet.5 Pressure (Leve- 31.es 71 P993,07RPV Pressure Lees 21, Ping 1) P992101Desgn Pressure
721
84 961
108 120Time (hr)
32 1111 156 1 16132 144 156 168
Figure 6.2-14e2. Drywell, Wetwell and RPV Pressures (72 - 144 hr)
6.2-298
26A6642AT Rev. 07ESBWR
450
400
350
300
0t.
250
o. 200
150
100
50
0
Design Control Document/Tier 2
72 108 144 180 216 252 288 324 360 396 432 468 504 540 576 612 648 684 720
Time (hr)
Figure 6.2-14e13. Drywell Pressure with Sensitivity to Vent FanSubmergence and PCC Pool Level (72 hr to 720 hr)
6.2-305
26A6642AT Rev. 07ESBWR Design Control Document/Tier 2
Table 6.2-49
PCCS Vent Fan Minimum Performance Requirements'
Normalized Fan Head AP/p m3 /Sm /s2 (ft2/s2) Flow (CFM)
2,410 (25,900) 0.071 (150)
2,380 (25,600) 0.141 (300)
2,290 (24,600) 0.283 (600)
2,050 (22,100) 0.472 (1,000)
1.880 (20.200) 0.566 (1.200)
1,390 (15,000) 0.741 (1,570)
1. The inlet losses for the PCCS are described in Table 6.2-8, Item 4. The outlet losses shallnot exceed a k/A 2 value of 1500 m-4 (174,000 fi-4).
6.2-191